Project Fact Sheet
Project Name: Physiotherapy Hydropool refurbishment –
Budget code OT0006
Location: Physiotherapy Department
Stage: Delivered
Client representative: Ann Dring - Therapy Services Manager & AHP Lead
Core Clinical & Support Services Division
Senior Project Manager (Capital): Alessandro Annunziata
Head of Capital Projects: John Brierley
Director of Estates: Phil Eagles
Project Update:
• Project completed in May 2016
• In Defects until May 2017
Project Brief:
In 2015, Milton Keynes University Hospital NHS Foundation Trust stated its intentions that the
hydrotherapy pool was very dated and the changing rooms were small and not easily disabled
accessible. Radiators & pipe work were rusty, window seals were hanging down, poolside
floor was not up to latest non slip standards, blown plaster due to leaking showers and water
drips into pool from leaking roof.
Construction works to create adequate areas for effective and efficient use of the hydropool
include as follows:
• Alteration of partition walls to
reconfigure the layout of both
changing rooms.
• New mechanical ventilation with
hygienic air grilles and heat recovery
• Hot and cold water services for
clinical sink and showers
• New windows with triple glazed
• New high levels luminaries in LED
• New clear rooflights in triple skins
• New insulation at roof level to reduce
condensation and heating cost
• Presence Detectors (PIR sensors)
designed to switch off lights if an
area is unoccupied
• New wireless emergency call system
• New hygienic Glass Reinforced
Polyester (GRP) doors
• New wall cladding in tiles
• New flooring in antislip ceramic tiles
Construction Project Team:
Project Manager: Alessandro Annunziata Lead Designer Alessandro Annunziata
Main Contractor Parias Commercial Interiors Ltd
Roofing Contractor Fenland Flat Roofing Ltd
Project Facts & Figures:
Budget: £230,000.00 Funding Source: Capital
Tendering: single stage with priced schedule of works
Contract: JCT Minor works
2nd
Tendering for roofing works only.

More Related Content

Similar to MKUH Physiotherapy Hydropool refurbishment Project Fact Sheet 2015

MKUH Project Fact Sheet Barium Project 2015
MKUH Project Fact Sheet Barium Project 2015MKUH Project Fact Sheet Barium Project 2015
MKUH Project Fact Sheet Barium Project 2015Alessandro Annunziata
 
MKUH Project Fact Sheet X-Ray room 3 & 4
MKUH Project Fact Sheet X-Ray room 3 & 4MKUH Project Fact Sheet X-Ray room 3 & 4
MKUH Project Fact Sheet X-Ray room 3 & 4Alessandro Annunziata
 
ICE Case Study 2016
ICE Case Study 2016ICE Case Study 2016
ICE Case Study 2016Steve Edgson
 
Green one- The first 5 Star Rated SVAGRIHA Project
Green one- The first 5 Star Rated SVAGRIHA ProjectGreen one- The first 5 Star Rated SVAGRIHA Project
Green one- The first 5 Star Rated SVAGRIHA ProjectNilanjan Bhowal
 
Healthcare projects 2013
Healthcare projects 2013Healthcare projects 2013
Healthcare projects 2013roger_lawson
 
Building services-i (2)
Building services-i (2)Building services-i (2)
Building services-i (2)Lwj Welson
 
DJC Top Projects 2015 - Breathe Building Project Description - Final
DJC Top Projects 2015 - Breathe Building Project Description - FinalDJC Top Projects 2015 - Breathe Building Project Description - Final
DJC Top Projects 2015 - Breathe Building Project Description - FinalChris Humphries
 
[Nordic GBC Conference 2013] Ville Reinikainen: Renewal of Meilahti Tower Hos...
[Nordic GBC Conference 2013] Ville Reinikainen: Renewal of Meilahti Tower Hos...[Nordic GBC Conference 2013] Ville Reinikainen: Renewal of Meilahti Tower Hos...
[Nordic GBC Conference 2013] Ville Reinikainen: Renewal of Meilahti Tower Hos...GBC Finland
 
Roof replacement and internal remedial works
Roof replacement and internal remedial worksRoof replacement and internal remedial works
Roof replacement and internal remedial worksgrahamelanders
 
