Quality Control & Quality
Assurance In Road Construction
1
By
Superintending Engineer,
TVCC,
BBMP
BBMP Quality Control :
➢Several lakhs of rupees being spent for Infrastructure
and other Improvement works in BBMP.
➢In order to ensure quality of works a full fledged,
well equipped in house laboratory is necessary.
➢Presently the BBMP has a quality control wing
constituting EE’s , AEE’s & AE’s.
➢The quality control lab is equipped for testing
cement, sand, metal, bitumen, bituminous mix, etc.,
➢The field Engineers shall make use of BBMP quality
control lab to ensure good quality works.
2
Emplaned Laboratories in BBMP
➢The BBMP has empanelled consultants / firms
having material testing laboratories.
➢The agency has to make its own arrangement to
convey the samples to the laboratories for testing .
3
❖ Quality Control
• Tests Necessary to Control a Product
• Determine Quality of Product being
Produced
• Performed by Contractor
4
❖ Quality Assurance
• Tests Necessary to Make a Decision on
Acceptance
• Ensure Product being Evaluated is What
the owner Specified
• Performed by Owner
5
Quality Control vs. Quality Assurance
•Quality Control (QC) = The contractors system in place during the
construction to manage, control and document his activities in order to
comply with contract requirements
• Quality Assurance (QA) = The Governments system in place to monitor
the Quality Control efforts of the contractor
6
High Quality
Finished Road
QC + QA =
3 Phases of Contractor Quality Control
A PR MA Y J U N J U L A U G S EP O C T N O V
C l e a r a n d G r u b
Ex c a v a t I o n
S u b - b a s e
B a s e P r e p.
Preparatory
Phase Start-up
Phase Production
Phase
7
3 Phases of Contractor Quality Control
What is involved?
Preparatory Phase
•Review Plans and Specs
•Verify submittal approval
•Check preliminary work
•Examine materials
•Discuss construction methods
•Review Safety
•Coordinate surveying and staking work
Start-up Phase
•Establish quality required
•Resolve conflicts
•Ensure testing is performed
•Establish detailed testing schedule based
on production schedule
•Review Safety
Production Phase
•Ensure Contract Compliance
•Conduct intermittent or continuous inspections to identify and correct
deficiencies
•Inspect completed phases before scheduled Government acceptance
•Ensure Testing reports are submitted
•Ensure rework is completed
8
❖ CONSTRUCTION PHASE-Quality Control
9
❖ Requirements
• Ensure Quality
• Create Durable National Assets
• Grossly Inadequate for Present day Needs
10
❖ Advantages
• Improved Quality
• Uniformity
• Economic Utilisation of Materials
• Reduction in User Cost
• Extra Cost – Fraction of Resulting Benefits
• ½ to 1% of Construction Cost
• Economic Return – 5 – 10% of Total Construction Cost
11
❖ Pre-requisites
• Provision for Quality Control in Construction,
Specification and Estimates
• Adequately Trained Staff
• Adequate Equipment
• Periodic Appraisal of the QC Data
• Updating of Knowledge by On-job Training
12
❖ Quality Control In Road Construction
• Control of Materials
• Test Procedure
• Frequency and Extent of Testing
• Acceptance Criteria
• Equipment Type & its Calibration
• Recording of Test Results
• Training for QC
13
❖ Quality Control Test
• Individual Materials
O Soil, Gravel, Aggregate, Binder
• Mixes
O Gradation of Aggregates, Mix Proportion, Mixed Design
Properties
• During Construction Process
O Spreading
O Segregation
O Temperature – Mixing, Laying, Rolling
14
❖ Quality Control Test
• Test on Compacted Layer
O Mixed Proportion (Unbound Layers)
O Density
O Mix proportion and Gradation (bound layers after extraction)
• Finished Surface
O Longitudinal Profile
O Transverse Profile
O Cross Slope
O Texture
15
❖Tests On Borrow Materials Of embankment/subgrade
Test Min. Desirable Frequency
Gradation/ Sand Content 1-2 Tests per 8000 m3 of Soil
Plasticity Index 1-2 Tests per 8000 m3 of Soil
Standard Proctor Test 1-2 Tests per 8000 m3 of Soil
CBR on a set of 3 One Test per 3000 m3
Specimens
Deleterious Constituents As Required
Natural Moisture Content One Test per 250 m3 of Soil
16
❖ Density Requirements Of Embankments And
Subgrade
Not less than 16.0 kN/cu.m
Not less than 15.2 kN/cu.m
Embankments upto 3 metres
height, not subjected to
extensive flooding
Not less than 17.5 kN/cu.m
Subgrade and earthern
