CCRv1.2SR588 Auto Load Service Locations Into Banner CCR1v1.2
1. Client Change Request (CCR) dcca572a-5dad-40d6-97d1-6d941d0b02ec-
161020174352.doc
Client Change Request
Project Name: SR588 – Auto Load Service Location into Banner
Document Title: SR588 Client Change Request-1
Document Version: 1.2
Author: Bridget Milton
Date: 02/17/2013
Document Status: Final-Internal
1 Description of Change:
This Client Change Request (CCR) encompasses updates across all phases of SR588 due
to the following:
• DBRD the document is in its final phase of GNG approval.
• Scope changes since the original Design through Implementation SOW was
delivered, including:
o GNG will send the AGL World CD data in a format to be agreed upon on a
monthly basis.
o Vertex to take the AGL World CD data and create a data source that can be
queried by the CRR team.
o Vertex will develop a query that has 3-4 field variables that can be input to
develop the initial account list.
o Vertex CRR team to output the list and review the list against the Rent Roll and
general data that will be supplied by GNG.
o GNG to supply guidance on how to create and work/verify the list vs. the rent-roll.
o Vertex CRR team creates a final, update account list that will be used as the data
to upload the list of accounts into Banner.
2 Reasons for Change / Business Benefits of Change:
The benefits / reasons for this Client Change Request (CCR) are the following:
Compliance with PSC regulations governing the treatment of Prepay customers.
3 Related Impacts:
This CCR impacts the following items:
• Updates to SR588 Detailed Business Requirements Document
• Updates SOW SR588 Design-Implementation Phase
• Construction phase scope
• Test Phase will consist of one set of Test Conditions. There will not be separate
Function Test and System Test Conditions.
Vertex Business Services Proprietary and Confidential
Last Saved: 10/20/2016 17:44:03 a10/p10 Page 1 of 3
2. Client Change Request (CCR) dcca572a-5dad-40d6-97d1-6d941d0b02ec-
161020174352.doc
4 Effort and cost estimate
The following estimate provides for completion of the Change Request. This CCR must
be approved by 03/15/2013 to maintain the planned project schedule.
Phase Hours Notes
Project Management
40 Hours increased to support the
requirements in this CCR.
Requirements
24 Hours increased the effort to
update the DBRD system
requirements, assumptions,
and dependencies sections.
Design
80 This CCR increases the
design, construction, test
effort, training and business
process document updates for
the phases of SR588.
Construction
200 Hours increased to support the
requirements in this CCR.
Testing
120 This CCR increases the test
effort for SR588.
Training
40 Hours increased to support the
requirements in this CCR.
NOTE: This estimate assumes
training will not be performed
by Vertex Development,
Business Analyst.
Deployment (and Monitoring)
40 This CCR increases the
deployment &/monitoring
phase of SR588. CCR1
requires new/modified
business processes for creating
units.
Totals
544 Hours increased to support the
request in this CCR.
Additional Remarks:
Hours increased on Requirements and SOW Design-Implementation phases to support
requirements in this CCR.
Vertex Business Services Proprietary and Confidential
Last Saved: 10/20/2016 17:43:53 a10/p10 Page 2 of 3
3. Client Change Request (CCR) dcca572a-5dad-40d6-97d1-6d941d0b02ec-
161020174352.doc
5 Approval signature
By signing this CCR, you are authorizing Vertex Business Services to proceed with the
work outlined in this document and guaranteeing full payment to Vertex Business Services
for the work performed.
Date: Date:
Project Manager
Vertex Business Services
Project Owner
Georgia Natural Gas
Date: Date:
Business Owner
Georgia Natural Gas
Date: Date:
Service Quality Owner
Georgia Natural Gas
Date: Date:
Vertex Business Services Proprietary and Confidential
Last Saved: 10/20/2016 17:44:03 a10/p10 Page 3 of 3