SlideShare a Scribd company logo
1 of 17
Download to read offline
Cable Preparation and Pulling 
Procedure Best Practices for 
Fiber Optic Indoor Tight-Buffered Cable 
© Panduit Corp. 2009 BEST PRACTICES PN447B 
 
Table of Contents 
3 
2.0 Preparation Notes Tools and Material – Tools and Materials ......................................... 3 
3.0 Pulling Procedure ........................................................................................................... 3 
4.0 Interconnect Cable Preparation ...................................................................................... 7 
4.1 Duplex Cable Preparation ............................................................................................... 7 
4.2 Simplex Cable Preparation ............................................................................................. 9 
5.0 Distribution Cable (≤ 24 fibers) Preparation .................................................................. 10 
5.1 Jacket Preparation ........................................................................................................ 10 
6.0 Distribution Cable (> 24 fibers) Preparation .................................................................. 12 
6.1 Jacket Preparation ........................................................................................................ 12 
6.2 Unit Preparation ............................................................................................................ 15 
7.0 Fiber Preparation .......................................................................................................... 17 
For Technical Support: www.panduit.com/resources/install_maintain.asp 
Page 1 of 17
© Panduit Corp. 2009 BEST PRACTICES PN447B 
DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES 
The practices contained herein are designed as a guide for use by persons having technical skill at their own 
discretion and risk. The recommended practices are based on average conditions. Panduit does not 
guarantee any favorable results or assume any liability in connection with this document. 
In addition, the materials and hardware referenced herein appear as examples, but in no way reflect the only 
tools and materials available to perform these installations. 
Local, State, Federal and Industry Codes and Regulations, as well as manufacturers requirements, must be 
consulted before proceeding with any project. Panduit makes no representations of, nor assumes any 
responsibility for, the accuracy or completeness of this document. Panduit disclaims any liability arising from 
any information contained herein or for the absence of same. 
For Technical Support: www.panduit.com/resources/install_maintain.asp 
Page 2 of 17
© Panduit Corp. 2009 BEST PRACTICES PN447B 
For Technical Support: www.panduit.com/resources/install_maintain.asp 
Page 3 of 17 
1.0 General Information 
This instruction manual is a step-by-step guide for end 
and termination of tight-buffered cable, including sheath 
removal, core preparation, and fiber preparation. Local 
company practices and specifications may be in place 
concerning cable access and how it relates to a specific 
product or application. Modifications that do not exceed 
the cable’s optical and mechanical performance 
specifications may be made to accommodate local 
company practices and specifications. These 
modifications should be made at the discretion of local 
company users. 
Step-by-step illustrations have been provided 
for your reference and orientation as you follow 
the procedures. 
2.0 Preparation Notes 
Gather the tools and materials to be used for the 
job and make sure they are approved by your 
company for use in the field and are in good 
working order. 
Record for future reference the cable 
identification markings, which consist of sheath 
number, footage, and cable description codes 
printed on the cable outer sheath. 
3.0 Pulling Procedure 
Tools and Materials 
1. Eye and Hand Protection 
2. Linesmen Pliers 
3. Tight Buffer Stripping Tool 
4. Wire Stripping Tool 
5. Scissors/Snips 
6. Sheath Knife 
7. Scissors/Snips 
8. Needle Nose Pliers
© Pa 
anduit Corp. 2009 
70 
Le 
00 Industrial D 
exington, SC 
1. Ge 
1.1 T 
mesh 
optic 
cable 
Drive 
29072 
eneral 
This procedur 
h pulling grip 
cables that a 
s include: 
• Tight Buffer 
• Unitized cab 
• Breakout cab 
Refer to the 
og for the max 
led. 
This issue in 
ocking armor. 
1.2 
Catal 
install 
1.3 T 
interlo 
2. P 
2.1 
Pull 
Grip 
ling Proce 
on Multifi 
re provides ins 
on Panduit m 
are not conne 
T PRACTICE 
edure: Ins 
ber Tight- 
structions for i 
multifiber tight 
ectorized. Exa 
red cables 
bles 
bles 
e appropriate 
ximum tensile 
ncludes grip 
. 
Precautions 
General Pre 
WA 
pro 
rec 
cu 
an 
ecautions 
Safety G 
Glasses 
ARNING: The 
otect the eyes 
commended w 
tting fiber. Pi 
d can damage 
S 
stalling a W 
-Buffered 
nstalling a wir 
t buffered fibe 
amples of suc 
cable specific 
load rating of 
re 
er 
ch 
cation sheet o 
the cable to b 
installation o 
e wearing of sa 
s from acciden 
. 
when handling 
eces of glass 
e the cornea o 
or 
be 
on cables wit 
afety glasses 
ntal injury is s 
g chemicals an 
fiber are very 
of the eye easi 
For Techn 
to 
strongly 
nd 
y sharp 
ily. 
nical Suppor 
BEST 
th 
rt: www.pan 
Wire Mes 
Fiber Op 
2.2 Ca 
sh Pulling 
tic Cables 
able Handlin 
s 
g Precautio 
Caution: Fibe 
excessive pu 
Consult the c 
cable you are 
sharply than 
radius. DO n 
cable than sp 
allow it to kin 
can alter the t 
cable – the ca 
er optic cable 
lling, bending 
cable specifica 
e installing. D 
the minimum 
ot apply more 
pecified. Do n 
nk. Doing so m 
transmission 
able may have 
3. Tools a 
3.1 The fol 
duit.com/res 
Page 4 of 17 
and Materials 
llowing tools a 
o complete th 
ems® pulling g 
cutters (diago 
suring tape 
y knife with ho 
tape, ¾ in. ( 
on tape, ¾ in 
es 
sors 
el, ball bearin 
wrench or scr 
y knife with ho 
required to 
• Kelle 
• Side 
• Meas 
• Utility 
knife 
• Vinyl 
• Fricti 
• Glove 
• Sciss 
• Swiv 
• Hex w 
• Utility 
sources/insta 
all_maintain. 
.asp 
Issue 1 
n 
is sensitive to 
g and crushing 
ation sheet for 
o not bend ca 
recommende 
e pulling force 
ot crush the c 
may cause dam 
characteristic 
e to be replace 
s 
and materials 
his procedure 
grip 
onal cutting p 
ook blade or c 
19.1mm) 
n. (19.1mm) 
ng type 
rewdriver 
ook blade 
PN447B 
October 2, 2009 
o 
g forces. 
r the 
able more 
d bend 
e to the 
cable or 
mage that 
cs of the 
ed. 
s are 
: 
pliers) 
cable 
9
© Panduit Corp. 2009 BEST PRACTICES PN447B 
For Technical Support: www.panduit.com/resources/install_maintain.asp 
Page 5 of 17 
4. Pulling Grip Selection and Installation 
4.1 Prior to installation, the proper size grip 
must be chosen for the cable to be pulled. 
Grip selection is based on the outside diameter 
of the cable (Figures 2 and 3) 
Cable 
Diameter 
PVC Jacket 
Aramid Yarn 
Coated Fiber 
Rip Cord 
Cable Diameter and Grip Size 
If cable diameter is in the 
range of…… 
Kellems part 
number 
2.5 ‐ 5.6mm (0.10 to 0.22in.) 033‐29‐1182 
5.3 ‐ 9.0mm (0.21 to 0.35in.) 
9.1 ‐ 12.2mm (0.36 to 0.48in.) 
12.3 ‐ 15.5mm (0.49 to 0.61in.) 
15.6 ‐ 18.5mm (0.62 to 0.73in.) 
18.6 ‐ 22.1mm (0.74 to 0.87in.) 
22.2 ‐ 25.4mm (0.88 to 1.0in.) 
033‐29‐1182 
033‐29‐1184 
033‐29‐1185 
033‐29‐1186 
033‐29‐1187 
033‐29‐1188 
Figure 2 Non-utilized Premises Cable 
Cable Diameter 
Aramid Yarn 
Cable Jacket 
Dielectric 
central member 
6‐fiber subunit 
Rip Cord 
Cross section of a 48-fiber 
Unitized Cable 
4.3 Once the proper grip is obtained, inspect it for 
damage broken wires, bulges due to stress, rust, etc. 
