Maximizing
Uptime in
Mission-Critical
Facilities
By Joe Soroka
Director of Technical Services
Lee Technologies
1
Maximizing Uptime in
Mission-Critical Facilities
As technology reaches into every corner of our
world, the importance of, and reliance on, your mission-
critical facility reaches new heights. Uptime is no longer a
lofty goal, it is an absolute necessity.
However, uptime is not a product that you specify
with the design of your facility, install, and then forget about.
A facility designed to 99.99% of availability will not
achieve/maintain that number, unless we fully understand the
many factors that affect uptime.
Maximum Uptime is a philosophy. It begins with the
planning of your facility, and remains a continuous process
through every step of design, construction, commissioning,
operations, failure analysis and recommissioning.
Lessons Learned Long Ago
Help Us Achieve Uptime Today
September 17, 1908: Orville Wright’s flying machine
crashes at Fort Meyer,Virginia, killing co-pilot T.E. Selfridge,
and an aircraft accident investigation board is born. The
Aeronautical Board of the U.S.Army Signal Corps and the
Aerial Experiment Association (AEA) headed by Alexander
Graham Bell and his associates, conducted a thorough
accident investigation. Through their findings, Dr. Bell
realized the importance of preventing failures in the future
2
and wrote an article entitled "The Lessons to be Learned
from Orville Wright’s Disaster".
“Lessons Learned” have become an essential tool in
the prevention of aircraft accidents. Today, based on their
investigation into the cause of an accident, the National
Transportation Safety Board (NTSB) develops and issues
"lessons learned" to prevent similar failures in the future.
Preventing failures in mission-critical facilities requires a
similar approach to ensure maximum uptime.
Four Categories of Failure
NTSB investigations establish that accidents occur
due to one or more types of failures: design failures,
catastrophic failures, compounding failures or human-error
failures. Downtime at mission-critical facilities can
be attributed to these four types of failures, as well, and
each requires a different approach on prevention. All four
types of potential failures must be examined, and "lessons
learned" programs established in order to realize Maximum
Uptime for your Mission-Critical Facilities.
Design Failures can be eliminated by first engaging with
competent vendors. Selecting the appropriate design firm,
integration firm, construction companies and commissioning
team along with the operations staff is crucial to acquiring
the experience needed to reduce these types of failures.
Catastrophic Failures are usually unpredictable in nature.
However, a comprehensive maintenance and operations
programs can identify and eliminate as many potential
problems as possible.This can also help eliminate the
3
condition that contributed to the weakness and minimize
the effects of truly unpredictable problems.
Compounding Failures are caused when multiple events
occur to create a failure. The lack of attention to details is a
leading cause in compounding failures. Little nuisance items
in a large facility are sometimes left unnoticed and by
themselves cause no ill effect to the facility, but along with
other problems, can combine to create a system failure.
Human-error Failures are a leading cause of failures in
mission-critical facilities. These failures can be reduced by
having an experienced staff that receives continuous training.
Even with a competent and trained staff, the requirement
for switch-level, detailed Methods-of-Procedure (MOPs) are
still required.These MOPs should be executed with a
pilot/co-pilot approach.
Begin with the End in Mind
Whether it’s new construction, upgrading or
operating an existing mission-critical facility, it is important
to carefully plan the work and to work the plan. In the
design phase, it is important to consult with design teams
experienced in the design of the particular type of mission-
critical facilities that your organization requires. A crucial
part of the design phase is the early development of the
Design Intent.
Unfortunately the Design Intent too often is not fully
4
developed, or is vague. The Design Intent should clearly
state the owner’s requirements. A well-created Design
Intent document will start with a narrative of the project
background, and provide a detailed discussion of the
required objectives and goals. Required functional uses and
requirements of the mission-critical facility should be clearly
explained.While often difficult to quantify, performance and
maintenance criteria should also be addressed. Finally, the
expected lifespan and overall quality of the project needs to
be defined.
A comprehensive Design Intent is crucial for all
involved parties to succeed in achieving maximum uptime in
a mission-critical facility.Without it, too much interpretation
by the various parties involved, can lead to compromises
and misunderstandings that weaken the integrity of
everything which follows.
Selecting a Design Concept
There is not a single ideal facility design configuration.
Any of a number of design concepts will accomplish similar
goals, each with its own advantages and disadvantages.The
required system reliability and project budget will be a
driving force.
However, there are four basic categories of design
concepts;Tier I,Tier II,Tier III and Tier IV.
Tier 1
• Single active delivery path
• Need (N) of capacity
5
• Site availability of 99.671 %
• Annual downtime of 28.8 hours
Tier II
• Single active delivery path
• Need + Redundancy (N+1) of capacity
• Site availability of 99.749 %
• Annual downtime of 22.0 hours
Tier III
• One active and one passive delivery path
• Need + Redundancy (N+1) of capacity
• Site availability of 99.982 %
• Annual downtime of 1.6 hours
Tier IV
• Two active delivery path
• Need + Need with Redundancy 2
(N+1) of capacity
• Site availability of 99.995 %
• Annual downtime of 0.4 hours
Setting the Pace
Developing a realistic project schedule and updating it
throughout the project will help eliminate unwanted
surprises and avoid delays. When developing the schedule,
determine the required milestones and list the items that
can impact them.
6
A Keepsake Moment
Keeping a detail construction log along with digital
pictures is very helpful to a project. After the site is
operational, there will come a time when you will want to
refer to the construction photos to see how a piece of
equipment was installed. Well-organized construction photo
albums will provide a wealth of information years after the
project’s completion when the operations staff must
perform maintenance, upgrades or repairs.
Safety First
Insist on vendors providing safety plans before any
work begins. Review the plans to ensure they’re current and
appropriate to your project. Injury and fatalities can effect
the reputation of your organization, along with the potential
for OSHA fines and other litigation costs.An unsafe project
will add additional costs and delays to the project. Invest the
upfront time to ensure the project site is safe from the
beginning. It will save time, money and possibly lives.
Equipment Selection & Integration
Selecting the right equipment vendors for the project
helps ensure its successful completion. It is crucial to
ensure that the equipment vendor meets the engineering
specifications. Beyond the equipment-side however, the
vendor’s ability to support the equipment is an equally
important consideration. This includes delivery times,
7
installation support, start-up services and the availability of
spare parts and authorized maintenance personnel.
For complex systems and fast-track projects, consider
using an equipment integrator. Complex systems rely on
the operation of multiple systems and platforms.Therefore,
it is essential to have the support of an organization focused
on the overall connectivity and interaction of multiple
systems.A qualified integrator can help eliminate the
confusion that multiple Request for Information (RFIs) from
various installing contractors can cause. Integrators provide
