SlideShare a Scribd company logo
1 of 9
6/21/2017 Fundamentals of Project Planning and Scheduling – MilestoneTask
https://milestonetask.com/2013/02/17/fundamentals­of­project­planning­and­scheduling/ 1/9
MilestoneTask
FEBRUARY 17, 2013 BY ATUL GAUR
Fundamentals of Project Planning and Scheduling
One of my smooth progressing engineering project was suddenly jolted by numerous emails
and phone calls from the project sponsor asking the management to expedite activities at
site. The project was going on quite smoothly as it had the best plan to back it up and we all
hoped that things would go as planned but eventually it did not work out that way. 
The project sponsors demanded an unexpected change in the project completion date in order
to meet their nancial goals. The complete project schedule had to be reworked in order to
meet the client expectations. Important milestones like site mobilization had to be advanced in
order to commence construction activities and complete the project as per the new deadlines.
Unforeseen Problems
As the site team got mobilized we were bombarded with myriad of problems some of them so
mundane that we were at times amazed dealing with the slew of such problems. These

MENU
6/21/2017 Fundamentals of Project Planning and Scheduling – MilestoneTask
https://milestonetask.com/2013/02/17/fundamentals­of­project­planning­and­scheduling/ 2/9
unexpected and unforeseen problems at site were a serious road blocks to smooth execution of
the project and timely completion of project activities.
We rst tried to ensure that the existing plan be put to maximum use however the way events
had unfolded at the construction site a complete new plan had to be worked out in order to
meet the challenging deadline set by the project sponsor.
The Project Manager was now expected to turn around things as the Management was under
tremendous pressure to show considerable progress at site. The project sponsor was keeping a
very close tab on the daily activities and also the overall project schedule. The new plan had to
address the lost time and also consider the challenges put forward in terms of reporting the
daily and weekly progress and the overall constrained project completion schedule.
The established activity schedule with a de ned sequence of activities had to be kept aside as
this was written down for normal delivery schedules. Since the activities had to be now
completed on a war footing a completely new activity schedule was developed. While
developing a new schedule the following was ensured.
The subsequent paragraphs describe some fundamental steps followed to develop and
implement a new project schedule.
Involve the Team
Involved all the individuals participating in the execution, enlisted the project activities once
again and worked out the correct sequence of activities. Under the heat of the moment it is a
tendency to avoid consensus and impose diktats, most of the times schedule developed
individually fail and those schedule which are a result of a team work succeed.
Simple Logic
Kept the schedule logic simple, easy to comprehend and tried to capture the exact sequence in
which the activities are likely to be executed. As the construction progresses there are events
which force deviation from the agreed sequence of activities, however I believe if the schedule
is worked out by taking on board all those involved in the execution, the deviation as a result of
external or unforeseen circumstances are likely to be fairly limited.
SMART Criteria
Activities listed in the project schedule were action oriented, speci c and measurable quantities
were assigned to all activities where ever possible.
Project Activities Vs Schedule Activities
Distinguished between project activities and schedule activities. There is a difference between
Schedule activities and project activities. As per the de nition Schedule activities are
decomposed from work break down structure and have an estimated cost, duration and
resource requirement. Schedule activities are connected to other schedule activities through a
logical relationship. If this distinction is not there the project schedule the PM as well as the
6/21/2017 Fundamentals of Project Planning and Scheduling – MilestoneTask
https://milestonetask.com/2013/02/17/fundamentals­of­project­planning­and­scheduling/ 3/9
project team ends up diverting their energies to project activities which has less signi cance on
the project completion. This hampers project progress and eventually affects project cost as
well as stake holder satisfaction.
The Critical Path
Included critical activities pertaining to project sponsor in the activity schedule as this helps in
better coordination with the project sponsor and gives a complete overview of the project. This
also allows project sponsor to undertake planning of important milestones like trials, joint
inspections etc. Clearly highlighted activities that fall on Critical Path. This obviates the need to
continuously scroll the Gantt chart to hunt for critical activities or navigate through various
menu options to get a list of critical activities. This facilitates project manager to continuously
monitor and control the critical activities and be in control of important project activities.
Customize MS Project
Use customized tracking view. In addition to feeding actual start and actual nish dates I believe
that the three important variances viz; duration, start and nish variances are equally important
in monitoring and controlling the project. These numbers provide a multitude of information
which has a deep impact on the project success. I rmly believe that in order to take complete
control of the project it is not only important that the scheduled activities nish on time but also
that the planned activities start as per the scheduled dates.
Graphical Indicators
Made the tracking view visually appealing by inserting graphical indicators in the three
variances column. In order to simplify things made use of simple formulae available in Microsoft
Project itself. There are innumerable sites on the internet that offer several ways by which
graphical indicators can be assigned to columns. However here again I used basic formulae
available in the software and tried not to complicate matters further. Graphic Indicators also
helped a great deal in reporting the project health to the top management as it gave a clear
picture of the present status of the project. The project team had to be made aware of the
discipline required in updating the project plan.
Baseline Plan
Did not forget to baseline the plan. No one can list all activities of a construction project and
more often than not new activities get added in the project schedule. Creating a baseline helps
in tracking the project it also helps in predicting the accuracy of the planning activities and can
help in highlighting those activities which were not part of the original project scope. Moreover
tracking the project through variances works only when the plan has a baseline.
Resource Plan
6/21/2017 Fundamentals of Project Planning and Scheduling – MilestoneTask
https://milestonetask.com/2013/02/17/fundamentals­of­project­planning­and­scheduling/ 4/9
The resources in terms of men, material and equipment were captured in the schedule.
Resources in order to complete a particular activity were mobilized well in advance. A weekly
look ahead schedule with well de ned resource requirement provided much required insight to
the project team members as well as resource managers responsible to ensure availability of
resources at site.
Communication Loop
Established a seamless communication loop with the site, suppliers, process engineers so that
information can be ascertained in a real time basis. Communication and feed back regarding
commencement of planned activities and bottle necks if any is of great importance in having a
complete control on the project. With out a well de ned communication and feed back loop
Project Manager and his other team members will face considerable dif culties in addressing
the situation and if these issues that surface on a daily basis are not resolved in time will
eventually become a serious situation hampering the project progress. A routine exchange of
information among various stake holders facilitated in speedy execution of the project well with
in the project sponsors expectations.
Tracking and Updating
Once the new schedule was in place activities were tracked on a daily basis, due to relentless
monitoring and control nally resulted in a Negative Finish Variance. This turnaround was not
easily accepted by the project sponsor as the sponsor’s believed that the challenge put forward
was too dif cult for anyone to overcome. However, after observing the schedule closely and
comparing the actual progress at site repeatedly the project sponsor had to admit that the
project is ahead of schedule without any compromise in quality and safety standards.
Conclusion
The crux of the matter is that if the fundamentals of planning and scheduling are applied
without any compromise the chances that the project schedule would slip is fairly limited and to
very large extent predictable. The bottom line is that the slippages in the schedule can be
recovered with a systematic approach to scheduling and planning. However the ability to do so
rests obviously with the Project Manager and his leadership capabilities.
Share this:
    1
More
Loading...
Related
6/21/2017 Fundamentals of Project Planning and Scheduling – MilestoneTask
https://milestonetask.com/2013/02/17/fundamentals­of­project­planning­and­scheduling/ 5/9
6 thoughts on “Fundamentals of Project Planning
and Scheduling”
 Schedule Management  Control, Management, Monitor, Plan, Project, Schedule
EDIT
Perils of Matrix Organisation
Structure
In "Organizational Structures"
15 Bene ts of a Project
Management Plan
In "Integration Management"
How to prepare an effective daily
project execution plan?
In "Schedule Management"

