SlideShare a Scribd company logo
1 of 13
Download to read offline
2004 Paving Conference
Joe J. Sanchez, P.E.
NMDOT
In collaboration with
Elias Archuleta, P.E.
Wilson & Company
Minimum Standards and
Congruence of Interests
 Two Distinct Areas
 During Design
 Engineering Responsibility (MUTCD, Engineers
Judgment, Designed Construction Phasing,
Minimizing Impact to the Traveling Public)
 Under Construction
 Contractor Responsibility ( Compliance with
Specification, Adjusting Construction Phasing,
Maintenance of Traffic Operations, Minimizing
Impact to the Traveling Public)
Design and Engineering
 Manual of Uniform Traffic Control Devices
 Sets Minimum Design Standards and Devices
 Engineers Judgment
 Experience and Knowledge to Adjust or Modify
Minimum Design Standards and Devices
 Designed Construction Phasing
 Anticipated Contractor Phasing for Construction
 Minimizing Impact to the Traveling Public
 Delays, Route Redundancy, Changes in MOT
Operations
Contractors Responsibility
 Compliance with the Project Specifications
 What Traffic Control or Traffic Operations Specification
Applies
 Adjustment of Construction Phasing
 How to Modify during Construction-TCP
 Maintenance of Traffic Operations
 Duration, Sequence, Locations, Devices, Engineering
Standards
 Minimizing Impact to the Traveling Public
 Detours, Route Redundancy, Travel Times/Distances,
Public Information/Notices
Congruence of Interests through
Areas of Conflict
 Construction Phasing
 Designers/Engineers need to Optimize
Flexibility in Traffic Control Plans and
Anticipated Phasing- Contractor/Design
Engineer Workshops (Means, Methods,
Costs)
 Contractors need to understand what is in
Project Specification Contract Documents
Direction, Limitations, Standards-
Design/Engineer/Contractor Workshops
(Design Standards, Phased EW, Costs of
Delays)
Why is Impact to the Traveling
Public Important
 For Engineer
 Contractor understands phasing-no change=perfect
TCP
 Minimal time delays for public-transparent between
construction and normal operations
 For Contractor
 Easy to Bid-easy to modify
 Minimal costs
 Good PR with the Citizens affected by the project
Original TCP
Revised TCP
Why was the Change “Win-Win”
 Contractor was able to work in an expanded
work zone (directly applicable to means and
methods, and costs)
 TCP change provided safer traffic
operations for users of intersection and
work zone ( directly applicable to reduced
traffic conflicts, associated time delays, and
costs-resulted in good PR)
Who else won
 The Department
 Increased safety at Intersection under
construction
 Contractor completed work more quickly
 Business Owners/Private Landowners,
and Roadway users were minimally
inconvenienced during construction
Where do we go from Here?
 Major area of unknown
 Actual Contractor Construction Phasing
 Affects - TCP, MOT, Revised TCP’s,
Earthwork, Time, and Costs
Your Chance to Affect Change
 Questionnaire
 Built around 2 conditions
 Full Reconstruction with complicated phasing
 Maintenance and rehabilitation
 Typical or Common areas of use
 Interstate and NHS routes
 State Oversight and State Routes
Mobility for Everyone

More Related Content

Viewers also liked

Shiseido Brand Audit
Shiseido Brand AuditShiseido Brand Audit
Shiseido Brand AuditSara Chen
 
Curso De Tanatoplastia Y Tanatopraxia
Curso De Tanatoplastia Y Tanatopraxia
Curso De Tanatoplastia Y Tanatopraxia
Curso De Tanatoplastia Y Tanatopraxia hollownymph4279
 
Antropologi hukum (Piyantoro PPT)
Antropologi hukum (Piyantoro PPT)Antropologi hukum (Piyantoro PPT)
Antropologi hukum (Piyantoro PPT)Belum Kerja
 
project on business communication
project on business communicationproject on business communication
project on business communicationBandel Ghosh
 
LOS MICROORGANISMOS EN LOS SERES HUMANOS Y ALIMENTOS
LOS MICROORGANISMOS EN LOS SERES HUMANOS Y ALIMENTOSLOS MICROORGANISMOS EN LOS SERES HUMANOS Y ALIMENTOS
LOS MICROORGANISMOS EN LOS SERES HUMANOS Y ALIMENTOSPAUL1235
 