the owner with a single point- of-contact, reducing the
project’s completion time, and ensuring that all of the
systems are properly installed and interconnected.
All Aboard
In addition, schedule a thorough onboard submittal
review meeting during the equipment procurement stage.
This meeting will help reduce RFIs, change orders and can
greatly improve the overall project schedule. The onboard
submittal review meeting should be attended by the owner,
engineers, general contractor, equipment integrator,
electrical and mechanical subcontractors, equipment
manufactures, commissioning agents and all parties involved
in the integration, installation, start-up and commissioning of
the site.
The submittal for each major piece of equipment
should be reviewed for engineering accuracy, required
equipment options, delivery essentials, proper space layout,
installation and start-up necessities.Any changes or
8
concerns for the equipment should be addressed and
resolved. It is easier to correct a potential problem during
the procurement phase than after the equipment has
shipped to the site.
The complexity of your mission-critical facility
increases due to interconnectivity and monitoring
requirements. Most engineering drawings do not show the
connection of control wiring to systems from other
manufacturers.Typically consulting engineers indicate these
connections with a cloud symbol and the words "By
Others." Avoid uncertainty by relying on a specialized
equipment integrator to develop the control drawings with
connection points. Control and monitoring connections are
essential to the overall health of the facility’s infrastructure,
and this is the time to ensure seamless integration.
Commissioning
Commissioning is the systematic process of verifying
and documenting the performance of the facility’s
equipment. This process has several distinct phases,
including the Planning Phase, Design Phase, Construction
Phase,Acceptance Phase and the Post-Acceptance Phase.
Commissioning a facility has many benefits providing
direct and indirect paybacks. Prior to starting the
commissioning program, take the time to define the key
purpose of the program. For example, systems can be setup
to achieve higher energy efficiency, but this may affect the
system reliability. Trade-offs between energy efficiency and
system reliability must be carefully weighed.This is ultimately
a priority-based decision for the owner.
9
There are a number of benefits to Commissioning a
facility, including:
• Improved system performance and reliability,
• Reduced energy consumption,
• Improved environmental controls and
Indoor Air Quality (IAQ),
• Hands-on training for operations and
maintenance personnel,
• Early identification of outstanding issues,
• Verification of operating parameters and
procedures,
• Establishing an operating baseline,
• Extended equipment life,
• Reduced occupant IAQ complaints
including hot and cold calls.
Commissioning Procedures
All operating procedures should be tested for
functionality during the Commissioning process. This
includes start-up and shutdown of equipment, equipment-
bypass and failure-recovery procedures. Equipment should
be exercised through all of the modes of operation.To avoid
future problems, it is essential to verify all operational
modes and procedure methods before the facility is
occupied.
Recommissioning
Recommissioning is the process of commissioning a
previously-commissioned facility to which changes have been
10
made. The original commissioning documents are used as a
baseline for the facility’s operating performance.When
developing the recommissioning plan, it is important that all
new equipment and upgrades are added to the new plan.
Since the building is occupied during the recommissioning
process, a detailed Method of Procedures must be
developed to allow complete testing without affecting the
facility operations. This may require temporarily placing
equipment out of service, in bypass mode, after-hour work
windows and the use of temporary equipment. In the case
of a mission-critical facility, great care must be taken to
evaluate the system and to develop the correct procedures
to ensure the required uptime.
How often a facility is recommissioned is dependent
upon several factors, including the required system
availability and reliability, the effects of improper
performance on operations, energy consumption, energy
costs, and the amount of changes and upgrades that have
occurred since the facility was last commissioned.Typically, a
mission-critical facility should be recommissioned every 3
to 6 years.
Retro-commissioning
Retro-commissioning is the process of commissioning
an existing building that has not previously been
commissioned. The retro-commissioning process is the
same as the commissioning process with the exception that
the building is occupied. Since the building is occupied and
needs to remain operational, proper planning and
development of detailed Method of Procedures will need to
occur in the same manner as a recommissioning effort.
11
Construction
Well-planned and meticulously implemented
construction is the key foundation to facility reliability and
maintainability.The owner should take an active role in
selecting and working with the team throughout the
construction process. A team approach to building your
mission-critical facility will help to ensure that your final
product will meet your specifications.
Construction Inspections
The owner, or the owner’s representative, should
conduct regular inspections of the jobsite during the
construction process to document and photograph the
installation process. Any items of concern should be
addressed immediately rather than waiting until after the
installation is completed. Correcting construction issues at
the time they occur will help to ensure that the project
stays on schedule and within budget.
Along with inspecting for proper installation,
inspection for proper safety procedures, overall organization
and cleanliness is a must. A dirty, disorganized and unsafe
construction site can lead to accidents, delays and mistakes.
Construction Meetings
Conduct regular construction meetings that are
professional and productive. Building a fast-track project for
a mission-critical facility requires a team approach and a
team is most effective working in unison. Good facilitation
12
and mediation skills can be tremendous assets.
Professionalism,Team Work and Expertise will deliver a
quality project on time.
Equipment Selection
When selecting equipment for your mission-critical
facilities, it is important to work with an Integrator to verify
that all of the equipment complies with the project
specifications. Listed below are some equipment options to
consider for a mission-critical facility.
Generators
When selecting the generator, review the technical
specifications to ensure that your project needs are met.
Review the generator’s available options. For example,
optional isolation valves on the jacket water heater hose are
inexpensive at the time of purchase. Replacing the jacket
water heater hose in the field however, will require taking
the generator out of service for an extended period of
time. Another generator option to consider is auxiliary
breaker contacts. Generator outages caused by a tripped or
open generator breaker are surprisingly common. In
addition, monitor and/or alarm the auxiliary contacts. The
generator is there to provide power in the case of an
outage, make sure it is ready when needed.
UPS Systems
There are as many different types of UPS systems as
there are topologies.Your requirements may be best suited
13
for a double conversion, line interactive or delta conversion.
Regardless of the type of system that fits
the application, make sure the appropriate internal and
external maintenance bypasses are installed. A maintenance
bypass should be sized to support 100% load on external
maintenance bypass while providing enough capacity to
perform 100% load tests.
UPS Batteries
When using Valve Regulated Lead Acid (VRLA)
batteries, specify multiple battery strings that can be
independently isolated by opening a breaker. With an