Atul Gaur / October 8, 2014 at 8:04 PM / Edit
Thank you for sharing this information
Like
Reply

Kylie Wilson / September 23, 2014 at 5:41 PM / Edit
To be successful in your career, a positive interaction with people
working around is a key. In a similar manner, it is extremely important to
identify and manage stakeholders. Stakeholder
management is important to the
success of every project. Involving and engaging with the right people in a
positive manner is highly important for project success.
Like
Reply

Atul Gaur / April 18, 2013 at 6:13 PM / Edit
Thank you!
Like
Reply

micheal lewis / April 13, 2013 at 5:59 PM / Edit
I appreciate you for sharing such a fabulous info with me. i need to learn updates like Atul you have shared
with me as i hold project management system of a software house now i manage my new projects exactly
like the points that you have describe by your article.
Like
Reply
6/21/2017 Fundamentals of Project Planning and Scheduling – MilestoneTask
https://milestonetask.com/2013/02/17/fundamentals­of­project­planning­and­scheduling/ 6/9
Leave a Reply
← 5 ASPECTS OF PROJECT MANAGEMENT 10 PROJECT MANAGEMENT PITFALLS TO AVOID →
Recent Posts
Earned Value Management: An Integrated Approach To Performance Measurement
June 16, 2017
Wrong Cost Estimates? – Solutions to Improve Project Pro‹tability
June 8, 2017
Bene‹ts of PMP Certi‹cation
June 1, 2017
A Step-by-Step Guide To PMP Certi‹cation
May 25, 2017
12 Essentials for a Project Manager
April 22, 2017
Categories