Lugares únicos en el mundo
Lugares únicos en el mundoLugares únicos en el mundo
Lugares únicos en el mundomiriam2807
 
Sizing of solar cooling systems
Sizing of solar cooling systemsSizing of solar cooling systems
Sizing of solar cooling systemsSolar Reference
 
efb2e0_aa9751d1d58043f9bff991cd29ff8d94
efb2e0_aa9751d1d58043f9bff991cd29ff8d94efb2e0_aa9751d1d58043f9bff991cd29ff8d94
efb2e0_aa9751d1d58043f9bff991cd29ff8d94Jacob Harris
 
Actividad 2 reconocimiento_434207_a
Actividad 2 reconocimiento_434207_aActividad 2 reconocimiento_434207_a
Actividad 2 reconocimiento_434207_aargompls
 
.Cronograma de examenes diciembre
.Cronograma de examenes diciembre.Cronograma de examenes diciembre
.Cronograma de examenes diciembreSecundaria135
 
Recuperación Tecnología e Informática Periodo Final
Recuperación Tecnología e Informática Periodo Final Recuperación Tecnología e Informática Periodo Final
Recuperación Tecnología e Informática Periodo Final karol066
 

Viewers also liked (15)

Shiseido Brand Audit
Shiseido Brand AuditShiseido Brand Audit
Shiseido Brand Audit
 
WWDC 2015 - Round Up
WWDC 2015 - Round UpWWDC 2015 - Round Up
WWDC 2015 - Round Up
 
Curso De Tanatoplastia Y Tanatopraxia
Curso De Tanatoplastia Y Tanatopraxia
Curso De Tanatoplastia Y Tanatopraxia
Curso De Tanatoplastia Y Tanatopraxia
 
Antropologi hukum (Piyantoro PPT)
Antropologi hukum (Piyantoro PPT)Antropologi hukum (Piyantoro PPT)
Antropologi hukum (Piyantoro PPT)
 
project on business communication
project on business communicationproject on business communication
project on business communication
 
LOS MICROORGANISMOS EN LOS SERES HUMANOS Y ALIMENTOS
LOS MICROORGANISMOS EN LOS SERES HUMANOS Y ALIMENTOSLOS MICROORGANISMOS EN LOS SERES HUMANOS Y ALIMENTOS
LOS MICROORGANISMOS EN LOS SERES HUMANOS Y ALIMENTOS
 
Lugares únicos en el mundo
Lugares únicos en el mundoLugares únicos en el mundo
Lugares únicos en el mundo
 
Sizing of solar cooling systems
Sizing of solar cooling systemsSizing of solar cooling systems
Sizing of solar cooling systems
 
Myslec jak-milionerzy
Myslec jak-milionerzyMyslec jak-milionerzy
Myslec jak-milionerzy
 
Suprema libertad de la voluntad de dios 4ta ronda equipo 4
Suprema libertad de la voluntad de dios 4ta ronda equipo 4Suprema libertad de la voluntad de dios 4ta ronda equipo 4
Suprema libertad de la voluntad de dios 4ta ronda equipo 4
 
Img ems
Img emsImg ems
Img ems
 
efb2e0_aa9751d1d58043f9bff991cd29ff8d94
efb2e0_aa9751d1d58043f9bff991cd29ff8d94efb2e0_aa9751d1d58043f9bff991cd29ff8d94
efb2e0_aa9751d1d58043f9bff991cd29ff8d94
 
Actividad 2 reconocimiento_434207_a
Actividad 2 reconocimiento_434207_aActividad 2 reconocimiento_434207_a
Actividad 2 reconocimiento_434207_a
 
.Cronograma de examenes diciembre
.Cronograma de examenes diciembre.Cronograma de examenes diciembre
.Cronograma de examenes diciembre
 
Recuperación Tecnología e Informática Periodo Final
Recuperación Tecnología e Informática Periodo Final Recuperación Tecnología e Informática Periodo Final
Recuperación Tecnología e Informática Periodo Final
 

Similar to 2004 Paving Conference CTTCP

COST EFFECIENT CHAP 2 ppt.pptx
COST EFFECIENT CHAP 2 ppt.pptxCOST EFFECIENT CHAP 2 ppt.pptx
COST EFFECIENT CHAP 2 ppt.pptxabedamtie
 