independently isolated VRLA battery string, maintenance can
be performed while keeping the critical load on the UPS
system.
Utilities
The August 2003 blackout affected communities
stretching from Detroit to New York. Seconds after the
power outage, thousands of generators received a start
signal and most of them started. However, dead batteries,
low fuel, low coolant, and generally poor maintenance left
the others in the dark.
The time to prepare for the next outage is now. In
addition to electrical utility outages, mission-critical facilities
must also prepare for failures from other utilities, including
telecommunications, water, sewer and gas.
14
In the event of a water outage, sufficient water will
be required to support the make-up water used in cooling
towers as well as water for staff requirements. Redundant
water sources, such as wells and storage tanks, are an
important part of a disaster plan.
In the event of a widespread outage, an adequate
supply of diesel fuel is also important. During normal times,
suppliers are able to provide more diesel fuel within hours,
but a widespread outage will severely impact delivery
schedules. Generator monitoring can help eliminate a fuel
shortage.
15
Monitoring
When selecting a monitoring system, understand the
system’s capabilities and establish the various alarms, trends
and notification to provide not only alarm notification, but
also important historical data that can be used to predict
and prevent failures. It is, of course, essential that the
monitoring system itself continues to operate when the
systems that are being monitored fail. Proper setup of
monitoring system alarm points is crucial to preventing
failures and/or minimizing their impact.
Operations and Maintenance Staffing
O&M Staffing
Once the site is operational you will need to decide
how to staff your facility. Whether you use inside or
outside staff it is important that the depth of knowledge
meets the requirements of your mission-critical facilities.
Operating Procedures
The development and verification of site operation,
maintenance and recovery procedures are vital to
maximizing uptime. Methods of Procedure (MOPs) should
be very thorough and specific, written to the switch level
detail, and tested during the project’s commissioning phase.
Too often the rush to bring the facility online overshadows
the need to develop, document and deploy MOPs. However,
waiting to develop a procedure to transfer the UPS system
to maintenance bypass could prove much more costly than
16
investing the time upfront to prepare for the inevitable.
Procedures should be developed early and tested before the
facility is fully operational.
Maintenance Windows
When designing or upgrading your facility, keep in
mind the quantity and length of maintenance windows
required to properly maintain the facility.The system will
need the appropriate redundancy and bypasses in order to
operate while maintenance is performed.An annual
maintenance matrix should accompany the equipment list to
ensure adequate redundancy allowances. Systems without
the appropriate maintenance allowances may require the
use of temporary equipment or the installation of additional
systems if continuous uptime is
a requirement.
Predictive Maintenance
Maintenance should go beyond remedial and
preventative maintenance to include predictive maintenance.
Using equipment trends and conducting a thorough failure
analysis after each incident will help predict and in-turn
proactively prevent future problems. All maintenance
documentation should be detailed, and provide methods for
predicting and anticipating potential troublespots and
weaknesses. Details are the building blocks of a
comprehensive predictive maintenance program.
Maintenance Planning
Plan all maintenance in advance. Start with the basics.
Develop a complete equipment list and use that as a basis
17
for the planning matrix. Have specific procedures in place
for each piece of equipment. The procedures should include
start-up, shutdown, bypass, lock-out tag-out, maintenance
and disaster recovery. Review maintenance windows and
implement an automated equipment maintenance schedule
that is strictly enforced.
Disaster Planning & Recovery
A comprehensive business continuity plan (BCP) is
required for all mission-critical facilities. It is equally
important to develop a comprehensive plan for all IT
equipment and supporting infrastructure in your mission-
critical facility. The plan should be a joint effort between the
IT and Facilities departments and should be tested and
updated at least once a year and/or as facilities changes
occur.
Training
It is also important to have a comprehensive training
program for the operation and maintenance
staff. Training should start with the equipment
manufacturer/installer. Start-ups and commissioning
offer ideal opportunities for training operation and
maintenance staff. Once the site is operational, schedule
regular training to keep operational and maintenance staff
current.
As-Built Drawings
After the installation, be sure to secure the project’s
as-built drawings. Invest the time to verify the accuracy of
18
the drawings. Then institute a practice that ensures that all
applicable drawings are undated as upgrades occur at the
facilities. If they do not exist, a set of as-built drawings
should be developed.As-built drawings are valuable tools in
quickly resolving problems and restoring service in the
event of a failure.Additionally, they are valuable when
initiating facility upgrades.
Keeping Good Company
Ultimately, maximum uptime in the mission-critical
facility runs on technology, trust and teamwork.Your
infrastructure integrator works to orchestrate and
coordinate the efforts of this diverse team to ensure your
mission-critical facility delivers the performance and
availability you require.
For an asset as crucial as your mission-critical
facility's infrastructure, it pays to invest the time to select a
company you can trust, with the experience and resources
to maximize uptime and mitigate risk. Ideally, your mission-
critical infrastructure specialist will offer you all of the
products, people, services and strategies needed to design,
integrate, commission, staff, maintain, service and monitor
your facility.Acquiring these crucial services from a single
source can greatly reduce headaches and finger-pointing in
the future.
Benefit from Lessons Learned
Technology has changed quite a bit in the nearly 100
years since “Orville Wright’s Disaster.” However, learning
from failure remains the key to ensuring that history doesn’t
repeat itself.
An experienced mission-critical facilities
infrastructure integrator can provide essential expertise in
preventing failures and ensuring maximum uptime.Whether
it’s design failures, catastrophic failures, compounding failures
or human-error failures, there are steps that can eliminate,
minimize or mitigate their effects.
And an ongoing site-specific "lessons learned" program will
become a living document that continues to help maximize
uptime for your mission-critical facilities.
Uptime is not a product and it is never complete.
Uptime is a philosophy. It is a never ending process that is
practiced, lived, learned and refined every day.
Lee Technologies designs, installs and maintains the physical infrastructure that powers
and protects mission-critical facilities throughout the United States.We offer customers
a single source for complete lifecycle solutions, including mission-critical infrastructure
assessments, design and construction management, equipment procurement,
integration, commissioning, operations and maintenance, staffing and monitoring.
Our goal is to provide our customers with the peace of mind that comes from
knowing their mission-critical resources will always be there - 24/7/365.
For more information on Lee’s entire line of infrastructure solutions, call 877-654-9662
or visit www.leetechnologies.com.
8 7 7 - 6 5 4 - 9 6 6 2 • w w w . l e e t e c h n o l o g i e s . c o m
12150 MONUMENT DRIVE, SUITE 150, FAIRFAX,VA 22033 • 703-968-0300 ext.155 • FAX 703-654-3680
W ASHINGTON, D.C. BALTIMORE RICHMOND ATLANTA LOS ANGELES