shoulders/ verges/backfill
Embankments exceeding 3
metres height or
embankments of any height
subject to long periods of
inundation
17
❖ Compaction Requirements For Embankment
And Subgrade
Not less than 97
Subgrade and Earthen
Shoulders
Relative Compaction as %
of MDD
Type of Work/ Material
Subgrade and 500 mm
portion just below the
subgrade
Not Allowed
Remaining Portion of
Embankment
Not Less than 90
18
Embankments Not less than 95
Expansive Clays:
❖ Frequency of Compaction Tests
One test for every 250 m3 of soil
subject to min. of 4 tests/day
Moisture Content prior to
compaction
Frequency (min)
Particulars
(a) Body of embankment At least one test per 1,000 m2 for
each layer
(b) Subgrade and shoulders At least one test per 500 m2 for each
layer
Degree of compaction
Regularly
Thickness of layer
19
❖ Location Of Density Test Points For Earth
Work
20
❖ Acceptance Criteria
Control should be based on the mean value of a
set of 5-10 density measurement.
The criteria for acceptance shall be subject to
the condition that the MEAN DENSITY is not
less than the specified density plus:
times the standard deviation
21
(No. of samples)0.5
1.65
1.65 −
❖ Granular Sub-base
Gradation One test per 200 m3
Atternberg limits One test per 200 m3
Moisture Content prior to One test per 250 m3
Compaction
Density of Compacted One test per 500 m2
Layer
Deleterious Constituents As Required
CBR As Required
22
❖ Lime/ Cement Stabilised Soil Sub-base
Quality of Lime/ Cement One Test for Each
Consignment Subject to a
Minimum of one Test per 5
Tonnes
Lime/Cement Content Regularly, through Procedural
Checks
Degree of Pulverisation 1-2 Tests per 8000 m3 of Soil
CBR or UCC As Required
Density One Test per 500 m2
23
❖Physical Requirements Of Coarse Aggregates For
Water Bound Macadam For Sub-base/base Courses
40 percent (Max.)
Requirements
T
est
Los Angeles Abrasion
Value
30 percent (Max.)
Combined Flakiness
and Elongation Indices
30 percent (Max.)
or Aggregate Impact
Value
24
❖ Water Bound Macadam
Aggregate Impact Value One Test per 200 m3 of
Aggregate
Grading One Test per 100 m3
Flakiness Index and
Elongation Index
One Test per 200 m3 of
Aggregate
Attenberg Limits of Binding
Material
One Test per 25 m3 of
Binding Material
Attenberg Limits of Portion
of Aggregate passing 425
micron sieve
One Test per 100 cubic
Metre of Aggregate
25
❖ Wet Mix Macadam
Aggregate Impact Value One Test per 200 m3 of
Aggregate
Grading One Test per 100 m3 of
Aggregate
Flakiness and Elongation
Index
One Test per 200 m3 of
Aggregate
Attenberg Limits of Portion
of Aggregate passing 425
micron sieve
One Test per 100 m3 of
Aggregate
Density of Compacted
Layer
One Test per 500 m3
26
❖ Prime Coat / Tack Coat
Quality of Binder Two Samples lot to be
subjected to all or some Tests
as Directed by the Engineer
Binder Temperature for
Application
At Regular Close Intervals
Rate of Spread of Binder Two Tests per Day
27
❖ Surface Dressing
Quality of Binder Two Samples per lot
Aggregate Impact Value One Test per 50 m3 of
Aggregate
- do -
28
Flakiness Index and
Elongation Index
Stripping Value of
Aggregates
3 specimens per source
Water Absorption of
Aggregates
- do -
Grading of Aggregates One Test per 25 m3 of
Aggregates
❖ Open-graded Premix Carpet/ Mix-seal
Surfacing
Quality of Binder Two Samples per lot to be
Subjected to all or some tests as
Directed by Engineer
One test per 50 m3 of Aggregates
- do -
29
Aggregate Impact
Value
FI and EI of
Aggregates
Stripping value 3 specimens per source
- do -
Water Absorption of
Aggregates
Grading of Aggregates One Test per 25 m3 of Aggregates
❖ Physical Requirements Of Aggregates For
Bituminous Macadam
40 % Max.
Los Angeles Abrasion
Value
Requirement
T
est
30
2 % Max.
Water Absorption
12 % Max.
Soundness
30 % Max.
Coating and Stripping of
Bitumen Aggregate
Mixtures
30 % Max.
FI and EI
❖ Bituminous Macadam
Quality of Binder Two Samples per lot to be
subjected to all or some tests as
directed by the Engineer
Aggregate Impact
Value
One Test per 50 m3 of Aggregate
31
FI and EI of
Aggregates
- do -
Stripping Value 3 specimens per source
Grading of
Aggregates
Two Tests per day per plant both on
the individual constituents and
mixed aggregates from the dryer
❖ Bituminous Penetration Macadam/ Built-up
Spray Grout
Quality of Binder Two Samples per lot to be
