SlideShare a Scribd company logo
1 of 10
Download to read offline
18 September 2007 – The Structural Engineer|39
paper: ahmadi-kashani et al
Fig 1. Egnatia motorway and location of Votonosi Bridge / Fig 2. Elevation and plan / Fig 3. Cross section of the deck and
piers a) Deck over pier with lane widths b) Deck at mid-span c) Piers M1N, M1S and M2N d) Pier M2S
Synopsis
The recently constructed Votonosi Bridge situated in an area
of outstanding natural beauty and within a seismically active
zone, forms part of the Egnatia motorway project in northern
Greece. With a main span of 230m, this bridge has the
longest span for balanced cantilever bridges constructed in
Greece to date. This paper provides general information
regarding the bridge and outlines its construction.
Introduction
The Egnatia motorway in northern Greece is one of the prior-
ity projects in the Trans-European Network for Transport
which will provide Europe with a fast and safe access route to
Turkey and the Middle East1
. It will also provide links to the
neighbouring Balkan countries and to the rest of mainland
Greece.Its main axis stretches from the port of Igoumenitsa on
the Ionian Sea to the town of Kipi at the Greek-Turkish border
(Fig 1).This axis is 680km long and consists of a dual two-lane
motorway with hard shoulders and includes more than 600
bridges with a total length of over 40km(ref.2). The design,
construction, maintenance, operation and exploitation of the
motorway is being managed by ‘Egnatia Odos AE’ (EOAE), a
company wholly owned by the Greek State which was estab-
lished in 1995 by the Greek Ministry of Environment,Planning
and Public Works. Kellogg Brown and Root (KBR) has acted as
the Project Manager since 1996, and Thales-Omek has been
involved in the construction management for its western region
since 1997.
In north-west Greece, the Egnatia motorway crosses moun-
tainous terrain demanding the construction of many major
tunnels and bridges. Situated in this region,Votonosi Bridge is
located near the village of Votonosi, between Antochory and
Votonosi Tunnels, and crosses a 500m wide river valley with a
depth of over 100m (Fig 1). This location demanded a bridge
with minimum number of piers to be cost effective.To meet this
and all other project requirements, a three-span balanced
cantilever bridge was selected for detail design and construc-
tion. With a number of in situ balanced cantilever bridges
already successfully completed by local contractors,this form of
construction is well established in Greece. However, with a
main span of 230m,Votonosi Bridge by far exceeded the longest
span previously constructed by this method (140m), and its
construction was therefore a challenge for the construction
industry.
This paper provides general information regarding Votonosi
Bridge, and outlines the design process and its construction.
General description
Votonosi Bridge consists of two independent 13.5m wide decks
located at 27.5m centres with each deck carrying two 3.75m
wide carriageways and a 2.5m wide hard shoulder over
Metsovitikos River and a local road.The north and south decks
are 478m and 490m long respectively,consisting of three spans
of 127m–224m–127m and 130m–230m–130m (Fig 2). The
superstructure has an upward longitudinal slope of approxi-
mately 5% eastwards. A 90m length of both decks at the east-
end is on a transition curve joining a 1000m radius circular
curve which results in the highway super-elevation increasing
from 2.5% to 5%.
The site investigation boreholes indicated that the ground
consists of thick/medium layers of sandstone inter-bedded with
thin layers of siltstone. The piers are founded on circular 10m
diameter rock sockets with depths of up to 25m resisting up to
140MN vertical load, 11MN shear force, and 300MN-m fixity
moment.The piers have heights varying from 45m to 53m and
comprise a 5m by 7m box section, except for the tallest pier
which has a 6m by 7m box section (Fig 3).
The relatively tall piers are sufficiently flexible to be
The construction of Votonosi Bridge, Greece
K. Ahmadi-
Kashani
PhD, CEng,
MIStructE, MIEI
Technical Advisor, KBR,
UK
I. Rentzeperis
PhD, TEE
General Manager,
EOAE, Greece
C. Brun
Construction Manager,
Thales-Omek, France
P. Papanikolas
PhD, TEE
Technical Manager,
EOAE, Greece
V. Tsebas
TEE
Site Manager, Mechaniki
AE, Greece
C. Miltsakakis
TEE
Site Engineer, Mechaniki
AE, Greece
Received: 10/06
Modified: 02/07
Accepted: 04/07
Keywords: Votonosi
Bridge, Greece, Road
bridges, Balanced
cantilever construction,
Egnatia Motorway,
Greece, Seismic design,
Foundations, Concrete
© K. Ahmadi-Kashani,
I. Rentzeperis, C. Brun,
P. Papanikolas, V. Tsebas,
& C. Miltsakakis
Your comments on this
paper are welcome and
will be published online
as Correspondence.
1
2
3a 3c
3b
3d
IOANNINA
N THESSALONIKI
BULGARIA
GREECE
Votonosi Bridge
NORTH DECK
SOUTH DECK
ANTHOCHORI
TUNNEL VOTONOSI
TUNNEL
3.00
130.00m
130.00m
126.60m
230.00m
223.90m
1.25 0.5 2.50 3.753.75 0.95 0.8
3.00
5.50
7.00
7.00
13.50
0.750.75
7.00
5.00
6.00
7.00
0.6
0.70
AON M1N M2N A3N
A3N
A3S
M2N
M2S
M1N
M1S
AON
AOS
126.60m
SE18 Votonosi bridge :Layout 1 12/9/07 16:05 Page 39
40|The Structural Engineer – 18 September 2007
Fig 4. Anti-uplift sliding bearing / Fig 5. Expansion joint detail / Fig 6. Bottom slab tendon anchorage
4 5
6
monolithically connected to the superstructure,and to form a central frame
to resist longitudinal loading and environmental effects including seismic
forces. At the abutments the deck is free to rotate and move longitudinally
via sliding pot bearings. Potential deck uplift during seismic events is
restricted by anti-uplift devices connected to the bearings (Fig 4). A guided
bearing at each abutment restricts the movement of the deck in the trans-
verse direction. Two elastomeric bearings are provided with sufficient gap
between the deck-ends and abutment cheek-walls to act as bumpers during
seismic events with intensities greater than the design earthquake. The
expansion joints allow a total bridge movement of up to 400mm at each end
(Fig 5).
Each superstructure consists of a box girder with a constant width of 7m
and a depth varying from 13.5m at the piers to 5.5m at mid-span. The web
thickness steps down from the piers towards mid-span taking values of
0.60m, 0.50m and 0.45m over a transition length of 0.75m.The top slab has
a thickness of 0.3m increasing to 0.5m at the edges, and the thickness of the
bottom slab varies from 1.3m at the piers to 0.3m at mid-span. The thick-
ness of the side cantilever varies from 0.65m at the root to 0.25m at the tip
(Fig 3).
Each pair of in situ concrete balanced cantilevers is connected to a 3m long
connecting in situ segment at mid-span: with approximately 16m long deck-
ends supported from the ground during construction. The length of the
cantilevers varies from 107m to 110m,each consisting of 26 in situ segments.
In order to limit the weight of the segments, their lengths vary from 3m to
4.5m for the first 13 segments, thereafter remaining constant at 5m. The
cantilever prestressing consists of 102 internal tendons made up of 19,
15.7mm diameter superstrand (19T15) arranged in two rows over the piers
with a tendon length of up to 227m.The tendons run through the upper slab
and are anchored at the segments’ end face within the slab thickening
without the need for blisters. Internal tendons are also placed in the bottom
slab to provide the continuity prestressing which comprise 32, 19T15 in the
main span and 12, 19T15 in the side spans. The continuity tendons are
anchored in 2m long blisters constructed at the edges of the bottom slab
(Fig 6).
Abutment galleries are provided to access the expansion joints and the
interior of the box girders for inspection and maintenance. Maintenance or
damage inspection of the inside of the hollow piers is by means of an access
hole at the pier top and then via ladders placed between permanent platforms
that are located at 5m intervals inside the piers. Inspection of the bearings
can be carried out from a platform situated in front of the abutments. The
provision of jacking points allows the replacement of the bearings.
Parapets consist of standard metal posts and railings in accordance with
the Greek regulations.The main drainage pipes are made of fibre glass and
run on the outer face of each box girder with connections to the deck inlets
via transverse drainage pipes under the deck cantilevers. Motorway service
ducts are located under the outer footpaths and provision of ventilation and
drainage holes are made near the web tops and the bottom slab,respectively.
A 1.0m by 1.5m opening in the bottom slab near abutment A0 is provided
for access in cases of emergency.
The relatively high (12m) west abutments dictate that the backfill spills
through either abutment between its two tapering legs founded on a spread
footing. The east abutments are of the bank seat type with spread footing
foundations located at two different levels due to the steep slope of the rock
face.
Design
The design of Votonosi Bridge was carried out in accordance with the
performance requirements set out in OSMEO3
, the design guidelines devel-
oped by EOAE. The loading and static design was based on German DIN
Standards including ZTVK 964
supplement for bridge design.To consider the
effect of deck plan curvature,a three dimensional computer model was devel-
oped with measures to include soil structure interaction. The time depend-
ent characteristic of the concrete was modelled in the analysis using an
estimated construction programme.
The analysis and design covered all stages of construction and was carried
out using SOFISTIK computer program which automated part of the design
process. A number of 3D finite element models were additionally developed
and analysed to determine the intensity of stress concentration in the rock
sockets,anchorage zones,and hammerheads.Camber analyses were carried
out during the balanced cantilever construction to determine the setting out
geometry of the segments using the time dependent properties of concrete
and allowing for site temperature and humidity at the time of casting.
Votonosi Bridge is situated within Greek seismic zone II with peak ground
acceleration (PGA) of 0.16g, upgraded by an importance factor of 1.35
. The
seismic design of the bridge followed the Greek codes of practice EAK6
and
E39/997
. Its seismic integrity during construction was assessed for a PGA
value of 0.104g.To allow for structural redundancy the‘behaviour factor’ was
assumed as 3.0 for the completed bridge, thus allowing formation of plastic
hinges at the top and bottom of the piers during major seismic events. The
behaviour factor was taken as 1.0 during the construction to prevent struc-
tural damage before commencement of service.
During the construction, combinations of the following load cases were
considered in the design:
• self weight of the form-travellers
paper: ahmadi-kashani et al
SE18 Votonosi bridge :Layout 1 12/9/07 16:05 Page 40
18 September 2007 – The Structural Engineer|41
8
9
7
Fig 7. Construction programme / Fig 8. Mobile crane for construction of rock sockets / Fig 9. Rock socket excavation
• self weight of the newly cast segments
• prestressing forces