More Related Content

What's hot

Improving Handover from Construction Phase to Commissioning Phase
Improving Handover from Construction Phase to Commissioning PhaseImproving Handover from Construction Phase to Commissioning Phase
Improving Handover from Construction Phase to Commissioning PhaseOlivia Wilson
 
Checklist for construction industry safety
Checklist for construction  industry safetyChecklist for construction  industry safety
Checklist for construction industry safetyStephen Au
 
On the journey of an enterprise transformation, Quality is still Job 1
On the journey of an enterprise transformation, Quality is still Job 1On the journey of an enterprise transformation, Quality is still Job 1
On the journey of an enterprise transformation, Quality is still Job 1Dave Mangot
 
Failure elimination made_simple_article_1_bk
Failure elimination made_simple_article_1_bkFailure elimination made_simple_article_1_bk
Failure elimination made_simple_article_1_bkRicky Smith CMRP, CMRT
 
Permit to Work (PTW) Software: Permit Control, Isolation & Control, Job Hazar...
Permit to Work (PTW) Software: Permit Control, Isolation & Control, Job Hazar...Permit to Work (PTW) Software: Permit Control, Isolation & Control, Job Hazar...
Permit to Work (PTW) Software: Permit Control, Isolation & Control, Job Hazar...ASK EHS Engineering & Consultants
 
SRE-iously! Defining the Principles, Habits, and Practices of Site Reliabilit...
SRE-iously! Defining the Principles, Habits, and Practices of Site Reliabilit...SRE-iously! Defining the Principles, Habits, and Practices of Site Reliabilit...
SRE-iously! Defining the Principles, Habits, and Practices of Site Reliabilit...Tori Wieldt
 
7 pitfalls of an oracle ebs upgrade biz tech[1]
7 pitfalls of an oracle ebs upgrade biz tech[1]7 pitfalls of an oracle ebs upgrade biz tech[1]
7 pitfalls of an oracle ebs upgrade biz tech[1]Thanapan Ittisakulchai
 
Root Cause Analysis - methods and best practice
Root Cause Analysis - methods and best practiceRoot Cause Analysis - methods and best practice
Root Cause Analysis - methods and best practiceMedgate Inc.
 
Refinery turnaround oil and gas
Refinery turnaround oil and gasRefinery turnaround oil and gas
Refinery turnaround oil and gasKaizenlogcom
 
Management of time uncertainty in agile
Management of time uncertainty in agileManagement of time uncertainty in agile
Management of time uncertainty in agileijseajournal
 
How to Overcome the 5 Barriers to Production App Security Testing
How to Overcome the 5 Barriers to Production App Security TestingHow to Overcome the 5 Barriers to Production App Security Testing
How to Overcome the 5 Barriers to Production App Security TestingCenzic
 
DOES14 - Reena Mathew and Dave Mangot - Salesforce
DOES14 - Reena Mathew and Dave Mangot - SalesforceDOES14 - Reena Mathew and Dave Mangot - Salesforce
DOES14 - Reena Mathew and Dave Mangot - SalesforceGene Kim
 
Why is your current PM Program not Effective?
Why is your current PM Program not Effective?Why is your current PM Program not Effective?
Why is your current PM Program not Effective?Ricky Smith CMRP, CMRT
 
Astr2013 tutorial by mike silverman of ops a la carte 40 years of halt, wha...
Astr2013 tutorial by mike silverman of ops a la carte   40 years of halt, wha...Astr2013 tutorial by mike silverman of ops a la carte   40 years of halt, wha...
Astr2013 tutorial by mike silverman of ops a la carte 40 years of halt, wha...ASQ Reliability Division
 
Engica ptw-electronic-permit-to-work-step-change-
Engica ptw-electronic-permit-to-work-step-change-Engica ptw-electronic-permit-to-work-step-change-
Engica ptw-electronic-permit-to-work-step-change-Risman BizNet
 

What's hot (19)

Improving Handover from Construction Phase to Commissioning Phase
Improving Handover from Construction Phase to Commissioning PhaseImproving Handover from Construction Phase to Commissioning Phase
Improving Handover from Construction Phase to Commissioning Phase
 
Checklist for construction industry safety
Checklist for construction  industry safetyChecklist for construction  industry safety
Checklist for construction industry safety
 
On the journey of an enterprise transformation, Quality is still Job 1
On the journey of an enterprise transformation, Quality is still Job 1On the journey of an enterprise transformation, Quality is still Job 1
On the journey of an enterprise transformation, Quality is still Job 1
 
Failure elimination made_simple_article_1_bk
Failure elimination made_simple_article_1_bkFailure elimination made_simple_article_1_bk
Failure elimination made_simple_article_1_bk
 
Permit to Work (PTW) Software: Permit Control, Isolation & Control, Job Hazar...
Permit to Work (PTW) Software: Permit Control, Isolation & Control, Job Hazar...Permit to Work (PTW) Software: Permit Control, Isolation & Control, Job Hazar...
Permit to Work (PTW) Software: Permit Control, Isolation & Control, Job Hazar...
 
SRE-iously! Defining the Principles, Habits, and Practices of Site Reliabilit...
SRE-iously! Defining the Principles, Habits, and Practices of Site Reliabilit...SRE-iously! Defining the Principles, Habits, and Practices of Site Reliabilit...
SRE-iously! Defining the Principles, Habits, and Practices of Site Reliabilit...
 
7 pitfalls of an oracle ebs upgrade biz tech[1]
7 pitfalls of an oracle ebs upgrade biz tech[1]7 pitfalls of an oracle ebs upgrade biz tech[1]
7 pitfalls of an oracle ebs upgrade biz tech[1]
 
Root Cause Analysis - methods and best practice
Root Cause Analysis - methods and best practiceRoot Cause Analysis - methods and best practice
Root Cause Analysis - methods and best practice
 
Refinery turnaround oil and gas
Refinery turnaround oil and gasRefinery turnaround oil and gas
Refinery turnaround oil and gas
 
Software fmea for medical devices
Software fmea for medical devicesSoftware fmea for medical devices
Software fmea for medical devices
 
Management of time uncertainty in agile
Management of time uncertainty in agileManagement of time uncertainty in agile
Management of time uncertainty in agile
 
How to Overcome the 5 Barriers to Production App Security Testing
How to Overcome the 5 Barriers to Production App Security TestingHow to Overcome the 5 Barriers to Production App Security Testing
How to Overcome the 5 Barriers to Production App Security Testing
 
The Basics Of Failures
The Basics Of FailuresThe Basics Of Failures
The Basics Of Failures
 
RCM
RCMRCM
RCM
 
Why RCM Doesn\'t Work
Why RCM Doesn\'t WorkWhy RCM Doesn\'t Work
Why RCM Doesn\'t Work
 
DOES14 - Reena Mathew and Dave Mangot - Salesforce
DOES14 - Reena Mathew and Dave Mangot - SalesforceDOES14 - Reena Mathew and Dave Mangot - Salesforce
DOES14 - Reena Mathew and Dave Mangot - Salesforce
 
Why is your current PM Program not Effective?
Why is your current PM Program not Effective?Why is your current PM Program not Effective?
Why is your current PM Program not Effective?
 
Astr2013 tutorial by mike silverman of ops a la carte 40 years of halt, wha...
Astr2013 tutorial by mike silverman of ops a la carte   40 years of halt, wha...Astr2013 tutorial by mike silverman of ops a la carte   40 years of halt, wha...
Astr2013 tutorial by mike silverman of ops a la carte 40 years of halt, wha...
 
