SlideShare a Scribd company logo
1 of 35
Chapter – 4
Construction Project
Costs Management
What is Cost and Project Cost Management?
Project cost management includes the
processes required to ensure that the
project is completed within an
approved budget.
Project Cost Management
 Project Cost Management includes the processes involved in
planning, estimating, budgeting, and controlling costs so that the
project can be completed within the approved budget.
 Cost Estimating – developing an approximation of the costs of
the resources needed to complete project activities.
 Cost Budgeting – aggregating the estimated costs of individual
activities or work packages to establish a cost baseline.
 Cost Control – influencing the factors that create cost variances
and controlling changes to the project budget.
Cost Budgeting: Processes
 Cost Aggregation
 Schedule activity cost estimates are aggregated by work packages in
accordance with the WBS.
 Reserve Analysis
 Reserve analysis establishes contingency reserves, such as the
management contingency reserve, that are allowances for unplanned,
but potentially required, changes. Such changes may result from risks
identified in the risk register.
 Funding Limit Reconciliation
 Large variations in the periodic expenditure of funds are usually
undesirable for organizational operations. Therefore, the expenditure
of funds is reconciled with the funding limits set by the customer or
performing organization on the disbursement of funds for the project.
Reserves
 Reserves are included in a cost estimate to mitigate cost risk by
allowing for future situations that are difficult to predict.
Contingency reserves allow for future situations that may
be partially planned for (sometimes called known
unknowns) and are included in the project cost baseline.
Management reserves allow for future situations that are
unpredictable (sometimes called unknown unknowns).
 Reserve Analysis
Many cost estimators include reserves, also called
contingency allowances, as costs in many schedule activity
cost estimates. This has the inherent problem of potentially
overstating the cost estimate for the schedule activity.
Cost Budgeting:
 Cost budgeting involves aggregating the estimated costs of
individual schedule activities or work packages to establish a
total cost baseline for measuring project performance.
 What is a budget?
A Plan
A Limit
A Schedule
A Reality Check
An Allocation
“ Cash is a King”
“A planned expression of money” (Wright .D
1994 “A practical foundation in costing”
Routledge)
For a defined activity shows;
Income & Expenditure
Total estimated costs
Defined period of time
Project Budget
The Project Budget is the time-based
spreadsheet that shows the project team's intent to
spend the organization's resources on project
activities.(The process of conversion of a resource
schedule into financial schedule).
It is the determination of costs associated with the
defined activities
Project Budget
It provides the baseline reference for subsequent
project monitoring and control (via The construction
plan and the associated cash flow estimates). Or it is a
guide for management.
It provides management with an understanding of how
funds will be utilized and expended over time for
projects or operations.
Project Budget
Reflects the actual scope at the site and the actual
quantities from construction issued drawings and a
standard productivity rate.
Include change orders and extra work orders in terms
of changed quantities and costs.
Should reflect the actual quantities placed and a
standard unit rate for each work activity.
Cost Budgeting: Outputs
 Cost Baseline
 The cost baseline is a time-phased
budget that is used as a basis against
which to measure, monitor, and control
overall cost performance on the project.
 Project Funding Requirements
 Funding requirements, total and
periodic (e.g., annual or quarterly), are
derived from the cost baseline and can
be established to exceed, usually by a
margin, to allow for either early
progress or cost overruns.
 Funding usually occurs in incremental
amounts that are not continuous, and,
therefore, appears as a step function.
Why Project Budgeting?
Why needs for preparing a project budget :
To identify the monetary requirement in time both in
the forms of how much and when so as to be able to
implement according to plans or contract
agreements constraints
To indicate organizations whether their projects are
in a position to look for diversified sources of
finances in order to carry them out successfully
To enable organization to rethink and overhaul their
operational systems so that they can meet their
contractual performance targets
Building the Planned Project Budget
Establishing the WBS is the first step in defining