subjected to all or some tests
as directed by the Engineer
Aggregate Impact Value One Test per 200 m3 of
Aggregate
32
FI and EI of Aggregates - do -
Stripping Value 3 specimens per source
Aggregate Grading One Test per 100 m3 of
aggregate
Temp. of Binder at
Application
At regular Close Intervals
Requirements For Semi-dense Bituminous
Concrete Mix
33
Not less than 4.0
percent
Binder Content, percent by weight
of mix
65-75
PercentageAir Voids in Mineral
aggregates filled with Bitumen
(VFB)
Marshall Stability 820 kg (1800 lbs) Min.
Marshall Flow 2-4
Percent Air Voids in Mix 3-5
Percent Air Voids in Mineral 13-15
Aggregate (VMA) Minimum
❖ Dense Bituminous Madacam/ Semi Dense
Bituminous Concrete/ Bituminous Concrete
Quality of Binder Two Samples per lot to be
subjected to all or some tests
as directed by the Engineer
Aggregate Impact Value One Test per 50 m3 of
Aggregate
F I and E I of Aggregates One Test per 50 m3 of
Aggregate
Stripping Value 3 Specimens per Source
Water Absorption of
Aggregates
- do -
Water Sensitivity of mix As Required for BC
34
❖Requirements Of Bituminous Concrete Mix
Min. VMAPercent related to
DesignAir Voids, %
3-5
PercentAir voids in Mix
2 - 4
Marshall Flow
900 kg Min.
Marshall Stability
1.5 % Max. LAV
Swell Test
Water Sensitivity
5- 6 (50-65 mm thick)
5 - 7 (30-45 mm thick)
Min. 75 % Retained Strength
Binder content percent by weight
of total mix
65 - 75
PercentAirvoids in Mineral
Aggregates filled by Bitumen
(VFB)
3.0 - 10-14 %
4.0 - 11-15%
5.0 - 12-16 %
35
❖ Testing Of Asphalt Mixes
■ Aggregate gradation
■ Asphalt content
■ Temperature
■ Theoretical maximum density
■ In-place density
■ Smoothness
■ Visual inspection
36
❖ Aggregate Gradation
■ SAMPLING
• STOCK PILE
• COLD FEEDER BELT
• HOT BINS
• EXTRACTED ASPHALT MIXTURE (END
PRODUCT)
37
❖ Trouble Shooting
■ Sampling stock pile
■ Check gradation of new material added
■ Segregation in feeder belt
■ Improper loading of cold bins
■ Improper setting of individual bins
38
❖ Asphalt Content
■ Important for satisfactory performance
■ Low asphalt content- less durable mix
■ More asphalt content- not stable mix
■ Affects film thickness, voids, stability and
flow
39
❖ Temperature
■ High enough to provide good coating on
aggregates
■ Allow satisfactory compaction
■ More heating – additional oxidation, loss
of volatiles, reduce mixture durability
40
❖ Temperature
Grade Bitumen Agg. Mix Rolling Laying
6
5 150 -
165
150 -
170
165
Max
90 Min 125
Min
9
0 140 -
160
140 -
165
155
Max
80 Min 115
Min
41
❖ Compaction
■ Commence From Edges And Progress Towards
Centre
■ Initial Breakdown Rolling – 8 To 10 T Smooth
Wheel Roller
■ Intermediate Rolling – 8-10 T Dead Wt. Or
Vibratory Roller.Pneumatic Tyred Roller –12-15 T
Wt. 5.6 Kg/Sq.Cm Pr.
■ Finished Rolling – 6-8 T Smooth Wheel Tandem
Roller
42
❖ Compaction
■ Roller Speed Not More Than 5 Kmph
■ Do Not Permit Rollers To Stand On Pavement
■ Prevent Oil Drop
■ Keep Wheels Just Moist Enough
43
Suggested Frequency And Amplitude For Vibratory
Compaction
Nature of
Soil/
Materials
Frequency
(CPM)
Amplitude
(mm)
Thickness of
Compaction,
mm
Rock 1800-2500 1.2 – 1.5 750
Sand/ Gravel 1800-2000 0.8 – 1.2 500
44
Sandy/clay
/clayey
1600-2000 0.8 – 1.2 600
Clay 2000-2500 0.8 – 1.0 400
Asphalt 2500-3500 0.4 – 0.6 50 – 75
Effect Of Speed Of Roller In Density And
Finish Surface
ROUGH
FINISH
SMOOTH
FINISH
HIGHER SPEED
LOW DENSITY
45
LOWER SPEED
HIGH DENSITY
OPERATION
SPEED
Relationship Between Compactability &
Temperature
46
47
48
❖ TACK COATING BY SPRAYER
49
❖ Tack Coat Without Crack Sealing
50
❖ Overlay Over Severely Cracked
Surface
51
❖ Inadequate Compaction And Excess
Binding Material
52
❖ WBM Surface Without Key Aggregates And Excess Binding
Material
53
❖ Shoulders At Higher Elevation
54
❖ Poorly Widened WBM Carriageway
55
❖ POORLY WIDENED WBM CARRIAGEWAY
56
❖ Depressed Carriageway
57
❖ Tack Coat Surfaced WBMLayer
58
Modern Equipment For
Quality Control Tests In
Highways Construction
59
Asphalt Content Guage
60
❖ Portable Pendulum Type Skid Resistance Tester
61
❖ Dynamic Skid Resistance Tester
62
❖PortableAsphalt Core Cutter
63
Non Nuclear Density Gauge
64
❖ Benkelmen Beam
65
❖ Fifth Wheel Bump Integrator (Roughometer)
66
❖ Nuclear Density Meter
67
Asphalt Content Guage
68
69
70
71
❖ Falling Weight Deflectometer
72
73