Atul Gaur / March 30, 2013 at 12:41 PM / Edit
Thanks a lot Pamela.
Like
Reply

Pamela Wilson / March 26, 2013 at 11:09 PM / Edit
Thanks for sharing the tips on how to plan and schedule a project. With companies outsourcing major
portions of a project to foreign countries, the project managers often have to work in a global
environment. The information will help readers in understanding various aspects of project management
with a few minutes.
Like
Reply
Enter your comment here...
6/21/2017 Fundamentals of Project Planning and Scheduling – MilestoneTask
https://milestonetask.com/2013/02/17/fundamentals­of­project­planning­and­scheduling/ 7/9
Earned Value Management: An Integrated Approach To Performance
Measurement
About
A Step-by-Step Guide To PMP Certi‹cation
When a project team member fails to deliver?
Project Success and Productivity
Categories
Select Category
Most Popular
Tags
Advantages
Control
Factors
Management
Monitor
Plan
Project
Schedule
Success
Team
Social
   
Facebook Page
Menu
Home
MilestoneTask
124 likes
Liked Share
6/21/2017 Fundamentals of Project Planning and Scheduling – MilestoneTask
https://milestonetask.com/2013/02/17/fundamentals­of­project­planning­and­scheduling/ 8/9
About
Author
Competencies
Experience
Contact
Blog
Awards
Resources
EVM Formulas
Archives
Select Month
Follow Blog via Email
Join 437 other followers
Follow
SOCIAL
      
FEEDS
 RSS - Posts
6/21/2017 Fundamentals of Project Planning and Scheduling – MilestoneTask
https://milestonetask.com/2013/02/17/fundamentals­of­project­planning­and­scheduling/ 9/9
Home About Contact Blog Awards Resources

More Related Content

What's hot

Building a-project-schedule
Building a-project-scheduleBuilding a-project-schedule
Building a-project-scheduleRaaz Karkee
 
Project Schedule Planning and Development - A Guide to Develop Reliable Proje...
Project Schedule Planning and Development - A Guide to Develop Reliable Proje...Project Schedule Planning and Development - A Guide to Develop Reliable Proje...
Project Schedule Planning and Development - A Guide to Develop Reliable Proje...Indra Pandu Prasetyo
 
Project time management
Project time managementProject time management
Project time managementJivan Nepali
 
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...IRJET Journal
 
project time management
 project time management project time management
project time managementHira Atiq
 
EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget InitiativesEPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget InitiativesEPC Group
 
Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013Chetanraj M
 
Scheduling of a five story residential apartment project
Scheduling of a five story residential apartment project Scheduling of a five story residential apartment project
Scheduling of a five story residential apartment project kaishwarya3
 
Primavara
PrimavaraPrimavara
Primavaradanabl
 
Project network scheduling and S-curve
Project network scheduling and S-curve Project network scheduling and S-curve
Project network scheduling and S-curve Satish Yadavalli
 
SDPM (Success Driven Project Management)
SDPM (Success Driven Project Management)SDPM (Success Driven Project Management)
SDPM (Success Driven Project Management)Peter Mello
 
Project management : Pert and Cpm
Project management : Pert and CpmProject management : Pert and Cpm
Project management : Pert and CpmShashank Kapoor
 
Project management-plan template
Project management-plan templateProject management-plan template
Project management-plan templateVivek Srivastava
 

What's hot (18)

Building a-project-schedule
Building a-project-scheduleBuilding a-project-schedule
Building a-project-schedule
 
Project Schedule Planning and Development - A Guide to Develop Reliable Proje...
Project Schedule Planning and Development - A Guide to Develop Reliable Proje...Project Schedule Planning and Development - A Guide to Develop Reliable Proje...
Project Schedule Planning and Development - A Guide to Develop Reliable Proje...
 
Primavera P6
Primavera P6Primavera P6
Primavera P6
 
Project time
Project timeProject time
Project time
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
Project time management
Project time managementProject time management
Project time management
 
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
project time management
 project time management project time management
project time management
 
EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget InitiativesEPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
 
Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013
 
MS Project 2010 Training
MS Project 2010 TrainingMS Project 2010 Training
MS Project 2010 Training
 
Scheduling of a five story residential apartment project
Scheduling of a five story residential apartment project Scheduling of a five story residential apartment project
Scheduling of a five story residential apartment project
 
Primavara
PrimavaraPrimavara
Primavara
 
Project network scheduling and S-curve
Project network scheduling and S-curve Project network scheduling and S-curve
Project network scheduling and S-curve
 
SDPM (Success Driven Project Management)
SDPM (Success Driven Project Management)SDPM (Success Driven Project Management)
SDPM (Success Driven Project Management)
 
Project management : Pert and Cpm
Project management : Pert and CpmProject management : Pert and Cpm
Project management : Pert and Cpm
 
Project management-plan template
Project management-plan templateProject management-plan template
Project management-plan template
 

Similar to Fundamentals of project planning and scheduling

Module Three Project Scope, Planning, and Time Management.docx
Module Three Project Scope, Planning, and Time Management.docxModule Three Project Scope, Planning, and Time Management.docx
Module Three Project Scope, Planning, and Time Management.docxgilpinleeanna
 