• an accidental drop of the newly cast segments
• construction loading
• temperature difference between the top and bottom of the deck
• variation in the ambient temperature
• differential settlement between adjacent substructures
• wind loading with differential pressure
• seismic loading
For the ‘in service’ design, combinations of the following load cases were
considered:
• dead load and superimposed load
• prestressing forces
• SLW30/60 traffic loading in accordance with DIN 1072
• temperature difference between top and bottom of the deck
• variation in the ambient temperature
• differential settlement between adjacent substructures
• wind loading
• seismic loading
The following classes of material were specified in the design:
• concrete (cube strength):
superstructure 45MPa
piers 45MPa
rock sockets (capping zone) 35MPa
rock socket (shaft) 25MPa
abutments 35MPa
approach slab 35MPa
• steel reinforcement BSt500 (St IV)
• prestressing tendons 1550/1750MPa
The design and constructability of the bridge was reviewed by EOAE,and
a category III check was carried out by an independent consultant. The
details of the analysis and the design are given in Ref (8).
Construction
General
The construction was carried out in accordance with TSY9
, a materials and
workmanship specification produced by EOAE based on national and inter-
national specifications. The works started in January 2000 and were
completed in December 2005 with the outline construction program shown
in Fig 7. The bridge is situated in a mountainous region and the adverse
winter weather dictated a stoppage of the works for approximately 2 months
of the year.
The site was served by two tower cranes placed between piers M1 and M2
with up to 100kN lifting capacity and 60m reach. Other major equipment
included a 300kN capacity mobile overhead gantry, two 125kVA generators,
a 100m3
/hr loader, two compressors with 850cfm and 335cfm capacities, six
8m3
capacity concrete mixer trucks, four concrete 101bar capacity pumps
with 47m3
/h output, a 10m3
truck, a 12hp gunite pump, a 8hp grouting
pump, a mini-excavator, and a drilling machine.
Due to the relatively long distance between the site and quarries, aggre-
gates were extracted from the nearby Metsovitikos River, crushed, screened
and washed for concrete production in a 50m3
/hr batching plant situated on
site. The batching plant for the construction of the nearby Megalorema
Viaduct2
,situated within 2km of the site,was also used in cases of emergency.
The details of the construction of the foundations, piers and superstruc-
ture of the bridge are described as follows.
Foundations
Access roads to the foundations were designed and constructed with the
emphasis on minimising damage to the environment.31 trial boreholes were
drilled at the pier and abutment locations.This was followed by levelling the
ground to install the mobile overhead gantry for the construction of the rock
sockets.Due to the level difference between the south and north rock sockets
at M2, an extended platform was built using a concrete enclosure filled with
compacted soil to allow the operation of the gantry over both sockets (Fig 8).
The excavation for the rock sockets was carried out in depth intervals of 3m
with drilling at the perimeter followed by sequential firing of explosive
charges placed in a helical formation. With the available drilling machines
the acceptable tolerance for vertical drilling could not be achieved for depths
of more than 15m. The drilling operation was, therefore, carried out in two
stages: a larger diameter than the design diameter was first formed for the
upper half of the socket,and the drilling machine was subsequently lowered
and placed on the base of the upper half in order to drill for the design diam-
eter lower half (Fig 9).
The excavated face was regularly inspected by a geologist to verify the geot-
echnical parameters assumed in the design, and to optimize the measures
required to support the exposed face.The rock face was stabilised using rock
anchors, steel beams, and corrugated metal sheets, followed by the installa-
tion of mesh reinforcement and shotcreting. Concreting the sockets was
carried out in 5 or 6 lifts with the depth of each lift varying from 3m to 5m
using up to 600m3
of concrete for each lift. Concrete temperature was
paper: ahmadi-kashani et al
SE18 Votonosi bridge :Layout 1 12/9/07 16:05 Page 41
42|The Structural Engineer – 18 September 2007
paper: ahmadi-kashani et al
controlled by means of early morning concerting in the summer months,and
using Portland cement type I.These measures reduced the risk of micro-crack
formation in the concrete due to excessive heat of hydration.
The top 3m of the rock socket consisted of a heavily reinforced ‘capping
zone’. The lower 4 or 5 ‘shaft’ lifts contained mainly vertical reinforcement
placed at the perimeter of the socket.Reinforcement installation and concret-
ing was carried out with the aid of the overhead gantry.A sump was provided
on the top surface of each segment to remove any excess water.The construc-
tion of each rock socket took between 3 and 4 months depending on the
quality and type of rock mass encountered.The maximum settlement of the
sockets after completion of the bridge was recorded as 4mm.
Piers
The piers were constructed using climbing formwork in 2.8m segments.The
reinforcement for the piers mainly comprised 7m prefabricated cages typi-
cally formed with six longitudinal reinforcement bars connected by stirrups.
The formwork and associated working platforms were fixed onto sockets
embedded on the previously cast segment. The formwork panels were held
in the upright position and were fixed in place with through ties.
Construction of a typical pier segment normally took 4 days to complete: 1.5
days to place the reinforcement, 1.5 days to install the formwork and 1 day
for concrete pouring and curing.
To avoid lapping reinforcement bars in the plastic hinge zones at the top
and bottom of the piers, the reinforcement cages in this region were fabri-
cated with14m/16m long rebars covering three segments, and were held
upright by steel framework that included three levels of working platforms
(Fig 10). Additional horizontal reinforcement links were placed in this zone
to confine both the concrete and vertical reinforcement,and to allow the safe
formation of plastic hinges during a major seismic event.In order for the piers
of each superstructure to resist similar seismic forces,the stiffness of the piers
had to be comparable;this meant that the M1 piers had to be extended down
into the ground (Fig 2). Concrete collars, 13m diameter and 10m deep, were
constructed around these piers to allow the inspection and repair of the
plastic hinge zones after a major earthquake (Fig 11).
Pier segments lower than 25m above ground level were concreted using
lorry mounted pumps. For higher levels, concrete was pumped through a
150mm diameter steel pipe fixed to the pier by means of a pump with an 80m
head capacity. Suitable aggregate grading and admixtures were used to
provide the required slump and consistency for the pumped concrete.
Temporary stairs and platforms were installed and used during the pier
construction. The construction of each pier took approximately 4 months to
complete.
The galvanised steel maintenance inspection ladders and platforms were
installed inside the piers prior to the construction of the hammerheads. Due
to the height of the piers the formwork for the hammerhead was supported
from the pier tops.Each hammerhead,13.5m high with two diaphragms,was
constructed in five phases using a proprietary formwork system (Fig 12).
Steel beams fixed to the inside walls of the piers supported the 2.5m thick
bottom slab.The construction of the hammerhead required special formwork
to include the various access openings to the interior of the piers and box
girders. Once the hammerhead was constructed, a temporary lift was
installed for each pair of M1 and M2 piers which together with a high level
truss spanning between the decks allowed access to both decks.The construc-
tion of each hammerhead took approximately 3 months to complete.
Superstructure
The superstructures were constructed using a proprietary form-traveller
weighing 800kN with a capacity to support a segment weight of 2500kN,and
with its centre of gravity up to 2.5m beyond the end of the segment. Each
traveller consisted of two main ‘A’ frames anchored to the deck and carried
a transverse truss from which the formwork for the webs and the upper and
lower slab soffits were suspended using high strength hangers. The move-
ment of each traveller was provided by two hydraulic rams.The top and sides
of the travellers were enclosed with a waterproofing tarpaulin to protect the
operatives from adverse weather. To meet the completion date, four pairs of
travellers were used during the construction (Fig 13).
The 6.6m length of the hammerheads was sufficient to place a pair of trav-
ellers braced to each other (Fig 14). Once the first pair of segments had been
cast symmetrically on the opposite sides of the piers, the bracing was
removed.The construction cycle for the next pair of segments consisted of the
following stages:
• moving the traveller to a new position
• adjusting the formwork levels for the new segments
• installing the reinforcement, prestressing ducts and tendons
• concreting the new segments
• prestressing the new segments
Each pair of segments was cast alternately in two stages:
1) The bottom slab and part of the webs, 2) The remainder of the webs and
the top slab. This sequence helped to reduce the unbalanced cantilever
loading, and resulted in better scheduling for the teams of labour involved.
Concreting each stage took about 3h and required up to 35m3
of concrete.The
depth of the upper section was kept constant resulting in a similar rein-
forcement arrangement. A number of surveys confirmed that the traveller
was sufficiently stiff to prevent separation of the first stage from the last
segment when the second stage was poured and added its weight to the trav-
eller. Casting the upper section at least 2 days after concreting the lower
section also helped in preventing crack formation at the construction joint
by ensuring sufficient bonding between the concrete and reinforcement.
The transportation of the reinforcement beyond the reach of the tower
crane was made possible by means of a light wagon driven by an electric
tractor on rails. A specialist team were responsible for placing the 100mm
internal diameter galvanized prestressing ducts, threading the tendons,
placing spiral reinforcement, stressing the tendons and grouting the ducts.
A grout test on a prestressed beam was successfully carried out prior to the
grouting the ducts. A steel template was used at the segment face to facili-
tate accurate placement of the tendons. The strands were delivered on coil
drums and were unrolled and pushed through the ducts by means of a
strand pushing machine.The minimum clear distance of 100mm between the
prestressing tendons specified in the design allowed for easy pouring and
compaction of the concrete and for placement of the traveller hangers.
Temporary 1.0m by 1.5m openings were provided in the top slab to allow the