Grasp the pulling eye in one hand (gloves are 
recommended) and smooth out the mesh with the 
other, tightening the wires. Figure 4 illustrates the 
technique, which is critical when reusing grips. 
4.2 Generally speaking, use the smallest grip which will 
fit over the cable’s outer jacket without excessive difficulty. 
Measure the cable diameter and determine the proper grip 
by locating the diameter in Table 1. 
Figure 4 
4.4 To ease installation, trim the end of the cable with side 
cutters to remove any protruding buffered fibers, yarn, or 
central member (Figure 5) 
Figure 5 
4.5 It is necessary to remove a section of outer jacket 
equal to half of the length of the mesh area of the grip. 
Mark this distance from the end of the cable with a 
permanent marker (Figure 6) 
Figure 6
© Pa 
4.6 
cable 
relax 
(3 in 
anduit Corp. 2009 
Use a pump 
e by bringin 
xing them unt 
.) beyond the 
Figu 
4.7 
you 
jack 
For 
jack 
com 
rem 
CAU 
blad 
the o 
units 
imm 
Figu 
ure 8 
4.8 
laye 
expo 
direc 
ping action to 
ng your han 
til the end of t 
e mark made i 
≥ 7.5 cm 
(≥ 3.0in. 
o “walk” the g 
nds together 
the grip is at l 
in step 4.5 (F 
sheath remov 
g to remove th 
grip over the 
r and then 
least 7.5 cm 
igure 7) 
al procedure 
he marked len 
cables, first 
end of the 
ether with vin 
aining jacket. 
T PRACTICE 
for the cable 
ngth of outer 
remove 15 c 
cable. Tap 
nyl electrical 
making ring c 
ife, do not cut 
oing so may d 
ble component 
w it. 
Beginning a 
er of friction 
osed cable co 
ction of the su 
IMP 
frict 
cou 
Figu 
Mark 
ure 7 
Follow the s 
are installing 
ket (Figure 8). 
non-unitized 
ket from the 
mponents toge 
ove the rema 
UTION: When 
de or cable kni 
outer jacket-d 
s or other cab 
mediately below 
cm (6 in.) of 
pe the cable 
tape. Then 
cuts with a ho 
t all the way th 
damage the su 
ts which lie 
at the end of t 
n tape over 
ore. The frict 
un-units or bu 
PORTANT: Do 
tion tape. Ele 
uld affect the p 
ure 9 
ook 
hrough 
ub 
the outer jack 
the entire le 
tion tape shou 
uffered fibers 
o not use black 
ctrical tape ha 
pulling grip’s p 
ket, wrap one 
ength of the 
uld follow the 
twists. 
k electrical tap 
as a slick oute 
performance. 
Frictio 
over 
n tape 
core 
For Tech 
pe in place of 
er surface and 
Ou 
ter jacket 
hnical Suppo 
BEST 
d 
ort: www.pan 
S 
4.9 
cable 
core 
Tug 
“Walk” the 
e core. Sm 
, moving from 
on the grip to 
Figu 
4.10 
on th 
of th 
throu 
The t 
again 
e grip over t 
ooth the me 
m the pulling 
o tighten it aga 
ure 10 
Starting at 
he cable jacke 
he grip. The 
ugh the tape. 
tape must be t 
nst the cable co 
Tug 
the friction ta 
esh back ove 
eye to the c 
ainst the core 
least 2.5 cm 
et wrap vinyl 
e mesh’s imp 
(Figure 11). 
tight because i 
ore. 
on the grip sl 
Figu 
ure 11 
Note 
alway 
the p 
that i 
4.11 
bear 
insta 
(1.0 in.) belo 
tape TIGHTL 
print should s 
it helps compr 
ightly to tighte 
en it. 
or more viny 
nal, outside lay 
is layers the ta 
g as it moves th 
the pulling ey 
nd pulling tap 
w ready for the 
: When two 
ys wrap the fin 
pulling eye. Th 
it will not snag 
ing swivel an 
allation is now 
Fig 
Grip 
4.12 
(36 i 
the e 
wate 
is pro 
gure 12 
Removal 
After comp 
n.) behind th 
exposed cab 
er intrusion. S 
otected from d 
nduit.com/re 
Page 6 of 17 
Connect t 
yl tape layers 
yer from the ca 
ape like roofing 
hrough the duc 
ye to the app 
pe. (Figure 12 
e cable pull. 
pull, cut the c 
ce a protectiv 
tape in place 
ed splicing sla 
pletion of the 
he grip. Plac 
le end and t 
Store the coile 
damage. 
esources/ins 
tall_maintain 
n.asp 
PN447B 
ape-covered 
er the cable 
cable jacket. 
e (Figure 10) 
ow the mesh 
LY to the top 
show clearly 
ress the mesh 
are desired, 
able jacket to 
g shingles, so 
ct. 
ropriate ball 
2). The grip 
cable 91 cm 
ve cap over 
e to prevent 
ack so that it
© Panduit Corp. 2009 BEST PRACTICES PN447B 
For Technical Support: www.panduit.com/resources/install_maintain.asp 
Page 7 of 17 
4.0 Interconnect Cable 
This procedure is intended to be used with 
interconnect cables, including both duplex 
and simplex cable designs. Two simplex 
cables comprise a single duplex cable. 
The length of cable sheath to be removed 
will depend on local company practices and 
specifications. Designate this distance 
from the end of the cable on the outer 
sheath. 
4.1 Duplex Cable Preparation 
There are two types of duplex cables. 
Sheathed Duplex 
Enclosing two simplex cables in an outer 
sheath created a duplex cable. To prepare 
this type of cable, with a sheath knife, cut 
the outer jacket at the designated distance. 
Gently flex the cable at the ring cut to 
separate or removal. 
Remove and discard the sheath section. 
No more than eight inches of sheath should 
be removed at once. Therefore, eight-inch 
sections must be removed until the final 
desired length is achieved. 
With the outer sheath the two internal 
simplex cables are not exposed. At this 
point advance to Section 4.2 for simplex 
cable preparation procedures. 
Duplex and simplex cables 
Ringing a sheathed cable outer jacket with a sheath knife. 
Flexing the sheathed cable at the ring cut 
Removing the outer section of the jacket
© Panduit Corp. 2009 BEST PRACTICES PN447B 
For Technical Support: www.panduit.com/resources/install_maintain.asp 
Page 8 of 17 
Zip-cord Duplex Cables 
Two simplex cables joined via a 
connecting membrane create a duplex 
cable. This type of duplex cable is 
referred to as zip-cord. 
To prepare a zip-cord style duplex 
cable, use an approved sheath knife to 
carefully separate the duplex cable into 
two simplex cables. Cut the membrane 
connecting the two simplex cables. 
Approximately one inch is sufficient. 
Firmly grasp the two separated simplex 
cables and pull them apart. They 
should separate easily. 
Separate the duplex cable into two 
simplex cables for the distance 
designated by local splicing/termination 
guidelines and vendor specifications. 
At this point, advance to Section 4.2 for 
Simplex Cable Preparation procedures. 
Cutting the membrane connecting the two cables 
Carefully separating the two cables by pulling them apart
© Panduit Corp. 2009 BEST PRACTICES PN447B 
For Technical Support: www.panduit.com/resources/install_maintain.asp 
Page 9 of 17 
Cutting the simplex jacket to expose the tight-buffered fiber 
Cutting the strength member yarns 
4.2 Simplex Cable Preparation 
The length of sheath to be removed from 
each simplex cable will be determined by 
local splicing/termination guidelines and 
vendor specifications. 
The manufacturer of the connector type 
being installed specifies the correct removal 
length for each cable component. 
Information similar to the following 
illustration should be provided with the 
connector. 
Using an approved set of strippers that do 
not come close to a diameter small enough 
to damage the fiber, select one simplex 
cable and cut the jacket at the length as 
specified by the connector manufacturer. 
Remove the length of outer jacket. This will 
expose the tight-buffered fiber and the 
strength member yarn. Separate the 
strength member yarn from the tight-buffered 
fiber. 
Cut off the strength members leaving the 
length specified by the connector 
manufacturer. 
At this point advance to Section 7.0 for Fiber 
Preparation procedures. 
Simplex cable 
Removing the outer length of the simplex jacket
© Panduit Corp. 2009 BEST PRACTICES PN447B 
For Technical Support: www.panduit.com/resources/install_maintain.asp 
Page 10 of 17 
5.0 Distribution Cable (24 Fibers or 
less Preparation) 
This procedure is intended for use with 
distribution cable with 24 or fewer tight-buffered 