76 s201905
76 s20190576 s201905
76 s201905IJRAT
 
Planning for it project success it-toolkits
Planning for it project success   it-toolkitsPlanning for it project success   it-toolkits
Planning for it project success it-toolkitsIT-Toolkits.org
 
Good scheduling practice
Good scheduling practiceGood scheduling practice
Good scheduling practicekrunalchem
 
Project Life Cycle final.pptx
Project Life Cycle final.pptxProject Life Cycle final.pptx
Project Life Cycle final.pptxPranshiGoyal2
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800PRIYANSHU KUMAR
 
Project scheduling
Project schedulingProject scheduling
Project schedulingJaafer Saeed
 
Advanced project management mod 3
Advanced project management mod 3Advanced project management mod 3
Advanced project management mod 3POOJA UDAYAN
 
Planning and scheduling Techniques.ppt
Planning and scheduling  Techniques.pptPlanning and scheduling  Techniques.ppt
Planning and scheduling Techniques.pptDejeneTsegaye6
 
Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and schedulingAditi Garg
 
Project Planning & Management
Project Planning & Management Project Planning & Management
Project Planning & Management Kashif-khan
 
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct ScienceWhy Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct ScienceAcumen
 
Effective Project Management
Effective Project ManagementEffective Project Management
Effective Project ManagementBinary Semantics
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedulesHatem Hegazi
 
PROJECT PLANNING METHODOLOGIES.pdf
PROJECT  PLANNING METHODOLOGIES.pdfPROJECT  PLANNING METHODOLOGIES.pdf
PROJECT PLANNING METHODOLOGIES.pdfSurashmie Kaalmegh
 
5 project management project planning
5 project management  project planning5 project management  project planning
5 project management project planningYasirHamour
 

Similar to Fundamentals of project planning and scheduling (20)

Module Three Project Scope, Planning, and Time Management.docx
Module Three Project Scope, Planning, and Time Management.docxModule Three Project Scope, Planning, and Time Management.docx
Module Three Project Scope, Planning, and Time Management.docx
 
76 s201905
76 s20190576 s201905
76 s201905
 
Planning for it project success it-toolkits
Planning for it project success   it-toolkitsPlanning for it project success   it-toolkits
Planning for it project success it-toolkits
 
Good scheduling practice
Good scheduling practiceGood scheduling practice
Good scheduling practice
 
Project Life Cycle final.pptx
Project Life Cycle final.pptxProject Life Cycle final.pptx
Project Life Cycle final.pptx
 
PROJECT PLANNING
PROJECT PLANNINGPROJECT PLANNING
PROJECT PLANNING
 
Unit II.pptx
Unit II.pptxUnit II.pptx
Unit II.pptx
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Advanced project management mod 3
Advanced project management mod 3Advanced project management mod 3
Advanced project management mod 3
 
Planning and scheduling Techniques.ppt
Planning and scheduling  Techniques.pptPlanning and scheduling  Techniques.ppt
Planning and scheduling Techniques.ppt
 
Planning And Managing The Project
Planning And Managing The ProjectPlanning And Managing The Project
Planning And Managing The Project
 
Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and scheduling
 
Project Planning & Management
Project Planning & Management Project Planning & Management
Project Planning & Management
 
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct ScienceWhy Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
 
Effective Project Management
Effective Project ManagementEffective Project Management
Effective Project Management
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedules
 
PROJECT PLANNING METHODOLOGIES.pdf
PROJECT  PLANNING METHODOLOGIES.pdfPROJECT  PLANNING METHODOLOGIES.pdf
PROJECT PLANNING METHODOLOGIES.pdf
 
5 project management project planning
5 project management  project planning5 project management  project planning
5 project management project planning
 

More from Atul Gaur PMP

PMBOK 5th Edition Study Notes
PMBOK 5th Edition Study NotesPMBOK 5th Edition Study Notes
PMBOK 5th Edition Study NotesAtul Gaur PMP
 
A Step-by-Step Guide To PMP Certification
A Step-by-Step Guide To PMP CertificationA Step-by-Step Guide To PMP Certification
A Step-by-Step Guide To PMP CertificationAtul Gaur PMP
 
EVM Techniques To Forecast Project Cost Performance
EVM Techniques To Forecast Project Cost PerformanceEVM Techniques To Forecast Project Cost Performance
EVM Techniques To Forecast Project Cost PerformanceAtul Gaur PMP
 
Project Monitoring Using Cost, Schedule Variance & EVM Performance Indicators
Project Monitoring Using Cost, Schedule Variance & EVM Performance IndicatorsProject Monitoring Using Cost, Schedule Variance & EVM Performance Indicators
Project Monitoring Using Cost, Schedule Variance & EVM Performance IndicatorsAtul Gaur PMP
 