equipment for prestressing the bottom slab tendons to be lowered into posi-
tion.
Following the installation of reinforcement and tendons,the internal form-
work for the box girder was placed in position, and preparation was made
for the concreting phase. For casting segments away from the pier, an addi-
tional concrete pump was installed on the hammerhead to facilitate concrete
delivery. The external formwork was backed with 50mm thick polystyrene
panels to insulate the concrete from the ambient temperature ranging from
–15°C to 40°C during the construction period. Installation of fan heaters
inside the box girder and radiant heaters on the deck during the winter
months provided acceptable conditions for concreting.In the summer months,
concreting was carried out early in the morning to avoid micro-cracking due
to excessive heat of hydration. Concrete samples were taken during casting
to determine its properties such as creep, shrinkage and modulus of elastic-
ity, which were then used in the camber analysis.
The average 28 days concrete strength achieved was 65MPa. The
prestressing was generally applied 3 days after concreting when the concrete
had attained a minimum strength of 40MPa. The tendons were tensioned
symmetrically from both ends in sequence about the centreline of the box
girder using a 3500kN capacity prestressing jack. The measured tendon
extensions were within 5% of their theoretical values.
The geometry of the balanced cantilevers was monitored by surveying the
coordinates of three steel plate markers placed at the tip of each segment.
One marker was installed at the centreline of the deck and the other two
located 5.5m either side of the centreline. The survey was carried out early
in the morning to avoid differential temperature effects.Measurements were
made on all the segments after three events: a) casting a pair of new
segments, b) prestressing the new segments and c) moving the travellers to
a new position. The results were compared with the theoretical values, and
after allowing for adjustments to comply with the design,a set of coordinates
were calculated for setting out the formwork for the next segment. The
extension of hangers transferring the weight of a segment to the traveller
was measured as 11mm, and was taken into account when setting out the
SE18 Votonosi bridge :Layout 1 12/9/07 16:05 Page 42
18 September 2007 – The Structural Engineer|43
paper: ahmadi-kashani et al
Fig 10. Pier reinforcement in plastic hinge zone / Fig 11. Collar for inspection of plastic hinge zone / Fig 12. Hammerhead construction
Fig 13. Utilisation of four pairs of form-travellers / Fig 14. Braced form-travellers / Fig 15. Support system for the deck-end at abutment A0
before backfilling / Fig 16. Restraining the tip of balanced cantilever adjacent to abutment A0
10
11
12
14
15
13
16
SE18 Votonosi bridge :Layout 1 12/9/07 16:06 Page 43
44|The Structural Engineer – 18 September 2007
paper: ahmadi-kashani et al
Fig 17. Support system for the deck-end at abutment A3/ Fig 18. Construction of the deck-end at abutment A3
Fig 19. Construction of the mid-span connecting segment/ Fig 20. Construction of central span connecting segment a) Elevation b) Cross-
section/ Fig 21. Construction of the edge beams / Fig 22. Theoretical and as built road levels / Fig 23. Votonosi Bridge nearing completion
17
19
18
21
23 22
20a
20b
SE18 Votonosi bridge :Layout 1 12/9/07 16:06 Page 44
18 September 2007 – The Structural Engineer|45
paper: ahmadi-kashani et al
formwork for the bottom slab.The construction of a new pair of segments was
planned on a 10 day cycle which was generally achieved after the initial
learning curve. The construction of each pair of balanced cantilever decks
took approximately 12 months to complete.After completion of the balanced
cantilever over pier M1,the travellers were removed and the deck levels were
surveyed. Subsequently, the construction of the 16m long deck-end next to
abutment A0 commenced.The formwork for the deck-end was supported on
a proprietary truss system which in turn was supported from the ground at
the two edges (Fig 15). The lateral and vertical movement of the cantilever
tip was prevented during concreting by means of a braced frame and by
anchoring the tip of the cantilever to the ground (Fig 16). The construction
of the deck-end consisted of the following sequence:
• concreting the bottom slab and part of the webs (stage 1 concreting)
• stressing a third of bottom slab tendons
• concreting the remainder of the webs and the top slab (stage 2 concreting)
• curing the concrete
• removal of the temporary truss
• de-tensioning and stressing the bottom slab tendons
Partial stressing of the bottom slab enabled the lower section of the deck-
end to carry the weight of stage 2 concreting and allowed the removal of the
temporary truss.
The 16m long deck-end next to abutmentA3 was subsequently constructed
by means of two pairs of right angle steel frames, pinned at the top and
bottom, with horizontal extension arms anchored to the cantilever tip (Figs
17 and 18). Before construction, the travellers were moved to pier M2 and a
deck level survey was carried out. The formwork was then placed on scaf-
folding supported on the steel frames. The construction of the A3 deck-end
was carried out in a sequence similar to that described for the A0 deck-end.
The connection of the cantilever tip to the deck required a careful concret-
ing procedure,including the use of a counterweight at mid-span and regular
monitoring.To minimise the effect of differential temperature,concreting was
carried out at night.The lower deck section constructed in the stage 1 concret-
ing was designed with sufficient reinforcement to span between the bearings
and the cantilever end, allowing for the removal of scaffolding after comple-
tion of the stage 1 concreting.
Prior to constructing the central connecting segment, a level survey was
carried out and the maximum level difference between the opposite cantilever
tips was found to be 16mm and 20mm for the south and north decks respec-
tively,bothwithintherequiredtolerance.Theexternalformworkfromthetrav-
eller was anchored to the segments each side of the gap to provide the
shuttering for the connecting segment.To correct the level difference between
the cable ducts in the bottom slab and to prevent relative vertical movement
of the cantilever tips,the two pairs of 600mm deep base beams of the travellers
were placed over the gap and anchored down to the deck (Fig 19).
Two horizontal steel I-beams were installed in the connecting segment
gaps bearing onto steel angles cast into the cantilever ends, and the gap
between the beams and the cantilevers tips were grouted.In order to prevent
relative horizontal movement between the cantilevers during concreting a
number of the bottom tendons were partially stressed (Fig 20). The bottom
slab and part of the webs were subsequently concreted and the steel beams
were removed. The remaining part of the webs and the top slab were
concreted followed by de-stressing the partially stressed tendons and subse-
quent stressing all the bottom slab tendons.As before,concreting was carried
out at night.
The construction of the deck-ends and the connecting segments were
carried out in the calm summer days in order to reduce the risk of any vibra-
tion damage during concreting. It is interesting to note that before casting
the connecting segments the cantilever tips deflected upward by 150mm due
to the sun shining on the deck top. It is also noted that, after completion of
the superstructure,the top of piers moved by 120mm laterally due to the plan
curvature of the bridge, as anticipated in the design.
Other activities carried out to complete the construction of the bridge
were as follows:
• backfilling behind the west abutment
• concreting the access holes in the top slab
• constructing parapet edge beams using counter-balanced form-travellers
(Fig 21)
• installing the parapets
• installing the deck waterproofing
• surfacing the deck
• installing the expansion joints
• installing the electricity cables and lighting columns
• installing the drainage system
• installing the lighting inside the box girder and the hollow piers
As shown in Fig 22, the vertical profile of the main span is conservatively
constructedabovethetheoreticalprofileinordertooffsetanyuncertaintiesdue
to the creep and shrinkage effects. The nearly completed Votonosi Bridge is
shown in Fig 23.
Conclusion
Votonosi Bridge, with a main span of 230m is the longest span for balanced
cantilever bridges constructed in Greece to date. Situated in a seismically
active zone and in an area of outstanding natural beauty, the design and
construction presented a new challenge to the client,designer,contractor and
supervisors.The successful and accident-free construction of this technically
demanding bridge is the result of constant diligence in the workplace and
teamwork from all the participants. The works were constructed through a
quality management system developed by EOAE/KBR which is used on all
projects under EOAE management.The experience gained in the design and
construction of Votonosi Bridge is being used in constructing a more chal-
lenging and longer span balanced cantilever Metsovitikos Bridge currently
under construction as part of Egnatia motorway project.
General data
Structural concrete: 29 000m3
;
Steel reinforcement: 5400t;
Post tensioning tendons: 1260t;
Duration of construction: 58 months;
Cost of construction: €20.7M
Credits and acknowledgment
The design and construction ofVotonosi Bridge is the combined effort of many
individuals in the following organisations:
Client: EOAE, Thessaloniki
Structural design: DOMI OE, Athens
Category III checker: VCE, Vienna
Designer of temporary works: Zografidis, Athens
Contractor: Mechaniki A.E, Athens
Project manager: KBR (UK), Leathearhead
Construction manager: Thales-Omek, Paris/Athens
Climbing formwork: DOKA, Germany
Form-travellers: NRS, Norway
The authors would like to thank Mr P Gibbons, KBR project manager, for
reviewing the paper.The opinions expressed by the authors do not necessarily
express those of EOAE, KBR, Thales-Omek and Mechaniki AE.
1. Hindley, G., Gibbons, P., Agius, M., Carr, B., Game, R. and Kashani, K.:
‘Linking past and present’, Civ. Eng., ASCE, 2004
2. Ahmadi-Kashani, K. and Gavaise, E.: ‘Bridges of Egnatia motorway’, Proc. 6th
Int. Conf. Short and Medium Span Bridges, Vancouver, Canada, 2002
3. OSMEO: ‘Guidelines for conducting road works design’, EOAE Internal
Report, 2000
4. ZTVK 96: ‘Zusätzliche Technische Vorschrift für Kunstwerke’, 1996
5. Ahmadi-Kashani, K.: Seismic design of Egnatia motorway bridges, Proc. Inst.
Civ. Eng., J. Bridge Eng., London, 2004
6. EAK: ‘National Greek anti-seismic regulations’, 2000
7. E39/99 – ‘National Greek directives on anti-seismic design of bridge’, 1999
8. Stathopoloulos, S., Kotsanopoulos, P., Stathopoloulos, E., Spyropolous, I.,
Stathopolous, K.: ‘Votonosi Bridge in Greece’, FIB Symp, New Delhi, 2004
9. TSY: ‘Specification for material and workmanship’, EOAE Internal Report,
2000
REFERENCES
SE18 Votonosi bridge :Layout 1 12/9/07 16:06 Page 45
Votonosi Bridge - The Structural Engineer

