SlideShare a Scribd company logo
1 of 48
Download to read offline
LIVING WITH LIDLIVING WITH LID
Site Design Implications of theg p
New C.3 Provisions
Mike Campbell, AICP, CPSWQ
April 23 2010April 23, 2010
Presentation AgendaPresentation Agenda
NPDES P it / P i i C 3• NPDES Permit / Provision C.3
• What Is LID?
– Definitions, Local Examples
• Case Studies / Alternative Designs• Case Studies / Alternative Designs
Using LID
R i l S l ti• Regional Solutions
• Conclusion
New NPDES Permits!New NPDES Permits!
• General Construction Permit –
adopted 9/2/09, effective 7/1/10, state-
wide, construction only.
• Municipal Regional Permit –
adopted 10/14/09, Bay Area MS4p y
dischargers only.
Municipal Regional
Permit (MRP)Permit (MRP)
Significant changes toSignificant changes to
Provision C.3 include:
– Low Impact Development
treatment controls required
for all new regulated public
d i t j t
HMH
and private projects
– Project size threshold forj
sites subject to
hydromodification controls
reduced to 1 acre (from 20(
acres)
Provision C 3 bii(1): Regulated Projects –Provision C.3.bii(1): Regulated Projects
Special Land Use Categories
- 10 000 s f threshold to be reduced to 5 000 s f10,000 s.f. threshold to be reduced to 5,000 s.f.
for auto service facilities, retail gasoline outlets,
restaurants & uncovered parking lotsrestaurants & uncovered parking lots
I l t ti d t 12/1/11- Implementation date: 12/1/11
Provision C 3 e: Alternative ComplianceProvision C.3.e: Alternative Compliance
O f ff- Option 1: treat a portion of the runoff with LID measures
onsite, and treat the remaining runoff with LID measures
at an offsite project in the same watershedat an offsite project in the same watershed
Option 2: treat a portion of the runoff with LID measures- Option 2: treat a portion of the runoff with LID measures
onsite, and provide in-lieu fees to treat the remaining
runoff with LID measures at a Regional Project in theg j
same watershed
Provision C 3 c: Low Impact DevelopmentProvision C.3.c: Low Impact Development
(LID)
- States that every regulated project must treat runoff with
100% LID measures onsite or at a joint treatment facility100% LID measures onsite or at a joint treatment facility
- LID measures defined as harvesting & re-use infiltrationLID measures defined as harvesting & re use, infiltration,
evapotranspiration, or biotreatment
Biotreatment can be considered only if it is infeasible to
implement harvesting & re-use, infiltration or evapotranspiration
at project siteat project site
- Implementation date: 12/1/11p
What is Low Impact Development (LID)?
• Goal is to reduce runoff and mimic a site’s
predevelopment hydrology by minimizing disturbedp p y gy y g
areas and impervious cover and then infiltrating, storing,
detaining, evapotranspiring, and/or biotreating
stormwater runoff close to its sourcestormwater runoff close to its source.
• Create functional and appealing site drainage that treats
stormwater as a resource rather than a waste product.p
• Practices include measures such as rain barrels and
cisterns, green roofs, permeable pavement, preserving
d l d d bi t t t th h iundeveloped open space, and biotreatment through rain
gardens, bioretention units, bioswales, and planter/tree
boxes.bo es
Issues to Manage for Successful LID
Implementation (Key Ingredients)Implementation (Key Ingredients)
• Local Policies – density and land useLocal Policies density and land use
• Public vs. Private Runoff
• Site Constraints – soil and groundwater
conditionsconditions
• Grading and Hydraulicsg y
• Landscape Design, Installation &
Maintenance
Local (pre-LID) treatment control examples:(p ) p
Grass Swale
I filt ti T hInfiltration Trench
Manhole Media Filter
Inlet Filter
Media Filter Vault
Recent examples of LID controls incorporatedp p
in local projects :
Green Roofs
Recent examples of LID controls incorporatedp p
in local projects :
Dual-use Infiltration Basin
Pervious Paving in Public
Park (interlocking pavers,
Pervious Paving in Parking
Lot (interlocking pavers)( g p ,
decomposed granite)
( g p )
Bioretention Area Adjacent to
Commercial Parking Lotg
Bioretention Cells Adjacent
to Recreational Facility
Parking LotParking Lot
Design Methodology for Volume-Based LID
Treatment Facilities
• Size facility by calculating storage capacity of facility as a function of rain gage