Engica ptw-electronic-permit-to-work-step-change-
Engica ptw-electronic-permit-to-work-step-change-Engica ptw-electronic-permit-to-work-step-change-
Engica ptw-electronic-permit-to-work-step-change-
 

Similar to Maximizing_Uptime_in_MC_Facilities

8 Best Practices for New Project Commissioning
8 Best Practices for New Project Commissioning8 Best Practices for New Project Commissioning
8 Best Practices for New Project CommissioningOlivia Wilson
 
Commissioning-Specific Best Practices during the Construction Phase
Commissioning-Specific Best Practices during the Construction PhaseCommissioning-Specific Best Practices during the Construction Phase
Commissioning-Specific Best Practices during the Construction PhaseOlivia Wilson
 
Reconsidering the Potential of Commissioning and Startup
Reconsidering the Potential of Commissioning and StartupReconsidering the Potential of Commissioning and Startup
Reconsidering the Potential of Commissioning and StartupOlivia Wilson
 
Chapter 01 - Introduction.pdf
Chapter 01 - Introduction.pdfChapter 01 - Introduction.pdf
Chapter 01 - Introduction.pdfAnas Nakash
 
Wind river webinar deck v1 as of april 23 2014 dw2
Wind river webinar deck v1 as of april 23 2014 dw2Wind river webinar deck v1 as of april 23 2014 dw2
Wind river webinar deck v1 as of april 23 2014 dw2Intel IoT
 
aw_survivalguide_r2opt
aw_survivalguide_r2optaw_survivalguide_r2opt
aw_survivalguide_r2optReza Abed
 
Automation Project Survival Guide.pptx
Automation Project Survival Guide.pptxAutomation Project Survival Guide.pptx
Automation Project Survival Guide.pptxRaymund Gatoc
 
Commissioning-Specific Best Practices during the Construction Phase
Commissioning-Specific Best Practices during the Construction PhaseCommissioning-Specific Best Practices during the Construction Phase
Commissioning-Specific Best Practices during the Construction PhaseOlivia Wilson
 
Commissioning-Specific Best Practices during the Construction Phase
Commissioning-Specific Best Practices during the Construction PhaseCommissioning-Specific Best Practices during the Construction Phase
Commissioning-Specific Best Practices during the Construction PhaseOlivia Wilson
 
Site-Reliability-Engineering-v2[6241].pdf
Site-Reliability-Engineering-v2[6241].pdfSite-Reliability-Engineering-v2[6241].pdf
Site-Reliability-Engineering-v2[6241].pdfDeepakGupta747774
 
Lect3 conventional vs modern spm
Lect3 conventional vs modern spmLect3 conventional vs modern spm
Lect3 conventional vs modern spmmeena466141
 
Disaster Recovery: Develop Efficient Critique for an Emergency
Disaster Recovery: Develop Efficient Critique for an EmergencyDisaster Recovery: Develop Efficient Critique for an Emergency
Disaster Recovery: Develop Efficient Critique for an Emergencysco813f8ko
 
MCVisionWP1A_2003
MCVisionWP1A_2003MCVisionWP1A_2003
MCVisionWP1A_2003Jason Reid
 
The Top Ten things that have been proven to effect software reliability
The Top Ten things that have been proven to effect software reliabilityThe Top Ten things that have been proven to effect software reliability
The Top Ten things that have been proven to effect software reliabilityAnn Marie Neufelder
 
Lect2 conventional software management
Lect2 conventional software managementLect2 conventional software management
Lect2 conventional software managementmeena466141
 
the-top-ten-things-that-have-been-proven-to-effect-software-reliability-1.pdf
the-top-ten-things-that-have-been-proven-to-effect-software-reliability-1.pdfthe-top-ten-things-that-have-been-proven-to-effect-software-reliability-1.pdf
the-top-ten-things-that-have-been-proven-to-effect-software-reliability-1.pdfmattcs901
 
Importance of Communication during the Commissioning Phase
Importance of Communication during the Commissioning PhaseImportance of Communication during the Commissioning Phase
Importance of Communication during the Commissioning PhaseOlivia Wilson
 
Boosting Field Efficiency with advanced Construction Field Productivity Softw...
Boosting Field Efficiency with advanced Construction Field Productivity Softw...Boosting Field Efficiency with advanced Construction Field Productivity Softw...
Boosting Field Efficiency with advanced Construction Field Productivity Softw...iFieldsmart Technologies
 
The Top Ten things that have been proven to effect software reliability
The Top Ten things that have been proven to effect software reliabilityThe Top Ten things that have been proven to effect software reliability
The Top Ten things that have been proven to effect software reliabilityAnn Marie Neufelder
 

Similar to Maximizing_Uptime_in_MC_Facilities (20)

8 Best Practices for New Project Commissioning
8 Best Practices for New Project Commissioning8 Best Practices for New Project Commissioning
8 Best Practices for New Project Commissioning
 
Commissioning-Specific Best Practices during the Construction Phase
Commissioning-Specific Best Practices during the Construction PhaseCommissioning-Specific Best Practices during the Construction Phase
Commissioning-Specific Best Practices during the Construction Phase
 
Reconsidering the Potential of Commissioning and Startup
Reconsidering the Potential of Commissioning and StartupReconsidering the Potential of Commissioning and Startup
Reconsidering the Potential of Commissioning and Startup
 
Chapter 01 - Introduction.pdf
Chapter 01 - Introduction.pdfChapter 01 - Introduction.pdf
Chapter 01 - Introduction.pdf
 
Wind river webinar deck v1 as of april 23 2014 dw2
Wind river webinar deck v1 as of april 23 2014 dw2Wind river webinar deck v1 as of april 23 2014 dw2
Wind river webinar deck v1 as of april 23 2014 dw2
 
aw_survivalguide_r2opt
aw_survivalguide_r2optaw_survivalguide_r2opt
aw_survivalguide_r2opt
 
Stay Ahead of Risk
Stay Ahead of RiskStay Ahead of Risk
Stay Ahead of Risk
 
Automation Project Survival Guide.pptx
Automation Project Survival Guide.pptxAutomation Project Survival Guide.pptx
Automation Project Survival Guide.pptx
 
Commissioning-Specific Best Practices during the Construction Phase
Commissioning-Specific Best Practices during the Construction PhaseCommissioning-Specific Best Practices during the Construction Phase
Commissioning-Specific Best Practices during the Construction Phase
 
Commissioning-Specific Best Practices during the Construction Phase
Commissioning-Specific Best Practices during the Construction PhaseCommissioning-Specific Best Practices during the Construction Phase
Commissioning-Specific Best Practices during the Construction Phase
 
Site-Reliability-Engineering-v2[6241].pdf
Site-Reliability-Engineering-v2[6241].pdfSite-Reliability-Engineering-v2[6241].pdf
Site-Reliability-Engineering-v2[6241].pdf
 
Lect3 conventional vs modern spm
Lect3 conventional vs modern spmLect3 conventional vs modern spm
Lect3 conventional vs modern spm
 