More Related Content

What's hot

HIGH FLOOD LEVEL BRIDGE CONSTRUCTION
HIGH FLOOD LEVEL BRIDGE CONSTRUCTIONHIGH FLOOD LEVEL BRIDGE CONSTRUCTION
HIGH FLOOD LEVEL BRIDGE CONSTRUCTIONTEJPRAKASH KUMAWAT
 
Submerged Floating Tunnel by Shantanu Patil
Submerged Floating Tunnel by Shantanu PatilSubmerged Floating Tunnel by Shantanu Patil
Submerged Floating Tunnel by Shantanu PatilShantanu Patil
 
20100514 pipe arch presentation to iem may 2010
20100514 pipe arch presentation to iem   may 201020100514 pipe arch presentation to iem   may 2010
20100514 pipe arch presentation to iem may 2010forcepraxeum
 
Ecg533 rock-tunnel-engineering
Ecg533 rock-tunnel-engineeringEcg533 rock-tunnel-engineering
Ecg533 rock-tunnel-engineeringJunaida Wally
 
Seismic protection of cable stayed bridge using supplemental devices
Seismic protection of cable stayed bridge using supplemental devicesSeismic protection of cable stayed bridge using supplemental devices
Seismic protection of cable stayed bridge using supplemental devicesManish Mall
 
Training Report on Bridge Construction
Training Report on Bridge ConstructionTraining Report on Bridge Construction
Training Report on Bridge ConstructionMAHAVIR MEENA
 
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTIONINDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTIONBhavek Sharma
 
Tunneling by tunnel boring machine
Tunneling by tunnel boring machineTunneling by tunnel boring machine
Tunneling by tunnel boring machineVISHAL KUMAR SINGH
 
Tunneling exploration
Tunneling explorationTunneling exploration
Tunneling explorationjamali husain
 
tunnel boring machine
tunnel boring machine tunnel boring machine
tunnel boring machine Milan Sheta
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sectionsjuwes
 

What's hot (20)

Tunnel boring machines123
Tunnel boring machines123Tunnel boring machines123
Tunnel boring machines123
 
HIGH FLOOD LEVEL BRIDGE CONSTRUCTION
HIGH FLOOD LEVEL BRIDGE CONSTRUCTIONHIGH FLOOD LEVEL BRIDGE CONSTRUCTION
HIGH FLOOD LEVEL BRIDGE CONSTRUCTION
 
Submerged Floating Tunnel by Shantanu Patil
Submerged Floating Tunnel by Shantanu PatilSubmerged Floating Tunnel by Shantanu Patil
Submerged Floating Tunnel by Shantanu Patil
 
Presentation1mining
Presentation1miningPresentation1mining
Presentation1mining
 
20100514 pipe arch presentation to iem may 2010
20100514 pipe arch presentation to iem   may 201020100514 pipe arch presentation to iem   may 2010
20100514 pipe arch presentation to iem may 2010
 
Ecg533 rock-tunnel-engineering
Ecg533 rock-tunnel-engineeringEcg533 rock-tunnel-engineering
Ecg533 rock-tunnel-engineering
 
Seismic protection of cable stayed bridge using supplemental devices
Seismic protection of cable stayed bridge using supplemental devicesSeismic protection of cable stayed bridge using supplemental devices
Seismic protection of cable stayed bridge using supplemental devices
 
Tunneling
TunnelingTunneling
Tunneling
 
Tbm
TbmTbm
Tbm
 
Training Report on Bridge Construction
Training Report on Bridge ConstructionTraining Report on Bridge Construction
Training Report on Bridge Construction
 
Tunnel engineering
  Tunnel engineering  Tunnel engineering
Tunnel engineering
 
Site visit presentation: Kwun Tong line extension
Site visit presentation: Kwun Tong line extensionSite visit presentation: Kwun Tong line extension
Site visit presentation: Kwun Tong line extension
 
Cut and cover
Cut and coverCut and cover
Cut and cover
 
Deh Cho Bridge
Deh Cho BridgeDeh Cho Bridge
Deh Cho Bridge
 
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTIONINDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
 
Tunneling by tunnel boring machine
Tunneling by tunnel boring machineTunneling by tunnel boring machine
Tunneling by tunnel boring machine
 
Tunneling exploration
Tunneling explorationTunneling exploration
Tunneling exploration
 
tunnel boring machine
tunnel boring machine tunnel boring machine
tunnel boring machine
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sections
 
tunneling & its effects
tunneling & its effectstunneling & its effects
tunneling & its effects
 

Viewers also liked (16)

Cv administrator
Cv   administratorCv   administrator
Cv administrator
 
Algebra
AlgebraAlgebra
Algebra
 
Pinocho
PinochoPinocho
Pinocho
 
Internet como herramienta
Internet como herramienta Internet como herramienta
Internet como herramienta
 
Diapositivas tic-4
Diapositivas tic-4Diapositivas tic-4
Diapositivas tic-4
 
fercundacion parte 2
fercundacion  parte 2fercundacion  parte 2
fercundacion parte 2
 