Treatment Facilities
y y g g p y y g g
data, unit basin storage, and size of drainage area
Unit basin storage: a function of soil type, % imperviousness & water quality storm size
• Design grading to convey surface runoff flows from paved surfaces to facility
• Verify surface slopes, pipe slopes, invert elevations to ensure system worksVerify surface slopes, pipe slopes, invert elevations to ensure system works
hydraulically
• Design drain down for the facility – must comply with local requirements (72 hrs.
t )typ.)
Goal: Look for ways to reduce drainage
i d i i di tarea size, reduce imperviousness, divert
flows to landscaping and create smaller
micro-treatment areas
Case Study 1 – Townhouse Development
2006 Approved Plan 2011 Plans
• Swales • Pervious concreteSwales
G
Pervious concrete
I filt ti b i• Grass pavers • Infiltration basins
• Below-ground
media filter vault
• Bioretention cells
2006 Approved Site Plan
2006 Approved Stormwater Control Plan
(Includes use of mechanical treatment and vegetative swales)
2006 Design Features & Treatment Controls
Swale in ParkBelow Ground Media Filter Swale in ParkBelow Ground Media Filter
Vault
Turf Pavers
Disconnected Downspouts
Alley Swales
2011 Stormwater Control Plan – Solution 1
(Includes use of pervious concrete, infiltration basins with pumps)(Includes use of pervious concrete, infiltration basins with pumps)
2011 Design Features & Pavement Options
Turf PaversPervious Concrete (alleys and parking)
Pervious Pavers (parking)
Pervious Pavers (for walks &
pedestrian areas)
Pervious Concrete Interlocking Pavers
Pervious
Pavement
Sections
Turf Pavers
Dual use park – infiltration basin Infiltration basin
Bioretention Cells (alley
drainage areas)
Infiltration Basins (open
space areas)
Infiltration Basin
(Portland Stormwater Manual)( )
Dual Use Basin – Los Gatos
2011 Stormwater Control Plan – Solution 2
(Includes use of pervious concrete, basins with pumps, and bioretention cell)(Includes use of pervious concrete, basins with pumps, and bioretention cell)
Bi i C llBioretention Cell (HMH)
Case Study 2 – Mixed Use Transit Oriented
DevelopmentDevelopment
2009 Approved Plan 2011 Plan
• Below-ground media
filter vault
• Below-ground
storage tanks
2009 Approved Plan 2011 Plan
filter vault
• Manhole media filter
storage tanks
• Green roofs• Manhole media filter
Grass pa ers
• Green roofs
Tree filters• Grass pavers • Tree filters
Bi t ti• Bioretention
P i t• Pervious concrete
2009 Approved Site Plan
2009 Approved Stormwater Management Plan
(Includes use of mechanical treatment and grass pavers)(Includes use of mechanical treatment and grass pavers)
2009 Design Features & Treatment Controls
Turf PaversMedia Filter Vault
Manhole Media
FilterFilter
2011 Stormwater Management Plan – Solution 1
(Includes use of pervious concrete and underground storage facilities)(Includes use of pervious concrete and underground storage facilities)
2011 Design Features & Treatment Controls
Solution 1Solution 1
Pervious Concrete
Underground Storage
Pervious Concrete
Underground Storage
Containers
2011 Stormwater Management Plan – Solution 2
(Includes use of pervious concrete, underground storage, ext. green roof, bioretention
cells & tree filter)
2011 Design Features & Treatment Controls
Solution 2Solution 2
Extensive Green Roof
Bioretention Cell
Tree Filters
2011 Stormwater Management Plan – Solution 3
(Includes use of pervious concrete, ext. & int.green roof, bioretention cells & tree filter)
2011 Design Features & Treatment Controls
Solution 3Solution 3
Intensive Green Roof
LID Solutions Report Card
Grade - BGrade - A Grade - B
Grade - C Grade - D
Regional ProjectsRegional Projects
• None currently available• None currently available
• Necessary for Alternative Compliance
(Provision C.3.e)
• HMH working with City of San Jose to
develop strategy (identify potential sites,
integrate with appropriate development
projects)
Potential Regional Facility Example
Los Angeles Regional Solution
( $13 / gallon of untreated runoff
per site)
Take Home Points
L - Localized, landscaped-based
runoff management
I - Impervious surface reduction
D - Design creativity!
#1 Hampton Park#1 - Hampton Park
(1097 Rock Ave.)
HMH (1570 Oakland Rd.)#2 - Lowe’s
(775 Ridder Park Dr )(775 Ridder Park Dr.)
#3 - Modern Ice
(652 Luna Park Dr.)