More Related Content

Similar to ppt1.pptx

Concrete Mix Design Report
Concrete Mix Design ReportConcrete Mix Design Report
Concrete Mix Design ReportZakaria Yahya
 
Non-Destructive-Testing-of-Concrete • Repair / Rehabilitation / Restoration
Non-Destructive-Testing-of-Concrete • Repair / Rehabilitation / RestorationNon-Destructive-Testing-of-Concrete • Repair / Rehabilitation / Restoration
Non-Destructive-Testing-of-Concrete • Repair / Rehabilitation / Restorationpandian18
 
crri_csir_odisha new tech JULY 2022.pptx
crri_csir_odisha new tech JULY 2022.pptxcrri_csir_odisha new tech JULY 2022.pptx
crri_csir_odisha new tech JULY 2022.pptxRipanJena
 
Effect of the use of crumb rubber in conventional bitumen on the marshall sta...
Effect of the use of crumb rubber in conventional bitumen on the marshall sta...Effect of the use of crumb rubber in conventional bitumen on the marshall sta...
Effect of the use of crumb rubber in conventional bitumen on the marshall sta...eSAT Journals
 
Project Report on Concrete Mix Design of Grade M35
Project Report on Concrete Mix Design of Grade M35Project Report on Concrete Mix Design of Grade M35
Project Report on Concrete Mix Design of Grade M35Gyan Prakash
 
Strengthening of concrete columns made from recycled concrete aggregate
Strengthening of concrete columns made from recycled concrete aggregateStrengthening of concrete columns made from recycled concrete aggregate
Strengthening of concrete columns made from recycled concrete aggregatenada khaled
 
1.2_Basic Engineering_Day 4.pptx
1.2_Basic Engineering_Day 4.pptx1.2_Basic Engineering_Day 4.pptx
1.2_Basic Engineering_Day 4.pptxJanak82
 
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...Mayur Rahangdale
 
CONCRETE MIX DESIGN
CONCRETE MIX DESIGNCONCRETE MIX DESIGN
CONCRETE MIX DESIGNNikul Gopani
 
Viscosity test of bitumen
Viscosity test of bitumenViscosity test of bitumen
Viscosity test of bitumenAmrit pandit
 
Concrete Mix Design.pdf
Concrete Mix Design.pdfConcrete Mix Design.pdf
Concrete Mix Design.pdfCE17Asheesh
 

Similar to ppt1.pptx (20)

Summer training report
Summer training reportSummer training report
Summer training report
 
Concrete Mix Design.pdf
Concrete Mix Design.pdfConcrete Mix Design.pdf
Concrete Mix Design.pdf
 
Concrete Mix Design Report
Concrete Mix Design ReportConcrete Mix Design Report
Concrete Mix Design Report
 
Fresh and harden properties of concrete
Fresh and harden properties of concreteFresh and harden properties of concrete
Fresh and harden properties of concrete
 