Earned Value Management An Integrated Approach To Performance Measurement
Earned Value Management An Integrated Approach To Performance MeasurementEarned Value Management An Integrated Approach To Performance Measurement
Earned Value Management An Integrated Approach To Performance MeasurementAtul Gaur PMP
 
Earned Value Management Example Article by Atul Gaur PMP
Earned Value Management Example Article by Atul Gaur PMPEarned Value Management Example Article by Atul Gaur PMP
Earned Value Management Example Article by Atul Gaur PMPAtul Gaur PMP
 
Project Management Competencies Atul Gaur PMP
Project Management Competencies Atul Gaur PMPProject Management Competencies Atul Gaur PMP
Project Management Competencies Atul Gaur PMPAtul Gaur PMP
 
Changes to Sixth Edition of PMBOK
Changes to Sixth Edition of PMBOKChanges to Sixth Edition of PMBOK
Changes to Sixth Edition of PMBOKAtul Gaur PMP
 
Critical path analysis solved example
Critical path analysis solved exampleCritical path analysis solved example
Critical path analysis solved exampleAtul Gaur PMP
 
BioMethanated Spent Wash Evaporator Project
BioMethanated Spent Wash Evaporator ProjectBioMethanated Spent Wash Evaporator Project
BioMethanated Spent Wash Evaporator ProjectAtul Gaur PMP
 

More from Atul Gaur PMP (11)

PMBOK 5th Edition Study Notes
PMBOK 5th Edition Study NotesPMBOK 5th Edition Study Notes
PMBOK 5th Edition Study Notes
 
A Step-by-Step Guide To PMP Certification
A Step-by-Step Guide To PMP CertificationA Step-by-Step Guide To PMP Certification
A Step-by-Step Guide To PMP Certification
 
EVM Techniques To Forecast Project Cost Performance
EVM Techniques To Forecast Project Cost PerformanceEVM Techniques To Forecast Project Cost Performance
EVM Techniques To Forecast Project Cost Performance
 
Project Monitoring Using Cost, Schedule Variance & EVM Performance Indicators
Project Monitoring Using Cost, Schedule Variance & EVM Performance IndicatorsProject Monitoring Using Cost, Schedule Variance & EVM Performance Indicators
Project Monitoring Using Cost, Schedule Variance & EVM Performance Indicators
 
Earned Value Management An Integrated Approach To Performance Measurement
Earned Value Management An Integrated Approach To Performance MeasurementEarned Value Management An Integrated Approach To Performance Measurement
Earned Value Management An Integrated Approach To Performance Measurement
 
Earned Value Management Example Article by Atul Gaur PMP
Earned Value Management Example Article by Atul Gaur PMPEarned Value Management Example Article by Atul Gaur PMP
Earned Value Management Example Article by Atul Gaur PMP
 
Project Management Competencies Atul Gaur PMP
Project Management Competencies Atul Gaur PMPProject Management Competencies Atul Gaur PMP
Project Management Competencies Atul Gaur PMP
 
Changes to Sixth Edition of PMBOK
Changes to Sixth Edition of PMBOKChanges to Sixth Edition of PMBOK
Changes to Sixth Edition of PMBOK
 
Critical path analysis solved example
Critical path analysis solved exampleCritical path analysis solved example
Critical path analysis solved example
 
PMP Exam Formulas
PMP Exam FormulasPMP Exam Formulas
PMP Exam Formulas
 
BioMethanated Spent Wash Evaporator Project
BioMethanated Spent Wash Evaporator ProjectBioMethanated Spent Wash Evaporator Project
BioMethanated Spent Wash Evaporator Project
 

Recently uploaded

Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGpr788182
 
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...Puja Sharma
 
KOTA 💋 Call Girl 9827461493 Call Girls in Escort service book now
KOTA 💋 Call Girl 9827461493 Call Girls in  Escort service book nowKOTA 💋 Call Girl 9827461493 Call Girls in  Escort service book now
KOTA 💋 Call Girl 9827461493 Call Girls in Escort service book nowkapoorjyoti4444
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Falcon Invoice Discounting
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfwill854175
 
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in PakistanChallenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistanvineshkumarsajnani12
 
Berhampur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Berhampur Call Girl Just Call 8084732287 Top Class Call Girl Service AvailableBerhampur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Berhampur Call Girl Just Call 8084732287 Top Class Call Girl Service Availablepr788182
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwaitdaisycvs
 
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165meghakumariji156
 
Bangalore Call Girl Just Call♥️ 8084732287 ♥️Top Class Call Girl Service Avai...
Bangalore Call Girl Just Call♥️ 8084732287 ♥️Top Class Call Girl Service Avai...Bangalore Call Girl Just Call♥️ 8084732287 ♥️Top Class Call Girl Service Avai...
Bangalore Call Girl Just Call♥️ 8084732287 ♥️Top Class Call Girl Service Avai...pr788182
 