More Related Content

What's hot

2011 6 14 Home Builders of MD Environmental Site Design Introduction
2011 6 14 Home Builders of MD Environmental Site Design Introduction2011 6 14 Home Builders of MD Environmental Site Design Introduction
2011 6 14 Home Builders of MD Environmental Site Design IntroductionTheodore Scott
 
Policy recommendations and considerations on peatlands & REDD+ for SBSTA
Policy recommendations and considerations on peatlands & REDD+ for SBSTAPolicy recommendations and considerations on peatlands & REDD+ for SBSTA
Policy recommendations and considerations on peatlands & REDD+ for SBSTAWetlands International
 
Caitriona Collins, IES/IBN Discussion Meeting: Waste soils on the island of I...
Caitriona Collins, IES/IBN Discussion Meeting: Waste soils on the island of I...Caitriona Collins, IES/IBN Discussion Meeting: Waste soils on the island of I...
Caitriona Collins, IES/IBN Discussion Meeting: Waste soils on the island of I...IES / IAQM
 
20150317 final-cs-ham-32 quincy
20150317 final-cs-ham-32 quincy20150317 final-cs-ham-32 quincy
20150317 final-cs-ham-32 quincyAnilAbdu1
 
Certifcation of Building Using GRIHA Rating System
Certifcation of Building Using GRIHA Rating SystemCertifcation of Building Using GRIHA Rating System
Certifcation of Building Using GRIHA Rating SystemSandeep Jain
 
Build it Green Landscape Points
Build it Green Landscape PointsBuild it Green Landscape Points
Build it Green Landscape Pointsmaclandscape
 
Chicago Green Alley Handbook, 2010
Chicago Green Alley Handbook, 2010Chicago Green Alley Handbook, 2010
Chicago Green Alley Handbook, 2010Daniel X. O'Neil
 
GRIHA Rating for MITS college compus
GRIHA Rating for MITS college compus GRIHA Rating for MITS college compus
GRIHA Rating for MITS college compus Raviteja Mukkara
 
Building as a Teaching Tool: School of Communication and Media at Montclair S...
Building as a Teaching Tool: School of Communication and Media at Montclair S...Building as a Teaching Tool: School of Communication and Media at Montclair S...
Building as a Teaching Tool: School of Communication and Media at Montclair S...Frank Cunha
 
Giới thiệu Hệ thống tiêu chí công trình xanh LOTUS BIO cho toà nhà đang vận h...
Giới thiệu Hệ thống tiêu chí công trình xanh LOTUS BIO cho toà nhà đang vận h...Giới thiệu Hệ thống tiêu chí công trình xanh LOTUS BIO cho toà nhà đang vận h...
Giới thiệu Hệ thống tiêu chí công trình xanh LOTUS BIO cho toà nhà đang vận h...Vietnam Green Building Council
 
Elgin Country Estate Project Summary as on 20160606
Elgin Country Estate Project Summary as on 20160606 Elgin Country Estate Project Summary as on 20160606
Elgin Country Estate Project Summary as on 20160606 John M Riggs
 