Non-Destructive-Testing-of-Concrete • Repair / Rehabilitation / Restoration
Non-Destructive-Testing-of-Concrete • Repair / Rehabilitation / RestorationNon-Destructive-Testing-of-Concrete • Repair / Rehabilitation / Restoration
Non-Destructive-Testing-of-Concrete • Repair / Rehabilitation / Restoration
 
crri_csir_odisha new tech JULY 2022.pptx
crri_csir_odisha new tech JULY 2022.pptxcrri_csir_odisha new tech JULY 2022.pptx
crri_csir_odisha new tech JULY 2022.pptx
 
Effect of the use of crumb rubber in conventional bitumen on the marshall sta...
Effect of the use of crumb rubber in conventional bitumen on the marshall sta...Effect of the use of crumb rubber in conventional bitumen on the marshall sta...
Effect of the use of crumb rubber in conventional bitumen on the marshall sta...
 
Project Report on Concrete Mix Design of Grade M35
Project Report on Concrete Mix Design of Grade M35Project Report on Concrete Mix Design of Grade M35
Project Report on Concrete Mix Design of Grade M35
 
Strengthening of concrete columns made from recycled concrete aggregate
Strengthening of concrete columns made from recycled concrete aggregateStrengthening of concrete columns made from recycled concrete aggregate
Strengthening of concrete columns made from recycled concrete aggregate
 
1.2_Basic Engineering_Day 4.pptx
1.2_Basic Engineering_Day 4.pptx1.2_Basic Engineering_Day 4.pptx
1.2_Basic Engineering_Day 4.pptx
 
A012550107
A012550107A012550107
A012550107
 
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
 
Properties of concrete
Properties of concrete Properties of concrete
Properties of concrete
 
SANDEEP PPT
SANDEEP PPTSANDEEP PPT
SANDEEP PPT
 
CONCRETE MIX DESIGN
CONCRETE MIX DESIGNCONCRETE MIX DESIGN
CONCRETE MIX DESIGN
 
Viscosity test of bitumen
Viscosity test of bitumenViscosity test of bitumen
Viscosity test of bitumen
 
Flow. .pdf
Flow. .pdfFlow. .pdf
Flow. .pdf
 
Mix design of concrete
Mix design of concreteMix design of concrete
Mix design of concrete
 
Concrete Mix Design.pdf
Concrete Mix Design.pdfConcrete Mix Design.pdf
Concrete Mix Design.pdf
 
Concrete Mix Design
Concrete Mix DesignConcrete Mix Design
Concrete Mix Design
 

Recently uploaded

Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxpritamlangde
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptAfnanAhmad53
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...ronahami
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdfKamal Acharya
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesMayuraD1
 
Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...
Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...
Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...gragchanchal546
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxMuhammadAsimMuhammad6
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdfAldoGarca30
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementDr. Deepak Mudgal
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdfKamal Acharya
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network DevicesChandrakantDivate1
 

Recently uploaded (20)

Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .ppt
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...
Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...
Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...
 
Signal Processing and Linear System Analysis
Signal Processing and Linear System AnalysisSignal Processing and Linear System Analysis
Signal Processing and Linear System Analysis
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth Reinforcement
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 