the project and in establishing the baseline.
All of the efforts used in producing the
deliverable of each task can be defined in terms
of cost (Labor, materials, facilities, services and
overhead).
Building the Planned Project Budget
• The sum of all tasks within the WBS constitutes the
total budget of the project.
Developing a Baseline Budget
for a Project
• Once a detailed budget is developed and
approved, the project manager should publish
this baseline and set it as a point of
comparison for actual performance progress.
• The baseline budget is the tool for measuring
how project changes affect our schedule and
budget.
Cost Budget Baseline
This process aggregates the estimated costs of
individual activities or work packages to establish and
authorized cost baseline.
Establish the Schedule Baseline
Preliminary Design 1.1.1 Jan Feb Mar Apr May
1.1.1.1 Define Specifications & Req.
1.1.1.2 Develop PreliminaryDesign
1.1.1.3 Review PreliminaryDesign
1.1.1.4 Incorporate Comments
1.1.1.5 PreliminaryDesignComplete
Based on the Project Scope and available resources, the work
activities in the WBS are scheduled to establish the Schedule
Baseline.
Schedule Baseline
Establish the Cost Baseline
Preliminary Design 1.1.1 Hours Jan Feb Mar Apr May
1.1.1.1 Define Specifications & Req. 1,500 1,000
1.1.1.2 Develop PreliminaryDesign 2,000 2,000
1.1.1.3 ReviewPreliminaryDesign 500 500
1.1.1.4 Incorporate Comments 320 320
1.1.1.5 PreliminaryDesignComplete 1,000
Cost Baseline
Notice in the chart the time phased hours associated with each task.
Integrated Scope, Schedule and Cost
PreliminaryDesign1.1.1 Hours Jan Feb Mar Apr May
1.1.1.1 Define Specifications & Req.
1,500 1,000
1.1.1.2 Develop PreliminaryDesign
2,000 2,000
1.1.1.3 Review PreliminaryDesign
500 500
1.1.1.4 Incorporate Comments
320 320
1.1.1.5 PreliminaryDesignComplete
1,000
Integrated Cost/Schedule Baseline
As the chart shows below , each task has an associated schedule
and time phased cost.
Current negotiated
contract cost
Estimated cost of additional
authorized unpriced work
(yet to be negotiated)
+ = CBB
Profit/Fee is not part of the Contract Budget Base (CBB)
The Contract Budget Base (CBB) represents the total budget for
all authorized contractual work, minus Profit/Fee.
The CBB can only be modified when duly authorized changes to
the contract are received. CBB is always calculated as follows:
The Budgeting Process
The Awarded Amount to the Builder is $219,999. This includes
Profit/Fee.
The Negotiated Total Cost, without Profit/Fee, for the project equals
$183,852. This will be the basis for developing the Contract Budget
Baseline (CBB). Again, remember that this amount is exclusive of Fee.
10/12/2023
20
• Developing the Project Budget
1. Develop Cost Components – Financial Vs Engineering
2. Use Project Budgeting Formats CWP Formats.xls
3. Assign and Fill in the different Costs into the project budgeting
structure
4. Prepare the Project Budget against schedule Project Budgeting
new-12.xls
• Formats for Project Budgeting CWP Formats.xls
– Master Schedule Format
– Resources (Material, Labor, Equipment)
Schedule Formats
– Cost Breakdown Format
– Project Budgeting (Construction) Format
– Cash Flow Format
– Project Budgeting (Financial) Formats
Cash Flows Programming
Financial / Budgetary / Cost Breakdown Structure
• Use Cost Breakdown Structure (CWP Formats)
• Use Financial / Budgetary Breakdown Structure
(CWP Formats)
• Determine Corresponding monthly expenses from
Resources Programming
• Cash flow Programming includes Cash inflows, Cash
outflows and Cash flow balance (Liquidity)
 Project cost control includes:
 Influencing the factors that create changes to the cost baseline
 Ensuring requested changes are agreed upon
 Managing the actual changes when and as they occur
 Assuring that potential cost overruns do not exceed the authorized
funding periodically and in total for the project
 Monitoring cost performance to detect and understand variances from the
cost baseline
 Recording all appropriate changes accurately against the cost baseline
 Preventing incorrect, inappropriate, or unapproved changes from being
included in the reported cost or resource usage
 Informing appropriate stakeholders of approved changes
 Acting to bring expected cost overruns within acceptable limits.
Cost Control
Cost Control Inputs:
Cost Baseline
Project Funding Requirements
Performance Reports
Work Performance Information
Approved Change Requests
Project Management Plan
Cost Control: Tools and Techniques
 Cost Change Control System
 A cost change control system, documented in the cost
management plan, defines the procedures by which the cost
baseline can be changed.
 Performance Measurement Analysis
 Performance measurement techniques help to assess the