GUWAHATI 💋 Call Girl 9827461493 Call Girls in Escort service book now
GUWAHATI 💋 Call Girl 9827461493 Call Girls in  Escort service book nowGUWAHATI 💋 Call Girl 9827461493 Call Girls in  Escort service book now
GUWAHATI 💋 Call Girl 9827461493 Call Girls in Escort service book nowkapoorjyoti4444
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1kcpayne
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAITim Wilson
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting
 
PARK STREET 💋 Call Girl 9827461493 Call Girls in Escort service book now
PARK STREET 💋 Call Girl 9827461493 Call Girls in  Escort service book nowPARK STREET 💋 Call Girl 9827461493 Call Girls in  Escort service book now
PARK STREET 💋 Call Girl 9827461493 Call Girls in Escort service book nowkapoorjyoti4444
 
Cuttack Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Cuttack Call Girl Just Call 8084732287 Top Class Call Girl Service AvailableCuttack Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Cuttack Call Girl Just Call 8084732287 Top Class Call Girl Service Availablepr788182
 
Puri CALL GIRL ❤️8084732287❤️ CALL GIRLS IN ESCORT SERVICE WE ARW PROVIDING
Puri CALL GIRL ❤️8084732287❤️ CALL GIRLS IN ESCORT SERVICE WE ARW PROVIDINGPuri CALL GIRL ❤️8084732287❤️ CALL GIRLS IN ESCORT SERVICE WE ARW PROVIDING
Puri CALL GIRL ❤️8084732287❤️ CALL GIRLS IN ESCORT SERVICE WE ARW PROVIDINGpriyakumari801827
 
Durg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTS
Durg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTSDurg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTS
Durg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTSkajalroy875762
 
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Adnet Communications
 

Recently uploaded (20)

Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
 
KOTA 💋 Call Girl 9827461493 Call Girls in Escort service book now
KOTA 💋 Call Girl 9827461493 Call Girls in  Escort service book nowKOTA 💋 Call Girl 9827461493 Call Girls in  Escort service book now
KOTA 💋 Call Girl 9827461493 Call Girls in Escort service book now
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in PakistanChallenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
 
Berhampur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Berhampur Call Girl Just Call 8084732287 Top Class Call Girl Service AvailableBerhampur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Berhampur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
 
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
 
Bangalore Call Girl Just Call♥️ 8084732287 ♥️Top Class Call Girl Service Avai...
Bangalore Call Girl Just Call♥️ 8084732287 ♥️Top Class Call Girl Service Avai...Bangalore Call Girl Just Call♥️ 8084732287 ♥️Top Class Call Girl Service Avai...
Bangalore Call Girl Just Call♥️ 8084732287 ♥️Top Class Call Girl Service Avai...
 
GUWAHATI 💋 Call Girl 9827461493 Call Girls in Escort service book now
GUWAHATI 💋 Call Girl 9827461493 Call Girls in  Escort service book nowGUWAHATI 💋 Call Girl 9827461493 Call Girls in  Escort service book now
GUWAHATI 💋 Call Girl 9827461493 Call Girls in Escort service book now
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
Buy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail AccountsBuy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail Accounts
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 
PARK STREET 💋 Call Girl 9827461493 Call Girls in Escort service book now
PARK STREET 💋 Call Girl 9827461493 Call Girls in  Escort service book nowPARK STREET 💋 Call Girl 9827461493 Call Girls in  Escort service book now
PARK STREET 💋 Call Girl 9827461493 Call Girls in Escort service book now
 
Cuttack Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Cuttack Call Girl Just Call 8084732287 Top Class Call Girl Service AvailableCuttack Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Cuttack Call Girl Just Call 8084732287 Top Class Call Girl Service Available
 
Puri CALL GIRL ❤️8084732287❤️ CALL GIRLS IN ESCORT SERVICE WE ARW PROVIDING
Puri CALL GIRL ❤️8084732287❤️ CALL GIRLS IN ESCORT SERVICE WE ARW PROVIDINGPuri CALL GIRL ❤️8084732287❤️ CALL GIRLS IN ESCORT SERVICE WE ARW PROVIDING
Puri CALL GIRL ❤️8084732287❤️ CALL GIRLS IN ESCORT SERVICE WE ARW PROVIDING
 
Durg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTS
Durg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTSDurg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTS
Durg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTS
 