Tc iv submited paper risk analysis and managements large epc projects
Tc iv submited paper risk analysis and managements  large epc projectsTc iv submited paper risk analysis and managements  large epc projects
Tc iv submited paper risk analysis and managements large epc projectsPALLA NARASIMHUDU
 
2016 11-03 ta bod highway-101-92 interchange
2016 11-03 ta bod highway-101-92 interchange2016 11-03 ta bod highway-101-92 interchange
2016 11-03 ta bod highway-101-92 interchangeAdina Levin
 
Dinamikler 2017 - Alan Sharp Sunum
Dinamikler 2017 - Alan Sharp SunumDinamikler 2017 - Alan Sharp Sunum
Dinamikler 2017 - Alan Sharp Sunumdinamikler17
 
HOCH,_Randall_E_2
HOCH,_Randall_E_2HOCH,_Randall_E_2
HOCH,_Randall_E_2Randy Hoch
 
S.D.Parson CV-Resume - 2016
S.D.Parson CV-Resume - 2016S.D.Parson CV-Resume - 2016
S.D.Parson CV-Resume - 2016Dean Parson
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Antonio Coladarce
 
Construction management
Construction managementConstruction management
Construction managementvhjadhav
 
CV _Eng_Tran Cong Danh_Project Engineer_15-Oct-16
CV _Eng_Tran Cong Danh_Project Engineer_15-Oct-16CV _Eng_Tran Cong Danh_Project Engineer_15-Oct-16
CV _Eng_Tran Cong Danh_Project Engineer_15-Oct-16Cong Danh Tran
 
SimScale Demo and Discussion on External AEC
SimScale Demo and Discussion on External AECSimScale Demo and Discussion on External AEC
SimScale Demo and Discussion on External AECSimScale
 
Environmental clearance of airports
Environmental clearance of airportsEnvironmental clearance of airports
Environmental clearance of airportsAbhishek Kumar Sinha
 
Project Name Motional Energy Generation and Recovery Associ.docx
Project Name Motional Energy Generation and Recovery Associ.docxProject Name Motional Energy Generation and Recovery Associ.docx
Project Name Motional Energy Generation and Recovery Associ.docxwkyra78
 
Arun das latest resume
Arun das latest resumeArun das latest resume
Arun das latest resumeArun Das
 

Similar to 2004 Paving Conference CTTCP (20)

Antonio MartinezArano B. Ch. E, MBA, PMP, Resume
Antonio MartinezArano B. Ch. E, MBA, PMP, ResumeAntonio MartinezArano B. Ch. E, MBA, PMP, Resume
Antonio MartinezArano B. Ch. E, MBA, PMP, Resume
 
COST EFFECIENT CHAP 2 ppt.pptx
COST EFFECIENT CHAP 2 ppt.pptxCOST EFFECIENT CHAP 2 ppt.pptx
COST EFFECIENT CHAP 2 ppt.pptx
 
Tc iv submited paper risk analysis and managements large epc projects
Tc iv submited paper risk analysis and managements  large epc projectsTc iv submited paper risk analysis and managements  large epc projects
Tc iv submited paper risk analysis and managements large epc projects
 
Senior Mechanical Engineer CV
Senior Mechanical Engineer CVSenior Mechanical Engineer CV
Senior Mechanical Engineer CV
 
2016 11-03 ta bod highway-101-92 interchange
2016 11-03 ta bod highway-101-92 interchange2016 11-03 ta bod highway-101-92 interchange
2016 11-03 ta bod highway-101-92 interchange
 
ST Electronics
ST ElectronicsST Electronics
ST Electronics
 
Dinamikler 2017 - Alan Sharp Sunum
Dinamikler 2017 - Alan Sharp SunumDinamikler 2017 - Alan Sharp Sunum
Dinamikler 2017 - Alan Sharp Sunum
 
HOCH,_Randall_E_2
HOCH,_Randall_E_2HOCH,_Randall_E_2
HOCH,_Randall_E_2
 
S.D.Parson CV-Resume - 2016
S.D.Parson CV-Resume - 2016S.D.Parson CV-Resume - 2016
S.D.Parson CV-Resume - 2016
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
 
Construction management
Construction managementConstruction management
Construction management
 