magnitude of any variances that will invariably occur.
 The earned value technique (EVT) compares the cumulative value
of the budgeted cost of work performed (earned) at the original
allocated budget amount to both the budgeted cost of work
scheduled (planned) and to the actual cost of work performed
(actual).
 This technique is especially useful for cost control, resource
management, and production.
Cost Control Tools:
 Cost Change Control System
 A cost change control system, documented in the cost management plan, defines
the procedures by which the cost baseline can be changed. It includes the forms,
documentation, tracking systems, and approval levels necessary for authorizing
changes.
 Performance Measurement Analysis
 Performance measurement techniques help to assess the magnitude of any
variances that will invariably occur. The earned value technique (EVT) compares
the cumulative value of the budgeted cost of work performed (earned) at the
original allocated budget amount to both the budgeted cost of work scheduled
(planned) and to the actual cost of work performed (actual). This technique is
especially useful for cost control, resource management, and production.
EVM: Earned Values Management
 The Earned Value Technique ( EV) involves developing these
key values for each schedule activity, work package, or control
account:
 It is a method measuring project performance by comparing the
amount of work planned with actually accomplished, in order to
determine if cost and schedule performance as planned.
Data Element Term Acronyms
Scheduled Work Budgeted Cost of Work Scheduled PV
Earned Value Budgeted Cost of work performed EV
Actuals Actual Cost of Work performed AC
Authorized Work Budget at Completion BAC
Forecasted Cost Estimate at Completion EAC
Work variance Schedule Variance SV
Cost Variance Cost Variance CV
Completion Variance Completion Variance VAC
 Cost variance (CV).
 CV equals earned value (EV) minus actual cost (AC).
The cost variance at the end of the project will be the difference
between the budget at completion (BAC) and the actual amount
spent.
Formula: CV= EV – AC
A negative value of CV would mean Cost over run
 Schedule Variance:
SV equals earned value (EV) minus planned (PV). Schedule
variance will ultimately equal zero when the project is completed
because all of the planned values will have been earned.
Formula: SV = EV – PV
Negative SV would mean Time over run.
Variance Calculations:
Performance Indices
 Cost performance index (CPI).
A CPI value less than 1.0 indicates a cost overrun of the
estimates. A CPI value greater than 1.0 indicates a cost under
run of the estimates.
CPI = EV /AC.
CPI is the most commonly used cost-efficiency indicator.
Formula: CPI = EV/AC
 Schedule performance index (SPI).
 The SPI is used, in addition to the schedule status , to predict
the completion date and is sometimes used in conjunction
with the CPI to forecast the project completion estimates. SPI
equals the ratio of the EV to the PV.
Formula: SPI = EV/PV
Estimate At Completion EAC:
EAC = AC+ETC
Estimate to Complete ETC:
ETC equals the revised estimate
for the work remaining.
The earned value technique in its various forms is a commonly
used method of performance measurement. It integrates project
scope, cost (or resource) and schedule measures to help the
project management team assess project performance.
Cost and Schedule Forecasting
Exercises:
Exercise #1:Schedule Variance Example.
PV = $ 42000
EV = $ 38000
AC = $ 48000
Budget at Completion BAC = $80000
SV = EV – PV = $38000 – 42000 = - $4000
SV % = SV/PV = -4000/42000 = -9.5 % Hence there is schedule
overrun of 9.5%
Exercise #2: Cost Variance Example.
CV = EV- AC = 38000 – 48000 = - 10000
CV% = CV/EV = -10000/38000 = -26 % Schedule overrun by 26%
# 3 Cost Performance Index ( CPI)
CPI = EV/AC = 38000/48000 = 0.79
 Hence $0.79 worth of work was done for every $ 1 spent.
#4 Schedule Performance Index: SPI
SPI = EV/PV = 38000/42000 = 0.90
$ 0.90 worth of work has been for each done for each $1.00
worth of work that was planned to be done.
 #5. Estimate at Completion and Variance at
Completion
EAC = BAC/CPI = 80000/0.79 = $101265
VAC = BAC – EAC = 80000-101265 = - $ 21265. The
project will exceed the planned budget by $21265
Problems:
#1:
BAC = 40 K
EV = 20 K
PV = 28 K
AC = 26 K
Determine:
% of work scheduled
% of budget spent
Cost Variance CV
Scheduled Variance SV
 Case 1:
 PV = 1600
 EV = 1600
 AC = 1600
 Ideal Case where every thing goes as per plan.
 Case2:
 PV= 1900
 EV= 1500
 ACP= 1700
 400 worth of work is behind schedule
 SV = EV- PV = 1500-1900= -400
 SV%= ( SV/PV)x100 = -21%
 CV = EV – AC = 1500 – 1700= -200 Cost overrun by 200
 CV% = (CV/EV)x100 = -13%
 SPI = EV/PV = $0.79
 CPI= EV/AC = $0.88