ppt1.pptx

  • 1. Quality Control & Quality Assurance In Road Construction 1 By Superintending Engineer, TVCC, BBMP
  • 2. BBMP Quality Control : ➢Several lakhs of rupees being spent for Infrastructure and other Improvement works in BBMP. ➢In order to ensure quality of works a full fledged, well equipped in house laboratory is necessary. ➢Presently the BBMP has a quality control wing constituting EE’s , AEE’s & AE’s. ➢The quality control lab is equipped for testing cement, sand, metal, bitumen, bituminous mix, etc., ➢The field Engineers shall make use of BBMP quality control lab to ensure good quality works. 2
  • 3. Emplaned Laboratories in BBMP ➢The BBMP has empanelled consultants / firms having material testing laboratories. ➢The agency has to make its own arrangement to convey the samples to the laboratories for testing . 3
  • 4. ❖ Quality Control • Tests Necessary to Control a Product • Determine Quality of Product being Produced • Performed by Contractor 4
  • 5. ❖ Quality Assurance • Tests Necessary to Make a Decision on Acceptance • Ensure Product being Evaluated is What the owner Specified • Performed by Owner 5
  • 6. Quality Control vs. Quality Assurance •Quality Control (QC) = The contractors system in place during the construction to manage, control and document his activities in order to comply with contract requirements • Quality Assurance (QA) = The Governments system in place to monitor the Quality Control efforts of the contractor 6 High Quality Finished Road QC + QA =
  • 7. 3 Phases of Contractor Quality Control A PR MA Y J U N J U L A U G S EP O C T N O V C l e a r a n d G r u b Ex c a v a t I o n S u b - b a s e B a s e P r e p. Preparatory Phase Start-up Phase Production Phase 7
  • 8. 3 Phases of Contractor Quality Control What is involved? Preparatory Phase •Review Plans and Specs •Verify submittal approval •Check preliminary work •Examine materials •Discuss construction methods •Review Safety •Coordinate surveying and staking work Start-up Phase •Establish quality required •Resolve conflicts •Ensure testing is performed •Establish detailed testing schedule based on production schedule •Review Safety Production Phase •Ensure Contract Compliance •Conduct intermittent or continuous inspections to identify and correct deficiencies •Inspect completed phases before scheduled Government acceptance •Ensure Testing reports are submitted •Ensure rework is completed 8
  • 10. ❖ Requirements • Ensure Quality • Create Durable National Assets • Grossly Inadequate for Present day Needs 10
  • 11. ❖ Advantages • Improved Quality • Uniformity • Economic Utilisation of Materials • Reduction in User Cost • Extra Cost – Fraction of Resulting Benefits • ½ to 1% of Construction Cost • Economic Return – 5 – 10% of Total Construction Cost 11
  • 12. ❖ Pre-requisites • Provision for Quality Control in Construction, Specification and Estimates • Adequately Trained Staff • Adequate Equipment • Periodic Appraisal of the QC Data • Updating of Knowledge by On-job Training 12
  • 13. ❖ Quality Control In Road Construction • Control of Materials • Test Procedure • Frequency and Extent of Testing • Acceptance Criteria • Equipment Type & its Calibration • Recording of Test Results • Training for QC 13
  • 14. ❖ Quality Control Test • Individual Materials O Soil, Gravel, Aggregate, Binder • Mixes O Gradation of Aggregates, Mix Proportion, Mixed Design Properties • During Construction Process O Spreading O Segregation O Temperature – Mixing, Laying, Rolling 14
  • 15. ❖ Quality Control Test • Test on Compacted Layer O Mixed Proportion (Unbound Layers) O Density O Mix proportion and Gradation (bound layers after extraction) • Finished Surface O Longitudinal Profile O Transverse Profile O Cross Slope O Texture 15
  • 16. ❖Tests On Borrow Materials Of embankment/subgrade Test Min. Desirable Frequency Gradation/ Sand Content 1-2 Tests per 8000 m3 of Soil Plasticity Index 1-2 Tests per 8000 m3 of Soil Standard Proctor Test 1-2 Tests per 8000 m3 of Soil CBR on a set of 3 One Test per 3000 m3 Specimens Deleterious Constituents As Required Natural Moisture Content One Test per 250 m3 of Soil 16
  • 17. ❖ Density Requirements Of Embankments And Subgrade Not less than 16.0 kN/cu.m Not less than 15.2 kN/cu.m Embankments upto 3 metres height, not subjected to extensive flooding Not less than 17.5 kN/cu.m Subgrade and earthern shoulders/ verges/backfill Embankments exceeding 3 metres height or embankments of any height subject to long periods of inundation 17