Cuento la historia de gabriela
Cuento la historia de gabrielaCuento la historia de gabriela
Cuento la historia de gabriela
 
Calendrier 2017
Calendrier 2017Calendrier 2017
Calendrier 2017
 
Tipos de energía q se utiliza en las nuevas
Tipos de energía q se utiliza en las nuevas Tipos de energía q se utiliza en las nuevas
Tipos de energía q se utiliza en las nuevas
 
Intro a sistemas
Intro a sistemasIntro a sistemas
Intro a sistemas
 
Personal Branding Workshop - Secondo Incontro
Personal Branding Workshop - Secondo IncontroPersonal Branding Workshop - Secondo Incontro
Personal Branding Workshop - Secondo Incontro
 
Jhosuegranda 8vo 12
Jhosuegranda 8vo 12Jhosuegranda 8vo 12
Jhosuegranda 8vo 12
 
Portfolio Nyura Sharova
Portfolio Nyura SharovaPortfolio Nyura Sharova
Portfolio Nyura Sharova
 
ARTICLE
ARTICLEARTICLE
ARTICLE
 
gkaur_Resume_CMA
gkaur_Resume_CMAgkaur_Resume_CMA
gkaur_Resume_CMA
 
Catacocha
CatacochaCatacocha
Catacocha
 

Similar to Votonosi Bridge - The Structural Engineer

Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed linkVicky Matwan
 
Assessing the interaction between the excavation of a large cavern and existi...
Assessing the interaction between the excavation of a large cavern and existi...Assessing the interaction between the excavation of a large cavern and existi...
Assessing the interaction between the excavation of a large cavern and existi...SYSTRA
 
Technical seminar
Technical seminarTechnical seminar
Technical seminarUjwal Ujwal
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMIshant Gautam.
 
Mokpo symposium pecker 2006
Mokpo symposium pecker 2006Mokpo symposium pecker 2006
Mokpo symposium pecker 2006gefyra-rion
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationShuBham RaNa
 
BUILDING STRUCTURE ASSIGNMENT 1
BUILDING STRUCTURE ASSIGNMENT 1BUILDING STRUCTURE ASSIGNMENT 1
BUILDING STRUCTURE ASSIGNMENT 1Nur Zaas
 
DYNAMIC ANALYSIS OF CONCRETE GIRDER BRIDGES UNDER STRONG EARTHQUAKES: THE EFF...
DYNAMIC ANALYSIS OF CONCRETE GIRDER BRIDGES UNDER STRONG EARTHQUAKES: THE EFF...DYNAMIC ANALYSIS OF CONCRETE GIRDER BRIDGES UNDER STRONG EARTHQUAKES: THE EFF...
DYNAMIC ANALYSIS OF CONCRETE GIRDER BRIDGES UNDER STRONG EARTHQUAKES: THE EFF...IAEME Publication
 
Tunnelling Methods.pdf
Tunnelling Methods.pdfTunnelling Methods.pdf
Tunnelling Methods.pdfSuryoNegoro3
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridgesSravan Kumar
 
Segmnetal construction of bridges
Segmnetal construction of bridgesSegmnetal construction of bridges
Segmnetal construction of bridgesCivil Engineers
 
Paper European Conference Athens 2011
Paper European Conference Athens 2011Paper European Conference Athens 2011
Paper European Conference Athens 2011ILIAS MICHALIS
 
A study of local scour at bridge pier
A study of local scour at bridge pierA study of local scour at bridge pier
A study of local scour at bridge pierShivkumar Yadav
 
4th athenian lecture
4th athenian lecture4th athenian lecture
4th athenian lecturegefyra-rion
 
IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...
IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...
IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...IRJET Journal
 

Similar to Votonosi Bridge - The Structural Engineer (20)

Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed link
 
Assessing the interaction between the excavation of a large cavern and existi...
Assessing the interaction between the excavation of a large cavern and existi...Assessing the interaction between the excavation of a large cavern and existi...
Assessing the interaction between the excavation of a large cavern and existi...
 
Technical seminar
Technical seminarTechnical seminar
Technical seminar
 
training report LMRC
training report LMRCtraining report LMRC
training report LMRC
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
 
Mokpo symposium pecker 2006
Mokpo symposium pecker 2006Mokpo symposium pecker 2006
Mokpo symposium pecker 2006
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
 
the millau viaduct
the millau viaductthe millau viaduct
the millau viaduct
 
1115
11151115
1115
 
BUILDING STRUCTURE ASSIGNMENT 1
BUILDING STRUCTURE ASSIGNMENT 1BUILDING STRUCTURE ASSIGNMENT 1
BUILDING STRUCTURE ASSIGNMENT 1
 
Bridge construction atlas
Bridge construction atlasBridge construction atlas
Bridge construction atlas
 
DYNAMIC ANALYSIS OF CONCRETE GIRDER BRIDGES UNDER STRONG EARTHQUAKES: THE EFF...
DYNAMIC ANALYSIS OF CONCRETE GIRDER BRIDGES UNDER STRONG EARTHQUAKES: THE EFF...DYNAMIC ANALYSIS OF CONCRETE GIRDER BRIDGES UNDER STRONG EARTHQUAKES: THE EFF...
DYNAMIC ANALYSIS OF CONCRETE GIRDER BRIDGES UNDER STRONG EARTHQUAKES: THE EFF...
 
Tunnelling Methods.pdf
Tunnelling Methods.pdfTunnelling Methods.pdf
Tunnelling Methods.pdf
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridges
 
Segmnetal construction of bridges
Segmnetal construction of bridgesSegmnetal construction of bridges
Segmnetal construction of bridges
 
Paper European Conference Athens 2011
Paper European Conference Athens 2011Paper European Conference Athens 2011
Paper European Conference Athens 2011
 
A study of local scour at bridge pier
A study of local scour at bridge pierA study of local scour at bridge pier
A study of local scour at bridge pier
 
Dfi2005 pecker
Dfi2005 peckerDfi2005 pecker
Dfi2005 pecker
 
4th athenian lecture
4th athenian lecture4th athenian lecture
4th athenian lecture
 
IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...
IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...
IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...
 

