SlideShare a Scribd company logo
1 of 6
SIMPLE SAMPLE
MEMORANDUM
ROGER H. MANDEL
Rmandel@PramsCo.com
Mobile #: 858-735-2038
Date: 30 April 2018
To: Program Management
Subj.: EARNED VALUE PROJECT MANAGEMENT ANALYSIS REPORT, Data
through 31 March 2018
1. Summary Status:
a. Data indicates the performance changes, as shown on Figure #1, from 31
January 2017 to 31 March 2018 as follows:
i. Percent scheduled to be completed at 68.02%
ii. Percent complete 46.76%, about 22% behind schedule
iii. Percent Spent of Budget at 64.39%, about 17.63% cost overrun
iv. Percent spent of Latest Revised Estimate at 54.71%
Figure #1
-
2,000,000
4,000,000
6,000,000
8,000,000
10,000,000
12,000,000
14,000,000
16,000,000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
SIMPLE SAMPLE
Budget $13.9M
Planned $9.48M
Schedule Variance
$2.98M
Cost Variance in
$2.45M
SAMPLE Page 1
SIMPLE SAMPLE
2. Trends, as shown on Figure #2:
a. With 15 months of data:
i. Schedule performance changed from 69.3% to 68.6%. Cumulative SPI 0.686.
ii. Cost performance changed from 75.2% to 72.6%. Cumulative CPI 0.726.
iii. Schedule and Cost Performance has a negative trend as shown on Figure #2
below.
Figure #2
0.400
0.500
0.600
0.700
0.800
0.900
1.000
1.100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
CPI 0.726
SPI 0.686
SIMPLE SAMPLE
Cumulative
3. Projections:
a. The analyst projects a significant cost overrun due to the
negative trends in cost performance. The Vendors Estimate at Completion
(EAC) changed from a cost overrun of about $1.97 million to now more like $2.45
million over the current performance measurement baseline of $13.9 million.
b. The significant trend data indicates a poor schedule
performance cumulative to date at about 68.6%. That calculated for every 100
hours planned the progress is at 68.6 hours. The SPI is 0.686.
c. The cumulative cost performance to date is at 72.6%. That
calculated for every $100 dollars expended the contractor earns (accomplishes)
$72.6 dollars’ worth of work. The CPI is 0.726.
SAMPLE Page 2
SIMPLE SAMPLE
4. Choice and Rationale:
a. The worst-case projection for the scheduled completion date, for these efforts,
will be missed by about 13 months. Scheduled completion date is stated as
January 2019. Completion is projected to be March 2020.
5. Major Areas of Concern as shown on Figure #3:
a. The behind schedule is shown as be being greater than 3
months and is projected to grow to, worst case at, 13 months. With only 15
months of data, the contractor is behind schedule by greater than 3 months, as
show of Figure #3.
b. Cost variance grew from -$1,970,000 to -$2,450,000.
Figure #3
150,000
2,150,000
4,150,000
6,150,000
8,150,000
10,150,000
12,150,000
SIMPLE SAMPLE
SV In Time
Greater than 3
months
6. Exhibit as shown on Figure # 4:
a. Analyst’s (Worst Case) Estimated Cost at Completion is $23.3 M.
b. Contractor’s Estimated Cost at Completion at $16.4 M.
c. Budget at $13.9 M.
d. Planned performance to date is $9.48 M.
e. Expended to date is $9.95 M.
f. Earned to date is $6.5 M.
g. Currently at least 3+ months behind schedule.
SAMPLE Page 3
SIMPLE SAMPLE
h. Cost overrun to date is $2.45 M.
Figure #4
Program: As of: 31-Mar-2018
Planned Earned Expended SV CV Budget Vendor's EAC
$9,480,000 $6,500,000 $8,950,000 ($2,980,000) ($2,450,000) $13,900,000 $16,350,000
Percent
Complete
Work
Remaining
Cumulative
CPI
6 Month
Moving Average
3 Month
Moving Average
Independent
Projection
Worst Case
Completed 15
Reporting
Periods
0.726 0.771 0.608 0.304 Independent
$10,189,231 $9,592,363 $12,164,384 $24,342,105 Projection
$19,139,231 $18,542,363 $21,114,384 $33,292,105 Worst Case
2.19%
3 MMA Current Work Remaining
4.38% 3.74% 53.24%
Independent Projected Completion Date 29-Mar-2020
31-Jan-2019
$24,342,105
$16,942,105
$33,292,105
Best Case $19,139,231
Most likely $26,215,668
Worst Case $33,292,105
Independent EAC
Project Cost Overrun
Projection of Average Earning Per Month for Remaining Work
Percent Complete
Cost of Work Remaining To Complete Performance Index
46.76%
Independent EAC
$7,400,000
Contract Completion Date
Independent Total Estimated Cost to Go
Dollars as StatedSIMPLE SAMPLE
Copy to:
The Essential EVM Formulas
Acronyms:
AC: Actual Cost (ACWP means Actual Cost of Work Performed). The cost for
the work performed.
ACWP: Actual Cost of Work Performed.
BAC: Budgeted at Completion, also Authorized Budget also Total Planned Value.
