SlideShare a Scribd company logo
1 of 52
Download to read offline
By: Patrick Graney & John Gaul
Client: NAVFAC Mid-Atlantic
Location: Norfolk Naval Shipyard (NNSY)
Portsmouth, VA
Team: JV – MN3M
Project Size
• Construction Cost ≈ $165 Million
• Design Fee ≈ $7 Million
Project Scope:
• 1250’ Long by 230’ Wide Pier
• 800’ Long Wharf (Hitchcock Street)
• Ballasted Deck
• Designed to Accommodate Any NAVY Vessel
(particularly during hurricanes)
• Jokingly described as “Pier Designed to Support
Utilities vs. Ships”
1st BIM Project for NAVFAC on East Coast
Pier 4
Pier 5
Pier 3
Estimation Tool
Improves Coordination
Effective Marketing Presentation of
Construction Approaches
Identifies Potential Construction Conflicts
Reduces Errors Made in Design Phase
Helps Clients & End Users Visualize
Product
Helps Owner Make Informed Decisions
Provides Material Inventory for Owner
REVIT® From AutoDesk®
• REVIT Structure – M&N (Gaul & Chris Greene)
• REVIT MEP – MMM Design Group
• REVIT Architecture – MMM Design Group
Compatible with AutoCAD, 3ds Max, &
Google SketchUp
• Import/export .dwg files
• Import/export 3D model
Model Developed after 35% Submittal and
was Submitted with Final Submittal
Design
• Utility Conflicts
• 3D Rendering – M&N (Jeanah Bauer)
• Owner can Visualize Final Product
Construction
• Contractor can Visualize Construction
• Scheduling/Phasing
• Equipment Maneuvering
NAVY
• Inventory
• Inspection – catalog damages/repairs
• Internal Marketing & Discussions
• Identify Utility Conflicts for Retrofits
Structural – Piles, Pile Caps, Deck, etc.
Civil – Stormwater, Grading, Paving
Mechanical – Water, Sanitary, SY Utilities
Electrical & Communications
Architectural - Buildings
Pier 5 – New Construction
Hitchcock Street – Renovation
View to Show Pier Supporting Utilities
View to Show Pier Supporting Utilities
Run Interference (Conflicts) Checks
Create Section & Elevation Views
• Views were exported to AutoCAD and compared
with Design Drawings
Quantity Take-Offs Performed
Salt Water Pipe Bend Conflicting with
Precast Concrete Panel
SW Pipe
Interference w/
PC Panel
SW Pipe
Interference w/
PC Panel
Section at Pier & Hitchcock St. Interface
Section at Pier & Hitchcock St. Interface
Hitchcock St. Closed Wharf Area
Hitchcock St. Closed Wharf Area
Pier 5 Crane Rail Beam
Model Exported to 3ds Max
NAVY & SKANSKA Happy with Product
• Reduction in RFIs
• Reduction in Turnaround Time on RFI’s
M&N’s Efforts
• 635 Man Hours (includes converting Revit Model
to Uniformat AutoCAD file Requested by NAVY)
• $61,795 ≈ 1.2% of overall fee.
Offshore Heavy Weather Mooring
Structure
• Piles Battered Inward to Reduce Obstructions in
Ship Channel
• Concern with Pile Day Lighting from MLLW to -20’
MLLW
• Possible Conflict with Mooring Anchor Plate
Model was an Independent Effort
• Not Requested by NAVY, & not submitted
• Developed as a Design Aid
Mooring Anchor Plate in Vicinity
• Cut Section at Elevation of Mooring Anchor Plate
• Export Section to AutoCAD
• Insert Contractor RFI Drawing into Section View
Identify Conflicts with Plate
Answer RFI & Adjust Design as Required
BIM Has Been Helpful By:
• Improving Coordination
• Identifying Potential Construction Conflicts
• Reduction in Errors Made in Design Phase
• Help Visualize End Product
Potential Future Uses of BIM for M&N
• Design Build Projects (Most Contractors are BIM
Ready)
• Projects with a High Possibility of Conflicts
• Sustainable Design
• Cataloging Deficiencies in I&R Work (can be done
in conjunction with GIS)

More Related Content

What's hot (14)

