1. PROJECT CONSOLIDATION OF SEWAGE DISPOSAL
ACTIVITIES IN KUJANG AND ANBYON CITIES
Gran Contract –External Actions of the European Union – DCI-FOOD/2012/308-855
Eng. Jose Miguel Ruiz Verona -Land and Water Management Engineer, B.Sc.,M.Sc.
Head of Project & Technical Advisor
2. Timeline
Duration: 3 years, starting from February 1th, 2013 till February
2016:
• Inception phase including inception and planning workshop:
March - December 2013
• Steering Committee establishment (SC) – November 2013.
• Signing of Memorandum of Understanding with MoCM &
People’s Committee– January 2014.
• Implementation of the physical actions in the project sites: since
April 2014
3. Project objective and expected results
Strengthen the resilience of urban communities, including social and health institutions,
in Kujang City (North Pyong‘an Province) and Anbyon City (Kangwon Province) by
improving food security, health and hygiene situation.
Results:
Urban water supply networks and sanitation facilities in private houses and
social/health institutions are rehabilitated and reinstalled.
Decentralized storage units and sewage disposal systems (DEWATS) are developed and
constructed.
A locally adapted concept in respect of reutilization of sewage waste products for
agriculture is defined and methods are applied.
The capacities of the users/operators are strengthened by implementation measures.
4. Target population,
counterparts and other
implementing partners
Target population:
• Anbyon City 27.500 inhabitants
• Kujang City 29.290 inhabitants
Counterparts:
• Ministry of City Management (MoCM)
• People’s Committee/Department of City Planning & Household Group
Other implementing partners:
• MoPH/DoPH, MoA/PAMC, MoE/PEMC, PED and Anti- epidemiological
Station
5. INCEPTION PHASE March – December 2013
• Ex-ante baseline survey: W&S coverages, water related diseases and
malnutrition recurrence, water consumption and availability (Q&Q) and
effluents pollution load.
• Assessment, designing, feasibility and cost estimation of the different
interventions.
• Operational Plan adjustment upon the findings and needs.
• Inception and Planning Workshop.
6.
7.
8. What is new in the project as a result of the assessment
conducted during the inception phase
Under result 3 new issues were identified not included yet in the
project:
• Stormwater management (flood hazard map development and
drainage)
• Flood control and prevention (river stabilization and regulation
measures)
11. REHABILITATION OF WSS
《SAFE DRINKING WATER SUPPLY》
WATER INTAKE AND
TRANSMISION PIPELINE
OVERHEAD TANKS
DISTRIBUTION
NETWORK AND
INHOUSE GRID
WATER QUALITY
TESTIN RUTINE
23. SANITATION FACILITIES
• CONSTRUCTION OF DOUBLE PIT VIP LATRINES (550
units)
• CONSTRUCTION OF COMMUNITY SANITATION
CENTER (4)
• INSTALLATION OF INDOOR TOILETS AND
DOWNPIPES (500 units)
• INTALLATION OF INDOOR TOILETS AT
SOCIAL/PUBLIC BUILDINGS
29. REHABILITATED INDOOR TOILETS IN SOCIAL/HEALTH INSTITUTIONS
INDOOR TOILET IN
ANBYON GUEST HOUSE
REHABILITATED INDOOR
TOILET IN ANBYON ANTI-
EPIDEMIOLOGICAL CENTER
30. Wastewater treatment,
reuse and disposal
• Simplified sewer system (Kujang): 1 full flash DEWATS
constructed, 8 under construction.
• Solid free sewer systems (Anbyon): 12 septic tanks
constructed and 4 DEWATS constructed, 4 under
construction.
33. WASTEWATER TREATMENT,
REUSE AND DISPOSAL
KUJANG COUNTY
DEWATS 9
BENEFICIARIES 5093
DRYING BED 456 ㎡
ANBYON COUNTY
DEWATS 8
BENEFICIARIES 3479
DRYING BED 240㎡
42. Reutilization of sewage
waste products
• Composting yard site selected, designed and construction
materials in process of procurement.
• Conduct a meeting with PC, MoA/AMC to define the use of
sewage products for agriculture/horticulture production,
aquaculture and environmental purposes
• Risk chain assessment scheme for the unsuitable use of
sludge an untreated excretes as fertilizer for horti/agriculture
production
43.
44.
45. SLUDGE DRYING BEDS IN ANBYON AND
KUJANG
ITEMS FOR THE SAFE HANDLING OF SLUDGE
47. Capacity building
• Onsite concrete workshops ( 2 events)
• DEWATS design and construction (2 events)
• O&M of the water supply systems (2 events)
• O&M of DEWATS, reuse of wastewater (2 events)
• Hydraulic calculation for the design of WSS (2 events)
• Catchment hydrology (1 event)
• Hygiene promotion campaign (2 events)
• Water quality testing ( 2 events)