SlideShare a Scribd company logo
1 of 2
Download to read offline
800.782.1500 | willscot.com
The Story
What other city in the US could have a public works program dubbed Project Neon than
Las Vegas? It is the largest and most expensive ($900 Million) undertaking of its kind in
Nevada and involves major new infrastructure construction and reconstruction involving
I-15 between Sahara Avenue and the Spaghetti Bowl, MLK Boulevard to the west, and
Industrial Road to the east. According to the Nevada Department of Transportation (NDOT),
the 3.7 mile stretch of I-15 covered by Project Neon is the busiest stretch of roadway in
NV handling 300,000 vehicles a day with 25,000 lane changes per hour, resulting in three
crashes per day. And the vehicle count is expected to double by 2035!
Kiewit Infrastructure West is the project’s contractor/designer and they needed temporary
office space to accommodate a substantial workforce through the project’s completion in
2019. Kiewit figured on a 10-plex for NDOT by mid-January 2016, a 15-plex for the design
firm by late January, and a 20-plex plus a 5-plex for themselves by early March. Kiewit is a
Williams Scotsman Strategic Account. Their history with us, fleet availability, customer service,
and our account executive’s experience with the Nevada Manufactured Housing Division
all contributed to our securing the modular order over our competitor.
We had one month to completely customize, deliver and install the first 10-plex for NDOT
by early January. Our Albuquerque branch worked tirelessly through the holidays, weekends
– whatever overtime was required – to get seven floors ready. Simultaneously, three floors
were shipped to the Las Vegas branch and they made modifications there. It all came
together and the 10-plex delivered on schedule.
Project Neon
LAS VEGAS, NEVADA
PROJECT FACTS
SOLUTION TYPE:
Office
SCOPE OF PROJECT:
36,000 square feet
TIME TO OCCUPANCY:
3months
Project Neon
LAS VEGAS, NEVADA
agreed. Once more, the Albuquerque
and Las Vegas teams went into action to
make all modifications and actually deliver
ahead of schedule!
After all of the units were on site, finish-
ing trim work was completed as well
as any additional adjustments the cus-
tomer requested.
A project of this scale calls for team work
on many levels dedicated to one goal for
ultimate success. That’s why we put such
a premium on collaboration in our com-
pany and we outshine the competition.
A similar approach was used for the 15-plex
needed for the design firm by mid-January.
An existing 13-plex was put to work as
well as a doublewide classroom that was
perfect for a conference space. The Albu-
querque and Las Vegas teams again worked
miles apart yet in tandem to honor the
customer’s due date.
Last stage: the 25 total units that would
house the Kiewit team due by early March.
We refurbished a 5-plex that was originally
part of a custom project for the Wynn
Hotel & Casino to Kiewit’s specifications.
Next on the agenda was the 20-plex.
To avoid adding the required fire sprin-
klers to a 20-plex, we suggested using
two 10-plexes (no sprinklers necessary)
connected by a deck and Kiewit readily
800.782.1500 | willscot.com

More Related Content

Similar to Project Neon Las Vegas

Optimize Process Management to Improve Business Outcomes - Webinar, September...
Optimize Process Management to Improve Business Outcomes - Webinar, September...Optimize Process Management to Improve Business Outcomes - Webinar, September...
Optimize Process Management to Improve Business Outcomes - Webinar, September...Aconex
 
Los Gatos Trail Letter San Jose to Caltrain
Los Gatos Trail Letter San Jose to CaltrainLos Gatos Trail Letter San Jose to Caltrain
Los Gatos Trail Letter San Jose to CaltrainAdina Levin
 
2017 AEC Excellence Awards Showcase Book
2017 AEC Excellence Awards Showcase Book2017 AEC Excellence Awards Showcase Book
2017 AEC Excellence Awards Showcase BookAutodesk AEC
 
Project Resume - HCL-Axon
Project Resume - HCL-AxonProject Resume - HCL-Axon
Project Resume - HCL-AxonLisa Loveland
 
Case Study: Modernizing the PMO with CA PPM 15
Case Study: Modernizing the PMO with CA PPM 15Case Study: Modernizing the PMO with CA PPM 15
Case Study: Modernizing the PMO with CA PPM 15CA Technologies
 