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
 

Fundamentals of project planning and scheduling

  • 1. 6/21/2017 Fundamentals of Project Planning and Scheduling – MilestoneTask https://milestonetask.com/2013/02/17/fundamentals­of­project­planning­and­scheduling/ 1/9 MilestoneTask FEBRUARY 17, 2013 BY ATUL GAUR Fundamentals of Project Planning and Scheduling One of my smooth progressing engineering project was suddenly jolted by numerous emails and phone calls from the project sponsor asking the management to expedite activities at site. The project was going on quite smoothly as it had the best plan to back it up and we all hoped that things would go as planned but eventually it did not work out that way.  The project sponsors demanded an unexpected change in the project completion date in order to meet their nancial goals. The complete project schedule had to be reworked in order to meet the client expectations. Important milestones like site mobilization had to be advanced in order to commence construction activities and complete the project as per the new deadlines. Unforeseen Problems As the site team got mobilized we were bombarded with myriad of problems some of them so mundane that we were at times amazed dealing with the slew of such problems. These  MENU
  • 2. 6/21/2017 Fundamentals of Project Planning and Scheduling – MilestoneTask https://milestonetask.com/2013/02/17/fundamentals­of­project­planning­and­scheduling/ 2/9 unexpected and unforeseen problems at site were a serious road blocks to smooth execution of the project and timely completion of project activities. We rst tried to ensure that the existing plan be put to maximum use however the way events had unfolded at the construction site a complete new plan had to be worked out in order to meet the challenging deadline set by the project sponsor. The Project Manager was now expected to turn around things as the Management was under tremendous pressure to show considerable progress at site. The project sponsor was keeping a very close tab on the daily activities and also the overall project schedule. The new plan had to address the lost time and also consider the challenges put forward in terms of reporting the daily and weekly progress and the overall constrained project completion schedule. The established activity schedule with a de ned sequence of activities had to be kept aside as this was written down for normal delivery schedules. Since the activities had to be now completed on a war footing a completely new activity schedule was developed. While developing a new schedule the following was ensured. The subsequent paragraphs describe some fundamental steps followed to develop and implement a new project schedule. Involve the Team Involved all the individuals participating in the execution, enlisted the project activities once again and worked out the correct sequence of activities. Under the heat of the moment it is a tendency to avoid consensus and impose diktats, most of the times schedule developed individually fail and those schedule which are a result of a team work succeed. Simple Logic Kept the schedule logic simple, easy to comprehend and tried to capture the exact sequence in which the activities are likely to be executed. As the construction progresses there are events which force deviation from the agreed sequence of activities, however I believe if the schedule is worked out by taking on board all those involved in the execution, the deviation as a result of external or unforeseen circumstances are likely to be fairly limited. SMART Criteria Activities listed in the project schedule were action oriented, speci c and measurable quantities were assigned to all activities where ever possible. Project Activities Vs Schedule Activities Distinguished between project activities and schedule activities. There is a difference between Schedule activities and project activities. As per the de nition Schedule activities are decomposed from work break down structure and have an estimated cost, duration and resource requirement. Schedule activities are connected to other schedule activities through a logical relationship. If this distinction is not there the project schedule the PM as well as the
  • 3. 6/21/2017 Fundamentals of Project Planning and Scheduling – MilestoneTask https://milestonetask.com/2013/02/17/fundamentals­of­project­planning­and­scheduling/ 3/9 project team ends up diverting their energies to project activities which has less signi cance on the project completion. This hampers project progress and eventually affects project cost as well as stake holder satisfaction. The Critical Path Included critical activities pertaining to project sponsor in the activity schedule as this helps in better coordination with the project sponsor and gives a complete overview of the project. This also allows project sponsor to undertake planning of important milestones like trials, joint inspections etc. Clearly highlighted activities that fall on Critical Path. This obviates the need to continuously scroll the Gantt chart to hunt for critical activities or navigate through various menu options to get a list of critical activities. This facilitates project manager to continuously monitor and control the critical activities and be in control of important project activities. Customize MS Project Use customized tracking view. In addition to feeding actual start and actual nish dates I believe that the three important variances viz; duration, start and nish variances are equally important in monitoring and controlling the project. These numbers provide a multitude of information which has a deep impact on the project success. I rmly believe that in order to take complete control of the project it is not only important that the scheduled activities nish on time but also that the planned activities start as per the scheduled dates. Graphical Indicators Made the tracking view visually appealing by inserting graphical indicators in the three variances column. In order to simplify things made use of simple formulae available in Microsoft Project itself. There are innumerable sites on the internet that offer several ways by which graphical indicators can be assigned to columns. However here again I used basic formulae available in the software and tried not to complicate matters further. Graphic Indicators also helped a great deal in reporting the project health to the top management as it gave a clear picture of the present status of the project. The project team had to be made aware of the discipline required in updating the project plan. Baseline Plan Did not forget to baseline the plan. No one can list all activities of a construction project and more often than not new activities get added in the project schedule. Creating a baseline helps in tracking the project it also helps in predicting the accuracy of the planning activities and can help in highlighting those activities which were not part of the original project scope. Moreover tracking the project through variances works only when the plan has a baseline. Resource Plan