fibers. The 24-fiber design consists 
of a core of 12 tight-buffered fibers around 
an upjacketed central strength member. 
Stranded around this core are 12 more 
fibers with filler units to complete the layer. 
Strength member yarns and a jacket cover 
the core. 
The 12-fiber design is similar to the 24-fiber 
design without the outer layer of fibers. For 
these procedures the 24-fiber design will be 
shown. The sheath removal for the 12-fiber 
design is identical with the exception of the 
outer core layer of fibers. 
5.1 Jacket Preparation 
The length of cable sheath to be removed 
will depend on local company practices and 
vendor specifications. If not otherwise 
specified, six feet should be sufficient. 
Designate this distance from the end of the 
cable on the outer sheath. Using an 
approved sheath knife, “ring” the 
circumference of the jacket at the 
designated distance. 
Using a sheath knife, “ring” the 
circumference of the jacket about six to eight 
inches from the end of the cable. 
Gently flex the cable at the cut to separate 
for removal. 
The end piece of the jacket can be removed 
and discarded. This will expose the strength 
member yarns and ripcord. 
Ringing the cable with a sheath knife 
Flexing the cable at the ring cut to separate sheath sections 
Removing the outer cable sheath section 
Exposing the ripcord
© Panduit Corp. 2009 BEST PRACTICES PN447B 
Grasp and wrap the ripcord around the 
needle-nose pliers. 
Pull the ripcord back to the first 
predetermined ring cut. 
Carefully separate the strength member 
yarns from the core and cit to the length 
prescribed by local practices and vendor 
specifications. 
At this point advance to Section 7.0 for Fiber 
Preparation procedures. 
Grasping the ripcord with needle nose pliers 
Pulling the ripcord to the predetermined ring cut 
For Technical Support: www.panduit.com/resources/install_maintain.asp 
Page 11 of 17 
Removing the split cable sheath 
Cutting the strength member yarns
© Panduit Corp. 2009 BEST PRACTICES PN447B 
For Technical Support: www.panduit.com/resources/install_maintain.asp 
Page 12 of 17 
6.0 Distribution Cable (Greater than 
24 Fibers) Preparation 
This procedure is intended for use with 
distribution cable with more than 24 fibers. 
The 72-fiber version of this design is used 
here for demonstration purposes. The 
procedure explained here will work with all 
other distribution cable with more than 24 
fibers. 
The 72-fiber cable consists of six jacketed 
unites stranded around an upjacketed CSM. 
There is tape and a jacket round each unit. 
Around the core of the six units are stranded 
strength member yarns – on top of which the 
outer jacket is applied. 
6.1 Jacket Preparation 
The length of cable sheath to be removed 
will depend on local company practices and 
vendor specifications. Designate this 
distance from the end of the cable on the 
outer sheath. 
Using the approved sheath knife, “ring” the 
circumference of the outer jacket at the 
designated distance. 
Using the sheath knife, “ring” the 
circumference of the outer jacket about six 
to eight inches from the end of the cable. 
The end piece of jacket can be removed and 
discarded. This will expose the strength 
member yarns and ripcord. 
Ringing the cable sheath with a sheath knife 
Flexing the cable at ring cut to separate sheath sections 
Exposing the ripcord after removal of jacket end piece
© Panduit Corp. 2009 BEST PRACTICES PN447B 
Grasp and wrap the ripcord around the 
needle-nose pliers. 
Pull the ripcord back to the first 
predetermined ring cut. 
If a ripcord is not provided carefully slit the 
outer jacket to the predetermined ring cut 
using a sheath knife. 
Remove this length of the jacket and discard 
it. 
Separate the strength member yarns from the 
core and cut to the length prescribed by local 
company practices and vendor specifications. 
Grasping the ripcord with needle-nose pliers and pulling back 
to predetermined ring cut 
Removing the split cable sheath 
Cutting the strength member yarns 
For Technical Support: www.panduit.com/resources/install_maintain.asp 
Page 13 of 17
© Panduit Corp. 2009 BEST PRACTICES PN447B 
The core of the six jacketed units is 
wrapped with a clear tape. This tape can 
now be unwrapped and discarded. This will 
expose the individual jacketed 
units for preparation. 
The six jacketed units are stranded around 
the CSM. Unwind the units to expose the 
CSM. 
Using approved cutters cut the CSM to the 
desired length for termination. Unwinding the clear tape 
Exposing the central strength member 
Cutting the central strength member 
For Technical Support: www.panduit.com/resources/install_maintain.asp 
Page 14 of 17
© Panduit Corp. 2009 BEST PRACTICES PN447B 
For Technical Support: www.panduit.com/resources/install_maintain.asp 
Page 15 of 17 
6.2 Unit Preparation 
The length of unit jacket to be removed will 
depend on local company practices and 
vendor specification. It is important to use 
care to avoid damaging the tight-buffered 
fibers in the core of the unit and also to 
avoid cutting the ripcord. 
Using the sheath knife gently “ring” the 
circumference of the unit jacket about four to 
six inches from the end of the unit. Again, it 
is very important to use care to avoid 
damaging the tight-buffered fibers in the 
core of the unit and also to avoid cutting the 
ripcord. 
Gently flex the unit at the cut to separate for 
removal. 
The end piece of unit jacket can be removed 
and discarded. This will expose the ripcord 
and the clear tape wrapped around the core. 
Cut the outer strength members 
Flexing the unit of the ring cut to separate jacket sections 
Removing the end piece of the unit jacket
© Panduit Corp. 2009 BEST PRACTICES PN447B 
Grasp and wrap the ripcord around the 
needle-nose pliers. 
Pull the ripcord back to the predetermined 
length. This will depend on local company 
practices and vendor specifications. Peel 
the jacket away to this point. 
Using the approved snips or scissors cut this 
length of jacket away. Use care to avoid 
cutting any of the tight-buffered fibers. 
The unit’s tight-buffered fibers are 
surrounded with strength member yarns. 
Carefully separate the tight-buffered fibers 
from the strength member yarns. 
Using approved snips or scissors cut the 
strength member yarns to the desired length 
for termination. 
At this point advance to Section 7.0 for fiber 
Preparation procedures. 
Grasping and pulling the ripcord with needle-nose pliers 
For Technical Support: www.panduit.com/resources/install_maintain.asp 
Page 16 of 17 
Exposing the ripcord 
Peeling off the unit jacket
© Panduit Corp. 2009 BEST PRACTICES PN447B 
For Instructions in Local Languages 
and Technical Support: 
www.panduit.com/resources/install_maintain.asp www.panduit.com 
E-mail: 
cs@panduit.com 
Fax: 
(708) 444-6993 
Page 17 of 17 
7.0 Fiber Preparation 
Using an approved stripping tool that scores 
the 900μm diameter tight-buffered coating, 
but does not touch the 125μm diameter of 
the fiber, remove the tight-buffered coating. 
For best results, strip and remove two 
inches or less at a time. When stripping 
either the tight-buffered coating or the fiber’s 
coating, hold the fiber carefully to avoid tight 
bends, while placing the fiber under tension. 
Small bend diameters and abrupt high 
stress can damage or break the fiber. 
With the fibers now exposed and accessible 
for termination refer to local 
splicing/termination guidelines and vendor 
specification. 
Refer back to Section 4.2 Simplex Cable 
Preparation for an example of manufacturer 
supplied connector termination instructions. 
Removing the tight buffering