Will a subway eventually run beneath the Las Vegas Strip?
Will a subway eventually run beneath the Las Vegas Strip?Will a subway eventually run beneath the Las Vegas Strip?
Will a subway eventually run beneath the Las Vegas Strip?lasvegasnewsarticles2015
 
Closed Loop Remediation with CA Automic Service Orchestration
Closed Loop Remediation with CA Automic Service OrchestrationClosed Loop Remediation with CA Automic Service Orchestration
Closed Loop Remediation with CA Automic Service OrchestrationCA Technologies
 
Mai gabica cv 2020
Mai gabica cv 2020Mai gabica cv 2020
Mai gabica cv 2020maigabica
 
Murch sit 061316
Murch sit 061316 Murch sit 061316
Murch sit 061316 shannonj87
 
Case Study: O2/Telefonica Transitions From CA eHealth® to CA Performance Mana...
Case Study: O2/Telefonica Transitions From CA eHealth® to CA Performance Mana...Case Study: O2/Telefonica Transitions From CA eHealth® to CA Performance Mana...
Case Study: O2/Telefonica Transitions From CA eHealth® to CA Performance Mana...CA Technologies
 
Utility - Renewal of Grid Infrastructure
Utility - Renewal of Grid InfrastructureUtility - Renewal of Grid Infrastructure
Utility - Renewal of Grid InfrastructureJens Frenzel
 
Contrack Watts Newsletter-Issue 6
Contrack Watts Newsletter-Issue 6Contrack Watts Newsletter-Issue 6
Contrack Watts Newsletter-Issue 6Peter A. Hanna, CPM
 
Cerimage Consulting Representative Projects
Cerimage Consulting Representative ProjectsCerimage Consulting Representative Projects
Cerimage Consulting Representative ProjectsCerimage Consulting
 
RACER_casestudy_buickcity_0115
RACER_casestudy_buickcity_0115RACER_casestudy_buickcity_0115
RACER_casestudy_buickcity_0115Bernadette Grafton
 

Similar to Project Neon Las Vegas (20)

Optimize Process Management to Improve Business Outcomes - Webinar, September...
Optimize Process Management to Improve Business Outcomes - Webinar, September...Optimize Process Management to Improve Business Outcomes - Webinar, September...
Optimize Process Management to Improve Business Outcomes - Webinar, September...
 
Los Gatos Trail Letter San Jose to Caltrain
Los Gatos Trail Letter San Jose to CaltrainLos Gatos Trail Letter San Jose to Caltrain
Los Gatos Trail Letter San Jose to Caltrain
 
2017 AEC Excellence Awards Showcase Book
2017 AEC Excellence Awards Showcase Book2017 AEC Excellence Awards Showcase Book
2017 AEC Excellence Awards Showcase Book
 
Project Resume - HCL-Axon
Project Resume - HCL-AxonProject Resume - HCL-Axon
Project Resume - HCL-Axon
 
Portfolio
PortfolioPortfolio
Portfolio
 
Case Study: Modernizing the PMO with CA PPM 15
Case Study: Modernizing the PMO with CA PPM 15Case Study: Modernizing the PMO with CA PPM 15
Case Study: Modernizing the PMO with CA PPM 15
 
Resume of Eng.Ali
Resume of  Eng.AliResume of  Eng.Ali
Resume of Eng.Ali
 
Will a subway eventually run beneath the Las Vegas Strip?
Will a subway eventually run beneath the Las Vegas Strip?Will a subway eventually run beneath the Las Vegas Strip?
Will a subway eventually run beneath the Las Vegas Strip?
 
Closed Loop Remediation with CA Automic Service Orchestration
Closed Loop Remediation with CA Automic Service OrchestrationClosed Loop Remediation with CA Automic Service Orchestration
Closed Loop Remediation with CA Automic Service Orchestration
 
RailWorks-Today-April-2016-L
RailWorks-Today-April-2016-LRailWorks-Today-April-2016-L
RailWorks-Today-April-2016-L
 
Mai gabica cv 2020
Mai gabica cv 2020Mai gabica cv 2020
Mai gabica cv 2020
 
Murch sit 061316
Murch sit 061316 Murch sit 061316
Murch sit 061316
 
L_Bacha_Project_Summary
L_Bacha_Project_SummaryL_Bacha_Project_Summary
L_Bacha_Project_Summary
 
MassDOT Developers Presentation - December 2009
MassDOT Developers Presentation - December 2009MassDOT Developers Presentation - December 2009
MassDOT Developers Presentation - December 2009
 
Case Study: O2/Telefonica Transitions From CA eHealth® to CA Performance Mana...
Case Study: O2/Telefonica Transitions From CA eHealth® to CA Performance Mana...Case Study: O2/Telefonica Transitions From CA eHealth® to CA Performance Mana...
Case Study: O2/Telefonica Transitions From CA eHealth® to CA Performance Mana...
 