MBA439:Savusavu port CBA
MBA439:Savusavu port CBAMBA439:Savusavu port CBA
MBA439:Savusavu port CBATanielaSila1
 
Griha presentation. for project managers..
Griha presentation. for project managers..Griha presentation. for project managers..
Griha presentation. for project managers..Devyani Dayal
 
George Leahy Resume
George Leahy  ResumeGeorge Leahy  Resume
George Leahy ResumeGeorge Leahy
 
Moffett RAB Site 25, September 9, 2010
Moffett RAB Site 25, September 9, 2010Moffett RAB Site 25, September 9, 2010
Moffett RAB Site 25, September 9, 2010Steve Williams
 
26 gunter deep borehole disposal
26 gunter deep borehole disposal26 gunter deep borehole disposal
26 gunter deep borehole disposalleann_mays
 

What's hot (20)

2011 6 14 Home Builders of MD Environmental Site Design Introduction
2011 6 14 Home Builders of MD Environmental Site Design Introduction2011 6 14 Home Builders of MD Environmental Site Design Introduction
2011 6 14 Home Builders of MD Environmental Site Design Introduction
 
Policy recommendations and considerations on peatlands & REDD+ for SBSTA
Policy recommendations and considerations on peatlands & REDD+ for SBSTAPolicy recommendations and considerations on peatlands & REDD+ for SBSTA
Policy recommendations and considerations on peatlands & REDD+ for SBSTA
 
Caitriona Collins, IES/IBN Discussion Meeting: Waste soils on the island of I...
Caitriona Collins, IES/IBN Discussion Meeting: Waste soils on the island of I...Caitriona Collins, IES/IBN Discussion Meeting: Waste soils on the island of I...
Caitriona Collins, IES/IBN Discussion Meeting: Waste soils on the island of I...
 
20150317 final-cs-ham-32 quincy
20150317 final-cs-ham-32 quincy20150317 final-cs-ham-32 quincy
20150317 final-cs-ham-32 quincy
 
GREEN BUILDING
GREEN BUILDING GREEN BUILDING
GREEN BUILDING
 
The Process of Building A Green Project
The Process of Building A Green ProjectThe Process of Building A Green Project
The Process of Building A Green Project
 
Certifcation of Building Using GRIHA Rating System
Certifcation of Building Using GRIHA Rating SystemCertifcation of Building Using GRIHA Rating System
Certifcation of Building Using GRIHA Rating System
 
Build it Green Landscape Points
Build it Green Landscape PointsBuild it Green Landscape Points
Build it Green Landscape Points
 
Chicago Green Alley Handbook, 2010
Chicago Green Alley Handbook, 2010Chicago Green Alley Handbook, 2010
Chicago Green Alley Handbook, 2010
 
GRIHA Rating for MITS college compus
GRIHA Rating for MITS college compus GRIHA Rating for MITS college compus
GRIHA Rating for MITS college compus
 
Building as a Teaching Tool: School of Communication and Media at Montclair S...
Building as a Teaching Tool: School of Communication and Media at Montclair S...Building as a Teaching Tool: School of Communication and Media at Montclair S...
Building as a Teaching Tool: School of Communication and Media at Montclair S...
 
Giới thiệu Hệ thống tiêu chí công trình xanh LOTUS BIO cho toà nhà đang vận h...
Giới thiệu Hệ thống tiêu chí công trình xanh LOTUS BIO cho toà nhà đang vận h...Giới thiệu Hệ thống tiêu chí công trình xanh LOTUS BIO cho toà nhà đang vận h...
Giới thiệu Hệ thống tiêu chí công trình xanh LOTUS BIO cho toà nhà đang vận h...
 