More Related Content

What's hot

8443-2 3M Silicone Rubber Cold Shrink Insulators
8443-2 3M Silicone Rubber Cold Shrink Insulators 8443-2 3M Silicone Rubber Cold Shrink Insulators
8443-2 3M Silicone Rubber Cold Shrink Insulators
Thorne & Derrick International
 
Hellermann Tyton - Cable Ties, Fixings & Stainless Steel Cable Ties
Hellermann Tyton - Cable Ties, Fixings & Stainless Steel Cable TiesHellermann Tyton - Cable Ties, Fixings & Stainless Steel Cable Ties
Hellermann Tyton - Cable Ties, Fixings & Stainless Steel Cable Ties
Thorne & Derrick International
 
Cablesys Data Center Do It Yourself Cabling System Catalog
Cablesys Data Center Do It Yourself Cabling System CatalogCablesys Data Center Do It Yourself Cabling System Catalog
Cablesys Data Center Do It Yourself Cabling System Catalog
Nick Flores
 
3M Cold Shrink High Voltage Cable Joints and Cable Terminations, Network Rail...
3M Cold Shrink High Voltage Cable Joints and Cable Terminations, Network Rail...3M Cold Shrink High Voltage Cable Joints and Cable Terminations, Network Rail...
3M Cold Shrink High Voltage Cable Joints and Cable Terminations, Network Rail...
Thorne & Derrick International
 
MEI 2012 Tech Roadmap
MEI 2012 Tech RoadmapMEI 2012 Tech Roadmap
MEI 2012 Tech Roadmap
VinceBeusan
 
Metro Moulding Industries Cataogue
Metro Moulding Industries CataogueMetro Moulding Industries Cataogue
Metro Moulding Industries Cataogue
METRO MOULDING
 
Ellis Patents - Cable Cleats, Cable Clamps & Cable Straps
Ellis Patents - Cable Cleats, Cable Clamps & Cable StrapsEllis Patents - Cable Cleats, Cable Clamps & Cable Straps
Ellis Patents - Cable Cleats, Cable Clamps & Cable Straps
Thorne & Derrick International
 

What's hot (19)

Icc products
Icc productsIcc products
Icc products
 
8443-2 3M Silicone Rubber Cold Shrink Insulators
8443-2 3M Silicone Rubber Cold Shrink Insulators 8443-2 3M Silicone Rubber Cold Shrink Insulators
8443-2 3M Silicone Rubber Cold Shrink Insulators
 
Hellermann Tyton - Cable Ties, Fixings & Stainless Steel Cable Ties
Hellermann Tyton - Cable Ties, Fixings & Stainless Steel Cable TiesHellermann Tyton - Cable Ties, Fixings & Stainless Steel Cable Ties
Hellermann Tyton - Cable Ties, Fixings & Stainless Steel Cable Ties
 
Cablesys Data Center Do It Yourself Cabling System Catalog
Cablesys Data Center Do It Yourself Cabling System CatalogCablesys Data Center Do It Yourself Cabling System Catalog
Cablesys Data Center Do It Yourself Cabling System Catalog
 
3M 8423-6 Cold Shrink Tube
3M 8423-6 Cold Shrink Tube3M 8423-6 Cold Shrink Tube
3M 8423-6 Cold Shrink Tube
 
Emtelle Fibre Optic Cables - Product Catalogue 2016
Emtelle Fibre Optic Cables - Product Catalogue 2016Emtelle Fibre Optic Cables - Product Catalogue 2016
Emtelle Fibre Optic Cables - Product Catalogue 2016
 
Fiber optic hand tools
Fiber optic hand toolsFiber optic hand tools
Fiber optic hand tools
 
3M Cold Shrink High Voltage Cable Joints and Cable Terminations, Network Rail...
3M Cold Shrink High Voltage Cable Joints and Cable Terminations, Network Rail...3M Cold Shrink High Voltage Cable Joints and Cable Terminations, Network Rail...
3M Cold Shrink High Voltage Cable Joints and Cable Terminations, Network Rail...
 