Vedam Design:- BWTS - Retrofits Services
Vedam Design:-  BWTS - Retrofits Services Vedam Design:-  BWTS - Retrofits Services
Vedam Design:- BWTS - Retrofits Services
 
wadhwa Briefing & Achievement
wadhwa Briefing & Achievementwadhwa Briefing & Achievement
wadhwa Briefing & Achievement
 
R stelmach aprs 2018 rev 2
R stelmach aprs 2018  rev 2R stelmach aprs 2018  rev 2
R stelmach aprs 2018 rev 2
 
HAULAGE
HAULAGEHAULAGE
HAULAGE
 
Session 3 - Michael Berna Indiana Logistics Summit 2012
Session 3 - Michael Berna Indiana Logistics Summit 2012Session 3 - Michael Berna Indiana Logistics Summit 2012
Session 3 - Michael Berna Indiana Logistics Summit 2012
 
Raytec Presentation1
Raytec Presentation1Raytec Presentation1
Raytec Presentation1
 
Curriculum Vitae.DOC
Curriculum Vitae.DOCCurriculum Vitae.DOC
Curriculum Vitae.DOC
 
Ship hull modelling
Ship hull modellingShip hull modelling
Ship hull modelling
 
End of Summer Intern Presentation-3
End of Summer Intern Presentation-3End of Summer Intern Presentation-3
End of Summer Intern Presentation-3
 
Vedam Designs: Solutions for Shallow Water maintenance Dredging
Vedam Designs: Solutions for Shallow Water maintenance DredgingVedam Designs: Solutions for Shallow Water maintenance Dredging
Vedam Designs: Solutions for Shallow Water maintenance Dredging
 
Sea to Ski Higway Improvements Project
Sea to Ski Higway Improvements ProjectSea to Ski Higway Improvements Project
Sea to Ski Higway Improvements Project
 
Oil refinery tank project
Oil refinery tank projectOil refinery tank project
Oil refinery tank project
 
Dec 22 2014 CSLL
Dec 22 2014 CSLLDec 22 2014 CSLL
Dec 22 2014 CSLL
 
Wagenborg times 3
Wagenborg times 3Wagenborg times 3
Wagenborg times 3
 

Similar to BIM-Pier5

Final acec design summit pres 2017
Final acec design summit pres 2017Final acec design summit pres 2017
Final acec design summit pres 2017melissanatech
 
Trusted BIM: Accurate As-Builts for Project Coordination
Trusted BIM: Accurate As-Builts for Project CoordinationTrusted BIM: Accurate As-Builts for Project Coordination
Trusted BIM: Accurate As-Builts for Project CoordinationClearEdge3D Inc
 
Linkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiLinkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiKrystian Gnysinski
 
Armtec Engineering's Top Picks - Case Studies and Design Review
Armtec Engineering's Top Picks - Case Studies and Design ReviewArmtec Engineering's Top Picks - Case Studies and Design Review
Armtec Engineering's Top Picks - Case Studies and Design ReviewCommunications Branding
 
SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)dgonano
 
Keep it Flowing! Culvert Design 20: Design, Durability & Applications
Keep it Flowing! Culvert Design 20: Design, Durability & ApplicationsKeep it Flowing! Culvert Design 20: Design, Durability & Applications
Keep it Flowing! Culvert Design 20: Design, Durability & ApplicationsCommunications Branding
 
Industrial Refrigeration Drafter - Comfortsystems USA
Industrial Refrigeration Drafter - Comfortsystems USAIndustrial Refrigeration Drafter - Comfortsystems USA
Industrial Refrigeration Drafter - Comfortsystems USABrian Cherry
 
Rong Vo Catia V5 Projects And Fea And Msc Adams Simulations
Rong Vo Catia V5 Projects And Fea And Msc Adams SimulationsRong Vo Catia V5 Projects And Fea And Msc Adams Simulations
Rong Vo Catia V5 Projects And Fea And Msc Adams SimulationsRong Vo
 
Cuiper Resume_Oct_2015
Cuiper Resume_Oct_2015Cuiper Resume_Oct_2015
Cuiper Resume_Oct_2015Glen, Cuiper
 
Resume_Swapan Sarkar
Resume_Swapan SarkarResume_Swapan Sarkar
Resume_Swapan SarkarSwapan Sarkar
 