PROJECT_STEPS
PROJECT_STEPSPROJECT_STEPS
PROJECT_STEPS
 
CV _Eng_Tran Cong Danh_Project Engineer_15-Oct-16
CV _Eng_Tran Cong Danh_Project Engineer_15-Oct-16CV _Eng_Tran Cong Danh_Project Engineer_15-Oct-16
CV _Eng_Tran Cong Danh_Project Engineer_15-Oct-16
 
Bill resume
Bill resumeBill resume
Bill resume
 
Economic Impact Analysis
Economic Impact AnalysisEconomic Impact Analysis
Economic Impact Analysis
 
Copp.ppt
Copp.pptCopp.ppt
Copp.ppt
 
SimScale Demo and Discussion on External AEC
SimScale Demo and Discussion on External AECSimScale Demo and Discussion on External AEC
SimScale Demo and Discussion on External AEC
 
Environmental clearance of airports
Environmental clearance of airportsEnvironmental clearance of airports
Environmental clearance of airports
 
Project Name Motional Energy Generation and Recovery Associ.docx
Project Name Motional Energy Generation and Recovery Associ.docxProject Name Motional Energy Generation and Recovery Associ.docx
Project Name Motional Energy Generation and Recovery Associ.docx
 
Arun das latest resume
Arun das latest resumeArun das latest resume
Arun das latest resume
 

2004 Paving Conference CTTCP

  • 1. 2004 Paving Conference Joe J. Sanchez, P.E. NMDOT In collaboration with Elias Archuleta, P.E. Wilson & Company
  • 2. Minimum Standards and Congruence of Interests  Two Distinct Areas  During Design  Engineering Responsibility (MUTCD, Engineers Judgment, Designed Construction Phasing, Minimizing Impact to the Traveling Public)  Under Construction  Contractor Responsibility ( Compliance with Specification, Adjusting Construction Phasing, Maintenance of Traffic Operations, Minimizing Impact to the Traveling Public)
  • 3. Design and Engineering  Manual of Uniform Traffic Control Devices  Sets Minimum Design Standards and Devices  Engineers Judgment  Experience and Knowledge to Adjust or Modify Minimum Design Standards and Devices  Designed Construction Phasing  Anticipated Contractor Phasing for Construction  Minimizing Impact to the Traveling Public  Delays, Route Redundancy, Changes in MOT Operations
  • 4. Contractors Responsibility  Compliance with the Project Specifications  What Traffic Control or Traffic Operations Specification Applies  Adjustment of Construction Phasing  How to Modify during Construction-TCP  Maintenance of Traffic Operations  Duration, Sequence, Locations, Devices, Engineering Standards  Minimizing Impact to the Traveling Public  Detours, Route Redundancy, Travel Times/Distances, Public Information/Notices
  • 5. Congruence of Interests through Areas of Conflict  Construction Phasing  Designers/Engineers need to Optimize Flexibility in Traffic Control Plans and Anticipated Phasing- Contractor/Design Engineer Workshops (Means, Methods, Costs)  Contractors need to understand what is in Project Specification Contract Documents Direction, Limitations, Standards- Design/Engineer/Contractor Workshops (Design Standards, Phased EW, Costs of Delays)
  • 6. Why is Impact to the Traveling Public Important  For Engineer  Contractor understands phasing-no change=perfect TCP  Minimal time delays for public-transparent between construction and normal operations  For Contractor  Easy to Bid-easy to modify  Minimal costs  Good PR with the Citizens affected by the project
  • 9. Why was the Change “Win-Win”  Contractor was able to work in an expanded work zone (directly applicable to means and methods, and costs)  TCP change provided safer traffic operations for users of intersection and work zone ( directly applicable to reduced traffic conflicts, associated time delays, and costs-resulted in good PR)
  • 10. Who else won  The Department  Increased safety at Intersection under construction  Contractor completed work more quickly  Business Owners/Private Landowners, and Roadway users were minimally inconvenienced during construction
  • 11. Where do we go from Here?  Major area of unknown  Actual Contractor Construction Phasing  Affects - TCP, MOT, Revised TCP’s, Earthwork, Time, and Costs
  • 12. Your Chance to Affect Change  Questionnaire  Built around 2 conditions  Full Reconstruction with complicated phasing  Maintenance and rehabilitation  Typical or Common areas of use  Interstate and NHS routes  State Oversight and State Routes