BCWP: Budget Cost for Work Performed. Completed (accomplished) budgeted work.
BCWS: Budget Cost for Work Scheduled. The cost for the work performed.
CPI: Cost Performance Index. Earned divided by Expended.
CV: Cost Variance. The mathematical difference between Earned and Expended.
EAC: Estimate at Completion
SAMPLE Page 4
SIMPLE SAMPLE
EV: Earned Value (BCWP means Budgeted Cost for Work Performed) also
Accomplished Work
ETC: Estimate to Complete. The estimated cost to complete all budgeted work.
IEAC: Independent Estimate at Completion. Independent projected cost at the
completion of all budgeted work.
PV: Planned Value (BCWS means Budgeted Cost for Work Scheduled)
SV: Schedule Variance. The mathematical difference between Earned and Planned.
SPI: Schedule Performance Index. Earned divided by Planned.
TCPI: To Complete Performance Index. The cost efficiency factor to complete
budgeted work or to complete all work at the EAC value.
WR: Work Remaining. The difference between the budgeted value and work
accomplished.
Formulas:
Cost Performance Index (CPI): CPI = EV / AC
Cost Variance (CV): CV = EV - AC
Cost Variance % (CV %): CV% = 100 x (CV / EV)
Estimate at Completion (EAC): ACWP cumulative + (Work Remaining / The Average
Projected Cost Performance Index for work remaining)
Independent Estimate at Complete (IEAC): IEAC calculations are based on the use of a
Performance Index and should be so stated:
IEAC = AC cumulative + (BAC - EV cumulative)/ Performance Index
IEAC = AC + (BAC - EV) / CPI current
IEAC = AC + (BAC - EV) / SPI current
IEAC = AC + (BAC - EV) / (SPI * CPI)
IEAC = AC + (BAC - EV) / ((SPI * .20) + (CPI * .80))
IEAC = AC + (BAC - EV) / CPI cumulative x (x equals the cumulative of the last x
periods)
IEAC = AC + (BAC - EV) / Projected Average CPI to completion
Percent Complete: Percent Complete = 100 x (EV cumulative / BAC)
Percent Spent: Percent Spent = 100 x (AC cumulative / BAC (or EAC))
Schedule Variance (SV): SV = EV - PV
Schedule Variance % (SV %): SV% = 100 x (SV / PV)
Schedule Performance Index (SPI): SPI = EV / PV
To Complete Performance Index (TCPI): TCPI to EAC = Work Remaining / Cost
Remaining
TCPI EAC: = (BAC - EV) / (EAC – AC)
Variance at Complete (VAC): VAC = BAC – EAC
Variance at Complete % (VAC %): VAC % = 100 x (VAC / BAC)
Work Remaining: BAC - BCWP
SAMPLE Page 5
SIMPLE SAMPLE
EV: Earned Value (BCWP means Budgeted Cost for Work Performed) also
Accomplished Work
ETC: Estimate to Complete. The estimated cost to complete all budgeted work.
IEAC: Independent Estimate at Completion. Independent projected cost at the
completion of all budgeted work.
PV: Planned Value (BCWS means Budgeted Cost for Work Scheduled)
SV: Schedule Variance. The mathematical difference between Earned and Planned.
SPI: Schedule Performance Index. Earned divided by Planned.
TCPI: To Complete Performance Index. The cost efficiency factor to complete
budgeted work or to complete all work at the EAC value.
WR: Work Remaining. The difference between the budgeted value and work
accomplished.
Formulas:
Cost Performance Index (CPI): CPI = EV / AC
Cost Variance (CV): CV = EV - AC
Cost Variance % (CV %): CV% = 100 x (CV / EV)
Estimate at Completion (EAC): ACWP cumulative + (Work Remaining / The Average
Projected Cost Performance Index for work remaining)
Independent Estimate at Complete (IEAC): IEAC calculations are based on the use of a
Performance Index and should be so stated:
IEAC = AC cumulative + (BAC - EV cumulative)/ Performance Index
IEAC = AC + (BAC - EV) / CPI current
IEAC = AC + (BAC - EV) / SPI current
IEAC = AC + (BAC - EV) / (SPI * CPI)
IEAC = AC + (BAC - EV) / ((SPI * .20) + (CPI * .80))
IEAC = AC + (BAC - EV) / CPI cumulative x (x equals the cumulative of the last x
periods)
IEAC = AC + (BAC - EV) / Projected Average CPI to completion
Percent Complete: Percent Complete = 100 x (EV cumulative / BAC)
Percent Spent: Percent Spent = 100 x (AC cumulative / BAC (or EAC))
Schedule Variance (SV): SV = EV - PV
Schedule Variance % (SV %): SV% = 100 x (SV / PV)
Schedule Performance Index (SPI): SPI = EV / PV
To Complete Performance Index (TCPI): TCPI to EAC = Work Remaining / Cost
Remaining
TCPI EAC: = (BAC - EV) / (EAC – AC)
Variance at Complete (VAC): VAC = BAC – EAC
Variance at Complete % (VAC %): VAC % = 100 x (VAC / BAC)
Work Remaining: BAC - BCWP
SAMPLE Page 5

