3. Because the CPI is 80% that means the project
is:
◦ currently behind schedule
◦ currently over-budget
4. CPI = 80%
BAC = $120,000
Estimate At Completion(EAC) = BAC/CPI
◦ EAC = 120,000/.80 = 150,000
The project is over-budget $30,000,
therefore the project is performing worse
then planned.
5. Estimated Time to Complete = Original Time
Estimate/SPI
Estimated Time = 1(year)/.87 = 1.149
Estimated Time to Complete is 1.149 years.
.149 years more then expected