7. Process
โขโฏ 2015 feasibility study โ reported September 3, 2015
โขโฏ IA project approval received November 24, 2015
โขโฏ Project kick-o๏ฌ presenta<on to WPSC on November 27, 2015
โขโฏ January 15, 2016: full day workshop on lake level issues with
Water Protec<on Steering CommiEee members. CommiEee
establishes an Extreme Lake Levels subcommiEee
โขโฏ April 1, 2016: Mee<ng with the Extreme Water Levels
subcommiEee of the Water Protec<on Steering CommiEee to
review dra^ Phase I report, discuss summer consulta<on
opportuni<es
โขโฏ May 3, 2016: Phase I report completed, submiEed to Graham
Sustainability Ins<tute