Resume_Swapan Sarkar
Resume_Swapan SarkarResume_Swapan Sarkar
Resume_Swapan SarkarSwapan Sarkar
 
Resume_Basavarajappa. L N
Resume_Basavarajappa. L NResume_Basavarajappa. L N
Resume_Basavarajappa. L NBasavaraj L N
 
Cad designer resume
Cad designer resumeCad designer resume
Cad designer resumeBrian Cherry
 
German perez lifes50+ design summary - deep wind 2018
German perez   lifes50+ design summary - deep wind 2018German perez   lifes50+ design summary - deep wind 2018
German perez lifes50+ design summary - deep wind 2018TECNALIA Marine Energy
 

Similar to BIM-Pier5 (20)

Final acec design summit pres 2017
Final acec design summit pres 2017Final acec design summit pres 2017
Final acec design summit pres 2017
 
projects
projectsprojects
projects
 
Trusted BIM: Accurate As-Builts for Project Coordination
Trusted BIM: Accurate As-Builts for Project CoordinationTrusted BIM: Accurate As-Builts for Project Coordination
Trusted BIM: Accurate As-Builts for Project Coordination
 
Concept to production - "The challenges of PM in the RNLI"
Concept to production - "The challenges of PM in the RNLI"Concept to production - "The challenges of PM in the RNLI"
Concept to production - "The challenges of PM in the RNLI"
 
Linkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiLinkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian Gnysinski
 
Armtec Engineering's Top Picks - Case Studies and Design Review
Armtec Engineering's Top Picks - Case Studies and Design ReviewArmtec Engineering's Top Picks - Case Studies and Design Review
Armtec Engineering's Top Picks - Case Studies and Design Review
 
SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)
 
Andrew Gutteridge
Andrew GutteridgeAndrew Gutteridge
Andrew Gutteridge
 
2015 CRW - Project Spotlight: New NY Bridge Project
2015 CRW -  Project Spotlight: New NY Bridge Project2015 CRW -  Project Spotlight: New NY Bridge Project
2015 CRW - Project Spotlight: New NY Bridge Project
 
Keep it Flowing! Culvert Design 20: Design, Durability & Applications
Keep it Flowing! Culvert Design 20: Design, Durability & ApplicationsKeep it Flowing! Culvert Design 20: Design, Durability & Applications
Keep it Flowing! Culvert Design 20: Design, Durability & Applications
 
Industrial Refrigeration Drafter - Comfortsystems USA
Industrial Refrigeration Drafter - Comfortsystems USAIndustrial Refrigeration Drafter - Comfortsystems USA
Industrial Refrigeration Drafter - Comfortsystems USA
 
Rong Vo Catia V5 Projects And Fea And Msc Adams Simulations
Rong Vo Catia V5 Projects And Fea And Msc Adams SimulationsRong Vo Catia V5 Projects And Fea And Msc Adams Simulations
Rong Vo Catia V5 Projects And Fea And Msc Adams Simulations
 
Cuiper Resume_Oct_2015
Cuiper Resume_Oct_2015Cuiper Resume_Oct_2015
Cuiper Resume_Oct_2015
 
Resume_Swapan Sarkar
Resume_Swapan SarkarResume_Swapan Sarkar
Resume_Swapan Sarkar
 
Resume_Swapan Sarkar
Resume_Swapan SarkarResume_Swapan Sarkar
Resume_Swapan Sarkar
 
Resume_Basavarajappa. L N
Resume_Basavarajappa. L NResume_Basavarajappa. L N
Resume_Basavarajappa. L N
 
Cad designer resume
Cad designer resumeCad designer resume
Cad designer resume
 
Byron CV 2016v5
Byron CV 2016v5Byron CV 2016v5
Byron CV 2016v5
 
successful applications of project visualization
successful applications of project visualizationsuccessful applications of project visualization
successful applications of project visualization
 
German perez lifes50+ design summary - deep wind 2018
German perez   lifes50+ design summary - deep wind 2018German perez   lifes50+ design summary - deep wind 2018
German perez lifes50+ design summary - deep wind 2018
 