Votonosi Bridge - The Structural Engineer

  • 1.
  • 2.
  • 3. 18 September 2007 – The Structural Engineer|39 paper: ahmadi-kashani et al Fig 1. Egnatia motorway and location of Votonosi Bridge / Fig 2. Elevation and plan / Fig 3. Cross section of the deck and piers a) Deck over pier with lane widths b) Deck at mid-span c) Piers M1N, M1S and M2N d) Pier M2S Synopsis The recently constructed Votonosi Bridge situated in an area of outstanding natural beauty and within a seismically active zone, forms part of the Egnatia motorway project in northern Greece. With a main span of 230m, this bridge has the longest span for balanced cantilever bridges constructed in Greece to date. This paper provides general information regarding the bridge and outlines its construction. Introduction The Egnatia motorway in northern Greece is one of the prior- ity projects in the Trans-European Network for Transport which will provide Europe with a fast and safe access route to Turkey and the Middle East1 . It will also provide links to the neighbouring Balkan countries and to the rest of mainland Greece.Its main axis stretches from the port of Igoumenitsa on the Ionian Sea to the town of Kipi at the Greek-Turkish border (Fig 1).This axis is 680km long and consists of a dual two-lane motorway with hard shoulders and includes more than 600 bridges with a total length of over 40km(ref.2). The design, construction, maintenance, operation and exploitation of the motorway is being managed by ‘Egnatia Odos AE’ (EOAE), a company wholly owned by the Greek State which was estab- lished in 1995 by the Greek Ministry of Environment,Planning and Public Works. Kellogg Brown and Root (KBR) has acted as the Project Manager since 1996, and Thales-Omek has been involved in the construction management for its western region since 1997. In north-west Greece, the Egnatia motorway crosses moun- tainous terrain demanding the construction of many major tunnels and bridges. Situated in this region,Votonosi Bridge is located near the village of Votonosi, between Antochory and Votonosi Tunnels, and crosses a 500m wide river valley with a depth of over 100m (Fig 1). This location demanded a bridge with minimum number of piers to be cost effective.To meet this and all other project requirements, a three-span balanced cantilever bridge was selected for detail design and construc- tion. With a number of in situ balanced cantilever bridges already successfully completed by local contractors,this form of construction is well established in Greece. However, with a main span of 230m,Votonosi Bridge by far exceeded the longest span previously constructed by this method (140m), and its construction was therefore a challenge for the construction industry. This paper provides general information regarding Votonosi Bridge, and outlines the design process and its construction. General description Votonosi Bridge consists of two independent 13.5m wide decks located at 27.5m centres with each deck carrying two 3.75m wide carriageways and a 2.5m wide hard shoulder over Metsovitikos River and a local road.The north and south decks are 478m and 490m long respectively,consisting of three spans of 127m–224m–127m and 130m–230m–130m (Fig 2). The superstructure has an upward longitudinal slope of approxi- mately 5% eastwards. A 90m length of both decks at the east- end is on a transition curve joining a 1000m radius circular curve which results in the highway super-elevation increasing from 2.5% to 5%. The site investigation boreholes indicated that the ground consists of thick/medium layers of sandstone inter-bedded with thin layers of siltstone. The piers are founded on circular 10m diameter rock sockets with depths of up to 25m resisting up to 140MN vertical load, 11MN shear force, and 300MN-m fixity moment.The piers have heights varying from 45m to 53m and comprise a 5m by 7m box section, except for the tallest pier which has a 6m by 7m box section (Fig 3). The relatively tall piers are sufficiently flexible to be The construction of Votonosi Bridge, Greece K. Ahmadi- Kashani PhD, CEng, MIStructE, MIEI Technical Advisor, KBR, UK I. Rentzeperis PhD, TEE General Manager, EOAE, Greece C. Brun Construction Manager, Thales-Omek, France P. Papanikolas PhD, TEE Technical Manager, EOAE, Greece V. Tsebas TEE Site Manager, Mechaniki AE, Greece C. Miltsakakis TEE Site Engineer, Mechaniki AE, Greece Received: 10/06 Modified: 02/07 Accepted: 04/07 Keywords: Votonosi Bridge, Greece, Road bridges, Balanced cantilever construction, Egnatia Motorway, Greece, Seismic design, Foundations, Concrete © K. Ahmadi-Kashani, I. Rentzeperis, C. Brun, P. Papanikolas, V. Tsebas, & C. Miltsakakis Your comments on this paper are welcome and will be published online as Correspondence. 1 2 3a 3c 3b 3d IOANNINA N THESSALONIKI BULGARIA GREECE Votonosi Bridge NORTH DECK SOUTH DECK ANTHOCHORI TUNNEL VOTONOSI TUNNEL 3.00 130.00m 130.00m 126.60m 230.00m 223.90m 1.25 0.5 2.50 3.753.75 0.95 0.8 3.00 5.50 7.00 7.00 13.50 0.750.75 7.00 5.00 6.00 7.00 0.6 0.70 AON M1N M2N A3N A3N A3S M2N M2S M1N M1S AON AOS 126.60m SE18 Votonosi bridge :Layout 1 12/9/07 16:05 Page 39
  • 4. 40|The Structural Engineer – 18 September 2007 Fig 4. Anti-uplift sliding bearing / Fig 5. Expansion joint detail / Fig 6. Bottom slab tendon anchorage 4 5 6 monolithically connected to the superstructure,and to form a central frame to resist longitudinal loading and environmental effects including seismic forces. At the abutments the deck is free to rotate and move longitudinally via sliding pot bearings. Potential deck uplift during seismic events is restricted by anti-uplift devices connected to the bearings (Fig 4). A guided bearing at each abutment restricts the movement of the deck in the trans- verse direction. Two elastomeric bearings are provided with sufficient gap between the deck-ends and abutment cheek-walls to act as bumpers during seismic events with intensities greater than the design earthquake. The expansion joints allow a total bridge movement of up to 400mm at each end (Fig 5). Each superstructure consists of a box girder with a constant width of 7m and a depth varying from 13.5m at the piers to 5.5m at mid-span. The web thickness steps down from the piers towards mid-span taking values of 0.60m, 0.50m and 0.45m over a transition length of 0.75m.The top slab has a thickness of 0.3m increasing to 0.5m at the edges, and the thickness of the bottom slab varies from 1.3m at the piers to 0.3m at mid-span. The thick- ness of the side cantilever varies from 0.65m at the root to 0.25m at the tip (Fig 3). Each pair of in situ concrete balanced cantilevers is connected to a 3m long connecting in situ segment at mid-span: with approximately 16m long deck- ends supported from the ground during construction. The length of the cantilevers varies from 107m to 110m,each consisting of 26 in situ segments. In order to limit the weight of the segments, their lengths vary from 3m to 4.5m for the first 13 segments, thereafter remaining constant at 5m. The cantilever prestressing consists of 102 internal tendons made up of 19, 15.7mm diameter superstrand (19T15) arranged in two rows over the piers with a tendon length of up to 227m.The tendons run through the upper slab and are anchored at the segments’ end face within the slab thickening without the need for blisters. Internal tendons are also placed in the bottom slab to provide the continuity prestressing which comprise 32, 19T15 in the main span and 12, 19T15 in the side spans. The continuity tendons are anchored in 2m long blisters constructed at the edges of the bottom slab (Fig 6). Abutment galleries are provided to access the expansion joints and the interior of the box girders for inspection and maintenance. Maintenance or damage inspection of the inside of the hollow piers is by means of an access hole at the pier top and then via ladders placed between permanent platforms that are located at 5m intervals inside the piers. Inspection of the bearings can be carried out from a platform situated in front of the abutments. The provision of jacking points allows the replacement of the bearings. Parapets consist of standard metal posts and railings in accordance with the Greek regulations.The main drainage pipes are made of fibre glass and run on the outer face of each box girder with connections to the deck inlets via transverse drainage pipes under the deck cantilevers. Motorway service ducts are located under the outer footpaths and provision of ventilation and drainage holes are made near the web tops and the bottom slab,respectively. A 1.0m by 1.5m opening in the bottom slab near abutment A0 is provided for access in cases of emergency. The relatively high (12m) west abutments dictate that the backfill spills through either abutment between its two tapering legs founded on a spread footing. The east abutments are of the bank seat type with spread footing foundations located at two different levels due to the steep slope of the rock face. Design The design of Votonosi Bridge was carried out in accordance with the performance requirements set out in OSMEO3 , the design guidelines devel- oped by EOAE. The loading and static design was based on German DIN Standards including ZTVK 964 supplement for bridge design.To consider the effect of deck plan curvature,a three dimensional computer model was devel- oped with measures to include soil structure interaction. The time depend- ent characteristic of the concrete was modelled in the analysis using an estimated construction programme. The analysis and design covered all stages of construction and was carried out using SOFISTIK computer program which automated part of the design process. A number of 3D finite element models were additionally developed and analysed to determine the intensity of stress concentration in the rock sockets,anchorage zones,and hammerheads.Camber analyses were carried out during the balanced cantilever construction to determine the setting out geometry of the segments using the time dependent properties of concrete and allowing for site temperature and humidity at the time of casting. Votonosi Bridge is situated within Greek seismic zone II with peak ground acceleration (PGA) of 0.16g, upgraded by an importance factor of 1.35 . The seismic design of the bridge followed the Greek codes of practice EAK6 and E39/997 . Its seismic integrity during construction was assessed for a PGA value of 0.104g.To allow for structural redundancy the‘behaviour factor’ was assumed as 3.0 for the completed bridge, thus allowing formation of plastic hinges at the top and bottom of the piers during major seismic events. The behaviour factor was taken as 1.0 during the construction to prevent struc- tural damage before commencement of service. During the construction, combinations of the following load cases were considered in the design: • self weight of the form-travellers paper: ahmadi-kashani et al SE18 Votonosi bridge :Layout 1 12/9/07 16:05 Page 40
