Canada France Hawaii Telescope
Intern: Kyle Mauri
Colorado State University
Mentor: Greg Green
Background Information
• Two Axes of Rotation
• Hour Angle (HA)
• Declination (Dec)
• Binding of the Current Pin Assembly
• Mirror Aluminizing
• Mirror Handling Cart Alignment
Mirror Cart
Rails
Mirror
Cell
The East Side tube
The Inner Hub assembly
Planning and Execution
• 1: Understand Drawings and Existing Hardware
• 2: Fully Define the problem and engineer a solution
• 3: Creating New Park Number to align handling cart and mirror
cell
• 4: Designing a viable solution
• 5: Machining and Fabrication
• 6: Assembly
1: Understanding The Past
• Vellum Drawings
• Converting Drawings from the 1970’s
• Learning Technical French
• Solidworks Modeling
• Determining Mass Properties
• Understanding Clearance and maximizing available space
• Stress analysis
Current Hardware
Pin Guide
Block Pin Receiving
Block
Pin
Sensors
Air Cylinder
Mounting
Bracket
2: The Objective(s)
• Realign the Telescope via Dec Pin assembly
• Stop the Dec. Pin from Binding in the Receiving Block
• Tighten Up tolerances
• Be able to Sense Remotely if Pin is Engaged or Not
• Convert to Digital Sensing Equipment
• Match Theoretical Models to Physical Hardware
• Make sure the theoretical is really there
Constraining Factors
• Time
• Installation Time Limited to one working day
• Design, Build/Fabricate, Assembly
• Materials
• Cost, Shipping Time, Availability all need to be considered
• Integration
• Must mount in existing hole patterns
• Needs to be able to use old sensing technology
• Ability
• If it can’t be bought what can we make and how long will it take
3: The New Park Number
20:00:38.6 19:45:32.5
4: The New Design
The New Hardware
• New Air Cylinder
• Increased bore size by 25%
• Magnetic sensor ready
• Flow control
• New Mounting Bracket
• More Robust
• Magnetic Reed Switches
• Custom Mounts
• Easy to Run Diagnostics
• New Pin
• Different Internal thread
5: The New (Physical) Hardware
Modifications
6: The Finished Product
Planning and Execution
1: Understand Drawings and Existing Hardware
2: Fully Define the problem and engineer a solution
3: Create New Park Number to align handling cart and mirror
cell
4: Design a viable solution
5: Machine and Fabricate
6: Assemble
• Canada France Hawaii Telescope
• Greg Green
• Mary Beth Laychak
• Nicole Tabac
• Akamai Workforce Initiative
• W.M. Keck Observatory
• Justin Pitts
• Cheyenne Maio-Silva
• Katelyn Chigami

More Related Content

Viewers also liked

Viewers also liked (9)

Bulshit poster
Bulshit posterBulshit poster
Bulshit poster
 
Sag strategy feedback_template_ukr_беденко
Sag strategy feedback_template_ukr_беденкоSag strategy feedback_template_ukr_беденко
Sag strategy feedback_template_ukr_беденко
 
The Heart of Jesus (Part 3) That We May Be One: John:17:20-26
The Heart of Jesus (Part 3) That We May Be One: John:17:20-26The Heart of Jesus (Part 3) That We May Be One: John:17:20-26
The Heart of Jesus (Part 3) That We May Be One: John:17:20-26
 
Instructivo a rectores 130215
Instructivo a rectores 130215Instructivo a rectores 130215
Instructivo a rectores 130215
 
258. solidaridad
258. solidaridad258. solidaridad
258. solidaridad
 
Artikel Trouw
Artikel TrouwArtikel Trouw
Artikel Trouw
 
Menajemen Berbasis sekolah
Menajemen Berbasis sekolah Menajemen Berbasis sekolah
Menajemen Berbasis sekolah
 
Mapas conseptuales
Mapas conseptualesMapas conseptuales
Mapas conseptuales
 
Curriculam_Vitae
Curriculam_VitaeCurriculam_Vitae
Curriculam_Vitae
 

Similar to Declination Pin Realignment

[Webinar] Faster Turnarounds: Equipment Replacement & Upgrades
[Webinar] Faster Turnarounds: Equipment Replacement & Upgrades[Webinar] Faster Turnarounds: Equipment Replacement & Upgrades
[Webinar] Faster Turnarounds: Equipment Replacement & UpgradesClearEdge3D Inc
 
Bim based process mining master thesis presentation
Bim based process mining master thesis presentation Bim based process mining master thesis presentation
Bim based process mining master thesis presentation Stijn van Schaijk
 