Cec application form_a
Cec application form_aCec application form_a
Cec application form_a
 
Elgin Country Estate Project Summary as on 20160606
Elgin Country Estate Project Summary as on 20160606 Elgin Country Estate Project Summary as on 20160606
Elgin Country Estate Project Summary as on 20160606
 
MBA439:Savusavu port CBA
MBA439:Savusavu port CBAMBA439:Savusavu port CBA
MBA439:Savusavu port CBA
 
Griha presentation. for project managers..
Griha presentation. for project managers..Griha presentation. for project managers..
Griha presentation. for project managers..
 
George Leahy Resume
George Leahy  ResumeGeorge Leahy  Resume
George Leahy Resume
 
Moffett RAB Site 25, September 9, 2010
Moffett RAB Site 25, September 9, 2010Moffett RAB Site 25, September 9, 2010
Moffett RAB Site 25, September 9, 2010
 
26 gunter deep borehole disposal
26 gunter deep borehole disposal26 gunter deep borehole disposal
26 gunter deep borehole disposal
 
21 Design Work Shop 7.30.2009
21 Design Work Shop 7.30.200921 Design Work Shop 7.30.2009
21 Design Work Shop 7.30.2009
 

Similar to APR 23 10 LIVING WITH LID [Compatibility Mode]

Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...
Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...
Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...Fu Michael Justin
 
1.-Landfill-basics.pdf
1.-Landfill-basics.pdf1.-Landfill-basics.pdf
1.-Landfill-basics.pdfMartinP31
 
Commercial sites and the delivery of sustainable drainage
Commercial sites and the delivery of sustainable drainageCommercial sites and the delivery of sustainable drainage
Commercial sites and the delivery of sustainable drainageACO Technologies plc
 
Himkaar Singh Diepsloot SW Report
Himkaar Singh Diepsloot SW ReportHimkaar Singh Diepsloot SW Report
Himkaar Singh Diepsloot SW ReportHimkaar Singh
 
Leed green associate pool a - answer
Leed green associate    pool a - answer Leed green associate    pool a - answer
Leed green associate pool a - answer Bilal Mohamed
 
Road development projects.
Road development projects.Road development projects.
Road development projects.Abhishek Rajput
 
Lisa stormcon presentation number one ieca
Lisa stormcon presentation number one iecaLisa stormcon presentation number one ieca
Lisa stormcon presentation number one iecaLisa Nisenson
 
IRJET - Reaearch on Methods of Controlling Soil Erosion
IRJET - Reaearch on Methods of Controlling Soil ErosionIRJET - Reaearch on Methods of Controlling Soil Erosion
IRJET - Reaearch on Methods of Controlling Soil ErosionIRJET Journal
 
EUCI Presentation: "Are You Prepared to Close Your Ash Ponds?" by Kent Nilsson
EUCI Presentation: "Are You Prepared to Close Your Ash Ponds?" by Kent NilssonEUCI Presentation: "Are You Prepared to Close Your Ash Ponds?" by Kent Nilsson
EUCI Presentation: "Are You Prepared to Close Your Ash Ponds?" by Kent NilssonTRC Companies, Inc.
 
Intent: The Real LEED Requirements
Intent: The Real LEED RequirementsIntent: The Real LEED Requirements
Intent: The Real LEED RequirementsScott DeGaro
 
IRJET - Reaearch on Erosion Controlling Methods
IRJET - Reaearch on Erosion Controlling MethodsIRJET - Reaearch on Erosion Controlling Methods
IRJET - Reaearch on Erosion Controlling MethodsIRJET Journal
 
Urban Runoff - Storm Water 101
Urban Runoff - Storm Water 101Urban Runoff - Storm Water 101
Urban Runoff - Storm Water 101Greg Gearheart
 

Similar to APR 23 10 LIVING WITH LID [Compatibility Mode] (20)

Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...
Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...
Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...
 