Panduit Panduct PanelMax Shielded Wiring Duct & Noise Shield - EMI/RFI Reduc...
 Panduit Panduct PanelMax Shielded Wiring Duct & Noise Shield - EMI/RFI Reduc... Panduit Panduct PanelMax Shielded Wiring Duct & Noise Shield - EMI/RFI Reduc...
Panduit Panduct PanelMax Shielded Wiring Duct & Noise Shield - EMI/RFI Reduc...
 
New Telesis guide 20191107_sp
New Telesis guide 20191107_spNew Telesis guide 20191107_sp
New Telesis guide 20191107_sp
 
Nexans Utility Tool Kit Case 82320 - Cable Preparation Tool Kit
Nexans Utility Tool Kit Case 82320 - Cable Preparation Tool KitNexans Utility Tool Kit Case 82320 - Cable Preparation Tool Kit
Nexans Utility Tool Kit Case 82320 - Cable Preparation Tool Kit
 
MEI 2012 Tech Roadmap
MEI 2012 Tech RoadmapMEI 2012 Tech Roadmap
MEI 2012 Tech Roadmap
 
Metro Moulding Industries Cataogue
Metro Moulding Industries CataogueMetro Moulding Industries Cataogue
Metro Moulding Industries Cataogue
 
Ellis Patents - Cable Cleats, Cable Clamps & Cable Straps
Ellis Patents - Cable Cleats, Cable Clamps & Cable StrapsEllis Patents - Cable Cleats, Cable Clamps & Cable Straps
Ellis Patents - Cable Cleats, Cable Clamps & Cable Straps
 
Super Rod - Cable Rods - Standard Set Cable Rods
Super Rod - Cable Rods - Standard Set Cable RodsSuper Rod - Cable Rods - Standard Set Cable Rods
Super Rod - Cable Rods - Standard Set Cable Rods
 
IRJET- Experimental Investigation on the Mechanical Properties of a PMC and H...
IRJET- Experimental Investigation on the Mechanical Properties of a PMC and H...IRJET- Experimental Investigation on the Mechanical Properties of a PMC and H...
IRJET- Experimental Investigation on the Mechanical Properties of a PMC and H...
 
3M Medium Voltage Cold Shrink Cable Joints & Terminations
3M Medium Voltage Cold Shrink Cable Joints & Terminations3M Medium Voltage Cold Shrink Cable Joints & Terminations
3M Medium Voltage Cold Shrink Cable Joints & Terminations
 
Emtelle FibreFlow Cable Ducts - Product Catalogue
Emtelle FibreFlow Cable Ducts - Product CatalogueEmtelle FibreFlow Cable Ducts - Product Catalogue
Emtelle FibreFlow Cable Ducts - Product Catalogue
 
Prysmian Bicon Multicleat And Multistrap Datasheet
Prysmian Bicon Multicleat And Multistrap DatasheetPrysmian Bicon Multicleat And Multistrap Datasheet
Prysmian Bicon Multicleat And Multistrap Datasheet
 

Similar to Foc pulling

UKPN 11kV 6.6kV HV Cable Jointing, Preparation & Installation Manual (Uncontr...
UKPN 11kV 6.6kV HV Cable Jointing, Preparation & Installation Manual (Uncontr...UKPN 11kV 6.6kV HV Cable Jointing, Preparation & Installation Manual (Uncontr...
UKPN 11kV 6.6kV HV Cable Jointing, Preparation & Installation Manual (Uncontr...
Thorne & Derrick International
 

Similar to Foc pulling (20)

Cable preparation in CCTV
Cable preparation in CCTVCable preparation in CCTV
Cable preparation in CCTV
 
194 adss cable-installationguide
194 adss cable-installationguide194 adss cable-installationguide
194 adss cable-installationguide
 
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
 
OFCPulling
OFCPullingOFCPulling
OFCPulling
 
OFC Puling
OFC PulingOFC Puling
OFC Puling
 
1. Heat Shrink Cable Termination (HV) - 11kV 33kV 3 Core XLPE BS6622 Cables
1. Heat Shrink Cable Termination (HV) - 11kV 33kV 3 Core XLPE BS6622 Cables1. Heat Shrink Cable Termination (HV) - 11kV 33kV 3 Core XLPE BS6622 Cables
1. Heat Shrink Cable Termination (HV) - 11kV 33kV 3 Core XLPE BS6622 Cables
 
Consac Cable - LV Cable Jointers & Jointing Procedures
Consac Cable - LV Cable Jointers & Jointing ProceduresConsac Cable - LV Cable Jointers & Jointing Procedures
Consac Cable - LV Cable Jointers & Jointing Procedures
 
Approach cable installation
Approach cable installationApproach cable installation
Approach cable installation
 
UKPN 11kV 6.6kV HV Cable Jointing, Preparation & Installation Manual (Uncontr...
UKPN 11kV 6.6kV HV Cable Jointing, Preparation & Installation Manual (Uncontr...UKPN 11kV 6.6kV HV Cable Jointing, Preparation & Installation Manual (Uncontr...
UKPN 11kV 6.6kV HV Cable Jointing, Preparation & Installation Manual (Uncontr...
 
Fiber Optic Cable Installation and Handling Instructions
Fiber Optic Cable Installation and Handling InstructionsFiber Optic Cable Installation and Handling Instructions
Fiber Optic Cable Installation and Handling Instructions
 
cisco-air-ant2566p4w-r-datasheet.pdf
cisco-air-ant2566p4w-r-datasheet.pdfcisco-air-ant2566p4w-r-datasheet.pdf
cisco-air-ant2566p4w-r-datasheet.pdf
 
FTTX Expanding our Reach with Fiber
FTTX Expanding our Reach with FiberFTTX Expanding our Reach with Fiber
FTTX Expanding our Reach with Fiber
 
Guide to Fiber Optic Patch Cord Management
Guide to Fiber Optic Patch Cord ManagementGuide to Fiber Optic Patch Cord Management
Guide to Fiber Optic Patch Cord Management
 
11kV 33kV Heat Shrink Terminations - Outdoor Armour Earthing Kits XLPE AWA Si...
11kV 33kV Heat Shrink Terminations - Outdoor Armour Earthing Kits XLPE AWA Si...11kV 33kV Heat Shrink Terminations - Outdoor Armour Earthing Kits XLPE AWA Si...
11kV 33kV Heat Shrink Terminations - Outdoor Armour Earthing Kits XLPE AWA Si...
 
Hawke Universal Cable Glands - Installation Instruction
Hawke Universal Cable Glands - Installation InstructionHawke Universal Cable Glands - Installation Instruction
Hawke Universal Cable Glands - Installation Instruction
 
RAYCHEM TERMINATION KIT-TYCO TERMINATION-케이블 종단-거-瑞侃工具包电缆终端-阿克巴交易
RAYCHEM TERMINATION KIT-TYCO TERMINATION-케이블 종단-거-瑞侃工具包电缆终端-阿克巴交易RAYCHEM TERMINATION KIT-TYCO TERMINATION-케이블 종단-거-瑞侃工具包电缆终端-阿克巴交易
RAYCHEM TERMINATION KIT-TYCO TERMINATION-케이블 종단-거-瑞侃工具包电缆终端-阿克巴交易
 
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...
 