  • 18. ❖ Compaction Requirements For Embankment And Subgrade Not less than 97 Subgrade and Earthen Shoulders Relative Compaction as % of MDD Type of Work/ Material Subgrade and 500 mm portion just below the subgrade Not Allowed Remaining Portion of Embankment Not Less than 90 18 Embankments Not less than 95 Expansive Clays:
  • 19. ❖ Frequency of Compaction Tests One test for every 250 m3 of soil subject to min. of 4 tests/day Moisture Content prior to compaction Frequency (min) Particulars (a) Body of embankment At least one test per 1,000 m2 for each layer (b) Subgrade and shoulders At least one test per 500 m2 for each layer Degree of compaction Regularly Thickness of layer 19
  • 20. ❖ Location Of Density Test Points For Earth Work 20
  • 21. ❖ Acceptance Criteria Control should be based on the mean value of a set of 5-10 density measurement. The criteria for acceptance shall be subject to the condition that the MEAN DENSITY is not less than the specified density plus: times the standard deviation 21 (No. of samples)0.5 1.65 1.65 −
  • 22. ❖ Granular Sub-base Gradation One test per 200 m3 Atternberg limits One test per 200 m3 Moisture Content prior to One test per 250 m3 Compaction Density of Compacted One test per 500 m2 Layer Deleterious Constituents As Required CBR As Required 22
  • 23. ❖ Lime/ Cement Stabilised Soil Sub-base Quality of Lime/ Cement One Test for Each Consignment Subject to a Minimum of one Test per 5 Tonnes Lime/Cement Content Regularly, through Procedural Checks Degree of Pulverisation 1-2 Tests per 8000 m3 of Soil CBR or UCC As Required Density One Test per 500 m2 23
  • 24. ❖Physical Requirements Of Coarse Aggregates For Water Bound Macadam For Sub-base/base Courses 40 percent (Max.) Requirements T est Los Angeles Abrasion Value 30 percent (Max.) Combined Flakiness and Elongation Indices 30 percent (Max.) or Aggregate Impact Value 24
  • 25. ❖ Water Bound Macadam Aggregate Impact Value One Test per 200 m3 of Aggregate Grading One Test per 100 m3 Flakiness Index and Elongation Index One Test per 200 m3 of Aggregate Attenberg Limits of Binding Material One Test per 25 m3 of Binding Material Attenberg Limits of Portion of Aggregate passing 425 micron sieve One Test per 100 cubic Metre of Aggregate 25
  • 26. ❖ Wet Mix Macadam Aggregate Impact Value One Test per 200 m3 of Aggregate Grading One Test per 100 m3 of Aggregate Flakiness and Elongation Index One Test per 200 m3 of Aggregate Attenberg Limits of Portion of Aggregate passing 425 micron sieve One Test per 100 m3 of Aggregate Density of Compacted Layer One Test per 500 m3 26
  • 27. ❖ Prime Coat / Tack Coat Quality of Binder Two Samples lot to be subjected to all or some Tests as Directed by the Engineer Binder Temperature for Application At Regular Close Intervals Rate of Spread of Binder Two Tests per Day 27
  • 28. ❖ Surface Dressing Quality of Binder Two Samples per lot Aggregate Impact Value One Test per 50 m3 of Aggregate - do - 28 Flakiness Index and Elongation Index Stripping Value of Aggregates 3 specimens per source Water Absorption of Aggregates - do - Grading of Aggregates One Test per 25 m3 of Aggregates
  • 29. ❖ Open-graded Premix Carpet/ Mix-seal Surfacing Quality of Binder Two Samples per lot to be Subjected to all or some tests as Directed by Engineer One test per 50 m3 of Aggregates - do - 29 Aggregate Impact Value FI and EI of Aggregates Stripping value 3 specimens per source - do - Water Absorption of Aggregates Grading of Aggregates One Test per 25 m3 of Aggregates
  • 30. ❖ Physical Requirements Of Aggregates For Bituminous Macadam 40 % Max. Los Angeles Abrasion Value Requirement T est 30 2 % Max. Water Absorption 12 % Max. Soundness 30 % Max. Coating and Stripping of Bitumen Aggregate Mixtures 30 % Max. FI and EI
  • 31. ❖ Bituminous Macadam Quality of Binder Two Samples per lot to be subjected to all or some tests as directed by the Engineer Aggregate Impact Value One Test per 50 m3 of Aggregate 31 FI and EI of Aggregates - do - Stripping Value 3 specimens per source Grading of Aggregates Two Tests per day per plant both on the individual constituents and mixed aggregates from the dryer