The permitting advantages and challenges of green infrastructure
The permitting advantages and challenges of green infrastructureThe permitting advantages and challenges of green infrastructure
The permitting advantages and challenges of green infrastructure
 
Eia procedures
Eia proceduresEia procedures
Eia procedures
 
1.-Landfill-basics.pdf
1.-Landfill-basics.pdf1.-Landfill-basics.pdf
1.-Landfill-basics.pdf
 
Commercial sites and the delivery of sustainable drainage
Commercial sites and the delivery of sustainable drainageCommercial sites and the delivery of sustainable drainage
Commercial sites and the delivery of sustainable drainage
 
green streets_richards
green streets_richardsgreen streets_richards
green streets_richards
 
Himkaar Singh Diepsloot SW Report
Himkaar Singh Diepsloot SW ReportHimkaar Singh Diepsloot SW Report
Himkaar Singh Diepsloot SW Report
 
Leed green associate pool a - answer
Leed green associate    pool a - answer Leed green associate    pool a - answer
Leed green associate pool a - answer
 
Road development projects.
Road development projects.Road development projects.
Road development projects.
 
Lisa stormcon presentation number one ieca
Lisa stormcon presentation number one iecaLisa stormcon presentation number one ieca
Lisa stormcon presentation number one ieca
 
IRJET - Reaearch on Methods of Controlling Soil Erosion
IRJET - Reaearch on Methods of Controlling Soil ErosionIRJET - Reaearch on Methods of Controlling Soil Erosion
IRJET - Reaearch on Methods of Controlling Soil Erosion
 
MAPD 2010 - Creating the box
MAPD 2010 - Creating the boxMAPD 2010 - Creating the box
MAPD 2010 - Creating the box
 
Liddesignandanalysis
LiddesignandanalysisLiddesignandanalysis
Liddesignandanalysis
 
EUCI Presentation: "Are You Prepared to Close Your Ash Ponds?" by Kent Nilsson
EUCI Presentation: "Are You Prepared to Close Your Ash Ponds?" by Kent NilssonEUCI Presentation: "Are You Prepared to Close Your Ash Ponds?" by Kent Nilsson
EUCI Presentation: "Are You Prepared to Close Your Ash Ponds?" by Kent Nilsson
 
Intent: The Real LEED Requirements
Intent: The Real LEED RequirementsIntent: The Real LEED Requirements
Intent: The Real LEED Requirements
 
IRJET - Reaearch on Erosion Controlling Methods
IRJET - Reaearch on Erosion Controlling MethodsIRJET - Reaearch on Erosion Controlling Methods
IRJET - Reaearch on Erosion Controlling Methods
 
Lawrence Park PIC 3 slides
Lawrence Park PIC 3 slidesLawrence Park PIC 3 slides
Lawrence Park PIC 3 slides
 
Urban Runoff - Storm Water 101
Urban Runoff - Storm Water 101Urban Runoff - Storm Water 101
Urban Runoff - Storm Water 101
 
Low impact development_coupled_with_floodplain_mitigation
Low impact development_coupled_with_floodplain_mitigationLow impact development_coupled_with_floodplain_mitigation
Low impact development_coupled_with_floodplain_mitigation
 
Area 38 pic 1 final presentation
Area 38 pic 1   final presentationArea 38 pic 1   final presentation
Area 38 pic 1 final presentation
 

APR 23 10 LIVING WITH LID [Compatibility Mode]