More Related Content

Similar to Project Cost Management

PM_Assignment3_Group1 (2).pptx
PM_Assignment3_Group1 (2).pptxPM_Assignment3_Group1 (2).pptx
PM_Assignment3_Group1 (2).pptxvanna37
 
L03 integration management
L03 integration managementL03 integration management
L03 integration managementAsa Chan
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updatedShraddha PMP
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimationSomashekar S.M
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptxYogesh Singh
 
PM Session 4
PM Session 4PM Session 4
PM Session 4dmdk12
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project managementselinasimpson1601
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementHayat Denzi
 
engineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptxengineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptxDr. ABEER KHALID MANSOUR
 
Software Project Management: Budget
Software Project Management: BudgetSoftware Project Management: Budget
Software Project Management: BudgetMinhas Kamal
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1reddvise
 
Bugetory Control.pptx
Bugetory Control.pptxBugetory Control.pptx
Bugetory Control.pptxKPiano
 
Project and process engineering management industrial engineering management
Project and process engineering management industrial engineering managementProject and process engineering management industrial engineering management
Project and process engineering management industrial engineering managementLuis Cabrera
 
Project management basics
Project management basicsProject management basics
Project management basicsAdewale Alafia
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenetAla Ibrahim
 
Mmi entrepreneurship 6
Mmi entrepreneurship 6Mmi entrepreneurship 6
Mmi entrepreneurship 6gatecomro
 

Similar to Project Cost Management (20)

PM_Assignment3_Group1 (2).pptx
PM_Assignment3_Group1 (2).pptxPM_Assignment3_Group1 (2).pptx
PM_Assignment3_Group1 (2).pptx
 
L03 integration management
L03 integration managementL03 integration management
L03 integration management
 
Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimation
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptx
 
PM Session 4
PM Session 4PM Session 4
PM Session 4
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
PMTT Lec 6.pdf
PMTT Lec 6.pdfPMTT Lec 6.pdf
PMTT Lec 6.pdf
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
engineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptxengineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptx
 
Software Project Management: Budget
Software Project Management: BudgetSoftware Project Management: Budget
Software Project Management: Budget
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
Project cost control
Project cost controlProject cost control
Project cost control
 
Bugetory Control.pptx
Bugetory Control.pptxBugetory Control.pptx
Bugetory Control.pptx
 
Project and process engineering management industrial engineering management
Project and process engineering management industrial engineering managementProject and process engineering management industrial engineering management
Project and process engineering management industrial engineering management
 
Project management basics
Project management basicsProject management basics
Project management basics
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenet
 
Mmi entrepreneurship 6
Mmi entrepreneurship 6Mmi entrepreneurship 6
Mmi entrepreneurship 6
 