More Related Content

Similar to Earned Value Management Project Analysis

Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementBaroness PM
 
Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfCost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfNabeel Ahmad
 
L06 cost management
L06 cost managementL06 cost management
L06 cost managementAsa Chan
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptRedhaElhuni
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.pptProfDrAnbalaganChinn
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxsagarlesley
 
Earned value management
Earned value managementEarned value management
Earned value managementwhizkris
 
Earned value management
Earned value managementEarned value management
Earned value managementGautam Kumar
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value ManagementMatt Stehling
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisBECM, RUET, Bangladesh
 
Pm 8 cost_management
Pm 8 cost_managementPm 8 cost_management
Pm 8 cost_managementRadiant Minds
 
Pm 8 cost_management
Pm 8 cost_managementPm 8 cost_management
Pm 8 cost_managementRadiant Minds
 

Similar to Earned Value Management Project Analysis (20)

Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
 
Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfCost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdf
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
CCP_SEC4_Progress and Cost Control
CCP_SEC4_Progress and Cost ControlCCP_SEC4_Progress and Cost Control
CCP_SEC4_Progress and Cost Control
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
Earned value management
Earned value managementEarned value management
Earned value management
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Evm.calculations.Summary sheet
Evm.calculations.Summary sheetEvm.calculations.Summary sheet
Evm.calculations.Summary sheet
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Pm 8 cost_management
Pm 8 cost_managementPm 8 cost_management
Pm 8 cost_management
 
Pm 8 cost_management
Pm 8 cost_managementPm 8 cost_management
Pm 8 cost_management
 

More from Roger H. Mandel

Evm intro. slide deck pp 03 october 2018
Evm intro. slide deck pp 03 october 2018Evm intro. slide deck pp 03 october 2018
Evm intro. slide deck pp 03 october 2018Roger H. Mandel
 
Evm intro. slide deck 13 may 2018
Evm intro. slide deck 13 may 2018Evm intro. slide deck 13 may 2018
Evm intro. slide deck 13 may 2018Roger H. Mandel
 
Evm power point 25 august 2015 prams co (2)
Evm power point 25 august 2015 prams co (2)Evm power point 25 august 2015 prams co (2)
Evm power point 25 august 2015 prams co (2)Roger H. Mandel
 
Evm power point january 2017
Evm power point  january 2017Evm power point  january 2017
Evm power point january 2017Roger H. Mandel
 
Evm power point 25 august 2015 prams co (2)
Evm power point 25 august 2015 prams co (2)Evm power point 25 august 2015 prams co (2)
Evm power point 25 august 2015 prams co (2)Roger H. Mandel
 

More from Roger H. Mandel (6)

Evm intro. slide deck pp 03 october 2018
Evm intro. slide deck pp 03 october 2018Evm intro. slide deck pp 03 october 2018
Evm intro. slide deck pp 03 october 2018
 