BIM-Pier5

  • 1. By: Patrick Graney & John Gaul
  • 2. Client: NAVFAC Mid-Atlantic Location: Norfolk Naval Shipyard (NNSY) Portsmouth, VA Team: JV – MN3M Project Size • Construction Cost ≈ $165 Million • Design Fee ≈ $7 Million
  • 3. Project Scope: • 1250’ Long by 230’ Wide Pier • 800’ Long Wharf (Hitchcock Street) • Ballasted Deck • Designed to Accommodate Any NAVY Vessel (particularly during hurricanes) • Jokingly described as “Pier Designed to Support Utilities vs. Ships” 1st BIM Project for NAVFAC on East Coast
  • 4.
  • 6.
  • 7.
  • 8. Estimation Tool Improves Coordination Effective Marketing Presentation of Construction Approaches Identifies Potential Construction Conflicts
  • 9. Reduces Errors Made in Design Phase Helps Clients & End Users Visualize Product Helps Owner Make Informed Decisions Provides Material Inventory for Owner
  • 10. REVIT® From AutoDesk® • REVIT Structure – M&N (Gaul & Chris Greene) • REVIT MEP – MMM Design Group • REVIT Architecture – MMM Design Group Compatible with AutoCAD, 3ds Max, & Google SketchUp • Import/export .dwg files • Import/export 3D model
  • 11. Model Developed after 35% Submittal and was Submitted with Final Submittal Design • Utility Conflicts • 3D Rendering – M&N (Jeanah Bauer) • Owner can Visualize Final Product
  • 12. Construction • Contractor can Visualize Construction • Scheduling/Phasing • Equipment Maneuvering NAVY • Inventory • Inspection – catalog damages/repairs • Internal Marketing & Discussions • Identify Utility Conflicts for Retrofits
  • 13. Structural – Piles, Pile Caps, Deck, etc. Civil – Stormwater, Grading, Paving Mechanical – Water, Sanitary, SY Utilities Electrical & Communications Architectural - Buildings
  • 14. Pier 5 – New Construction
  • 16.
  • 17.
  • 18.
  • 19.
  • 20.
  • 21.
  • 22.
  • 23.
  • 24.
  • 25.
  • 26.
  • 27. View to Show Pier Supporting Utilities
  • 28. View to Show Pier Supporting Utilities
  • 29. Run Interference (Conflicts) Checks Create Section & Elevation Views • Views were exported to AutoCAD and compared with Design Drawings Quantity Take-Offs Performed
  • 30. Salt Water Pipe Bend Conflicting with Precast Concrete Panel
  • 31. SW Pipe Interference w/ PC Panel SW Pipe Interference w/ PC Panel
  • 32. Section at Pier & Hitchcock St. Interface
  • 33. Section at Pier & Hitchcock St. Interface
  • 36. Pier 5 Crane Rail Beam
  • 38.
  • 39.
  • 40.
  • 41.
  • 42.
  • 43. NAVY & SKANSKA Happy with Product • Reduction in RFIs • Reduction in Turnaround Time on RFI’s M&N’s Efforts • 635 Man Hours (includes converting Revit Model to Uniformat AutoCAD file Requested by NAVY) • $61,795 ≈ 1.2% of overall fee.
  • 44. Offshore Heavy Weather Mooring Structure • Piles Battered Inward to Reduce Obstructions in Ship Channel • Concern with Pile Day Lighting from MLLW to -20’ MLLW • Possible Conflict with Mooring Anchor Plate Model was an Independent Effort • Not Requested by NAVY, & not submitted • Developed as a Design Aid
  • 45.
  • 46.
  • 47.
  • 48.
  • 49.
  • 50. Mooring Anchor Plate in Vicinity • Cut Section at Elevation of Mooring Anchor Plate • Export Section to AutoCAD • Insert Contractor RFI Drawing into Section View Identify Conflicts with Plate Answer RFI & Adjust Design as Required
  • 51.
  • 52. BIM Has Been Helpful By: • Improving Coordination • Identifying Potential Construction Conflicts • Reduction in Errors Made in Design Phase • Help Visualize End Product Potential Future Uses of BIM for M&N • Design Build Projects (Most Contractors are BIM Ready) • Projects with a High Possibility of Conflicts • Sustainable Design • Cataloging Deficiencies in I&R Work (can be done in conjunction with GIS)