  • 4. 6/21/2017 Fundamentals of Project Planning and Scheduling – MilestoneTask https://milestonetask.com/2013/02/17/fundamentals­of­project­planning­and­scheduling/ 4/9 The resources in terms of men, material and equipment were captured in the schedule. Resources in order to complete a particular activity were mobilized well in advance. A weekly look ahead schedule with well de ned resource requirement provided much required insight to the project team members as well as resource managers responsible to ensure availability of resources at site. Communication Loop Established a seamless communication loop with the site, suppliers, process engineers so that information can be ascertained in a real time basis. Communication and feed back regarding commencement of planned activities and bottle necks if any is of great importance in having a complete control on the project. With out a well de ned communication and feed back loop Project Manager and his other team members will face considerable dif culties in addressing the situation and if these issues that surface on a daily basis are not resolved in time will eventually become a serious situation hampering the project progress. A routine exchange of information among various stake holders facilitated in speedy execution of the project well with in the project sponsors expectations. Tracking and Updating Once the new schedule was in place activities were tracked on a daily basis, due to relentless monitoring and control nally resulted in a Negative Finish Variance. This turnaround was not easily accepted by the project sponsor as the sponsor’s believed that the challenge put forward was too dif cult for anyone to overcome. However, after observing the schedule closely and comparing the actual progress at site repeatedly the project sponsor had to admit that the project is ahead of schedule without any compromise in quality and safety standards. Conclusion The crux of the matter is that if the fundamentals of planning and scheduling are applied without any compromise the chances that the project schedule would slip is fairly limited and to very large extent predictable. The bottom line is that the slippages in the schedule can be recovered with a systematic approach to scheduling and planning. However the ability to do so rests obviously with the Project Manager and his leadership capabilities. Share this:     1 More Loading... Related
  • 5. 6/21/2017 Fundamentals of Project Planning and Scheduling – MilestoneTask https://milestonetask.com/2013/02/17/fundamentals­of­project­planning­and­scheduling/ 5/9 6 thoughts on “Fundamentals of Project Planning and Scheduling”  Schedule Management  Control, Management, Monitor, Plan, Project, Schedule EDIT Perils of Matrix Organisation Structure In "Organizational Structures" 15 Bene ts of a Project Management Plan In "Integration Management" How to prepare an effective daily project execution plan? In "Schedule Management"  Atul Gaur / October 8, 2014 at 8:04 PM / Edit Thank you for sharing this information Like Reply  Kylie Wilson / September 23, 2014 at 5:41 PM / Edit To be successful in your career, a positive interaction with people working around is a key. In a similar manner, it is extremely important to identify and manage stakeholders. Stakeholder management is important to the success of every project. Involving and engaging with the right people in a positive manner is highly important for project success. Like Reply  Atul Gaur / April 18, 2013 at 6:13 PM / Edit Thank you! Like Reply  micheal lewis / April 13, 2013 at 5:59 PM / Edit I appreciate you for sharing such a fabulous info with me. i need to learn updates like Atul you have shared with me as i hold project management system of a software house now i manage my new projects exactly like the points that you have describe by your article. Like Reply
  • 6. 6/21/2017 Fundamentals of Project Planning and Scheduling – MilestoneTask https://milestonetask.com/2013/02/17/fundamentals­of­project­planning­and­scheduling/ 6/9 Leave a Reply ← 5 ASPECTS OF PROJECT MANAGEMENT 10 PROJECT MANAGEMENT PITFALLS TO AVOID → Recent Posts Earned Value Management: An Integrated Approach To Performance Measurement June 16, 2017 Wrong Cost Estimates? – Solutions to Improve Project Pro‹tability June 8, 2017 Bene‹ts of PMP Certi‹cation June 1, 2017 A Step-by-Step Guide To PMP Certi‹cation May 25, 2017 12 Essentials for a Project Manager April 22, 2017 Categories  Atul Gaur / March 30, 2013 at 12:41 PM / Edit Thanks a lot Pamela. Like Reply  Pamela Wilson / March 26, 2013 at 11:09 PM / Edit Thanks for sharing the tips on how to plan and schedule a project. With companies outsourcing major portions of a project to foreign countries, the project managers often have to work in a global environment. The information will help readers in understanding various aspects of project management with a few minutes. Like Reply Enter your comment here...
  • 7. 6/21/2017 Fundamentals of Project Planning and Scheduling – MilestoneTask https://milestonetask.com/2013/02/17/fundamentals­of­project­planning­and­scheduling/ 7/9 Earned Value Management: An Integrated Approach To Performance Measurement About A Step-by-Step Guide To PMP Certi‹cation When a project team member fails to deliver? Project Success and Productivity Categories Select Category Most Popular Tags Advantages Control Factors Management Monitor Plan Project Schedule Success Team Social     Facebook Page Menu Home MilestoneTask 124 likes Liked Share