Reliability data analysis provides a wide-range of benefits, including the
opportunity to optimize the timing of equipment overhauls and inspections,
the content of maintenance procedures, as well as the life cycle costing of
sparing and upgrade programs in operating facilities world-wide.
As data standardization can result in improved quality of data, the
International Standard ISO 14224 (Collection and exchange of reliability and
maintenance data for equipment) provides a comprehensive basis for the
collection of reliability and maintenance (RM) data in a standard format for
equipment in all facilities and operations during the operational life cycle of
equipment.
In this example, the number of spare pumps and most demanded
components necessary to maintain centrifugal pumps distributed in several
operating installations for two years is estimated using the RM data and the
Poisson Distribution. The following relevant definitions for this article were
extracted and adapted for this example from ISO 14224:2006.
 Boundary: A clear boundary description is imperative for the data
analysis. Inlet and outlet valves and suction strainer are not within
the boundary. The pump drivers along with their auxiliary systems
are not included (electric motor, gas turbine or combustion engine).
 Taxonomy: According to standard classification presented in Figure
1 shows RM data on levels 6 (equipment unit) to level 9 (parts).
 Equipment Attributes: The centrifugal pumps are classified as
rotating equipment and are sub-divided (Refer to Figure 2).
© Monaco Engineering Solutions
APPLICATION OF USING THE
POISSON DISTRIBUTION METHOD
TO CALCULATE NUMBER OF SPARE
PARTS
Fabio Oshiro
Principal Risk & Reliability Engineer
References
BS EN ISO 14224:2006 Collection and exchange of
reliability and maintenance data for equipment, BSI,
2007.
OREDA Handbook 2015, 6th edition – Volume I.
USP, Producao, v.21, n. 4, out./dez. 2011, p. 656-666,
“Spare parts inventor control: a literature review”,
Rego, Jose Roberto; Mesquita, Marco Aurelio.
Croston, J.D.: Forecasting and Stock Control for
Intermittent Demands. Operational Research
Quarterly, Vol.23, No 3, pp. 289-303, September 1972
Figure 2— Equipment Attributes (adapted from BS EN ISO 14224: 2006)
Figure 1—Taxonomy (BS EN ISO 14224: 2006)
© Monaco Engineering Solutions
 Failure and maintenance parameters: The RM data for exploration and production equipment from a wide
variety of geographic areas, installations, equipment types and operating conditions is presented in the Off-
shore & Onshore Reliability Data (OREDA) Handbook.
 Failure mechanism: the physical, chemical or other process or combination of processes that leads to the
failure. They are divided in the following major categories: mechanical, instrumentation and electrical fail-
ures; external influence; and miscellaneous. For the centrifugal pump, leakage, mechanical failure - general
and faulty signal/indication/alarm are the main mechanisms of failure corresponding to 23%.
 Failure mode is the effect by which a failure is observed on the failed item and for the purpose of this ex-
ample it can simplistic be divided into three types:
 Desired function is not obtained (e.g. failure to start);
 Specified function lost or outside accepted operational limits (e.g. spurious stop, high output);
 Failure indication is observed but there is no immediate and critical impact on the equipment-
unit function.
 The centrifugal pump failure modes with the highest failure rate are abnormal instrument reading (AIR), ex-
ternal leakage - process medium (ELP) and external leakage - utility medium (ELU).
 The Seals and valves are the maintainable items with the highest failure rates, after unknown and other
items.
Poisson distribution method
The Poisson distribution is a method often applied to
forecast the number of spare parts using reliability analysis.
The demand for spare parts for replacement or due to
failure follows the Poisson distribution when the events
occur at a constant average rate and in any interval
independent of the number of events occurring, i.e. given
that a failure has just occurred, it has no influence on the
