2011 Transportation
Oversight Activities
in North America
Transnuclear Inc.
Clark Vanderniet
Director of Regulatory Affairs
Transnuclear Inc.
Transportation Oversight
In 2011 AREVA Implemented Two Significant Endeavors Related
to the Non-spent Fuel Transportation Arena
 The creation of an AREVA North American Transportation Oversight organization and
 The transfer of ownership of type-B transportation packages from AREVA Fuels to
Transnuclear Inc.
Slide #2
Transportation Oversight
Creation of the AREVA North American Transportation Oversight
Organization
 Transnuclear Inc. was assigned to institute a North America Transportation Oversight
program similar to the program used by AREVA in Europe.
 Transnuclear Inc. dedicated resources to the establishment of the North American
Transportation Oversight organization.
 The AREVA North American Transportation Oversight organization was charged with
performing audits and inspections of all AREVA transportation suppliers in North
America.
The Transfer of Ownership of Type-B Transportation Packages from
AREVA Fuels to Transnuclear Inc.
 The Transition Process moved from the Due Diligence reviews into the Acceptance
Determination reviews.
 The Transition Process encompassed the transfer of over 1400 packages
 Additional resources were dedicated to the Transition process to facilitate the
completion of the reviews in 2012.
Transnuclear Inc.
Slide #3
Transportation Oversight
Full Implementation of the AREVA North American
Transportation Oversight Organization
 AREVA North American Transportation Oversight transitioned from a Transnuclear Inc.
organization into an AREVA Corporate organization.
 AREVA North American Transportation Oversight personnel completed training for
Hazardous Materials, NRC/DOT shipping regulations, and Inspection and Audit
performance.
 AREVA North American Transportation Oversight performed audits on most of the over-
the-road, freight forwarding and material handling suppliers servicing AREVA shipments
in North America.
 36 independent inspections were performed by AREVA North American Transportation
Oversight inspectors on AREVA shipments in North America.
 AREVA North American Transportation Oversight responded to several
events/situations, considered off-normal and preformed assessments of the problems
which were shared with all AREVA entities in North America.
Transnuclear Inc.
Slide #4
Transportation Oversight
The Transnuclear Inc. Packaging Transition Process.
 Visual Verification were performed on all package to verify that containers were in an
acceptable condition to be included in the Transition Process.
 All available documentation for the containers were collected, reviewed, cataloged,
scanned and digitized as necessary to support licensing and regulatory review of the
packages
 Package type that are in the Transition Process included:
MAP-12 RAJ-II ANF-250
UX-30 SP-1, 2, &3, and the OP-TU
Transnuclear Inc.
Slide #5
Transportation Oversight
Results of AREVA North American Transportation Oversight
Organization Activities
 AREVA North American Transportation Oversight audits identified a large gradient in the
depth of Quality Assurance Programs at the various AREVA suppliers.
 AREVA North American Transportation Oversight inspections identified problems in
approximately 50% of the AREVA shipments.
 AREVA North American Transportation Oversight response to off-normal events
included collision of a fuel shipment with bridgework, UX-30 locking pin discrepancies,
and container repair issues.
Transnuclear Inc.
Slide #6
Transportation Oversight
Results of Transnuclear Inc. Packaging Transition Process.
 Visual Verification identified concerns with the proper marking of packaging with tri-foil
symbols, issues with the storage and handling of packaging, inconsistent use of various
models of locking pins, and final fabrication inspection issues with new packages.
 Documentation reviews discovered missing documentation for packaging that was in
use, inconsistencies in the implementation of inspection and maintenance practices as
specified in the Safety Analysis Report requirements, and inadequate controls for the
storage and handling of records.
Transnuclear Inc.
Slide #7
Transportation Oversight
Issues Needing Clarification and Resolution by the AREVA Oversight
Organization.
 Consistency and reporting threshold for 10 CFR 71.95 reports.
 Disposition or continued use of packaging that has an inconsistent documentation set
as required by 10 CFR 71.
 Responsibility of packaging owner with regard to proper handling and reporting of
issues to Certificate Holder or Licensee.
 Proper handling and closure of legacy issues with packaging.
 Dual Certification of packaging for different users.
Transnuclear Inc.
Slide #8
Transportation Oversight
Questions?
Transnuclear Inc.
Slide #9

More Related Content

What's hot

What's hot (8)

Christopher A Pruett Resume
Christopher A Pruett ResumeChristopher A Pruett Resume
Christopher A Pruett Resume
 
PCAPP Laboratory February 26, 2014
PCAPP Laboratory February 26, 2014PCAPP Laboratory February 26, 2014
PCAPP Laboratory February 26, 2014
 
Brian McDonald CV
Brian McDonald CVBrian McDonald CV
Brian McDonald CV
 
Dynamic Positions, LLC-widescreen
Dynamic Positions, LLC-widescreenDynamic Positions, LLC-widescreen
Dynamic Positions, LLC-widescreen
 
Ellis, Melissa, Tellevate, NESHAP Regulations Update, 2015 Midwest Environmen...
Ellis, Melissa, Tellevate, NESHAP Regulations Update, 2015 Midwest Environmen...Ellis, Melissa, Tellevate, NESHAP Regulations Update, 2015 Midwest Environmen...
Ellis, Melissa, Tellevate, NESHAP Regulations Update, 2015 Midwest Environmen...
 