More from DejeneTsegaye6

Contract Specification and Quantity Surveying.docx
Contract Specification and Quantity Surveying.docxContract Specification and Quantity Surveying.docx
Contract Specification and Quantity Surveying.docxDejeneTsegaye6
 
Contract Specification and Quantity Surveying.docx
Contract Specification and Quantity Surveying.docxContract Specification and Quantity Surveying.docx
Contract Specification and Quantity Surveying.docxDejeneTsegaye6
 
Contract Specification and Quantity Surveying.docx
Contract Specification and Quantity Surveying.docxContract Specification and Quantity Surveying.docx
Contract Specification and Quantity Surveying.docxDejeneTsegaye6
 
CSQS ch 1, 2& 3 lec. note.pdf
CSQS ch 1, 2& 3 lec. note.pdfCSQS ch 1, 2& 3 lec. note.pdf
CSQS ch 1, 2& 3 lec. note.pdfDejeneTsegaye6
 
Planning and scheduling Techniques.ppt
Planning and scheduling  Techniques.pptPlanning and scheduling  Techniques.ppt
Planning and scheduling Techniques.pptDejeneTsegaye6
 
Chapter 5 - Human Resource Management..pptx
Chapter 5 - Human Resource Management..pptxChapter 5 - Human Resource Management..pptx
Chapter 5 - Human Resource Management..pptxDejeneTsegaye6
 

More from DejeneTsegaye6 (8)

Contract Specification and Quantity Surveying.docx
Contract Specification and Quantity Surveying.docxContract Specification and Quantity Surveying.docx
Contract Specification and Quantity Surveying.docx
 
Site Organization.ppt
Site Organization.pptSite Organization.ppt
Site Organization.ppt
 
Contract Specification and Quantity Surveying.docx
Contract Specification and Quantity Surveying.docxContract Specification and Quantity Surveying.docx
Contract Specification and Quantity Surveying.docx
 
Contract Specification and Quantity Surveying.docx
Contract Specification and Quantity Surveying.docxContract Specification and Quantity Surveying.docx
Contract Specification and Quantity Surveying.docx
 
CSQS ch 1, 2& 3 lec. note.pdf
CSQS ch 1, 2& 3 lec. note.pdfCSQS ch 1, 2& 3 lec. note.pdf
CSQS ch 1, 2& 3 lec. note.pdf
 
Planning and scheduling Techniques.ppt
Planning and scheduling  Techniques.pptPlanning and scheduling  Techniques.ppt
Planning and scheduling Techniques.ppt
 
Chapter 5 - Human Resource Management..pptx
Chapter 5 - Human Resource Management..pptxChapter 5 - Human Resource Management..pptx
Chapter 5 - Human Resource Management..pptx
 
Site Organization.ppt
Site Organization.pptSite Organization.ppt
Site Organization.ppt
 

Recently uploaded

The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptxENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptxAnaBeatriceAblay2
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerunnathinaik
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxsocialsciencegdgrohi
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 

Recently uploaded (20)

The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptxENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developer
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 