Trusted BIM: Accurate As-Builts for Project Coordination
Trusted BIM: Accurate As-Builts for Project CoordinationTrusted BIM: Accurate As-Builts for Project Coordination
Trusted BIM: Accurate As-Builts for Project CoordinationClearEdge3D Inc
 
Introduction to Engineering Design Process
Introduction to Engineering Design ProcessIntroduction to Engineering Design Process
Introduction to Engineering Design ProcessLk Rigor
 
SUPERPresentation_JulianClaudio
SUPERPresentation_JulianClaudioSUPERPresentation_JulianClaudio
SUPERPresentation_JulianClaudioJulian Claudio
 
AME Presentation - ThP-39 - Jacksonville 2014
AME Presentation - ThP-39 - Jacksonville 2014AME Presentation - ThP-39 - Jacksonville 2014
AME Presentation - ThP-39 - Jacksonville 2014Andrew Feller
 
Waste Not Want Not
Waste Not Want NotWaste Not Want Not
Waste Not Want Notsflaig
 
additivemanufacturingppt-161015184713.pdf
additivemanufacturingppt-161015184713.pdfadditivemanufacturingppt-161015184713.pdf
additivemanufacturingppt-161015184713.pdfSahilS39
 
FC VSM Presentation Future State Aug 5 -7 2013
FC VSM Presentation Future State Aug 5 -7  2013FC VSM Presentation Future State Aug 5 -7  2013
FC VSM Presentation Future State Aug 5 -7 2013Donna Skala
 
Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Chris Baichoo
 
MongoDB World 2019: From Traditional Oil and Gas to Sustainable Energy OR Fro...
MongoDB World 2019: From Traditional Oil and Gas to Sustainable Energy OR Fro...MongoDB World 2019: From Traditional Oil and Gas to Sustainable Energy OR Fro...
MongoDB World 2019: From Traditional Oil and Gas to Sustainable Energy OR Fro...MongoDB
 
NAI-Interconnect-Solutions-PPT-E_cmp.pptx
NAI-Interconnect-Solutions-PPT-E_cmp.pptxNAI-Interconnect-Solutions-PPT-E_cmp.pptx
NAI-Interconnect-Solutions-PPT-E_cmp.pptxssusera85eeb1
 
Lean Kanban India 2019 Conference | Thinking Business Agility | Saikat Das
Lean Kanban India 2019 Conference | Thinking Business Agility | Saikat DasLean Kanban India 2019 Conference | Thinking Business Agility | Saikat Das
Lean Kanban India 2019 Conference | Thinking Business Agility | Saikat DasLeanKanbanIndia
 
Julianna Ricci Portfolio 2016
Julianna Ricci Portfolio 2016Julianna Ricci Portfolio 2016
Julianna Ricci Portfolio 2016Julianna Ricci
 

Similar to Declination Pin Realignment (20)

[Webinar] Faster Turnarounds: Equipment Replacement & Upgrades
[Webinar] Faster Turnarounds: Equipment Replacement & Upgrades[Webinar] Faster Turnarounds: Equipment Replacement & Upgrades
[Webinar] Faster Turnarounds: Equipment Replacement & Upgrades
 
Bim based process mining master thesis presentation
Bim based process mining master thesis presentation Bim based process mining master thesis presentation
Bim based process mining master thesis presentation
 
Trusted BIM: Accurate As-Builts for Project Coordination
Trusted BIM: Accurate As-Builts for Project CoordinationTrusted BIM: Accurate As-Builts for Project Coordination
Trusted BIM: Accurate As-Builts for Project Coordination
 
Introduction to Engineering Design Process
Introduction to Engineering Design ProcessIntroduction to Engineering Design Process
Introduction to Engineering Design Process
 
SUPERPresentation_JulianClaudio
SUPERPresentation_JulianClaudioSUPERPresentation_JulianClaudio
SUPERPresentation_JulianClaudio
 
Dcs capabilities
Dcs capabilitiesDcs capabilities
Dcs capabilities
 
AME Presentation - ThP-39 - Jacksonville 2014
AME Presentation - ThP-39 - Jacksonville 2014AME Presentation - ThP-39 - Jacksonville 2014
AME Presentation - ThP-39 - Jacksonville 2014
 
Waste Not Want Not
Waste Not Want NotWaste Not Want Not
Waste Not Want Not
 
additivemanufacturingppt-161015184713.pdf
additivemanufacturingppt-161015184713.pdfadditivemanufacturingppt-161015184713.pdf
additivemanufacturingppt-161015184713.pdf
 
Additive manufacturing ppt
Additive manufacturing pptAdditive manufacturing ppt
Additive manufacturing ppt
 
