The Borough of Leonia provided a schedule for its 2018 road resurfacing program from July 9th through August 10th. American Asphalt will be conducting milling and paving operations on various streets throughout this period. Residents on affected streets will be notified in advance by American Asphalt, and road closures will be updated in Waze. The schedule provides the anticipated dates for milling and paving each set of streets.
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Leonia 2018 resurfacing schedule (7.2.18)
1. Borough of Leonia – 2018 Road Program
Anticipated Schedule as of 7/2/18
Below is the approximate anticipated schedule for the 2018 resurfacing program as provided
by American Asphalt. Please note that these dates and locations may change, and that all
residents living on an impacted street will be noticed by the contractor - American Asphalt -
before any work will begin. Additionally, the Borough will keep updated road closures in
Waze, so community members may use that as well.
Monday 07/09/2018-07 /13/2018
Inlet Restoration
Monday 07/16/2018
Milling Operations
Moore Ave/ Ames Ave/ Sylvan Ave (Start)
Tuesday 07/17/2018
Milling Operations
Sylvan Ave (Finish)/ Highwood Ave/ Park Ave (Start)
Wednesday 07/18/2018
Milling Operations
Park Ave (Finish)/ Orchard Place/ Christie St (Start)
Paving Operations
Moore Ave/ Ames Ave/ Sylvan Ave/ Highwood Ave
Thursday 07/19/2018
Milling Operations
Christie St (Finish)/ Palmer Place/ Charles Place/ Winthrop Place
Paving Operations
Park Ave/ Orchard Place/ Christie St
Friday 07/20/2018
Milling Operations
Knapp Terrace/ Christie Lane/ Irving St/ Cumley Terrace/ Oratam Terrace
Paving Operations
Christie St/ Palmer Place/ Charles Place/ Winthrop Place
Monday 07/23/2018
Milling Operations
Chestnut St/ Allaire Ave/ Crescent Ave
Paving Operations
Knapp Terrace/ Christie Lane/ Irving St/ Cumley Terrace/ Oratam Terrace