Project Cost Management

  • 1. Chapter – 4 Construction Project Costs Management
  • 2. What is Cost and Project Cost Management? Project cost management includes the processes required to ensure that the project is completed within an approved budget.
  • 3. Project Cost Management  Project Cost Management includes the processes involved in planning, estimating, budgeting, and controlling costs so that the project can be completed within the approved budget.  Cost Estimating – developing an approximation of the costs of the resources needed to complete project activities.  Cost Budgeting – aggregating the estimated costs of individual activities or work packages to establish a cost baseline.  Cost Control – influencing the factors that create cost variances and controlling changes to the project budget.
  • 4. Cost Budgeting: Processes  Cost Aggregation  Schedule activity cost estimates are aggregated by work packages in accordance with the WBS.  Reserve Analysis  Reserve analysis establishes contingency reserves, such as the management contingency reserve, that are allowances for unplanned, but potentially required, changes. Such changes may result from risks identified in the risk register.  Funding Limit Reconciliation  Large variations in the periodic expenditure of funds are usually undesirable for organizational operations. Therefore, the expenditure of funds is reconciled with the funding limits set by the customer or performing organization on the disbursement of funds for the project.
  • 5. Reserves  Reserves are included in a cost estimate to mitigate cost risk by allowing for future situations that are difficult to predict. Contingency reserves allow for future situations that may be partially planned for (sometimes called known unknowns) and are included in the project cost baseline. Management reserves allow for future situations that are unpredictable (sometimes called unknown unknowns).  Reserve Analysis Many cost estimators include reserves, also called contingency allowances, as costs in many schedule activity cost estimates. This has the inherent problem of potentially overstating the cost estimate for the schedule activity.
  • 6. Cost Budgeting:  Cost budgeting involves aggregating the estimated costs of individual schedule activities or work packages to establish a total cost baseline for measuring project performance.  What is a budget? A Plan A Limit A Schedule A Reality Check An Allocation “ Cash is a King” “A planned expression of money” (Wright .D 1994 “A practical foundation in costing” Routledge) For a defined activity shows; Income & Expenditure Total estimated costs Defined period of time
  • 7. Project Budget The Project Budget is the time-based spreadsheet that shows the project team's intent to spend the organization's resources on project activities.(The process of conversion of a resource schedule into financial schedule). It is the determination of costs associated with the defined activities
  • 8. Project Budget It provides the baseline reference for subsequent project monitoring and control (via The construction plan and the associated cash flow estimates). Or it is a guide for management. It provides management with an understanding of how funds will be utilized and expended over time for projects or operations.
  • 9.
  • 10. Project Budget Reflects the actual scope at the site and the actual quantities from construction issued drawings and a standard productivity rate. Include change orders and extra work orders in terms of changed quantities and costs. Should reflect the actual quantities placed and a standard unit rate for each work activity.
  • 11. Cost Budgeting: Outputs  Cost Baseline  The cost baseline is a time-phased budget that is used as a basis against which to measure, monitor, and control overall cost performance on the project.  Project Funding Requirements  Funding requirements, total and periodic (e.g., annual or quarterly), are derived from the cost baseline and can be established to exceed, usually by a margin, to allow for either early progress or cost overruns.  Funding usually occurs in incremental amounts that are not continuous, and, therefore, appears as a step function.
  • 12. Why Project Budgeting? Why needs for preparing a project budget : To identify the monetary requirement in time both in the forms of how much and when so as to be able to implement according to plans or contract agreements constraints To indicate organizations whether their projects are in a position to look for diversified sources of finances in order to carry them out successfully To enable organization to rethink and overhaul their operational systems so that they can meet their contractual performance targets
