2. 2
2
Presentation Contents
• 4 major projects (introduction, my role, professional
growth)
– Major Hazard Facility (MHF)
– M2 Transformer Temperature Alarms
– M2 Paper Break Camera System
– Recovery Boiler’s 5 & 6 (R5/6) Superheater Tube Temperature
Probes
• Training / experiance
• Life in the Valley
3. 3
3
MHF
Introduction
• Australian Paper (Maryvale mill) is a MHF
• Safety Case
– How we manage safety at our MHF
My Role
• Finding and tagging ~100 untagged MHF assets
4. 4
4
MHF
My Role
• Managed the updating of BECA marked piping and
instrumentation diagrams (P&IDs) show all MHF assets
• Added previously unrecorded MHF assets to instrument
calibration system (Caltrack)
5. 5
5
MHF
My Role
• Documented ‘unreachable’ MHF assets
– Created work requests for area assistance
• Attend MHF meetings to report progress
– Worked within WorkSafe MHF licence renewal deadline
6. 6
6
Professional Growth
• Read P&IDs
• Locate assets
• Maryvale mill
• Safety
– Personal protective equipment (PPE)
– Signing into areas
• MHF
– Identification of MHF locations & critical assets
MHF
8. 8
8
My Role
• Investigated old switching type indicators
• Sourced and purchased new site standard WIKA
indicator/transmitters
• Documentation
– Loop connection diagrams
– Junction box drawings
• Installation
• Distributed Control System (DCS)
– Logic
– Human Machine Interface (HMI) Graphics
• Commissioning
M2 Transformer Temperature Alarms
14. 14
14
M2 Paper Break Camera System
Introduction
• Making paper is not a perfect process
• Paper breaks
– Hard to diagnose (insects, falling debris, dripping, inconsistent pulp
from the head box etc.)
– Unplanned downtime expense
– Camera system
• Portable trial camera system (WEBVISION)
Purchased and
installed at M2
Decided to
reinstall at M2
Moved to other paper machines
Reinstallation
at M2
15. 15
15
Justification for Reinstallation
M2 Paper Break Camera System
M2 unplanned downtime cost $3388/hour
M2 average breaks per day (2011) 3.72 (rose to ~6 in 2012)
M2 average break time 12 minutes
Average break cost $677.60/break
M2 paper machine production 290 days/year
Saving assuming one break per day reduction $196,504/year
Project cost $30,000
Return on investment (ROI) 555%
16. 16
16
My Role
• Read available documentation
• Diagnosed reason that camera system was not functioning:
– Sourced and replaced broken switch to power up WEBVISION system.
– Fixed non functioning capture computers
• Power supply replaced with a spare
• HDD formatted and imaged with working capture unit’s HDD
• Swapped single input video card with dual input card from M4
• Wrote a scope of work
– Extracted drawings from WEBVISION documentation and organise boilermakers to make up
brackets for cameras and lights
– Assisted electricians with installation
• Prepare cameras (power/video connections, housing, focus, aperture, exposure
zoom)
• Create/updated company documentation
• Training and handover
M2 Paper Break Camera System
22. 22
22
Professional Growth
• Cameras
– Aperture
– Exposure
– Focus
– Lighting
– Fault finding
• Better estimate installation times
• Process of getting work done
• Communication with trades
M2 Paper Break Camera System
24. 24
24
• Old
• New
R5/6 Superheater Tube Temperature Probes
Bailey DCS
ABB DCS
Temperature
transmitter
HMI
25. 25
25
My Role
• Ascertain what work had already been completed and what
was left to do
• Prepare wiring diagrams for remaining work
R5/6 Superheater Tube Temperature Probes
26. 26
26
My Role
• Prepare loop connection diagrams for each loop (135)
R5/6 Superheater Tube Temperature Probes
27. 27
27
My Role
• Source quotes for remaining work
– Relocation of 89 loops from R5 and
46 loops from R6
• Manage contractors work
• Commission
– Check wiring/cabling/ferrules are correct
– Programming of transmitters and making
sure each loop is functioning correctly
– Enabling new DCS programming and linking
to operators graphics (HMI)
R5/6 Superheater Tube Temperature Probes
28. 28
28
Professional Growth
• Wiring diagrams and loop connection diagrams are
essential for:
– Installation
– Decommissioning
– System analysis and modification
– Fault finding
• Temperature sensors
• Manage contractors work
• Bailey and ABB DCS
R5/6 Superheater Tube Temperature Probes
29. 29
29
• CMMS (PBS4)
• Thermal imaging
• DC motor maintenance
• DCS
– METSO
– ABB
• Electrical Equipment in Hazardous Areas (EEHA)
• Cardiopulmonary resuscitation (CPR)
• Job Safety Analysis (JSA)
• Transformer Oil Sampling
Training / Experience
30. 30
30
• Netball – 2 seasons (Churchill)
• Badminton – 2 seasons (Traralgon)
• Indoor cricket – 2nd seasons (Traralgon)
• Golf – AP Golf Day
• Latrobe Young Professionals (LYP) group events
• Fishing at Lake Hyland
Life in the Valley
31. 31
31
Staff
• Daryl Adams - E/I Engineer - HV, SESO
• Alex ‘Zac’ Crewe - Power/Recovery E/I Engineer
• Steven Gooda - DCS Engineer
• Jeff Buckett – Head of Maintenance - E/I
• Andrew Sun - Asset Management Engineer
• Muditha Hasthanayake - M1 & M2 E/I Engineer
• Milinda Senanayake - Graduate E/I Engineer
• Tom Hagley - M3 E/I Engineer
• Edward Trickett – General Manager - Paper
• Trevor Niejalke - M1/M2/M3 E/I Superintendent
• Anthony Beckett - M5 Production Superintendent
• Alan Jenkinson - M5 E/I Engineer
• Raymond Smith - 2011 IBL Mechanical Engineering Student
• Brendan Jilbert - M1/M2 Machine Manager
Acknowledgements
32. 32
32
Trades/Technicians
• David Lothian - M1/2/3 E/I
• Bill Vansambeek - DCS Technician
• Andrew Daly - E/I Central Workshop Planner
• Rodney Hewat - E/I Central Workshop L/H & Acting SESO
• Ben Bowen - Central Workshop E/I
• Rudy Bence, Contractor – VB & Co planner
• Nick Calla - M1/M2/M3 E/I Planner
• Craig Bassi - HP Technician
• Brian Spiteri – Boilermakers
Young Professionals
Acknowledgements