time elapsed until the next failure. The number of failures
in a given time would be given by .
Where: λ = failure rate,
t = length of time being considered,
x = number of failures.
The probability of failures (n) in time (t) is given by R(t):
© Monaco Engineering Solutions
Calculations:
N = 143 centrifugal pumps
λpumps = 51.66 failures / 106
hours (from OREDA)
Components: assuming 12.22% and 6.24% of the critical
pump failures are caused respectively by seals and valves
λseals = 0,1222 λpumps = 6,31 failures / 106
hours
λvalves = 0,0624 λpumps = 3.22 failures / 106
hours
t = 2 years trepair = 27 hours
For the calculation, the spare parts are divided in repairable
and non-repairable.
Non-repairable items:
In this example, seals and valves for the centrifugal pump
are considered non-repairable items. For the Poisson
Distribution equation, the number of failures (x) is equal to
number of spares. Using the Poisson distribution, the
results obtained are presented in Table 1.
© Monaco Engineering Solutions
Seals
n f R
0 0.00000 0.00 %
1 0.00000 0.00 %
5 0.00112 0.16 %
10 0.03651 8.39 %
15 0.10027 48.51 %
20 0.05333 87.82 %
21 0.04017 91.84 %
22 0.02888 94.73 %
23 0.01986 96.71 %
Valves
n f R
0 0.00031 0.03 %
1 0.00251 0.28 %
3 0.02729 3.01 %
5 0.08900 18.44 %
10 0.10113 80.82 %
11 0.07425 88.25 %
12 0.04997 93.25 %
13 0.03104 96.35 %
14 0.01791 98.14 %
Table 1—Poisson Distribution—Seals and Valves
The fill rate or confidence level is the required probability of having a spare part in inventory when required
(90% =< R =< 95%). The recommended number of spare parts (only for seals and valves) for 143 centrifugal pumps
based on Poisson distribution and assuming a required confidence level between 90% and 95% is 21 seals and
12 valves.
Repairable items: For repairable parts, a stock level of spares is calculated to compensate for items undergoing the
process of repair (trepair = 27 hours).
Pumps
n-1 f R
0 0.819174 81.92 %
1 0.163392 98.26 %
2 0.016295 99.89 %
3 0.001083 99.99 %
Table 2—Poisson Distribution—Pumps
Since the time to repair centrifugal pumps is relatively
short, the probability of a second pump failing while the
first one is in repair is fairly low. As a result, considering the
fill rate (≥90%), the recommended number of spares is two
pumps. The result obtained is presented in Table 2, where
n = 2 (n-1).
Scrap and condemned items: Additional spare parts need
to be considered in order to compensate for the
condemnation or scrappage of repairable items. Calculating
the number of failures during the period, it is possible to
determine this number. In this example, the scrap rate
considered is 5%.
MINIMISING RISK
MAXIMISING PERFORMANCE
Monaco Engineering Solutions
Americas ● Europe ● Middle East ● Africa ● Asia Pacific
mes.info@mes-international.com
Pumps
n f R
0 0.000000 0.00 %
50 0.000000 0.00 %
100 0.001055 0.42 %
120 0.025596 21.80 %
140 0.022128 83.51 %
141 0.020312 85.54 %
142 0.18513 87.39 %
143 0.016756 89.06 %
144 0.015060 90.57 %
145 0.013443 91.91 %
Table 3—Poisson Distribution—Pump failures
Using the Poisson distribution, it is estimated that 144 failures
(see Table 3) may occur and 8 additional pumps are
recommended.
In summary, 10 centrifugal pumps, 21 seals and 12 valves are
necessary to maintain the 143 centrifugal pumps in operation for
two years with approximately 90% confidence.
The annual cost of equipment unreliability in the petroleum,
natural gas and petrochemical industries is significant. As a result,
analyses of reliability and maintainability data (RM) have become
of increased importance. As a consequence, the application of
standards, such as ISO 14224, is highly recommended to obtain
better quality of data.
As presented, RM data can also be used to estimate the quantity
of spare parts demanded during a determined period of time by
means of the application the Poisson distribution method.
The Poisson distribution is a simplified approach to estimate the
number of required spares when little process information is
known. If detailed engineering data is available a detailed
approach using Monte Carlo methods is recommended. © Monaco Engineering Solutions