  • 1. LIVING WITH LIDLIVING WITH LID Site Design Implications of theg p New C.3 Provisions Mike Campbell, AICP, CPSWQ April 23 2010April 23, 2010
  • 2. Presentation AgendaPresentation Agenda NPDES P it / P i i C 3• NPDES Permit / Provision C.3 • What Is LID? – Definitions, Local Examples • Case Studies / Alternative Designs• Case Studies / Alternative Designs Using LID R i l S l ti• Regional Solutions • Conclusion
  • 3. New NPDES Permits!New NPDES Permits! • General Construction Permit – adopted 9/2/09, effective 7/1/10, state- wide, construction only. • Municipal Regional Permit – adopted 10/14/09, Bay Area MS4p y dischargers only.
  • 4. Municipal Regional Permit (MRP)Permit (MRP) Significant changes toSignificant changes to Provision C.3 include: – Low Impact Development treatment controls required for all new regulated public d i t j t HMH and private projects – Project size threshold forj sites subject to hydromodification controls reduced to 1 acre (from 20( acres)
  • 5. Provision C 3 bii(1): Regulated Projects –Provision C.3.bii(1): Regulated Projects Special Land Use Categories - 10 000 s f threshold to be reduced to 5 000 s f10,000 s.f. threshold to be reduced to 5,000 s.f. for auto service facilities, retail gasoline outlets, restaurants & uncovered parking lotsrestaurants & uncovered parking lots I l t ti d t 12/1/11- Implementation date: 12/1/11
  • 6. Provision C 3 e: Alternative ComplianceProvision C.3.e: Alternative Compliance O f ff- Option 1: treat a portion of the runoff with LID measures onsite, and treat the remaining runoff with LID measures at an offsite project in the same watershedat an offsite project in the same watershed Option 2: treat a portion of the runoff with LID measures- Option 2: treat a portion of the runoff with LID measures onsite, and provide in-lieu fees to treat the remaining runoff with LID measures at a Regional Project in theg j same watershed
  • 7. Provision C 3 c: Low Impact DevelopmentProvision C.3.c: Low Impact Development (LID) - States that every regulated project must treat runoff with 100% LID measures onsite or at a joint treatment facility100% LID measures onsite or at a joint treatment facility - LID measures defined as harvesting & re-use infiltrationLID measures defined as harvesting & re use, infiltration, evapotranspiration, or biotreatment Biotreatment can be considered only if it is infeasible to implement harvesting & re-use, infiltration or evapotranspiration at project siteat project site - Implementation date: 12/1/11p
  • 8. What is Low Impact Development (LID)? • Goal is to reduce runoff and mimic a site’s predevelopment hydrology by minimizing disturbedp p y gy y g areas and impervious cover and then infiltrating, storing, detaining, evapotranspiring, and/or biotreating stormwater runoff close to its sourcestormwater runoff close to its source. • Create functional and appealing site drainage that treats stormwater as a resource rather than a waste product.p • Practices include measures such as rain barrels and cisterns, green roofs, permeable pavement, preserving d l d d bi t t t th h iundeveloped open space, and biotreatment through rain gardens, bioretention units, bioswales, and planter/tree boxes.bo es
  • 9. Issues to Manage for Successful LID Implementation (Key Ingredients)Implementation (Key Ingredients) • Local Policies – density and land useLocal Policies density and land use • Public vs. Private Runoff • Site Constraints – soil and groundwater conditionsconditions • Grading and Hydraulicsg y • Landscape Design, Installation & Maintenance
  • 10. Local (pre-LID) treatment control examples:(p ) p Grass Swale I filt ti T hInfiltration Trench
  • 11. Manhole Media Filter Inlet Filter Media Filter Vault
  • 12. Recent examples of LID controls incorporatedp p in local projects : Green Roofs
  • 13. Recent examples of LID controls incorporatedp p in local projects : Dual-use Infiltration Basin
  • 14. Pervious Paving in Public Park (interlocking pavers, Pervious Paving in Parking Lot (interlocking pavers)( g p , decomposed granite) ( g p )
  • 15. Bioretention Area Adjacent to Commercial Parking Lotg Bioretention Cells Adjacent to Recreational Facility Parking LotParking Lot