  • 5. 18 September 2007 – The Structural Engineer|41 8 9 7 Fig 7. Construction programme / Fig 8. Mobile crane for construction of rock sockets / Fig 9. Rock socket excavation • self weight of the newly cast segments • prestressing forces • an accidental drop of the newly cast segments • construction loading • temperature difference between the top and bottom of the deck • variation in the ambient temperature • differential settlement between adjacent substructures • wind loading with differential pressure • seismic loading For the ‘in service’ design, combinations of the following load cases were considered: • dead load and superimposed load • prestressing forces • SLW30/60 traffic loading in accordance with DIN 1072 • temperature difference between top and bottom of the deck • variation in the ambient temperature • differential settlement between adjacent substructures • wind loading • seismic loading The following classes of material were specified in the design: • concrete (cube strength): superstructure 45MPa piers 45MPa rock sockets (capping zone) 35MPa rock socket (shaft) 25MPa abutments 35MPa approach slab 35MPa • steel reinforcement BSt500 (St IV) • prestressing tendons 1550/1750MPa The design and constructability of the bridge was reviewed by EOAE,and a category III check was carried out by an independent consultant. The details of the analysis and the design are given in Ref (8). Construction General The construction was carried out in accordance with TSY9 , a materials and workmanship specification produced by EOAE based on national and inter- national specifications. The works started in January 2000 and were completed in December 2005 with the outline construction program shown in Fig 7. The bridge is situated in a mountainous region and the adverse winter weather dictated a stoppage of the works for approximately 2 months of the year. The site was served by two tower cranes placed between piers M1 and M2 with up to 100kN lifting capacity and 60m reach. Other major equipment included a 300kN capacity mobile overhead gantry, two 125kVA generators, a 100m3 /hr loader, two compressors with 850cfm and 335cfm capacities, six 8m3 capacity concrete mixer trucks, four concrete 101bar capacity pumps with 47m3 /h output, a 10m3 truck, a 12hp gunite pump, a 8hp grouting pump, a mini-excavator, and a drilling machine. Due to the relatively long distance between the site and quarries, aggre- gates were extracted from the nearby Metsovitikos River, crushed, screened and washed for concrete production in a 50m3 /hr batching plant situated on site. The batching plant for the construction of the nearby Megalorema Viaduct2 ,situated within 2km of the site,was also used in cases of emergency. The details of the construction of the foundations, piers and superstruc- ture of the bridge are described as follows. Foundations Access roads to the foundations were designed and constructed with the emphasis on minimising damage to the environment.31 trial boreholes were drilled at the pier and abutment locations.This was followed by levelling the ground to install the mobile overhead gantry for the construction of the rock sockets.Due to the level difference between the south and north rock sockets at M2, an extended platform was built using a concrete enclosure filled with compacted soil to allow the operation of the gantry over both sockets (Fig 8). The excavation for the rock sockets was carried out in depth intervals of 3m with drilling at the perimeter followed by sequential firing of explosive charges placed in a helical formation. With the available drilling machines the acceptable tolerance for vertical drilling could not be achieved for depths of more than 15m. The drilling operation was, therefore, carried out in two stages: a larger diameter than the design diameter was first formed for the upper half of the socket,and the drilling machine was subsequently lowered and placed on the base of the upper half in order to drill for the design diam- eter lower half (Fig 9). The excavated face was regularly inspected by a geologist to verify the geot- echnical parameters assumed in the design, and to optimize the measures required to support the exposed face.The rock face was stabilised using rock anchors, steel beams, and corrugated metal sheets, followed by the installa- tion of mesh reinforcement and shotcreting. Concreting the sockets was carried out in 5 or 6 lifts with the depth of each lift varying from 3m to 5m using up to 600m3 of concrete for each lift. Concrete temperature was paper: ahmadi-kashani et al SE18 Votonosi bridge :Layout 1 12/9/07 16:05 Page 41
  • 6. 42|The Structural Engineer – 18 September 2007 paper: ahmadi-kashani et al controlled by means of early morning concerting in the summer months,and using Portland cement type I.These measures reduced the risk of micro-crack formation in the concrete due to excessive heat of hydration. The top 3m of the rock socket consisted of a heavily reinforced ‘capping zone’. The lower 4 or 5 ‘shaft’ lifts contained mainly vertical reinforcement placed at the perimeter of the socket.Reinforcement installation and concret- ing was carried out with the aid of the overhead gantry.A sump was provided on the top surface of each segment to remove any excess water.The construc- tion of each rock socket took between 3 and 4 months depending on the quality and type of rock mass encountered.The maximum settlement of the sockets after completion of the bridge was recorded as 4mm. Piers The piers were constructed using climbing formwork in 2.8m segments.The reinforcement for the piers mainly comprised 7m prefabricated cages typi- cally formed with six longitudinal reinforcement bars connected by stirrups. The formwork and associated working platforms were fixed onto sockets embedded on the previously cast segment. The formwork panels were held in the upright position and were fixed in place with through ties. Construction of a typical pier segment normally took 4 days to complete: 1.5 days to place the reinforcement, 1.5 days to install the formwork and 1 day for concrete pouring and curing. To avoid lapping reinforcement bars in the plastic hinge zones at the top and bottom of the piers, the reinforcement cages in this region were fabri- cated with14m/16m long rebars covering three segments, and were held upright by steel framework that included three levels of working platforms (Fig 10). Additional horizontal reinforcement links were placed in this zone to confine both the concrete and vertical reinforcement,and to allow the safe formation of plastic hinges during a major seismic event.In order for the piers of each superstructure to resist similar seismic forces,the stiffness of the piers had to be comparable;this meant that the M1 piers had to be extended down into the ground (Fig 2). Concrete collars, 13m diameter and 10m deep, were constructed around these piers to allow the inspection and repair of the plastic hinge zones after a major earthquake (Fig 11). Pier segments lower than 25m above ground level were concreted using lorry mounted pumps. For higher levels, concrete was pumped through a 150mm diameter steel pipe fixed to the pier by means of a pump with an 80m head capacity. Suitable aggregate grading and admixtures were used to provide the required slump and consistency for the pumped concrete. Temporary stairs and platforms were installed and used during the pier construction. The construction of each pier took approximately 4 months to complete. The galvanised steel maintenance inspection ladders and platforms were installed inside the piers prior to the construction of the hammerheads. Due to the height of the piers the formwork for the hammerhead was supported from the pier tops.Each hammerhead,13.5m high with two diaphragms,was constructed in five phases using a proprietary formwork system (Fig 12). Steel beams fixed to the inside walls of the piers supported the 2.5m thick bottom slab.The construction of the hammerhead required special formwork to include the various access openings to the interior of the piers and box girders. Once the hammerhead was constructed, a temporary lift was installed for each pair of M1 and M2 piers which together with a high level truss spanning between the decks allowed access to both decks.The construc- tion of each hammerhead took approximately 3 months to complete. Superstructure The superstructures were constructed using a proprietary form-traveller weighing 800kN with a capacity to support a segment weight of 2500kN,and with its centre of gravity up to 2.5m beyond the end of the segment. Each traveller consisted of two main ‘A’ frames anchored to the deck and carried a transverse truss from which the formwork for the webs and the upper and lower slab soffits were suspended using high strength hangers. The move- ment of each traveller was provided by two hydraulic rams.The top and sides of the travellers were enclosed with a waterproofing tarpaulin to protect the operatives from adverse weather. To meet the completion date, four pairs of travellers were used during the construction (Fig 13). The 6.6m length of the hammerheads was sufficient to place a pair of trav- ellers braced to each other (Fig 14). Once the first pair of segments had been cast symmetrically on the opposite sides of the piers, the bracing was removed.The construction cycle for the next pair of segments consisted of the following stages: • moving the traveller to a new position • adjusting the formwork levels for the new segments • installing the reinforcement, prestressing ducts and tendons • concreting the new segments • prestressing the new segments Each pair of segments was cast alternately in two stages: 1) The bottom slab and part of the webs, 2) The remainder of the webs and the top slab. This sequence helped to reduce the unbalanced cantilever loading, and resulted in better scheduling for the teams of labour involved. Concreting each stage took about 3h and required up to 35m3 of concrete.The depth of the upper section was kept constant resulting in a similar rein- forcement arrangement. A number of surveys confirmed that the traveller was sufficiently stiff to prevent separation of the first stage from the last segment when the second stage was poured and added its weight to the trav- eller. Casting the upper section at least 2 days after concreting the lower section also helped in preventing crack formation at the construction joint by ensuring sufficient bonding between the concrete and reinforcement. The transportation of the reinforcement beyond the reach of the tower crane was made possible by means of a light wagon driven by an electric tractor on rails. A specialist team were responsible for placing the 100mm internal diameter galvanized prestressing ducts, threading the tendons, placing spiral reinforcement, stressing the tendons and grouting the ducts. A grout test on a prestressed beam was successfully carried out prior to the grouting the ducts. A steel template was used at the segment face to facili- tate accurate placement of the tendons. The strands were delivered on coil drums and were unrolled and pushed through the ducts by means of a strand pushing machine.The minimum clear distance of 100mm between the prestressing tendons specified in the design allowed for easy pouring and compaction of the concrete and for placement of the traveller hangers. Temporary 1.0m by 1.5m openings