More Related Content

What's hot

Spare parts management
Spare parts managementSpare parts management
Spare parts managementMedha Yadav
 
Spare parts management
Spare parts management Spare parts management
Spare parts management Smita Sinha
 
KEY TO PROFITABILITY: SPARE PART MANAGEMENT
KEY TO PROFITABILITY: SPARE PART MANAGEMENTKEY TO PROFITABILITY: SPARE PART MANAGEMENT
KEY TO PROFITABILITY: SPARE PART MANAGEMENTDr. V.N. Tikku
 
Control systems for spare parts.
Control systems for spare parts.Control systems for spare parts.
Control systems for spare parts.Medha Yadav
 
SMRP (1997) Proactive Maintenance Slides by John Day - 1997
SMRP (1997) Proactive Maintenance Slides by John Day - 1997SMRP (1997) Proactive Maintenance Slides by John Day - 1997
SMRP (1997) Proactive Maintenance Slides by John Day - 1997Ricky Smith CMRP, CMRT
 
Spare parts management
Spare parts managementSpare parts management
Spare parts managementMedha Yadav
 
Rcm 4 hour overview for rcm teams
Rcm 4 hour overview for rcm teamsRcm 4 hour overview for rcm teams
Rcm 4 hour overview for rcm teamsMatthew Clemens
 
Reliability centered maintenance
Reliability centered maintenanceReliability centered maintenance
Reliability centered maintenancePankaj Singh
 
Maintenance strategy
Maintenance strategyMaintenance strategy
Maintenance strategygumma alsgier
 
Maintenance Management
Maintenance ManagementMaintenance Management
Maintenance ManagementVijay325
 
Leaning The Warehouse
Leaning The WarehouseLeaning The Warehouse
Leaning The WarehouseJim Malone
 
Machine maintenance presentation
Machine maintenance presentationMachine maintenance presentation
Machine maintenance presentationhimu_kamrul
 
Equipment Taxonomy for the Collection of Maintenance and Reliability Data
Equipment Taxonomy for the Collection of Maintenance and Reliability DataEquipment Taxonomy for the Collection of Maintenance and Reliability Data
Equipment Taxonomy for the Collection of Maintenance and Reliability DataRicky Smith CMRP, CMRT
 
Application of ISO 14224 Methods in SAP
Application of ISO 14224 Methods in SAPApplication of ISO 14224 Methods in SAP
Application of ISO 14224 Methods in SAPTony Ciliberti PE
 
8 Steps To Success In Maintenance Planning And Scheduling
8 Steps To Success In Maintenance Planning And Scheduling8 Steps To Success In Maintenance Planning And Scheduling
8 Steps To Success In Maintenance Planning And SchedulingRicky Smith CMRP, CMRT
 
Introduction to Reliability Centered Maintenance
Introduction to Reliability Centered MaintenanceIntroduction to Reliability Centered Maintenance
Introduction to Reliability Centered MaintenanceDibyendu De
 
Boeing - Reliability Centered Maintenance
Boeing - Reliability Centered MaintenanceBoeing - Reliability Centered Maintenance
Boeing - Reliability Centered MaintenanceNandhagopal Muralithar
 

What's hot (20)

03.chapter3.4.spares.criticality
03.chapter3.4.spares.criticality03.chapter3.4.spares.criticality
03.chapter3.4.spares.criticality
 
Spare parts management
Spare parts managementSpare parts management
Spare parts management
 
Spare parts management
Spare parts management Spare parts management
Spare parts management
 
KEY TO PROFITABILITY: SPARE PART MANAGEMENT
KEY TO PROFITABILITY: SPARE PART MANAGEMENTKEY TO PROFITABILITY: SPARE PART MANAGEMENT
KEY TO PROFITABILITY: SPARE PART MANAGEMENT
 
Control systems for spare parts.
Control systems for spare parts.Control systems for spare parts.
Control systems for spare parts.
 