  • 16. Design Methodology for Volume-Based LID Treatment Facilities • Size facility by calculating storage capacity of facility as a function of rain gage Treatment Facilities y y g g p y y g g data, unit basin storage, and size of drainage area Unit basin storage: a function of soil type, % imperviousness & water quality storm size • Design grading to convey surface runoff flows from paved surfaces to facility • Verify surface slopes, pipe slopes, invert elevations to ensure system worksVerify surface slopes, pipe slopes, invert elevations to ensure system works hydraulically • Design drain down for the facility – must comply with local requirements (72 hrs. t )typ.) Goal: Look for ways to reduce drainage i d i i di tarea size, reduce imperviousness, divert flows to landscaping and create smaller micro-treatment areas
  • 17. Case Study 1 – Townhouse Development 2006 Approved Plan 2011 Plans • Swales • Pervious concreteSwales G Pervious concrete I filt ti b i• Grass pavers • Infiltration basins • Below-ground media filter vault • Bioretention cells
  • 19. 2006 Approved Stormwater Control Plan (Includes use of mechanical treatment and vegetative swales)
  • 20. 2006 Design Features & Treatment Controls Swale in ParkBelow Ground Media Filter Swale in ParkBelow Ground Media Filter Vault Turf Pavers
  • 22. 2011 Stormwater Control Plan – Solution 1 (Includes use of pervious concrete, infiltration basins with pumps)(Includes use of pervious concrete, infiltration basins with pumps)
  • 23. 2011 Design Features & Pavement Options Turf PaversPervious Concrete (alleys and parking) Pervious Pavers (parking) Pervious Pavers (for walks & pedestrian areas)
  • 24. Pervious Concrete Interlocking Pavers Pervious Pavement Sections Turf Pavers
  • 25. Dual use park – infiltration basin Infiltration basin Bioretention Cells (alley drainage areas) Infiltration Basins (open space areas)
  • 26. Infiltration Basin (Portland Stormwater Manual)( ) Dual Use Basin – Los Gatos
  • 27. 2011 Stormwater Control Plan – Solution 2 (Includes use of pervious concrete, basins with pumps, and bioretention cell)(Includes use of pervious concrete, basins with pumps, and bioretention cell)
  • 28. Bi i C llBioretention Cell (HMH)
  • 29. Case Study 2 – Mixed Use Transit Oriented DevelopmentDevelopment 2009 Approved Plan 2011 Plan • Below-ground media filter vault • Below-ground storage tanks 2009 Approved Plan 2011 Plan filter vault • Manhole media filter storage tanks • Green roofs• Manhole media filter Grass pa ers • Green roofs Tree filters• Grass pavers • Tree filters Bi t ti• Bioretention P i t• Pervious concrete
  • 31.
  • 32.
  • 33. 2009 Approved Stormwater Management Plan (Includes use of mechanical treatment and grass pavers)(Includes use of mechanical treatment and grass pavers)
  • 34. 2009 Design Features & Treatment Controls Turf PaversMedia Filter Vault Manhole Media FilterFilter
  • 35. 2011 Stormwater Management Plan – Solution 1 (Includes use of pervious concrete and underground storage facilities)(Includes use of pervious concrete and underground storage facilities)
  • 36. 2011 Design Features & Treatment Controls Solution 1Solution 1 Pervious Concrete Underground Storage Pervious Concrete Underground Storage Containers
  • 37. 2011 Stormwater Management Plan – Solution 2 (Includes use of pervious concrete, underground storage, ext. green roof, bioretention cells & tree filter)
  • 38. 2011 Design Features & Treatment Controls Solution 2Solution 2 Extensive Green Roof Bioretention Cell
  • 40. 2011 Stormwater Management Plan – Solution 3 (Includes use of pervious concrete, ext. & int.green roof, bioretention cells & tree filter)
  • 41. 2011 Design Features & Treatment Controls Solution 3Solution 3 Intensive Green Roof
  • 42. LID Solutions Report Card Grade - BGrade - A Grade - B Grade - C Grade - D
  • 43. Regional ProjectsRegional Projects • None currently available• None currently available • Necessary for Alternative Compliance (Provision C.3.e) • HMH working with City of San Jose to develop strategy (identify potential sites, integrate with appropriate development projects)
  • 45. Los Angeles Regional Solution ( $13 / gallon of untreated runoff per site)
  • 46. Take Home Points L - Localized, landscaped-based runoff management I - Impervious surface reduction D - Design creativity!
  • 47.
  • 48. #1 Hampton Park#1 - Hampton Park (1097 Rock Ave.) HMH (1570 Oakland Rd.)#2 - Lowe’s (775 Ridder Park Dr )(775 Ridder Park Dr.) #3 - Modern Ice (652 Luna Park Dr.)