Evm intro. slide deck 13 may 2018
Evm intro. slide deck 13 may 2018Evm intro. slide deck 13 may 2018
Evm intro. slide deck 13 may 2018
 
Evm power point 25 august 2015 prams co (2)
Evm power point 25 august 2015 prams co (2)Evm power point 25 august 2015 prams co (2)
Evm power point 25 august 2015 prams co (2)
 
Evm power point january 2017
Evm power point  january 2017Evm power point  january 2017
Evm power point january 2017
 
Evm power point 25 august 2015 prams co (2)
Evm power point 25 august 2015 prams co (2)Evm power point 25 august 2015 prams co (2)
Evm power point 25 august 2015 prams co (2)
 
Education January 2014
Education January 2014Education January 2014
Education January 2014
 

Recently uploaded

Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...Hasting Chen
 
Microsoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AIMicrosoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AITatiana Gurgel
 
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...henrik385807
 
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...NETWAYS
 
call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@vikas rana
 
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779Delhi Call girls
 
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024eCommerce Institute
 
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...NETWAYS
 
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...NETWAYS
 
Motivation and Theory Maslow and Murray pdf
Motivation and Theory Maslow and Murray pdfMotivation and Theory Maslow and Murray pdf
Motivation and Theory Maslow and Murray pdfakankshagupta7348026
 
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝soniya singh
 
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night EnjoyCall Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night EnjoyPooja Nehwal
 
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...NETWAYS
 
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...Kayode Fayemi
 
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls KolkataRussian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkataanamikaraghav4
 
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Salam Al-Karadaghi
 
Mohammad_Alnahdi_Oral_Presentation_Assignment.pptx
Mohammad_Alnahdi_Oral_Presentation_Assignment.pptxMohammad_Alnahdi_Oral_Presentation_Assignment.pptx
Mohammad_Alnahdi_Oral_Presentation_Assignment.pptxmohammadalnahdi22
 
George Lever - eCommerce Day Chile 2024
George Lever -  eCommerce Day Chile 2024George Lever -  eCommerce Day Chile 2024
George Lever - eCommerce Day Chile 2024eCommerce Institute
 
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...Sheetaleventcompany
 
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )Pooja Nehwal
 

Recently uploaded (20)

Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
 
Microsoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AIMicrosoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AI
 
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
 
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
 
call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@
 
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
 
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
 
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
 
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
 
Motivation and Theory Maslow and Murray pdf
Motivation and Theory Maslow and Murray pdfMotivation and Theory Maslow and Murray pdf
Motivation and Theory Maslow and Murray pdf
 
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
 
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night EnjoyCall Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
 
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
 
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
 
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls KolkataRussian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
 
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
 
Mohammad_Alnahdi_Oral_Presentation_Assignment.pptx
Mohammad_Alnahdi_Oral_Presentation_Assignment.pptxMohammad_Alnahdi_Oral_Presentation_Assignment.pptx
Mohammad_Alnahdi_Oral_Presentation_Assignment.pptx
 
George Lever - eCommerce Day Chile 2024
George Lever -  eCommerce Day Chile 2024George Lever -  eCommerce Day Chile 2024
George Lever - eCommerce Day Chile 2024
 