Utility - Renewal of Grid Infrastructure
Utility - Renewal of Grid InfrastructureUtility - Renewal of Grid Infrastructure
Utility - Renewal of Grid Infrastructure
 
Contrack Watts Newsletter-Issue 6
Contrack Watts Newsletter-Issue 6Contrack Watts Newsletter-Issue 6
Contrack Watts Newsletter-Issue 6
 
Cerimage Consulting Representative Projects
Cerimage Consulting Representative ProjectsCerimage Consulting Representative Projects
Cerimage Consulting Representative Projects
 
RACER_casestudy_buickcity_0115
RACER_casestudy_buickcity_0115RACER_casestudy_buickcity_0115
RACER_casestudy_buickcity_0115
 
RCJackson Portfolioo
RCJackson PortfoliooRCJackson Portfolioo
RCJackson Portfolioo
 

Project Neon Las Vegas

  • 1. 800.782.1500 | willscot.com The Story What other city in the US could have a public works program dubbed Project Neon than Las Vegas? It is the largest and most expensive ($900 Million) undertaking of its kind in Nevada and involves major new infrastructure construction and reconstruction involving I-15 between Sahara Avenue and the Spaghetti Bowl, MLK Boulevard to the west, and Industrial Road to the east. According to the Nevada Department of Transportation (NDOT), the 3.7 mile stretch of I-15 covered by Project Neon is the busiest stretch of roadway in NV handling 300,000 vehicles a day with 25,000 lane changes per hour, resulting in three crashes per day. And the vehicle count is expected to double by 2035! Kiewit Infrastructure West is the project’s contractor/designer and they needed temporary office space to accommodate a substantial workforce through the project’s completion in 2019. Kiewit figured on a 10-plex for NDOT by mid-January 2016, a 15-plex for the design firm by late January, and a 20-plex plus a 5-plex for themselves by early March. Kiewit is a Williams Scotsman Strategic Account. Their history with us, fleet availability, customer service, and our account executive’s experience with the Nevada Manufactured Housing Division all contributed to our securing the modular order over our competitor. We had one month to completely customize, deliver and install the first 10-plex for NDOT by early January. Our Albuquerque branch worked tirelessly through the holidays, weekends – whatever overtime was required – to get seven floors ready. Simultaneously, three floors were shipped to the Las Vegas branch and they made modifications there. It all came together and the 10-plex delivered on schedule. Project Neon LAS VEGAS, NEVADA PROJECT FACTS SOLUTION TYPE: Office SCOPE OF PROJECT: 36,000 square feet TIME TO OCCUPANCY: 3months
  • 2. Project Neon LAS VEGAS, NEVADA agreed. Once more, the Albuquerque and Las Vegas teams went into action to make all modifications and actually deliver ahead of schedule! After all of the units were on site, finish- ing trim work was completed as well as any additional adjustments the cus- tomer requested. A project of this scale calls for team work on many levels dedicated to one goal for ultimate success. That’s why we put such a premium on collaboration in our com- pany and we outshine the competition. A similar approach was used for the 15-plex needed for the design firm by mid-January. An existing 13-plex was put to work as well as a doublewide classroom that was perfect for a conference space. The Albu- querque and Las Vegas teams again worked miles apart yet in tandem to honor the customer’s due date. Last stage: the 25 total units that would house the Kiewit team due by early March. We refurbished a 5-plex that was originally part of a custom project for the Wynn Hotel & Casino to Kiewit’s specifications. Next on the agenda was the 20-plex. To avoid adding the required fire sprin- klers to a 20-plex, we suggested using two 10-plexes (no sprinklers necessary) connected by a deck and Kiewit readily 800.782.1500 | willscot.com