Sales-Service Manager resume
Sales-Service Manager resumeSales-Service Manager resume
Sales-Service Manager resume
 
Cruz Leal Resume
Cruz Leal ResumeCruz Leal Resume
Cruz Leal Resume
 
Joshua J
Joshua JJoshua J
Joshua J
 

Similar to 2011 Transportation Oversight Presentatioin to NRC

Similar to 2011 Transportation Oversight Presentatioin to NRC (11)

PerformanceAppraisal 2015
PerformanceAppraisal 2015PerformanceAppraisal 2015
PerformanceAppraisal 2015
 
Lockheed Martin Production Supervisor
Lockheed Martin Production SupervisorLockheed Martin Production Supervisor
Lockheed Martin Production Supervisor
 
Clint Calip Jr.
Clint Calip Jr.Clint Calip Jr.
Clint Calip Jr.
 
Ovid newsletter may 2014
Ovid newsletter  may 2014Ovid newsletter  may 2014
Ovid newsletter may 2014
 
Vetting.ppt
Vetting.pptVetting.ppt
Vetting.ppt
 
SMS Records & Workflow Foundation
SMS Records & Workflow FoundationSMS Records & Workflow Foundation
SMS Records & Workflow Foundation
 
OFRPReport
OFRPReportOFRPReport
OFRPReport
 
Resume-Harvey_Polk-August 2015
Resume-Harvey_Polk-August 2015Resume-Harvey_Polk-August 2015
Resume-Harvey_Polk-August 2015
 
Chris Helbig Resume
Chris Helbig ResumeChris Helbig Resume
Chris Helbig Resume
 
AWWA G481-14
AWWA G481-14AWWA G481-14
AWWA G481-14
 
ORourke Resume
ORourke ResumeORourke Resume
ORourke Resume
 

2011 Transportation Oversight Presentatioin to NRC

  • 1. 2011 Transportation Oversight Activities in North America Transnuclear Inc. Clark Vanderniet Director of Regulatory Affairs Transnuclear Inc.
  • 2. Transportation Oversight In 2011 AREVA Implemented Two Significant Endeavors Related to the Non-spent Fuel Transportation Arena  The creation of an AREVA North American Transportation Oversight organization and  The transfer of ownership of type-B transportation packages from AREVA Fuels to Transnuclear Inc. Slide #2
  • 3. Transportation Oversight Creation of the AREVA North American Transportation Oversight Organization  Transnuclear Inc. was assigned to institute a North America Transportation Oversight program similar to the program used by AREVA in Europe.  Transnuclear Inc. dedicated resources to the establishment of the North American Transportation Oversight organization.  The AREVA North American Transportation Oversight organization was charged with performing audits and inspections of all AREVA transportation suppliers in North America. The Transfer of Ownership of Type-B Transportation Packages from AREVA Fuels to Transnuclear Inc.  The Transition Process moved from the Due Diligence reviews into the Acceptance Determination reviews.  The Transition Process encompassed the transfer of over 1400 packages  Additional resources were dedicated to the Transition process to facilitate the completion of the reviews in 2012. Transnuclear Inc. Slide #3
  • 4. Transportation Oversight Full Implementation of the AREVA North American Transportation Oversight Organization  AREVA North American Transportation Oversight transitioned from a Transnuclear Inc. organization into an AREVA Corporate organization.  AREVA North American Transportation Oversight personnel completed training for Hazardous Materials, NRC/DOT shipping regulations, and Inspection and Audit performance.  AREVA North American Transportation Oversight performed audits on most of the over- the-road, freight forwarding and material handling suppliers servicing AREVA shipments in North America.  36 independent inspections were performed by AREVA North American Transportation Oversight inspectors on AREVA shipments in North America.  AREVA North American Transportation Oversight responded to several events/situations, considered off-normal and preformed assessments of the problems which were shared with all AREVA entities in North America. Transnuclear Inc. Slide #4
  • 5. Transportation Oversight The Transnuclear Inc. Packaging Transition Process.  Visual Verification were performed on all package to verify that containers were in an acceptable condition to be included in the Transition Process.  All available documentation for the containers were collected, reviewed, cataloged, scanned and digitized as necessary to support licensing and regulatory review of the packages  Package type that are in the Transition Process included: MAP-12 RAJ-II ANF-250 UX-30 SP-1, 2, &3, and the OP-TU Transnuclear Inc. Slide #5
  • 6. Transportation Oversight Results of AREVA North American Transportation Oversight Organization Activities  AREVA North American Transportation Oversight audits identified a large gradient in the depth of Quality Assurance Programs at the various AREVA suppliers.  AREVA North American Transportation Oversight inspections identified problems in approximately 50% of the AREVA shipments.  AREVA North American Transportation Oversight response to off-normal events included collision of a fuel shipment with bridgework, UX-30 locking pin discrepancies, and container repair issues. Transnuclear Inc. Slide #6
  • 7. Transportation Oversight Results of Transnuclear Inc. Packaging Transition Process.  Visual Verification identified concerns with the proper marking of packaging with tri-foil symbols, issues with the storage and handling of packaging, inconsistent use of various models of locking pins, and final fabrication inspection issues with new packages.  Documentation reviews discovered missing documentation for packaging that was in use, inconsistencies in the implementation of inspection and maintenance practices as specified in the Safety Analysis Report requirements, and inadequate controls for the storage and handling of records. Transnuclear Inc. Slide #7
  • 8. Transportation Oversight Issues Needing Clarification and Resolution by the AREVA Oversight Organization.  Consistency and reporting threshold for 10 CFR 71.95 reports.  Disposition or continued use of packaging that has an inconsistent documentation set as required by 10 CFR 71.  Responsibility of packaging owner with regard to proper handling and reporting of issues to Certificate Holder or Licensee.  Proper handling and closure of legacy issues with packaging.  Dual Certification of packaging for different users. Transnuclear Inc. Slide #8