Hillcrest Primary School LEED Project Profile | Miron Construction
7610 - INDIAN PRAIRIE COMMUNITY UNIT SCHOOL DISTRICT 204 - Metea Valley High School
1. dbdivane bros. electric co.
www.divanebros.com
Owner
Board of Education
Aurora, Illinois
Customer
Turner Construction Company
Chicago, Illinois
Location
Metea Valley High School
Aurora, Illinois
Services
• Project Management
• New Construction
Date
July 2008 – February 2010
Key Personnel
Patrick Murphy, Project
Manager
Brian McCarty, General
Foreman
Construction Cost
$12,656,000.00
Metea Valley High School
Indian Prairie Community Unit
School District 204
Scope of Services
Electrical Construction Services were provided for the construction of a new
466,000 square foot High School for the Board of Education in the Indian
Prairie Community School District 204.
Project Description
Divane Bros. Electric Co. installed the entire system for the lighting, power,
standby generator and the Information System raceways as well as
theatrical equipment for the new High School. Also installing two 4000 Amp
services and over 50 remote branch panel boards. The school building
required 5000 different light fixtures for the classrooms, science labs, auto
shops, theater, swimming pools, gymnasiums, art work shops, TV studio, a
large media center, kitchen and a roof top Greenhouse.
All the work was done at an aggressive schedule for more than a year
requiring 45 electricians and six day work weeks.