  • 13. Building the Planned Project Budget Establishing the WBS is the first step in defining the project and in establishing the baseline. All of the efforts used in producing the deliverable of each task can be defined in terms of cost (Labor, materials, facilities, services and overhead). Building the Planned Project Budget • The sum of all tasks within the WBS constitutes the total budget of the project.
  • 14. Developing a Baseline Budget for a Project • Once a detailed budget is developed and approved, the project manager should publish this baseline and set it as a point of comparison for actual performance progress. • The baseline budget is the tool for measuring how project changes affect our schedule and budget.
  • 15. Cost Budget Baseline This process aggregates the estimated costs of individual activities or work packages to establish and authorized cost baseline.
  • 16. Establish the Schedule Baseline Preliminary Design 1.1.1 Jan Feb Mar Apr May 1.1.1.1 Define Specifications & Req. 1.1.1.2 Develop PreliminaryDesign 1.1.1.3 Review PreliminaryDesign 1.1.1.4 Incorporate Comments 1.1.1.5 PreliminaryDesignComplete Based on the Project Scope and available resources, the work activities in the WBS are scheduled to establish the Schedule Baseline. Schedule Baseline
  • 17. Establish the Cost Baseline Preliminary Design 1.1.1 Hours Jan Feb Mar Apr May 1.1.1.1 Define Specifications & Req. 1,500 1,000 1.1.1.2 Develop PreliminaryDesign 2,000 2,000 1.1.1.3 ReviewPreliminaryDesign 500 500 1.1.1.4 Incorporate Comments 320 320 1.1.1.5 PreliminaryDesignComplete 1,000 Cost Baseline Notice in the chart the time phased hours associated with each task.
  • 18. Integrated Scope, Schedule and Cost PreliminaryDesign1.1.1 Hours Jan Feb Mar Apr May 1.1.1.1 Define Specifications & Req. 1,500 1,000 1.1.1.2 Develop PreliminaryDesign 2,000 2,000 1.1.1.3 Review PreliminaryDesign 500 500 1.1.1.4 Incorporate Comments 320 320 1.1.1.5 PreliminaryDesignComplete 1,000 Integrated Cost/Schedule Baseline As the chart shows below , each task has an associated schedule and time phased cost.
  • 19. Current negotiated contract cost Estimated cost of additional authorized unpriced work (yet to be negotiated) + = CBB Profit/Fee is not part of the Contract Budget Base (CBB) The Contract Budget Base (CBB) represents the total budget for all authorized contractual work, minus Profit/Fee. The CBB can only be modified when duly authorized changes to the contract are received. CBB is always calculated as follows: The Budgeting Process The Awarded Amount to the Builder is $219,999. This includes Profit/Fee. The Negotiated Total Cost, without Profit/Fee, for the project equals $183,852. This will be the basis for developing the Contract Budget Baseline (CBB). Again, remember that this amount is exclusive of Fee.
  • 20. 10/12/2023 20 • Developing the Project Budget 1. Develop Cost Components – Financial Vs Engineering 2. Use Project Budgeting Formats CWP Formats.xls 3. Assign and Fill in the different Costs into the project budgeting structure 4. Prepare the Project Budget against schedule Project Budgeting new-12.xls
  • 21. • Formats for Project Budgeting CWP Formats.xls – Master Schedule Format – Resources (Material, Labor, Equipment) Schedule Formats – Cost Breakdown Format – Project Budgeting (Construction) Format – Cash Flow Format – Project Budgeting (Financial) Formats
  • 22. Cash Flows Programming Financial / Budgetary / Cost Breakdown Structure • Use Cost Breakdown Structure (CWP Formats) • Use Financial / Budgetary Breakdown Structure (CWP Formats) • Determine Corresponding monthly expenses from Resources Programming • Cash flow Programming includes Cash inflows, Cash outflows and Cash flow balance (Liquidity)
  • 23.  Project cost control includes:  Influencing the factors that create changes to the cost baseline  Ensuring requested changes are agreed upon  Managing the actual changes when and as they occur  Assuring that potential cost overruns do not exceed the authorized funding periodically and in total for the project  Monitoring cost performance to detect and understand variances from the cost baseline  Recording all appropriate changes accurately against the cost baseline  Preventing incorrect, inappropriate, or unapproved changes from being included in the reported cost or resource usage  Informing appropriate stakeholders of approved changes  Acting to bring expected cost overruns within acceptable limits. Cost Control
  • 24. Cost Control Inputs: Cost Baseline Project Funding Requirements Performance Reports Work Performance Information Approved Change Requests Project Management Plan