Waveform Cable Jointing Manual - Preparing & Working on LV Waveform Cable
Waveform Cable Jointing Manual - Preparing & Working on LV Waveform CableWaveform Cable Jointing Manual - Preparing & Working on LV Waveform Cable
Waveform Cable Jointing Manual - Preparing & Working on LV Waveform Cable
 
Epp 0275-12 02 - 1xcore term.(2) RAYCHEM
Epp 0275-12 02 - 1xcore term.(2) RAYCHEM Epp 0275-12 02 - 1xcore term.(2) RAYCHEM
Epp 0275-12 02 - 1xcore term.(2) RAYCHEM
 
003-377.pdf
003-377.pdf003-377.pdf
003-377.pdf
 

Foc pulling

  • 1. Cable Preparation and Pulling Procedure Best Practices for Fiber Optic Indoor Tight-Buffered Cable © Panduit Corp. 2009 BEST PRACTICES PN447B Table of Contents 3 2.0 Preparation Notes Tools and Material – Tools and Materials ......................................... 3 3.0 Pulling Procedure ........................................................................................................... 3 4.0 Interconnect Cable Preparation ...................................................................................... 7 4.1 Duplex Cable Preparation ............................................................................................... 7 4.2 Simplex Cable Preparation ............................................................................................. 9 5.0 Distribution Cable (≤ 24 fibers) Preparation .................................................................. 10 5.1 Jacket Preparation ........................................................................................................ 10 6.0 Distribution Cable (> 24 fibers) Preparation .................................................................. 12 6.1 Jacket Preparation ........................................................................................................ 12 6.2 Unit Preparation ............................................................................................................ 15 7.0 Fiber Preparation .......................................................................................................... 17 For Technical Support: www.panduit.com/resources/install_maintain.asp Page 1 of 17
  • 2. © Panduit Corp. 2009 BEST PRACTICES PN447B DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES The practices contained herein are designed as a guide for use by persons having technical skill at their own discretion and risk. The recommended practices are based on average conditions. Panduit does not guarantee any favorable results or assume any liability in connection with this document. In addition, the materials and hardware referenced herein appear as examples, but in no way reflect the only tools and materials available to perform these installations. Local, State, Federal and Industry Codes and Regulations, as well as manufacturers requirements, must be consulted before proceeding with any project. Panduit makes no representations of, nor assumes any responsibility for, the accuracy or completeness of this document. Panduit disclaims any liability arising from any information contained herein or for the absence of same. For Technical Support: www.panduit.com/resources/install_maintain.asp Page 2 of 17
  • 3. © Panduit Corp. 2009 BEST PRACTICES PN447B For Technical Support: www.panduit.com/resources/install_maintain.asp Page 3 of 17 1.0 General Information This instruction manual is a step-by-step guide for end and termination of tight-buffered cable, including sheath removal, core preparation, and fiber preparation. Local company practices and specifications may be in place concerning cable access and how it relates to a specific product or application. Modifications that do not exceed the cable’s optical and mechanical performance specifications may be made to accommodate local company practices and specifications. These modifications should be made at the discretion of local company users. Step-by-step illustrations have been provided for your reference and orientation as you follow the procedures. 2.0 Preparation Notes Gather the tools and materials to be used for the job and make sure they are approved by your company for use in the field and are in good working order. Record for future reference the cable identification markings, which consist of sheath number, footage, and cable description codes printed on the cable outer sheath. 3.0 Pulling Procedure Tools and Materials 1. Eye and Hand Protection 2. Linesmen Pliers 3. Tight Buffer Stripping Tool 4. Wire Stripping Tool 5. Scissors/Snips 6. Sheath Knife 7. Scissors/Snips 8. Needle Nose Pliers
  • 4. © Pa anduit Corp. 2009 70 Le 00 Industrial D exington, SC 1. Ge 1.1 T mesh optic cable Drive 29072 eneral This procedur h pulling grip cables that a s include: • Tight Buffer • Unitized cab • Breakout cab Refer to the og for the max led. This issue in ocking armor. 1.2 Catal install 1.3 T interlo 2. P 2.1 Pull Grip ling Proce on Multifi re provides ins on Panduit m are not conne T PRACTICE edure: Ins ber Tight- structions for i multifiber tight ectorized. Exa red cables bles bles e appropriate ximum tensile ncludes grip . Precautions General Pre WA pro rec cu an ecautions Safety G Glasses ARNING: The otect the eyes commended w tting fiber. Pi d can damage S stalling a W -Buffered nstalling a wir t buffered fibe amples of suc cable specific load rating of re er ch cation sheet o the cable to b installation o e wearing of sa s from acciden . when handling eces of glass e the cornea o or be on cables wit afety glasses ntal injury is s g chemicals an fiber are very of the eye easi For Techn to strongly nd y sharp ily. nical Suppor BEST th rt: www.pan Wire Mes Fiber Op 2.2 Ca sh Pulling tic Cables able Handlin s g Precautio Caution: Fibe excessive pu Consult the c cable you are sharply than radius. DO n cable than sp allow it to kin can alter the t cable – the ca er optic cable lling, bending cable specifica e installing. D the minimum ot apply more pecified. Do n nk. Doing so m transmission able may have 3. Tools a 3.1 The fol duit.com/res Page 4 of 17 and Materials llowing tools a o complete th ems® pulling g cutters (diago suring tape y knife with ho tape, ¾ in. ( on tape, ¾ in es sors el, ball bearin wrench or scr y knife with ho required to • Kelle • Side • Meas • Utility knife • Vinyl • Fricti • Glove • Sciss • Swiv • Hex w • Utility sources/insta all_maintain. .asp Issue 1 n is sensitive to g and crushing ation sheet for o not bend ca recommende e pulling force ot crush the c may cause dam characteristic e to be replace s and materials his procedure grip onal cutting p ook blade or c 19.1mm) n. (19.1mm) ng type rewdriver ook blade PN447B October 2, 2009 o g forces. r the able more d bend e to the cable or mage that cs of the ed. s are : pliers) cable 9