  • 32. ❖ Bituminous Penetration Macadam/ Built-up Spray Grout Quality of Binder Two Samples per lot to be subjected to all or some tests as directed by the Engineer Aggregate Impact Value One Test per 200 m3 of Aggregate 32 FI and EI of Aggregates - do - Stripping Value 3 specimens per source Aggregate Grading One Test per 100 m3 of aggregate Temp. of Binder at Application At regular Close Intervals
  • 33. Requirements For Semi-dense Bituminous Concrete Mix 33 Not less than 4.0 percent Binder Content, percent by weight of mix 65-75 PercentageAir Voids in Mineral aggregates filled with Bitumen (VFB) Marshall Stability 820 kg (1800 lbs) Min. Marshall Flow 2-4 Percent Air Voids in Mix 3-5 Percent Air Voids in Mineral 13-15 Aggregate (VMA) Minimum
  • 34. ❖ Dense Bituminous Madacam/ Semi Dense Bituminous Concrete/ Bituminous Concrete Quality of Binder Two Samples per lot to be subjected to all or some tests as directed by the Engineer Aggregate Impact Value One Test per 50 m3 of Aggregate F I and E I of Aggregates One Test per 50 m3 of Aggregate Stripping Value 3 Specimens per Source Water Absorption of Aggregates - do - Water Sensitivity of mix As Required for BC 34
  • 35. ❖Requirements Of Bituminous Concrete Mix Min. VMAPercent related to DesignAir Voids, % 3-5 PercentAir voids in Mix 2 - 4 Marshall Flow 900 kg Min. Marshall Stability 1.5 % Max. LAV Swell Test Water Sensitivity 5- 6 (50-65 mm thick) 5 - 7 (30-45 mm thick) Min. 75 % Retained Strength Binder content percent by weight of total mix 65 - 75 PercentAirvoids in Mineral Aggregates filled by Bitumen (VFB) 3.0 - 10-14 % 4.0 - 11-15% 5.0 - 12-16 % 35
  • 36. ❖ Testing Of Asphalt Mixes ■ Aggregate gradation ■ Asphalt content ■ Temperature ■ Theoretical maximum density ■ In-place density ■ Smoothness ■ Visual inspection 36
  • 37. ❖ Aggregate Gradation ■ SAMPLING • STOCK PILE • COLD FEEDER BELT • HOT BINS • EXTRACTED ASPHALT MIXTURE (END PRODUCT) 37
  • 38. ❖ Trouble Shooting ■ Sampling stock pile ■ Check gradation of new material added ■ Segregation in feeder belt ■ Improper loading of cold bins ■ Improper setting of individual bins 38
  • 39. ❖ Asphalt Content ■ Important for satisfactory performance ■ Low asphalt content- less durable mix ■ More asphalt content- not stable mix ■ Affects film thickness, voids, stability and flow 39
  • 40. ❖ Temperature ■ High enough to provide good coating on aggregates ■ Allow satisfactory compaction ■ More heating – additional oxidation, loss of volatiles, reduce mixture durability 40
  • 41. ❖ Temperature Grade Bitumen Agg. Mix Rolling Laying 6 5 150 - 165 150 - 170 165 Max 90 Min 125 Min 9 0 140 - 160 140 - 165 155 Max 80 Min 115 Min 41
  • 42. ❖ Compaction ■ Commence From Edges And Progress Towards Centre ■ Initial Breakdown Rolling – 8 To 10 T Smooth Wheel Roller ■ Intermediate Rolling – 8-10 T Dead Wt. Or Vibratory Roller.Pneumatic Tyred Roller –12-15 T Wt. 5.6 Kg/Sq.Cm Pr. ■ Finished Rolling – 6-8 T Smooth Wheel Tandem Roller 42
  • 43. ❖ Compaction ■ Roller Speed Not More Than 5 Kmph ■ Do Not Permit Rollers To Stand On Pavement ■ Prevent Oil Drop ■ Keep Wheels Just Moist Enough 43
  • 44. Suggested Frequency And Amplitude For Vibratory Compaction Nature of Soil/ Materials Frequency (CPM) Amplitude (mm) Thickness of Compaction, mm Rock 1800-2500 1.2 – 1.5 750 Sand/ Gravel 1800-2000 0.8 – 1.2 500 44 Sandy/clay /clayey 1600-2000 0.8 – 1.2 600 Clay 2000-2500 0.8 – 1.0 400 Asphalt 2500-3500 0.4 – 0.6 50 – 75
  • 45. Effect Of Speed Of Roller In Density And Finish Surface ROUGH FINISH SMOOTH FINISH HIGHER SPEED LOW DENSITY 45 LOWER SPEED HIGH DENSITY OPERATION SPEED
  • 47. 47
  • 48. 48
  • 49. ❖ TACK COATING BY SPRAYER 49
  • 50. ❖ Tack Coat Without Crack Sealing 50
  • 51. ❖ Overlay Over Severely Cracked Surface 51
  • 52. ❖ Inadequate Compaction And Excess Binding Material 52
  • 53. ❖ WBM Surface Without Key Aggregates And Excess Binding Material 53
  • 54. ❖ Shoulders At Higher Elevation 54
  • 55. ❖ Poorly Widened WBM Carriageway 55
  • 56. ❖ POORLY WIDENED WBM CARRIAGEWAY 56
  • 58. ❖ Tack Coat Surfaced WBMLayer 58
  • 59. Modern Equipment For Quality Control Tests In Highways Construction 59
  • 61. ❖ Portable Pendulum Type Skid Resistance Tester 61
  • 62. ❖ Dynamic Skid Resistance Tester 62
  • 66. ❖ Fifth Wheel Bump Integrator (Roughometer) 66
  • 69. 69
  • 70. 70
  • 71. 71
  • 72. ❖ Falling Weight Deflectometer 72
  • 73. 73