CSCMP 2014: Battle-Testing Your Distribution Center Design
CSCMP 2014: Battle-Testing Your Distribution Center DesignCSCMP 2014: Battle-Testing Your Distribution Center Design
CSCMP 2014: Battle-Testing Your Distribution Center Design
 
Jeff Garrigues Portfolio
Jeff Garrigues PortfolioJeff Garrigues Portfolio
Jeff Garrigues Portfolio
 
Winter '15 & Spring '16
Winter '15 & Spring '16Winter '15 & Spring '16
Winter '15 & Spring '16
 
FC VSM Presentation Future State Aug 5 -7 2013
FC VSM Presentation Future State Aug 5 -7  2013FC VSM Presentation Future State Aug 5 -7  2013
FC VSM Presentation Future State Aug 5 -7 2013
 
Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006
 
MongoDB World 2019: From Traditional Oil and Gas to Sustainable Energy OR Fro...
MongoDB World 2019: From Traditional Oil and Gas to Sustainable Energy OR Fro...MongoDB World 2019: From Traditional Oil and Gas to Sustainable Energy OR Fro...
MongoDB World 2019: From Traditional Oil and Gas to Sustainable Energy OR Fro...
 
NAI-Interconnect-Solutions-PPT-E_cmp.pptx
NAI-Interconnect-Solutions-PPT-E_cmp.pptxNAI-Interconnect-Solutions-PPT-E_cmp.pptx
NAI-Interconnect-Solutions-PPT-E_cmp.pptx
 
Lean Kanban India 2019 Conference | Thinking Business Agility | Saikat Das
Lean Kanban India 2019 Conference | Thinking Business Agility | Saikat DasLean Kanban India 2019 Conference | Thinking Business Agility | Saikat Das
Lean Kanban India 2019 Conference | Thinking Business Agility | Saikat Das
 
My Qualifications
My QualificationsMy Qualifications
My Qualifications
 
Julianna Ricci Portfolio 2016
Julianna Ricci Portfolio 2016Julianna Ricci Portfolio 2016
Julianna Ricci Portfolio 2016
 

Declination Pin Realignment

  • 1. Canada France Hawaii Telescope Intern: Kyle Mauri Colorado State University Mentor: Greg Green
  • 2. Background Information • Two Axes of Rotation • Hour Angle (HA) • Declination (Dec) • Binding of the Current Pin Assembly • Mirror Aluminizing • Mirror Handling Cart Alignment
  • 5. The Inner Hub assembly
  • 6. Planning and Execution • 1: Understand Drawings and Existing Hardware • 2: Fully Define the problem and engineer a solution • 3: Creating New Park Number to align handling cart and mirror cell • 4: Designing a viable solution • 5: Machining and Fabrication • 6: Assembly
  • 7. 1: Understanding The Past • Vellum Drawings • Converting Drawings from the 1970’s • Learning Technical French • Solidworks Modeling • Determining Mass Properties • Understanding Clearance and maximizing available space • Stress analysis
  • 8.
  • 9. Current Hardware Pin Guide Block Pin Receiving Block Pin
  • 11. 2: The Objective(s) • Realign the Telescope via Dec Pin assembly • Stop the Dec. Pin from Binding in the Receiving Block • Tighten Up tolerances • Be able to Sense Remotely if Pin is Engaged or Not • Convert to Digital Sensing Equipment • Match Theoretical Models to Physical Hardware • Make sure the theoretical is really there
  • 12. Constraining Factors • Time • Installation Time Limited to one working day • Design, Build/Fabricate, Assembly • Materials • Cost, Shipping Time, Availability all need to be considered • Integration • Must mount in existing hole patterns • Needs to be able to use old sensing technology • Ability • If it can’t be bought what can we make and how long will it take
  • 13. 3: The New Park Number 20:00:38.6 19:45:32.5
  • 14. 4: The New Design
  • 15. The New Hardware • New Air Cylinder • Increased bore size by 25% • Magnetic sensor ready • Flow control • New Mounting Bracket • More Robust • Magnetic Reed Switches • Custom Mounts • Easy to Run Diagnostics • New Pin • Different Internal thread
  • 16. 5: The New (Physical) Hardware
  • 17.
  • 18.
  • 20.
  • 21. 6: The Finished Product
  • 22.
  • 23. Planning and Execution 1: Understand Drawings and Existing Hardware 2: Fully Define the problem and engineer a solution 3: Create New Park Number to align handling cart and mirror cell 4: Design a viable solution 5: Machine and Fabricate 6: Assemble
  • 24. • Canada France Hawaii Telescope • Greg Green • Mary Beth Laychak • Nicole Tabac • Akamai Workforce Initiative • W.M. Keck Observatory • Justin Pitts • Cheyenne Maio-Silva • Katelyn Chigami