SMRP (1997) Proactive Maintenance Slides by John Day - 1997
SMRP (1997) Proactive Maintenance Slides by John Day - 1997SMRP (1997) Proactive Maintenance Slides by John Day - 1997
SMRP (1997) Proactive Maintenance Slides by John Day - 1997
 
Spare parts management
Spare parts managementSpare parts management
Spare parts management
 
Rcm 4 hour overview for rcm teams
Rcm 4 hour overview for rcm teamsRcm 4 hour overview for rcm teams
Rcm 4 hour overview for rcm teams
 
Reliability centered maintenance
Reliability centered maintenanceReliability centered maintenance
Reliability centered maintenance
 
Maintenance strategy
Maintenance strategyMaintenance strategy
Maintenance strategy
 
Maintenance Management
Maintenance ManagementMaintenance Management
Maintenance Management
 
Leaning The Warehouse
Leaning The WarehouseLeaning The Warehouse
Leaning The Warehouse
 
Maintenance strategies
Maintenance strategiesMaintenance strategies
Maintenance strategies
 
OEE
OEEOEE
OEE
 
Machine maintenance presentation
Machine maintenance presentationMachine maintenance presentation
Machine maintenance presentation
 
Equipment Taxonomy for the Collection of Maintenance and Reliability Data
Equipment Taxonomy for the Collection of Maintenance and Reliability DataEquipment Taxonomy for the Collection of Maintenance and Reliability Data
Equipment Taxonomy for the Collection of Maintenance and Reliability Data
 
Application of ISO 14224 Methods in SAP
Application of ISO 14224 Methods in SAPApplication of ISO 14224 Methods in SAP
Application of ISO 14224 Methods in SAP
 
8 Steps To Success In Maintenance Planning And Scheduling
8 Steps To Success In Maintenance Planning And Scheduling8 Steps To Success In Maintenance Planning And Scheduling
8 Steps To Success In Maintenance Planning And Scheduling
 
Introduction to Reliability Centered Maintenance
Introduction to Reliability Centered MaintenanceIntroduction to Reliability Centered Maintenance
Introduction to Reliability Centered Maintenance
 
Boeing - Reliability Centered Maintenance
Boeing - Reliability Centered MaintenanceBoeing - Reliability Centered Maintenance
Boeing - Reliability Centered Maintenance
 

Similar to Spare Parts Forecasting using Poisson Distribution

Application of Reliability Analysis for Predicting Failures in Cement Industry
Application of Reliability Analysis for Predicting Failures in Cement IndustryApplication of Reliability Analysis for Predicting Failures in Cement Industry
Application of Reliability Analysis for Predicting Failures in Cement Industrytheijes
 
Principal component analysis based approach for fault diagnosis in pneumatic ...
Principal component analysis based approach for fault diagnosis in pneumatic ...Principal component analysis based approach for fault diagnosis in pneumatic ...
Principal component analysis based approach for fault diagnosis in pneumatic ...eSAT Publishing House
 
Vibration Analysis of a Centrifugal Pump
Vibration Analysis of a Centrifugal PumpVibration Analysis of a Centrifugal Pump
Vibration Analysis of a Centrifugal PumpIRJET Journal
 
METUGE OKANE E. END OF COURSE DISSERTATION FINAL REVISION 2015
METUGE OKANE E. END OF COURSE DISSERTATION FINAL REVISION 2015METUGE OKANE E. END OF COURSE DISSERTATION FINAL REVISION 2015
METUGE OKANE E. END OF COURSE DISSERTATION FINAL REVISION 2015metuge okane
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)IJERD Editor
 
Prediction of Case Loss Due to Machine Downtime in Nigerian Bottling Company
Prediction of Case Loss Due to Machine Downtime in Nigerian Bottling CompanyPrediction of Case Loss Due to Machine Downtime in Nigerian Bottling Company
Prediction of Case Loss Due to Machine Downtime in Nigerian Bottling CompanyIJCMESJOURNAL
 
2001 Nissan Pathfinder Service Repair Manual
2001 Nissan Pathfinder Service Repair Manual2001 Nissan Pathfinder Service Repair Manual
2001 Nissan Pathfinder Service Repair Manualfujjfjksekmdm
 