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
 
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
 

Earned Value Management Project Analysis

  • 1. SIMPLE SAMPLE MEMORANDUM ROGER H. MANDEL Rmandel@PramsCo.com Mobile #: 858-735-2038 Date: 30 April 2018 To: Program Management Subj.: EARNED VALUE PROJECT MANAGEMENT ANALYSIS REPORT, Data through 31 March 2018 1. Summary Status: a. Data indicates the performance changes, as shown on Figure #1, from 31 January 2017 to 31 March 2018 as follows: i. Percent scheduled to be completed at 68.02% ii. Percent complete 46.76%, about 22% behind schedule iii. Percent Spent of Budget at 64.39%, about 17.63% cost overrun iv. Percent spent of Latest Revised Estimate at 54.71% Figure #1 - 2,000,000 4,000,000 6,000,000 8,000,000 10,000,000 12,000,000 14,000,000 16,000,000 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 SIMPLE SAMPLE Budget $13.9M Planned $9.48M Schedule Variance $2.98M Cost Variance in $2.45M SAMPLE Page 1
  • 2. SIMPLE SAMPLE 2. Trends, as shown on Figure #2: a. With 15 months of data: i. Schedule performance changed from 69.3% to 68.6%. Cumulative SPI 0.686. ii. Cost performance changed from 75.2% to 72.6%. Cumulative CPI 0.726. iii. Schedule and Cost Performance has a negative trend as shown on Figure #2 below. Figure #2 0.400 0.500 0.600 0.700 0.800 0.900 1.000 1.100 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 CPI 0.726 SPI 0.686 SIMPLE SAMPLE Cumulative 3. Projections: a. The analyst projects a significant cost overrun due to the negative trends in cost performance. The Vendors Estimate at Completion (EAC) changed from a cost overrun of about $1.97 million to now more like $2.45 million over the current performance measurement baseline of $13.9 million. b. The significant trend data indicates a poor schedule performance cumulative to date at about 68.6%. That calculated for every 100 hours planned the progress is at 68.6 hours. The SPI is 0.686. c. The cumulative cost performance to date is at 72.6%. That calculated for every $100 dollars expended the contractor earns (accomplishes) $72.6 dollars’ worth of work. The CPI is 0.726. SAMPLE Page 2
  • 3. SIMPLE SAMPLE 4. Choice and Rationale: a. The worst-case projection for the scheduled completion date, for these efforts, will be missed by about 13 months. Scheduled completion date is stated as January 2019. Completion is projected to be March 2020. 5. Major Areas of Concern as shown on Figure #3: a. The behind schedule is shown as be being greater than 3 months and is projected to grow to, worst case at, 13 months. With only 15 months of data, the contractor is behind schedule by greater than 3 months, as show of Figure #3. b. Cost variance grew from -$1,970,000 to -$2,450,000. Figure #3 150,000 2,150,000 4,150,000 6,150,000 8,150,000 10,150,000 12,150,000 SIMPLE SAMPLE SV In Time Greater than 3 months 6. Exhibit as shown on Figure # 4: a. Analyst’s (Worst Case) Estimated Cost at Completion is $23.3 M. b. Contractor’s Estimated Cost at Completion at $16.4 M. c. Budget at $13.9 M. d. Planned performance to date is $9.48 M. e. Expended to date is $9.95 M. f. Earned to date is $6.5 M. g. Currently at least 3+ months behind schedule. SAMPLE Page 3
  • 4. SIMPLE SAMPLE h. Cost overrun to date is $2.45 M. Figure #4 Program: As of: 31-Mar-2018 Planned Earned Expended SV CV Budget Vendor's EAC $9,480,000 $6,500,000 $8,950,000 ($2,980,000) ($2,450,000) $13,900,000 $16,350,000 Percent Complete Work Remaining Cumulative CPI 6 Month Moving Average 3 Month Moving Average Independent Projection Worst Case Completed 15 Reporting Periods 0.726 0.771 0.608 0.304 Independent $10,189,231 $9,592,363 $12,164,384 $24,342,105 Projection $19,139,231 $18,542,363 $21,114,384 $33,292,105 Worst Case 2.19% 3 MMA Current Work Remaining 4.38% 3.74% 53.24% Independent Projected Completion Date 29-Mar-2020 31-Jan-2019 $24,342,105 $16,942,105 $33,292,105 Best Case $19,139,231 Most likely $26,215,668 Worst Case $33,292,105 Independent EAC Project Cost Overrun Projection of Average Earning Per Month for Remaining Work Percent Complete Cost of Work Remaining To Complete Performance Index 46.76% Independent EAC $7,400,000 Contract Completion Date Independent Total Estimated Cost to Go Dollars as StatedSIMPLE SAMPLE Copy to: The Essential EVM Formulas Acronyms: AC: Actual Cost (ACWP means Actual Cost of Work Performed). The cost for the work performed. ACWP: Actual Cost of Work Performed. BAC: Budgeted at Completion, also Authorized Budget also Total Planned Value. BCWP: Budget Cost for Work Performed. Completed (accomplished) budgeted work. BCWS: Budget Cost for Work Scheduled. The cost for the work performed. CPI: Cost Performance Index. Earned divided by Expended. CV: Cost Variance. The mathematical difference between Earned and Expended. EAC: Estimate at Completion SAMPLE Page 4