Disaster Recovery: Develop Efficient Critique for an Emergency
Disaster Recovery: Develop Efficient Critique for an EmergencyDisaster Recovery: Develop Efficient Critique for an Emergency
Disaster Recovery: Develop Efficient Critique for an Emergency
 
MCVisionWP1A_2003
MCVisionWP1A_2003MCVisionWP1A_2003
MCVisionWP1A_2003
 
The Top Ten things that have been proven to effect software reliability
The Top Ten things that have been proven to effect software reliabilityThe Top Ten things that have been proven to effect software reliability
The Top Ten things that have been proven to effect software reliability
 
Lect2 conventional software management
Lect2 conventional software managementLect2 conventional software management
Lect2 conventional software management
 
the-top-ten-things-that-have-been-proven-to-effect-software-reliability-1.pdf
the-top-ten-things-that-have-been-proven-to-effect-software-reliability-1.pdfthe-top-ten-things-that-have-been-proven-to-effect-software-reliability-1.pdf
the-top-ten-things-that-have-been-proven-to-effect-software-reliability-1.pdf
 
Importance of Communication during the Commissioning Phase
Importance of Communication during the Commissioning PhaseImportance of Communication during the Commissioning Phase
Importance of Communication during the Commissioning Phase
 
Boosting Field Efficiency with advanced Construction Field Productivity Softw...
Boosting Field Efficiency with advanced Construction Field Productivity Softw...Boosting Field Efficiency with advanced Construction Field Productivity Softw...
Boosting Field Efficiency with advanced Construction Field Productivity Softw...
 
The Top Ten things that have been proven to effect software reliability
The Top Ten things that have been proven to effect software reliabilityThe Top Ten things that have been proven to effect software reliability
The Top Ten things that have been proven to effect software reliability
 