Reliability Assessment of Induction Motor Drive using Failure Mode Effects An...
Reliability Assessment of Induction Motor Drive using Failure Mode Effects An...Reliability Assessment of Induction Motor Drive using Failure Mode Effects An...
Reliability Assessment of Induction Motor Drive using Failure Mode Effects An...IOSR Journals
 
Failure Analysis of Feedstock Preheater Unit of the Kaduna Refinery using Fai...
Failure Analysis of Feedstock Preheater Unit of the Kaduna Refinery using Fai...Failure Analysis of Feedstock Preheater Unit of the Kaduna Refinery using Fai...
Failure Analysis of Feedstock Preheater Unit of the Kaduna Refinery using Fai...theijes
 
2003 Daewoo Matiz Service Repair Manual 1.pdf
2003 Daewoo Matiz Service Repair Manual 1.pdf2003 Daewoo Matiz Service Repair Manual 1.pdf
2003 Daewoo Matiz Service Repair Manual 1.pdfujfjkskmmdm
 
IRJET- Experimental Study on Flow through Venturimeter
IRJET- Experimental Study on Flow through VenturimeterIRJET- Experimental Study on Flow through Venturimeter
IRJET- Experimental Study on Flow through VenturimeterIRJET Journal
 

Similar to Spare Parts Forecasting using Poisson Distribution (14)

Application of Reliability Analysis for Predicting Failures in Cement Industry
Application of Reliability Analysis for Predicting Failures in Cement IndustryApplication of Reliability Analysis for Predicting Failures in Cement Industry
Application of Reliability Analysis for Predicting Failures in Cement Industry
 
Principal component analysis based approach for fault diagnosis in pneumatic ...
Principal component analysis based approach for fault diagnosis in pneumatic ...Principal component analysis based approach for fault diagnosis in pneumatic ...
Principal component analysis based approach for fault diagnosis in pneumatic ...
 
Vibration Analysis of a Centrifugal Pump
Vibration Analysis of a Centrifugal PumpVibration Analysis of a Centrifugal Pump
Vibration Analysis of a Centrifugal Pump
 
C012231827
C012231827C012231827
C012231827
 
METUGE OKANE E. END OF COURSE DISSERTATION FINAL REVISION 2015
METUGE OKANE E. END OF COURSE DISSERTATION FINAL REVISION 2015METUGE OKANE E. END OF COURSE DISSERTATION FINAL REVISION 2015
METUGE OKANE E. END OF COURSE DISSERTATION FINAL REVISION 2015
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)
 
UM PROJECT
UM PROJECTUM PROJECT
UM PROJECT
 
Prediction of Case Loss Due to Machine Downtime in Nigerian Bottling Company
Prediction of Case Loss Due to Machine Downtime in Nigerian Bottling CompanyPrediction of Case Loss Due to Machine Downtime in Nigerian Bottling Company
Prediction of Case Loss Due to Machine Downtime in Nigerian Bottling Company
 
2001 Nissan Pathfinder Service Repair Manual
2001 Nissan Pathfinder Service Repair Manual2001 Nissan Pathfinder Service Repair Manual
2001 Nissan Pathfinder Service Repair Manual
 
Reliability Assessment of Induction Motor Drive using Failure Mode Effects An...
Reliability Assessment of Induction Motor Drive using Failure Mode Effects An...Reliability Assessment of Induction Motor Drive using Failure Mode Effects An...
Reliability Assessment of Induction Motor Drive using Failure Mode Effects An...
 
Rams 2007 paper pdf
Rams 2007 paper pdfRams 2007 paper pdf
Rams 2007 paper pdf
 
Failure Analysis of Feedstock Preheater Unit of the Kaduna Refinery using Fai...
Failure Analysis of Feedstock Preheater Unit of the Kaduna Refinery using Fai...Failure Analysis of Feedstock Preheater Unit of the Kaduna Refinery using Fai...
Failure Analysis of Feedstock Preheater Unit of the Kaduna Refinery using Fai...
 