  • 5. © Panduit Corp. 2009 BEST PRACTICES PN447B For Technical Support: www.panduit.com/resources/install_maintain.asp Page 5 of 17 4. Pulling Grip Selection and Installation 4.1 Prior to installation, the proper size grip must be chosen for the cable to be pulled. Grip selection is based on the outside diameter of the cable (Figures 2 and 3) Cable Diameter PVC Jacket Aramid Yarn Coated Fiber Rip Cord Cable Diameter and Grip Size If cable diameter is in the range of…… Kellems part number 2.5 ‐ 5.6mm (0.10 to 0.22in.) 033‐29‐1182 5.3 ‐ 9.0mm (0.21 to 0.35in.) 9.1 ‐ 12.2mm (0.36 to 0.48in.) 12.3 ‐ 15.5mm (0.49 to 0.61in.) 15.6 ‐ 18.5mm (0.62 to 0.73in.) 18.6 ‐ 22.1mm (0.74 to 0.87in.) 22.2 ‐ 25.4mm (0.88 to 1.0in.) 033‐29‐1182 033‐29‐1184 033‐29‐1185 033‐29‐1186 033‐29‐1187 033‐29‐1188 Figure 2 Non-utilized Premises Cable Cable Diameter Aramid Yarn Cable Jacket Dielectric central member 6‐fiber subunit Rip Cord Cross section of a 48-fiber Unitized Cable 4.3 Once the proper grip is obtained, inspect it for damage broken wires, bulges due to stress, rust, etc. Grasp the pulling eye in one hand (gloves are recommended) and smooth out the mesh with the other, tightening the wires. Figure 4 illustrates the technique, which is critical when reusing grips. 4.2 Generally speaking, use the smallest grip which will fit over the cable’s outer jacket without excessive difficulty. Measure the cable diameter and determine the proper grip by locating the diameter in Table 1. Figure 4 4.4 To ease installation, trim the end of the cable with side cutters to remove any protruding buffered fibers, yarn, or central member (Figure 5) Figure 5 4.5 It is necessary to remove a section of outer jacket equal to half of the length of the mesh area of the grip. Mark this distance from the end of the cable with a permanent marker (Figure 6) Figure 6
  • 6. © Pa 4.6 cable relax (3 in anduit Corp. 2009 Use a pump e by bringin xing them unt .) beyond the Figu 4.7 you jack For jack com rem CAU blad the o units imm Figu ure 8 4.8 laye expo direc ping action to ng your han til the end of t e mark made i ≥ 7.5 cm (≥ 3.0in. o “walk” the g nds together the grip is at l in step 4.5 (F sheath remov g to remove th grip over the r and then least 7.5 cm igure 7) al procedure he marked len cables, first end of the ether with vin aining jacket. T PRACTICE for the cable ngth of outer remove 15 c cable. Tap nyl electrical making ring c ife, do not cut oing so may d ble component w it. Beginning a er of friction osed cable co ction of the su IMP frict cou Figu Mark ure 7 Follow the s are installing ket (Figure 8). non-unitized ket from the mponents toge ove the rema UTION: When de or cable kni outer jacket-d s or other cab mediately below cm (6 in.) of pe the cable tape. Then cuts with a ho t all the way th damage the su ts which lie at the end of t n tape over ore. The frict un-units or bu PORTANT: Do tion tape. Ele uld affect the p ure 9 ook hrough ub the outer jack the entire le tion tape shou uffered fibers o not use black ctrical tape ha pulling grip’s p ket, wrap one ength of the uld follow the twists. k electrical tap as a slick oute performance. Frictio over n tape core For Tech pe in place of er surface and Ou ter jacket hnical Suppo BEST d ort: www.pan S 4.9 cable core Tug “Walk” the e core. Sm , moving from on the grip to Figu 4.10 on th of th throu The t again e grip over t ooth the me m the pulling o tighten it aga ure 10 Starting at he cable jacke he grip. The ugh the tape. tape must be t nst the cable co Tug the friction ta esh back ove eye to the c ainst the core least 2.5 cm et wrap vinyl e mesh’s imp (Figure 11). tight because i ore. on the grip sl Figu ure 11 Note alway the p that i 4.11 bear insta (1.0 in.) belo tape TIGHTL print should s it helps compr ightly to tighte en it. or more viny nal, outside lay is layers the ta g as it moves th the pulling ey nd pulling tap w ready for the : When two ys wrap the fin pulling eye. Th it will not snag ing swivel an allation is now Fig Grip 4.12 (36 i the e wate is pro gure 12 Removal After comp n.) behind th exposed cab er intrusion. S otected from d nduit.com/re Page 6 of 17 Connect t yl tape layers yer from the ca ape like roofing hrough the duc ye to the app pe. (Figure 12 e cable pull. pull, cut the c ce a protectiv tape in place ed splicing sla pletion of the he grip. Plac le end and t Store the coile damage. esources/ins tall_maintain n.asp PN447B ape-covered er the cable cable jacket. e (Figure 10) ow the mesh LY to the top show clearly ress the mesh are desired, able jacket to g shingles, so ct. ropriate ball 2). The grip cable 91 cm ve cap over e to prevent ack so that it
  • 7. © Panduit Corp. 2009 BEST PRACTICES PN447B For Technical Support: www.panduit.com/resources/install_maintain.asp Page 7 of 17 4.0 Interconnect Cable This procedure is intended to be used with interconnect cables, including both duplex and simplex cable designs. Two simplex cables comprise a single duplex cable. The length of cable sheath to be removed will depend on local company practices and specifications. Designate this distance from the end of the cable on the outer sheath. 4.1 Duplex Cable Preparation There are two types of duplex cables. Sheathed Duplex Enclosing two simplex cables in an outer sheath created a duplex cable. To prepare this type of cable, with a sheath knife, cut the outer jacket at the designated distance. Gently flex the cable at the ring cut to separate or removal. Remove and discard the sheath section. No more than eight inches of sheath should be removed at once. Therefore, eight-inch sections must be removed until the final desired length is achieved. With the outer sheath the two internal simplex cables are not exposed. At this point advance to Section 4.2 for simplex cable preparation procedures. Duplex and simplex cables Ringing a sheathed cable outer jacket with a sheath knife. Flexing the sheathed cable at the ring cut Removing the outer section of the jacket
  • 8. © Panduit Corp. 2009 BEST PRACTICES PN447B For Technical Support: www.panduit.com/resources/install_maintain.asp Page 8 of 17 Zip-cord Duplex Cables Two simplex cables joined via a connecting membrane create a duplex cable. This type of duplex cable is referred to as zip-cord. To prepare a zip-cord style duplex cable, use an approved sheath knife to carefully separate the duplex cable into two simplex cables. Cut the membrane connecting the two simplex cables. Approximately one inch is sufficient. Firmly grasp the two separated simplex cables and pull them apart. They should separate easily. Separate the duplex cable into two simplex cables for the distance designated by local splicing/termination guidelines and vendor specifications. At this point, advance to Section 4.2 for Simplex Cable Preparation procedures. Cutting the membrane connecting the two cables Carefully separating the two cables by pulling them apart
  • 9. © Panduit Corp. 2009 BEST PRACTICES PN447B For Technical Support: www.panduit.com/resources/install_maintain.asp Page 9 of 17 Cutting the simplex jacket to expose the tight-buffered fiber Cutting the strength member yarns 4.2 Simplex Cable Preparation The length of sheath to be removed from each simplex cable will be determined by local splicing/termination guidelines and vendor specifications. The manufacturer of the connector type being installed specifies the correct removal length for each cable component. Information similar to the following illustration should be provided with the connector. Using an approved set of strippers that do not come close to a diameter small enough to damage the fiber, select one simplex cable and cut the jacket at the length as specified by the connector manufacturer. Remove the length of outer jacket. This will expose the tight-buffered fiber and the strength member yarn. Separate the strength member yarn from the tight-buffered fiber. Cut off the strength members leaving the length specified by the connector manufacturer. At this point advance to Section 7.0 for Fiber Preparation procedures. Simplex cable Removing the outer length of the simplex jacket