  • 25. Cost Control: Tools and Techniques  Cost Change Control System  A cost change control system, documented in the cost management plan, defines the procedures by which the cost baseline can be changed.  Performance Measurement Analysis  Performance measurement techniques help to assess the magnitude of any variances that will invariably occur.  The earned value technique (EVT) compares the cumulative value of the budgeted cost of work performed (earned) at the original allocated budget amount to both the budgeted cost of work scheduled (planned) and to the actual cost of work performed (actual).  This technique is especially useful for cost control, resource management, and production.
  • 26. Cost Control Tools:  Cost Change Control System  A cost change control system, documented in the cost management plan, defines the procedures by which the cost baseline can be changed. It includes the forms, documentation, tracking systems, and approval levels necessary for authorizing changes.  Performance Measurement Analysis  Performance measurement techniques help to assess the magnitude of any variances that will invariably occur. The earned value technique (EVT) compares the cumulative value of the budgeted cost of work performed (earned) at the original allocated budget amount to both the budgeted cost of work scheduled (planned) and to the actual cost of work performed (actual). This technique is especially useful for cost control, resource management, and production.
  • 27. EVM: Earned Values Management  The Earned Value Technique ( EV) involves developing these key values for each schedule activity, work package, or control account:  It is a method measuring project performance by comparing the amount of work planned with actually accomplished, in order to determine if cost and schedule performance as planned. Data Element Term Acronyms Scheduled Work Budgeted Cost of Work Scheduled PV Earned Value Budgeted Cost of work performed EV Actuals Actual Cost of Work performed AC Authorized Work Budget at Completion BAC Forecasted Cost Estimate at Completion EAC Work variance Schedule Variance SV Cost Variance Cost Variance CV Completion Variance Completion Variance VAC
  • 28.  Cost variance (CV).  CV equals earned value (EV) minus actual cost (AC). The cost variance at the end of the project will be the difference between the budget at completion (BAC) and the actual amount spent. Formula: CV= EV – AC A negative value of CV would mean Cost over run  Schedule Variance: SV equals earned value (EV) minus planned (PV). Schedule variance will ultimately equal zero when the project is completed because all of the planned values will have been earned. Formula: SV = EV – PV Negative SV would mean Time over run. Variance Calculations:
  • 29. Performance Indices  Cost performance index (CPI). A CPI value less than 1.0 indicates a cost overrun of the estimates. A CPI value greater than 1.0 indicates a cost under run of the estimates. CPI = EV /AC. CPI is the most commonly used cost-efficiency indicator. Formula: CPI = EV/AC  Schedule performance index (SPI).  The SPI is used, in addition to the schedule status , to predict the completion date and is sometimes used in conjunction with the CPI to forecast the project completion estimates. SPI equals the ratio of the EV to the PV. Formula: SPI = EV/PV
  • 30. Estimate At Completion EAC: EAC = AC+ETC Estimate to Complete ETC: ETC equals the revised estimate for the work remaining.
  • 31. The earned value technique in its various forms is a commonly used method of performance measurement. It integrates project scope, cost (or resource) and schedule measures to help the project management team assess project performance.
  • 32. Cost and Schedule Forecasting Exercises: Exercise #1:Schedule Variance Example. PV = $ 42000 EV = $ 38000 AC = $ 48000 Budget at Completion BAC = $80000 SV = EV – PV = $38000 – 42000 = - $4000 SV % = SV/PV = -4000/42000 = -9.5 % Hence there is schedule overrun of 9.5% Exercise #2: Cost Variance Example. CV = EV- AC = 38000 – 48000 = - 10000 CV% = CV/EV = -10000/38000 = -26 % Schedule overrun by 26%
  • 33. # 3 Cost Performance Index ( CPI) CPI = EV/AC = 38000/48000 = 0.79  Hence $0.79 worth of work was done for every $ 1 spent. #4 Schedule Performance Index: SPI SPI = EV/PV = 38000/42000 = 0.90 $ 0.90 worth of work has been for each done for each $1.00 worth of work that was planned to be done.  #5. Estimate at Completion and Variance at Completion EAC = BAC/CPI = 80000/0.79 = $101265 VAC = BAC – EAC = 80000-101265 = - $ 21265. The project will exceed the planned budget by $21265
  • 34. Problems: #1: BAC = 40 K EV = 20 K PV = 28 K AC = 26 K Determine: % of work scheduled % of budget spent Cost Variance CV Scheduled Variance SV
  • 35.  Case 1:  PV = 1600  EV = 1600  AC = 1600  Ideal Case where every thing goes as per plan.  Case2:  PV= 1900  EV= 1500  ACP= 1700  400 worth of work is behind schedule  SV = EV- PV = 1500-1900= -400  SV%= ( SV/PV)x100 = -21%  CV = EV – AC = 1500 – 1700= -200 Cost overrun by 200  CV% = (CV/EV)x100 = -13%  SPI = EV/PV = $0.79  CPI= EV/AC = $0.88