2003 Daewoo Matiz Service Repair Manual 1.pdf
2003 Daewoo Matiz Service Repair Manual 1.pdf2003 Daewoo Matiz Service Repair Manual 1.pdf
2003 Daewoo Matiz Service Repair Manual 1.pdf
 
IRJET- Experimental Study on Flow through Venturimeter
IRJET- Experimental Study on Flow through VenturimeterIRJET- Experimental Study on Flow through Venturimeter
IRJET- Experimental Study on Flow through Venturimeter
 

Recently uploaded

Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Recently uploaded (20)

Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 

Spare Parts Forecasting using Poisson Distribution

  • 1. Reliability data analysis provides a wide-range of benefits, including the opportunity to optimize the timing of equipment overhauls and inspections, the content of maintenance procedures, as well as the life cycle costing of sparing and upgrade programs in operating facilities world-wide. As data standardization can result in improved quality of data, the International Standard ISO 14224 (Collection and exchange of reliability and maintenance data for equipment) provides a comprehensive basis for the collection of reliability and maintenance (RM) data in a standard format for equipment in all facilities and operations during the operational life cycle of equipment. In this example, the number of spare pumps and most demanded components necessary to maintain centrifugal pumps distributed in several operating installations for two years is estimated using the RM data and the Poisson Distribution. The following relevant definitions for this article were extracted and adapted for this example from ISO 14224:2006.  Boundary: A clear boundary description is imperative for the data analysis. Inlet and outlet valves and suction strainer are not within the boundary. The pump drivers along with their auxiliary systems are not included (electric motor, gas turbine or combustion engine).  Taxonomy: According to standard classification presented in Figure 1 shows RM data on levels 6 (equipment unit) to level 9 (parts).  Equipment Attributes: The centrifugal pumps are classified as rotating equipment and are sub-divided (Refer to Figure 2). © Monaco Engineering Solutions APPLICATION OF USING THE POISSON DISTRIBUTION METHOD TO CALCULATE NUMBER OF SPARE PARTS Fabio Oshiro Principal Risk & Reliability Engineer References BS EN ISO 14224:2006 Collection and exchange of reliability and maintenance data for equipment, BSI, 2007. OREDA Handbook 2015, 6th edition – Volume I. USP, Producao, v.21, n. 4, out./dez. 2011, p. 656-666, “Spare parts inventor control: a literature review”, Rego, Jose Roberto; Mesquita, Marco Aurelio. Croston, J.D.: Forecasting and Stock Control for Intermittent Demands. Operational Research Quarterly, Vol.23, No 3, pp. 289-303, September 1972
  • 2. Figure 2— Equipment Attributes (adapted from BS EN ISO 14224: 2006) Figure 1—Taxonomy (BS EN ISO 14224: 2006) © Monaco Engineering Solutions  Failure and maintenance parameters: The RM data for exploration and production equipment from a wide variety of geographic areas, installations, equipment types and operating conditions is presented in the Off- shore & Onshore Reliability Data (OREDA) Handbook.  Failure mechanism: the physical, chemical or other process or combination of processes that leads to the failure. They are divided in the following major categories: mechanical, instrumentation and electrical fail- ures; external influence; and miscellaneous. For the centrifugal pump, leakage, mechanical failure - general and faulty signal/indication/alarm are the main mechanisms of failure corresponding to 23%.  Failure mode is the effect by which a failure is observed on the failed item and for the purpose of this ex- ample it can simplistic be divided into three types:  Desired function is not obtained (e.g. failure to start);  Specified function lost or outside accepted operational limits (e.g. spurious stop, high output);  Failure indication is observed but there is no immediate and critical impact on the equipment- unit function.  The centrifugal pump failure modes with the highest failure rate are abnormal instrument reading (AIR), ex- ternal leakage - process medium (ELP) and external leakage - utility medium (ELU).  The Seals and valves are the maintainable items with the highest failure rates, after unknown and other items.