  • 10. © Panduit Corp. 2009 BEST PRACTICES PN447B For Technical Support: www.panduit.com/resources/install_maintain.asp Page 10 of 17 5.0 Distribution Cable (24 Fibers or less Preparation) This procedure is intended for use with distribution cable with 24 or fewer tight-buffered fibers. The 24-fiber design consists of a core of 12 tight-buffered fibers around an upjacketed central strength member. Stranded around this core are 12 more fibers with filler units to complete the layer. Strength member yarns and a jacket cover the core. The 12-fiber design is similar to the 24-fiber design without the outer layer of fibers. For these procedures the 24-fiber design will be shown. The sheath removal for the 12-fiber design is identical with the exception of the outer core layer of fibers. 5.1 Jacket Preparation The length of cable sheath to be removed will depend on local company practices and vendor specifications. If not otherwise specified, six feet should be sufficient. Designate this distance from the end of the cable on the outer sheath. Using an approved sheath knife, “ring” the circumference of the jacket at the designated distance. Using a sheath knife, “ring” the circumference of the jacket about six to eight inches from the end of the cable. Gently flex the cable at the cut to separate for removal. The end piece of the jacket can be removed and discarded. This will expose the strength member yarns and ripcord. Ringing the cable with a sheath knife Flexing the cable at the ring cut to separate sheath sections Removing the outer cable sheath section Exposing the ripcord
  • 11. © Panduit Corp. 2009 BEST PRACTICES PN447B Grasp and wrap the ripcord around the needle-nose pliers. Pull the ripcord back to the first predetermined ring cut. Carefully separate the strength member yarns from the core and cit to the length prescribed by local practices and vendor specifications. At this point advance to Section 7.0 for Fiber Preparation procedures. Grasping the ripcord with needle nose pliers Pulling the ripcord to the predetermined ring cut For Technical Support: www.panduit.com/resources/install_maintain.asp Page 11 of 17 Removing the split cable sheath Cutting the strength member yarns
  • 12. © Panduit Corp. 2009 BEST PRACTICES PN447B For Technical Support: www.panduit.com/resources/install_maintain.asp Page 12 of 17 6.0 Distribution Cable (Greater than 24 Fibers) Preparation This procedure is intended for use with distribution cable with more than 24 fibers. The 72-fiber version of this design is used here for demonstration purposes. The procedure explained here will work with all other distribution cable with more than 24 fibers. The 72-fiber cable consists of six jacketed unites stranded around an upjacketed CSM. There is tape and a jacket round each unit. Around the core of the six units are stranded strength member yarns – on top of which the outer jacket is applied. 6.1 Jacket Preparation The length of cable sheath to be removed will depend on local company practices and vendor specifications. Designate this distance from the end of the cable on the outer sheath. Using the approved sheath knife, “ring” the circumference of the outer jacket at the designated distance. Using the sheath knife, “ring” the circumference of the outer jacket about six to eight inches from the end of the cable. The end piece of jacket can be removed and discarded. This will expose the strength member yarns and ripcord. Ringing the cable sheath with a sheath knife Flexing the cable at ring cut to separate sheath sections Exposing the ripcord after removal of jacket end piece
  • 13. © Panduit Corp. 2009 BEST PRACTICES PN447B Grasp and wrap the ripcord around the needle-nose pliers. Pull the ripcord back to the first predetermined ring cut. If a ripcord is not provided carefully slit the outer jacket to the predetermined ring cut using a sheath knife. Remove this length of the jacket and discard it. Separate the strength member yarns from the core and cut to the length prescribed by local company practices and vendor specifications. Grasping the ripcord with needle-nose pliers and pulling back to predetermined ring cut Removing the split cable sheath Cutting the strength member yarns For Technical Support: www.panduit.com/resources/install_maintain.asp Page 13 of 17
  • 14. © Panduit Corp. 2009 BEST PRACTICES PN447B The core of the six jacketed units is wrapped with a clear tape. This tape can now be unwrapped and discarded. This will expose the individual jacketed units for preparation. The six jacketed units are stranded around the CSM. Unwind the units to expose the CSM. Using approved cutters cut the CSM to the desired length for termination. Unwinding the clear tape Exposing the central strength member Cutting the central strength member For Technical Support: www.panduit.com/resources/install_maintain.asp Page 14 of 17
  • 15. © Panduit Corp. 2009 BEST PRACTICES PN447B For Technical Support: www.panduit.com/resources/install_maintain.asp Page 15 of 17 6.2 Unit Preparation The length of unit jacket to be removed will depend on local company practices and vendor specification. It is important to use care to avoid damaging the tight-buffered fibers in the core of the unit and also to avoid cutting the ripcord. Using the sheath knife gently “ring” the circumference of the unit jacket about four to six inches from the end of the unit. Again, it is very important to use care to avoid damaging the tight-buffered fibers in the core of the unit and also to avoid cutting the ripcord. Gently flex the unit at the cut to separate for removal. The end piece of unit jacket can be removed and discarded. This will expose the ripcord and the clear tape wrapped around the core. Cut the outer strength members Flexing the unit of the ring cut to separate jacket sections Removing the end piece of the unit jacket
  • 16. © Panduit Corp. 2009 BEST PRACTICES PN447B Grasp and wrap the ripcord around the needle-nose pliers. Pull the ripcord back to the predetermined length. This will depend on local company practices and vendor specifications. Peel the jacket away to this point. Using the approved snips or scissors cut this length of jacket away. Use care to avoid cutting any of the tight-buffered fibers. The unit’s tight-buffered fibers are surrounded with strength member yarns. Carefully separate the tight-buffered fibers from the strength member yarns. Using approved snips or scissors cut the strength member yarns to the desired length for termination. At this point advance to Section 7.0 for fiber Preparation procedures. Grasping and pulling the ripcord with needle-nose pliers For Technical Support: www.panduit.com/resources/install_maintain.asp Page 16 of 17 Exposing the ripcord Peeling off the unit jacket
  • 17. © Panduit Corp. 2009 BEST PRACTICES PN447B For Instructions in Local Languages and Technical Support: www.panduit.com/resources/install_maintain.asp www.panduit.com E-mail: cs@panduit.com Fax: (708) 444-6993 Page 17 of 17 7.0 Fiber Preparation Using an approved stripping tool that scores the 900μm diameter tight-buffered coating, but does not touch the 125μm diameter of the fiber, remove the tight-buffered coating. For best results, strip and remove two inches or less at a time. When stripping either the tight-buffered coating or the fiber’s coating, hold the fiber carefully to avoid tight bends, while placing the fiber under tension. Small bend diameters and abrupt high stress can damage or break the fiber. With the fibers now exposed and accessible for termination refer to local splicing/termination guidelines and vendor specification. Refer back to Section 4.2 Simplex Cable Preparation for an example of manufacturer supplied connector termination instructions. Removing the tight buffering