Maximizing_Uptime_in_MC_Facilities

  • 1. Maximizing Uptime in Mission-Critical Facilities By Joe Soroka Director of Technical Services Lee Technologies
  • 2. 1 Maximizing Uptime in Mission-Critical Facilities As technology reaches into every corner of our world, the importance of, and reliance on, your mission- critical facility reaches new heights. Uptime is no longer a lofty goal, it is an absolute necessity. However, uptime is not a product that you specify with the design of your facility, install, and then forget about. A facility designed to 99.99% of availability will not achieve/maintain that number, unless we fully understand the many factors that affect uptime. Maximum Uptime is a philosophy. It begins with the planning of your facility, and remains a continuous process through every step of design, construction, commissioning, operations, failure analysis and recommissioning. Lessons Learned Long Ago Help Us Achieve Uptime Today September 17, 1908: Orville Wright’s flying machine crashes at Fort Meyer,Virginia, killing co-pilot T.E. Selfridge, and an aircraft accident investigation board is born. The Aeronautical Board of the U.S.Army Signal Corps and the Aerial Experiment Association (AEA) headed by Alexander Graham Bell and his associates, conducted a thorough accident investigation. Through their findings, Dr. Bell realized the importance of preventing failures in the future
  • 3. 2 and wrote an article entitled "The Lessons to be Learned from Orville Wright’s Disaster". “Lessons Learned” have become an essential tool in the prevention of aircraft accidents. Today, based on their investigation into the cause of an accident, the National Transportation Safety Board (NTSB) develops and issues "lessons learned" to prevent similar failures in the future. Preventing failures in mission-critical facilities requires a similar approach to ensure maximum uptime. Four Categories of Failure NTSB investigations establish that accidents occur due to one or more types of failures: design failures, catastrophic failures, compounding failures or human-error failures. Downtime at mission-critical facilities can be attributed to these four types of failures, as well, and each requires a different approach on prevention. All four types of potential failures must be examined, and "lessons learned" programs established in order to realize Maximum Uptime for your Mission-Critical Facilities. Design Failures can be eliminated by first engaging with competent vendors. Selecting the appropriate design firm, integration firm, construction companies and commissioning team along with the operations staff is crucial to acquiring the experience needed to reduce these types of failures. Catastrophic Failures are usually unpredictable in nature. However, a comprehensive maintenance and operations programs can identify and eliminate as many potential problems as possible.This can also help eliminate the
  • 4. 3 condition that contributed to the weakness and minimize the effects of truly unpredictable problems. Compounding Failures are caused when multiple events occur to create a failure. The lack of attention to details is a leading cause in compounding failures. Little nuisance items in a large facility are sometimes left unnoticed and by themselves cause no ill effect to the facility, but along with other problems, can combine to create a system failure. Human-error Failures are a leading cause of failures in mission-critical facilities. These failures can be reduced by having an experienced staff that receives continuous training. Even with a competent and trained staff, the requirement for switch-level, detailed Methods-of-Procedure (MOPs) are still required.These MOPs should be executed with a pilot/co-pilot approach. Begin with the End in Mind Whether it’s new construction, upgrading or operating an existing mission-critical facility, it is important to carefully plan the work and to work the plan. In the design phase, it is important to consult with design teams experienced in the design of the particular type of mission- critical facilities that your organization requires. A crucial part of the design phase is the early development of the Design Intent. Unfortunately the Design Intent too often is not fully
  • 5. 4 developed, or is vague. The Design Intent should clearly state the owner’s requirements. A well-created Design Intent document will start with a narrative of the project background, and provide a detailed discussion of the required objectives and goals. Required functional uses and requirements of the mission-critical facility should be clearly explained.While often difficult to quantify, performance and maintenance criteria should also be addressed. Finally, the expected lifespan and overall quality of the project needs to be defined. A comprehensive Design Intent is crucial for all involved parties to succeed in achieving maximum uptime in a mission-critical facility.Without it, too much interpretation by the various parties involved, can lead to compromises and misunderstandings that weaken the integrity of everything which follows. Selecting a Design Concept There is not a single ideal facility design configuration. Any of a number of design concepts will accomplish similar goals, each with its own advantages and disadvantages.The required system reliability and project budget will be a driving force. However, there are four basic categories of design concepts;Tier I,Tier II,Tier III and Tier IV. Tier 1 • Single active delivery path • Need (N) of capacity
  • 6. 5 • Site availability of 99.671 % • Annual downtime of 28.8 hours Tier II • Single active delivery path • Need + Redundancy (N+1) of capacity • Site availability of 99.749 % • Annual downtime of 22.0 hours Tier III • One active and one passive delivery path • Need + Redundancy (N+1) of capacity • Site availability of 99.982 % • Annual downtime of 1.6 hours Tier IV • Two active delivery path • Need + Need with Redundancy 2 (N+1) of capacity • Site availability of 99.995 % • Annual downtime of 0.4 hours Setting the Pace Developing a realistic project schedule and updating it throughout the project will help eliminate unwanted surprises and avoid delays. When developing the schedule, determine the required milestones and list the items that can impact them.
  • 7. 6 A Keepsake Moment Keeping a detail construction log along with digital pictures is very helpful to a project. After the site is operational, there will come a time when you will want to refer to the construction photos to see how a piece of equipment was installed. Well-organized construction photo albums will provide a wealth of information years after the project’s completion when the operations staff must perform maintenance, upgrades or repairs. Safety First Insist on vendors providing safety plans before any work begins. Review the plans to ensure they’re current and appropriate to your project. Injury and fatalities can effect the reputation of your organization, along with the potential for OSHA fines and other litigation costs.An unsafe project will add additional costs and delays to the project. Invest the upfront time to ensure the project site is safe from the beginning. It will save time, money and possibly lives. Equipment Selection & Integration Selecting the right equipment vendors for the project helps ensure its successful completion. It is crucial to ensure that the equipment vendor meets the engineering specifications. Beyond the equipment-side however, the vendor’s ability to support the equipment is an equally important consideration. This includes delivery times,
  • 8. 7 installation support, start-up services and the availability of spare parts and authorized maintenance personnel. For complex systems and fast-track projects, consider using an equipment integrator. Complex systems rely on the operation of multiple systems and platforms.Therefore, it is essential to have the support of an organization focused on the overall connectivity and interaction of multiple systems.A qualified integrator can help eliminate the confusion that multiple Request for Information (RFIs) from various installing contractors can cause. Integrators provide the owner with a single point- of-contact, reducing the project’s completion time, and ensuring that all of the systems are properly installed and interconnected. All Aboard In addition, schedule a thorough onboard submittal review meeting during the equipment procurement stage. This meeting will help reduce RFIs, change orders and can greatly improve the overall project schedule. The onboard submittal review meeting should be attended by the owner, engineers, general contractor, equipment integrator, electrical and mechanical subcontractors, equipment manufactures, commissioning agents and all parties involved in the integration, installation, start-up and commissioning of the site. The submittal for each major piece of equipment should be reviewed for engineering accuracy, required equipment options, delivery essentials, proper space layout, installation and start-up necessities.Any changes or
  • 9. 8 concerns for the equipment should be addressed and resolved. It is easier to correct a potential problem during the procurement phase than after the equipment has shipped to the site. The complexity of your mission-critical facility increases due to interconnectivity and monitoring requirements. Most engineering drawings do not show the connection of control wiring to systems from other manufacturers.Typically consulting engineers indicate these connections with a cloud symbol and the words "By Others." Avoid uncertainty by relying on a specialized equipment integrator to develop the control drawings with connection points. Control and monitoring connections are essential to the overall health of the facility’s infrastructure, and this is the time to ensure seamless integration. Commissioning Commissioning is the systematic process of verifying and documenting the performance of the facility’s equipment. This process has several distinct phases, including the Planning Phase, Design Phase, Construction Phase,Acceptance Phase and the Post-Acceptance Phase. Commissioning a facility has many benefits providing direct and indirect paybacks. Prior to starting the commissioning program, take the time to define the key purpose of the program. For example, systems can be setup to achieve higher energy efficiency, but this may affect the system reliability. Trade-offs between energy efficiency and system reliability must be carefully weighed.This is ultimately a priority-based decision for the owner.
  • 10. 9 There are a number of benefits to Commissioning a facility, including: • Improved system performance and reliability, • Reduced energy consumption, • Improved environmental controls and Indoor Air Quality (IAQ), • Hands-on training for operations and maintenance personnel, • Early identification of outstanding issues, • Verification of operating parameters and procedures, • Establishing an operating baseline, • Extended equipment life, • Reduced occupant IAQ complaints including hot and cold calls. Commissioning Procedures All operating procedures should be tested for functionality during the Commissioning process. This includes start-up and shutdown of equipment, equipment- bypass and failure-recovery procedures. Equipment should be exercised through all of the modes of operation.To avoid future problems, it is essential to verify all operational modes and procedure methods before the facility is occupied. Recommissioning Recommissioning is the process of commissioning a previously-commissioned facility to which changes have been