  • 3. Poisson distribution method The Poisson distribution is a method often applied to forecast the number of spare parts using reliability analysis. The demand for spare parts for replacement or due to failure follows the Poisson distribution when the events occur at a constant average rate and in any interval independent of the number of events occurring, i.e. given that a failure has just occurred, it has no influence on the time elapsed until the next failure. The number of failures in a given time would be given by . Where: λ = failure rate, t = length of time being considered, x = number of failures. The probability of failures (n) in time (t) is given by R(t): © Monaco Engineering Solutions Calculations: N = 143 centrifugal pumps λpumps = 51.66 failures / 106 hours (from OREDA) Components: assuming 12.22% and 6.24% of the critical pump failures are caused respectively by seals and valves λseals = 0,1222 λpumps = 6,31 failures / 106 hours λvalves = 0,0624 λpumps = 3.22 failures / 106 hours t = 2 years trepair = 27 hours For the calculation, the spare parts are divided in repairable and non-repairable. Non-repairable items: In this example, seals and valves for the centrifugal pump are considered non-repairable items. For the Poisson Distribution equation, the number of failures (x) is equal to number of spares. Using the Poisson distribution, the results obtained are presented in Table 1.
  • 4. © Monaco Engineering Solutions Seals n f R 0 0.00000 0.00 % 1 0.00000 0.00 % 5 0.00112 0.16 % 10 0.03651 8.39 % 15 0.10027 48.51 % 20 0.05333 87.82 % 21 0.04017 91.84 % 22 0.02888 94.73 % 23 0.01986 96.71 % Valves n f R 0 0.00031 0.03 % 1 0.00251 0.28 % 3 0.02729 3.01 % 5 0.08900 18.44 % 10 0.10113 80.82 % 11 0.07425 88.25 % 12 0.04997 93.25 % 13 0.03104 96.35 % 14 0.01791 98.14 % Table 1—Poisson Distribution—Seals and Valves The fill rate or confidence level is the required probability of having a spare part in inventory when required (90% =< R =< 95%). The recommended number of spare parts (only for seals and valves) for 143 centrifugal pumps based on Poisson distribution and assuming a required confidence level between 90% and 95% is 21 seals and 12 valves. Repairable items: For repairable parts, a stock level of spares is calculated to compensate for items undergoing the process of repair (trepair = 27 hours). Pumps n-1 f R 0 0.819174 81.92 % 1 0.163392 98.26 % 2 0.016295 99.89 % 3 0.001083 99.99 % Table 2—Poisson Distribution—Pumps Since the time to repair centrifugal pumps is relatively short, the probability of a second pump failing while the first one is in repair is fairly low. As a result, considering the fill rate (≥90%), the recommended number of spares is two pumps. The result obtained is presented in Table 2, where n = 2 (n-1). Scrap and condemned items: Additional spare parts need to be considered in order to compensate for the condemnation or scrappage of repairable items. Calculating the number of failures during the period, it is possible to determine this number. In this example, the scrap rate considered is 5%.
  • 5. MINIMISING RISK MAXIMISING PERFORMANCE Monaco Engineering Solutions Americas ● Europe ● Middle East ● Africa ● Asia Pacific mes.info@mes-international.com Pumps n f R 0 0.000000 0.00 % 50 0.000000 0.00 % 100 0.001055 0.42 % 120 0.025596 21.80 % 140 0.022128 83.51 % 141 0.020312 85.54 % 142 0.18513 87.39 % 143 0.016756 89.06 % 144 0.015060 90.57 % 145 0.013443 91.91 % Table 3—Poisson Distribution—Pump failures Using the Poisson distribution, it is estimated that 144 failures (see Table 3) may occur and 8 additional pumps are recommended. In summary, 10 centrifugal pumps, 21 seals and 12 valves are necessary to maintain the 143 centrifugal pumps in operation for two years with approximately 90% confidence. The annual cost of equipment unreliability in the petroleum, natural gas and petrochemical industries is significant. As a result, analyses of reliability and maintainability data (RM) have become of increased importance. As a consequence, the application of standards, such as ISO 14224, is highly recommended to obtain better quality of data. As presented, RM data can also be used to estimate the quantity of spare parts demanded during a determined period of time by means of the application the Poisson distribution method. The Poisson distribution is a simplified approach to estimate the number of required spares when little process information is known. If detailed engineering data is available a detailed approach using Monte Carlo methods is recommended. © Monaco Engineering Solutions