were provided in the top slab to allow the equipment for prestressing the bottom slab tendons to be lowered into posi- tion. Following the installation of reinforcement and tendons,the internal form- work for the box girder was placed in position, and preparation was made for the concreting phase. For casting segments away from the pier, an addi- tional concrete pump was installed on the hammerhead to facilitate concrete delivery. The external formwork was backed with 50mm thick polystyrene panels to insulate the concrete from the ambient temperature ranging from –15°C to 40°C during the construction period. Installation of fan heaters inside the box girder and radiant heaters on the deck during the winter months provided acceptable conditions for concreting.In the summer months, concreting was carried out early in the morning to avoid micro-cracking due to excessive heat of hydration. Concrete samples were taken during casting to determine its properties such as creep, shrinkage and modulus of elastic- ity, which were then used in the camber analysis. The average 28 days concrete strength achieved was 65MPa. The prestressing was generally applied 3 days after concreting when the concrete had attained a minimum strength of 40MPa. The tendons were tensioned symmetrically from both ends in sequence about the centreline of the box girder using a 3500kN capacity prestressing jack. The measured tendon extensions were within 5% of their theoretical values. The geometry of the balanced cantilevers was monitored by surveying the coordinates of three steel plate markers placed at the tip of each segment. One marker was installed at the centreline of the deck and the other two located 5.5m either side of the centreline. The survey was carried out early in the morning to avoid differential temperature effects.Measurements were made on all the segments after three events: a) casting a pair of new segments, b) prestressing the new segments and c) moving the travellers to a new position. The results were compared with the theoretical values, and after allowing for adjustments to comply with the design,a set of coordinates were calculated for setting out the formwork for the next segment. The extension of hangers transferring the weight of a segment to the traveller was measured as 11mm, and was taken into account when setting out the SE18 Votonosi bridge :Layout 1 12/9/07 16:05 Page 42
  • 7. 18 September 2007 – The Structural Engineer|43 paper: ahmadi-kashani et al Fig 10. Pier reinforcement in plastic hinge zone / Fig 11. Collar for inspection of plastic hinge zone / Fig 12. Hammerhead construction Fig 13. Utilisation of four pairs of form-travellers / Fig 14. Braced form-travellers / Fig 15. Support system for the deck-end at abutment A0 before backfilling / Fig 16. Restraining the tip of balanced cantilever adjacent to abutment A0 10 11 12 14 15 13 16 SE18 Votonosi bridge :Layout 1 12/9/07 16:06 Page 43
  • 8. 44|The Structural Engineer – 18 September 2007 paper: ahmadi-kashani et al Fig 17. Support system for the deck-end at abutment A3/ Fig 18. Construction of the deck-end at abutment A3 Fig 19. Construction of the mid-span connecting segment/ Fig 20. Construction of central span connecting segment a) Elevation b) Cross- section/ Fig 21. Construction of the edge beams / Fig 22. Theoretical and as built road levels / Fig 23. Votonosi Bridge nearing completion 17 19 18 21 23 22 20a 20b SE18 Votonosi bridge :Layout 1 12/9/07 16:06 Page 44
  • 9. 18 September 2007 – The Structural Engineer|45 paper: ahmadi-kashani et al formwork for the bottom slab.The construction of a new pair of segments was planned on a 10 day cycle which was generally achieved after the initial learning curve. The construction of each pair of balanced cantilever decks took approximately 12 months to complete.After completion of the balanced cantilever over pier M1,the travellers were removed and the deck levels were surveyed. Subsequently, the construction of the 16m long deck-end next to abutment A0 commenced.The formwork for the deck-end was supported on a proprietary truss system which in turn was supported from the ground at the two edges (Fig 15). The lateral and vertical movement of the cantilever tip was prevented during concreting by means of a braced frame and by anchoring the tip of the cantilever to the ground (Fig 16). The construction of the deck-end consisted of the following sequence: • concreting the bottom slab and part of the webs (stage 1 concreting) • stressing a third of bottom slab tendons • concreting the remainder of the webs and the top slab (stage 2 concreting) • curing the concrete • removal of the temporary truss • de-tensioning and stressing the bottom slab tendons Partial stressing of the bottom slab enabled the lower section of the deck- end to carry the weight of stage 2 concreting and allowed the removal of the temporary truss. The 16m long deck-end next to abutmentA3 was subsequently constructed by means of two pairs of right angle steel frames, pinned at the top and bottom, with horizontal extension arms anchored to the cantilever tip (Figs 17 and 18). Before construction, the travellers were moved to pier M2 and a deck level survey was carried out. The formwork was then placed on scaf- folding supported on the steel frames. The construction of the A3 deck-end was carried out in a sequence similar to that described for the A0 deck-end. The connection of the cantilever tip to the deck required a careful concret- ing procedure,including the use of a counterweight at mid-span and regular monitoring.To minimise the effect of differential temperature,concreting was carried out at night.The lower deck section constructed in the stage 1 concret- ing was designed with sufficient reinforcement to span between the bearings and the cantilever end, allowing for the removal of scaffolding after comple- tion of the stage 1 concreting. Prior to constructing the central connecting segment, a level survey was carried out and the maximum level difference between the opposite cantilever tips was found to be 16mm and 20mm for the south and north decks respec- tively,bothwithintherequiredtolerance.Theexternalformworkfromthetrav- eller was anchored to the segments each side of the gap to provide the shuttering for the connecting segment.To correct the level difference between the cable ducts in the bottom slab and to prevent relative vertical movement of the cantilever tips,the two pairs of 600mm deep base beams of the travellers were placed over the gap and anchored down to the deck (Fig 19). Two horizontal steel I-beams were installed in the connecting segment gaps bearing onto steel angles cast into the cantilever ends, and the gap between the beams and the cantilevers tips were grouted.In order to prevent relative horizontal movement between the cantilevers during concreting a number of the bottom tendons were partially stressed (Fig 20). The bottom slab and part of the webs were subsequently concreted and the steel beams were removed. The remaining part of the webs and the top slab were concreted followed by de-stressing the partially stressed tendons and subse- quent stressing all the bottom slab tendons.As before,concreting was carried out at night. The construction of the deck-ends and the connecting segments were carried out in the calm summer days in order to reduce the risk of any vibra- tion damage during concreting. It is interesting to note that before casting the connecting segments the cantilever tips deflected upward by 150mm due to the sun shining on the deck top. It is also noted that, after completion of the superstructure,the top of piers moved by 120mm laterally due to the plan curvature of the bridge, as anticipated in the design. Other activities carried out to complete the construction of the bridge were as follows: • backfilling behind the west abutment • concreting the access holes in the top slab • constructing parapet edge beams using counter-balanced form-travellers (Fig 21) • installing the parapets • installing the deck waterproofing • surfacing the deck • installing the expansion joints • installing the electricity cables and lighting columns • installing the drainage system • installing the lighting inside the box girder and the hollow piers As shown in Fig 22, the vertical profile of the main span is conservatively constructedabovethetheoreticalprofileinordertooffsetanyuncertaintiesdue to the creep and shrinkage effects. The nearly completed Votonosi Bridge is shown in Fig 23. Conclusion Votonosi Bridge, with a main span of 230m is the longest span for balanced cantilever bridges constructed in Greece to date. Situated in a seismically active zone and in an area of outstanding natural beauty, the design and construction presented a new challenge to the client,designer,contractor and supervisors.The successful and accident-free construction of this technically demanding bridge is the result of constant diligence in the workplace and teamwork from all the participants. The works were constructed through a quality management system developed by EOAE/KBR which is used on all projects under EOAE management.The experience gained in the design and construction of Votonosi Bridge is being used in constructing a more chal- lenging and longer span balanced cantilever Metsovitikos Bridge currently under construction as part of Egnatia motorway project. General data Structural concrete: 29 000m3 ; Steel reinforcement: 5400t; Post tensioning tendons: 1260t; Duration of construction: 58 months; Cost of construction: €20.7M Credits and acknowledgment The design and construction ofVotonosi Bridge is the combined effort of many individuals in the following organisations: Client: EOAE, Thessaloniki Structural design: DOMI OE, Athens Category III checker: VCE, Vienna Designer of temporary works: Zografidis, Athens Contractor: Mechaniki A.E, Athens Project manager: KBR (UK), Leathearhead Construction manager: Thales-Omek, Paris/Athens Climbing formwork: DOKA, Germany Form-travellers: NRS, Norway The authors would like to thank Mr P Gibbons, KBR project manager, for reviewing the paper.The opinions expressed by the authors do not necessarily express those of EOAE, KBR, Thales-Omek and Mechaniki AE. 1. Hindley, G., Gibbons, P., Agius, M., Carr, B., Game, R. and Kashani, K.: ‘Linking past and present’, Civ. Eng., ASCE, 2004 2. Ahmadi-Kashani, K. and Gavaise, E.: ‘Bridges of Egnatia motorway’, Proc. 6th Int. Conf. Short and Medium Span Bridges, Vancouver, Canada, 2002 3. OSMEO: ‘Guidelines for conducting road works design’, EOAE Internal Report, 2000 4. ZTVK 96: ‘Zusätzliche Technische Vorschrift für Kunstwerke’, 1996 5. Ahmadi-Kashani, K.: Seismic design of Egnatia motorway bridges, Proc. Inst. Civ. Eng., J. Bridge Eng., London, 2004 6. EAK: ‘National Greek anti-seismic regulations’, 2000 7. E39/99 – ‘National Greek directives on anti-seismic design of bridge’, 1999 8. Stathopoloulos, S., Kotsanopoulos, P., Stathopoloulos, E., Spyropolous, I., Stathopolous, K.: ‘Votonosi Bridge in Greece’, FIB Symp, New Delhi, 2004 9. TSY: ‘Specification for material and workmanship’, EOAE Internal Report, 2000 REFERENCES SE18 Votonosi bridge :Layout 1 12/9/07 16:06 Page 45