  • 5. SIMPLE SAMPLE EV: Earned Value (BCWP means Budgeted Cost for Work Performed) also Accomplished Work ETC: Estimate to Complete. The estimated cost to complete all budgeted work. IEAC: Independent Estimate at Completion. Independent projected cost at the completion of all budgeted work. PV: Planned Value (BCWS means Budgeted Cost for Work Scheduled) SV: Schedule Variance. The mathematical difference between Earned and Planned. SPI: Schedule Performance Index. Earned divided by Planned. TCPI: To Complete Performance Index. The cost efficiency factor to complete budgeted work or to complete all work at the EAC value. WR: Work Remaining. The difference between the budgeted value and work accomplished. Formulas: Cost Performance Index (CPI): CPI = EV / AC Cost Variance (CV): CV = EV - AC Cost Variance % (CV %): CV% = 100 x (CV / EV) Estimate at Completion (EAC): ACWP cumulative + (Work Remaining / The Average Projected Cost Performance Index for work remaining) Independent Estimate at Complete (IEAC): IEAC calculations are based on the use of a Performance Index and should be so stated: IEAC = AC cumulative + (BAC - EV cumulative)/ Performance Index IEAC = AC + (BAC - EV) / CPI current IEAC = AC + (BAC - EV) / SPI current IEAC = AC + (BAC - EV) / (SPI * CPI) IEAC = AC + (BAC - EV) / ((SPI * .20) + (CPI * .80)) IEAC = AC + (BAC - EV) / CPI cumulative x (x equals the cumulative of the last x periods) IEAC = AC + (BAC - EV) / Projected Average CPI to completion Percent Complete: Percent Complete = 100 x (EV cumulative / BAC) Percent Spent: Percent Spent = 100 x (AC cumulative / BAC (or EAC)) Schedule Variance (SV): SV = EV - PV Schedule Variance % (SV %): SV% = 100 x (SV / PV) Schedule Performance Index (SPI): SPI = EV / PV To Complete Performance Index (TCPI): TCPI to EAC = Work Remaining / Cost Remaining TCPI EAC: = (BAC - EV) / (EAC – AC) Variance at Complete (VAC): VAC = BAC – EAC Variance at Complete % (VAC %): VAC % = 100 x (VAC / BAC) Work Remaining: BAC - BCWP SAMPLE Page 5
  • 6. SIMPLE SAMPLE EV: Earned Value (BCWP means Budgeted Cost for Work Performed) also Accomplished Work ETC: Estimate to Complete. The estimated cost to complete all budgeted work. IEAC: Independent Estimate at Completion. Independent projected cost at the completion of all budgeted work. PV: Planned Value (BCWS means Budgeted Cost for Work Scheduled) SV: Schedule Variance. The mathematical difference between Earned and Planned. SPI: Schedule Performance Index. Earned divided by Planned. TCPI: To Complete Performance Index. The cost efficiency factor to complete budgeted work or to complete all work at the EAC value. WR: Work Remaining. The difference between the budgeted value and work accomplished. Formulas: Cost Performance Index (CPI): CPI = EV / AC Cost Variance (CV): CV = EV - AC Cost Variance % (CV %): CV% = 100 x (CV / EV) Estimate at Completion (EAC): ACWP cumulative + (Work Remaining / The Average Projected Cost Performance Index for work remaining) Independent Estimate at Complete (IEAC): IEAC calculations are based on the use of a Performance Index and should be so stated: IEAC = AC cumulative + (BAC - EV cumulative)/ Performance Index IEAC = AC + (BAC - EV) / CPI current IEAC = AC + (BAC - EV) / SPI current IEAC = AC + (BAC - EV) / (SPI * CPI) IEAC = AC + (BAC - EV) / ((SPI * .20) + (CPI * .80)) IEAC = AC + (BAC - EV) / CPI cumulative x (x equals the cumulative of the last x periods) IEAC = AC + (BAC - EV) / Projected Average CPI to completion Percent Complete: Percent Complete = 100 x (EV cumulative / BAC) Percent Spent: Percent Spent = 100 x (AC cumulative / BAC (or EAC)) Schedule Variance (SV): SV = EV - PV Schedule Variance % (SV %): SV% = 100 x (SV / PV) Schedule Performance Index (SPI): SPI = EV / PV To Complete Performance Index (TCPI): TCPI to EAC = Work Remaining / Cost Remaining TCPI EAC: = (BAC - EV) / (EAC – AC) Variance at Complete (VAC): VAC = BAC – EAC Variance at Complete % (VAC %): VAC % = 100 x (VAC / BAC) Work Remaining: BAC - BCWP SAMPLE Page 5