  • 11. 10 made. The original commissioning documents are used as a baseline for the facility’s operating performance.When developing the recommissioning plan, it is important that all new equipment and upgrades are added to the new plan. Since the building is occupied during the recommissioning process, a detailed Method of Procedures must be developed to allow complete testing without affecting the facility operations. This may require temporarily placing equipment out of service, in bypass mode, after-hour work windows and the use of temporary equipment. In the case of a mission-critical facility, great care must be taken to evaluate the system and to develop the correct procedures to ensure the required uptime. How often a facility is recommissioned is dependent upon several factors, including the required system availability and reliability, the effects of improper performance on operations, energy consumption, energy costs, and the amount of changes and upgrades that have occurred since the facility was last commissioned.Typically, a mission-critical facility should be recommissioned every 3 to 6 years. Retro-commissioning Retro-commissioning is the process of commissioning an existing building that has not previously been commissioned. The retro-commissioning process is the same as the commissioning process with the exception that the building is occupied. Since the building is occupied and needs to remain operational, proper planning and development of detailed Method of Procedures will need to occur in the same manner as a recommissioning effort.
  • 12. 11 Construction Well-planned and meticulously implemented construction is the key foundation to facility reliability and maintainability.The owner should take an active role in selecting and working with the team throughout the construction process. A team approach to building your mission-critical facility will help to ensure that your final product will meet your specifications. Construction Inspections The owner, or the owner’s representative, should conduct regular inspections of the jobsite during the construction process to document and photograph the installation process. Any items of concern should be addressed immediately rather than waiting until after the installation is completed. Correcting construction issues at the time they occur will help to ensure that the project stays on schedule and within budget. Along with inspecting for proper installation, inspection for proper safety procedures, overall organization and cleanliness is a must. A dirty, disorganized and unsafe construction site can lead to accidents, delays and mistakes. Construction Meetings Conduct regular construction meetings that are professional and productive. Building a fast-track project for a mission-critical facility requires a team approach and a team is most effective working in unison. Good facilitation
  • 13. 12 and mediation skills can be tremendous assets. Professionalism,Team Work and Expertise will deliver a quality project on time. Equipment Selection When selecting equipment for your mission-critical facilities, it is important to work with an Integrator to verify that all of the equipment complies with the project specifications. Listed below are some equipment options to consider for a mission-critical facility. Generators When selecting the generator, review the technical specifications to ensure that your project needs are met. Review the generator’s available options. For example, optional isolation valves on the jacket water heater hose are inexpensive at the time of purchase. Replacing the jacket water heater hose in the field however, will require taking the generator out of service for an extended period of time. Another generator option to consider is auxiliary breaker contacts. Generator outages caused by a tripped or open generator breaker are surprisingly common. In addition, monitor and/or alarm the auxiliary contacts. The generator is there to provide power in the case of an outage, make sure it is ready when needed. UPS Systems There are as many different types of UPS systems as there are topologies.Your requirements may be best suited
  • 14. 13 for a double conversion, line interactive or delta conversion. Regardless of the type of system that fits the application, make sure the appropriate internal and external maintenance bypasses are installed. A maintenance bypass should be sized to support 100% load on external maintenance bypass while providing enough capacity to perform 100% load tests. UPS Batteries When using Valve Regulated Lead Acid (VRLA) batteries, specify multiple battery strings that can be independently isolated by opening a breaker. With an independently isolated VRLA battery string, maintenance can be performed while keeping the critical load on the UPS system. Utilities The August 2003 blackout affected communities stretching from Detroit to New York. Seconds after the power outage, thousands of generators received a start signal and most of them started. However, dead batteries, low fuel, low coolant, and generally poor maintenance left the others in the dark. The time to prepare for the next outage is now. In addition to electrical utility outages, mission-critical facilities must also prepare for failures from other utilities, including telecommunications, water, sewer and gas.
  • 15. 14 In the event of a water outage, sufficient water will be required to support the make-up water used in cooling towers as well as water for staff requirements. Redundant water sources, such as wells and storage tanks, are an important part of a disaster plan. In the event of a widespread outage, an adequate supply of diesel fuel is also important. During normal times, suppliers are able to provide more diesel fuel within hours, but a widespread outage will severely impact delivery schedules. Generator monitoring can help eliminate a fuel shortage.
  • 16. 15 Monitoring When selecting a monitoring system, understand the system’s capabilities and establish the various alarms, trends and notification to provide not only alarm notification, but also important historical data that can be used to predict and prevent failures. It is, of course, essential that the monitoring system itself continues to operate when the systems that are being monitored fail. Proper setup of monitoring system alarm points is crucial to preventing failures and/or minimizing their impact. Operations and Maintenance Staffing O&M Staffing Once the site is operational you will need to decide how to staff your facility. Whether you use inside or outside staff it is important that the depth of knowledge meets the requirements of your mission-critical facilities. Operating Procedures The development and verification of site operation, maintenance and recovery procedures are vital to maximizing uptime. Methods of Procedure (MOPs) should be very thorough and specific, written to the switch level detail, and tested during the project’s commissioning phase. Too often the rush to bring the facility online overshadows the need to develop, document and deploy MOPs. However, waiting to develop a procedure to transfer the UPS system to maintenance bypass could prove much more costly than
  • 17. 16 investing the time upfront to prepare for the inevitable. Procedures should be developed early and tested before the facility is fully operational. Maintenance Windows When designing or upgrading your facility, keep in mind the quantity and length of maintenance windows required to properly maintain the facility.The system will need the appropriate redundancy and bypasses in order to operate while maintenance is performed.An annual maintenance matrix should accompany the equipment list to ensure adequate redundancy allowances. Systems without the appropriate maintenance allowances may require the use of temporary equipment or the installation of additional systems if continuous uptime is a requirement. Predictive Maintenance Maintenance should go beyond remedial and preventative maintenance to include predictive maintenance. Using equipment trends and conducting a thorough failure analysis after each incident will help predict and in-turn proactively prevent future problems. All maintenance documentation should be detailed, and provide methods for predicting and anticipating potential troublespots and weaknesses. Details are the building blocks of a comprehensive predictive maintenance program. Maintenance Planning Plan all maintenance in advance. Start with the basics. Develop a complete equipment list and use that as a basis
  • 18. 17 for the planning matrix. Have specific procedures in place for each piece of equipment. The procedures should include start-up, shutdown, bypass, lock-out tag-out, maintenance and disaster recovery. Review maintenance windows and implement an automated equipment maintenance schedule that is strictly enforced. Disaster Planning & Recovery A comprehensive business continuity plan (BCP) is required for all mission-critical facilities. It is equally important to develop a comprehensive plan for all IT equipment and supporting infrastructure in your mission- critical facility. The plan should be a joint effort between the IT and Facilities departments and should be tested and updated at least once a year and/or as facilities changes occur. Training It is also important to have a comprehensive training program for the operation and maintenance staff. Training should start with the equipment manufacturer/installer. Start-ups and commissioning offer ideal opportunities for training operation and maintenance staff. Once the site is operational, schedule regular training to keep operational and maintenance staff current. As-Built Drawings After the installation, be sure to secure the project’s as-built drawings. Invest the time to verify the accuracy of
  • 19. 18 the drawings. Then institute a practice that ensures that all applicable drawings are undated as upgrades occur at the facilities. If they do not exist, a set of as-built drawings should be developed.As-built drawings are valuable tools in quickly resolving problems and restoring service in the event of a failure.Additionally, they are valuable when initiating facility upgrades. Keeping Good Company Ultimately, maximum uptime in the mission-critical facility runs on technology, trust and teamwork.Your infrastructure integrator works to orchestrate and coordinate the efforts of this diverse team to ensure your mission-critical facility delivers the performance and availability you require. For an asset as crucial as your mission-critical facility's infrastructure, it pays to invest the time to select a company you can trust, with the experience and resources to maximize uptime and mitigate risk. Ideally, your mission- critical infrastructure specialist will offer you all of the products, people, services and strategies needed to design, integrate, commission, staff, maintain, service and monitor your facility.Acquiring these crucial services from a single source can greatly reduce headaches and finger-pointing in the future. Benefit from Lessons Learned Technology has changed quite a bit in the nearly 100 years since “Orville Wright’s Disaster.” However, learning
  • 20. from failure remains the key to ensuring that history doesn’t repeat itself. An experienced mission-critical facilities infrastructure integrator can provide essential expertise in preventing failures and ensuring maximum uptime.Whether it’s design failures, catastrophic failures, compounding failures or human-error failures, there are steps that can eliminate, minimize or mitigate their effects. And an ongoing site-specific "lessons learned" program will become a living document that continues to help maximize uptime for your mission-critical facilities. Uptime is not a product and it is never complete. Uptime is a philosophy. It is a never ending process that is practiced, lived, learned and refined every day. Lee Technologies designs, installs and maintains the physical infrastructure that powers and protects mission-critical facilities throughout the United States.We offer customers a single source for complete lifecycle solutions, including mission-critical infrastructure assessments, design and construction management, equipment procurement, integration, commissioning, operations and maintenance, staffing and monitoring. Our goal is to provide our customers with the peace of mind that comes from knowing their mission-critical resources will always be there - 24/7/365. For more information on Lee’s entire line of infrastructure solutions, call 877-654-9662 or visit www.leetechnologies.com. 8 7 7 - 6 5 4 - 9 6 6 2 • w w w . l e e t e c h n o l o g i e s . c o m 12150 MONUMENT DRIVE, SUITE 150, FAIRFAX,VA 22033 • 703-968-0300 ext.155 • FAX 703-654-3680 W ASHINGTON, D.C. BALTIMORE RICHMOND ATLANTA LOS ANGELES