IAED 342-Research Presentation
IAED 342-Research PresentationIAED 342-Research Presentation
IAED 342-Research PresentationSerra's Art Studio
 
How to design and construct a 18ha commercial nursery
How to design and construct a 18ha commercial nurseryHow to design and construct a 18ha commercial nursery
How to design and construct a 18ha commercial nurseryvekadviesgroep
 
Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...
Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...
Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...Blake Morgan
 
Experiences in Barcelona: Energy-efficient refurbishment in residential build...
Experiences in Barcelona: Energy-efficient refurbishment in residential build...Experiences in Barcelona: Energy-efficient refurbishment in residential build...
Experiences in Barcelona: Energy-efficient refurbishment in residential build...GrowSmarter
 
Office fit out from Dribuild
Office fit out from DribuildOffice fit out from Dribuild
Office fit out from DribuildMichael McVey
 
MicroVent: Energy-Efficient, Façade-Integrated Ventilation Systems with Heat ...
MicroVent: Energy-Efficient, Façade-Integrated Ventilation Systems with Heat ...MicroVent: Energy-Efficient, Façade-Integrated Ventilation Systems with Heat ...
MicroVent: Energy-Efficient, Façade-Integrated Ventilation Systems with Heat ...RINNO
 
Ppt5 exp lonodn - kevin cope & alex yakimov ( imperial college ) data cent...
Ppt5   exp lonodn - kevin cope & alex yakimov ( imperial college )  data cent...Ppt5   exp lonodn - kevin cope & alex yakimov ( imperial college )  data cent...
Ppt5 exp lonodn - kevin cope & alex yakimov ( imperial college ) data cent...JISC's Green ICT Programme
 

Similar to MKUH Physiotherapy Hydropool refurbishment Project Fact Sheet 2015 (20)

MKUH Project Fact Sheet Barium Project 2015
MKUH Project Fact Sheet Barium Project 2015MKUH Project Fact Sheet Barium Project 2015
MKUH Project Fact Sheet Barium Project 2015
 
MKUH Project Fact Sheet X-Ray room 3 & 4
MKUH Project Fact Sheet X-Ray room 3 & 4MKUH Project Fact Sheet X-Ray room 3 & 4
MKUH Project Fact Sheet X-Ray room 3 & 4
 
Murray Ward - PM report
Murray Ward - PM reportMurray Ward - PM report
Murray Ward - PM report
 
ICE Case Study 2016
ICE Case Study 2016ICE Case Study 2016
ICE Case Study 2016
 
Green one- The first 5 Star Rated SVAGRIHA Project
Green one- The first 5 Star Rated SVAGRIHA ProjectGreen one- The first 5 Star Rated SVAGRIHA Project
Green one- The first 5 Star Rated SVAGRIHA Project
 
Healthcare projects 2013
Healthcare projects 2013Healthcare projects 2013
Healthcare projects 2013
 
BREEAM
BREEAMBREEAM
BREEAM
 
Building services-i (2)
Building services-i (2)Building services-i (2)
Building services-i (2)
 
DJC Top Projects 2015 - Breathe Building Project Description - Final
DJC Top Projects 2015 - Breathe Building Project Description - FinalDJC Top Projects 2015 - Breathe Building Project Description - Final
DJC Top Projects 2015 - Breathe Building Project Description - Final
 
[Nordic GBC Conference 2013] Ville Reinikainen: Renewal of Meilahti Tower Hos...
[Nordic GBC Conference 2013] Ville Reinikainen: Renewal of Meilahti Tower Hos...[Nordic GBC Conference 2013] Ville Reinikainen: Renewal of Meilahti Tower Hos...
[Nordic GBC Conference 2013] Ville Reinikainen: Renewal of Meilahti Tower Hos...
 
Roof replacement and internal remedial works
Roof replacement and internal remedial worksRoof replacement and internal remedial works
Roof replacement and internal remedial works
 
IAED 342-Research Presentation
IAED 342-Research PresentationIAED 342-Research Presentation
IAED 342-Research Presentation
 
Ne zer+ d2+2+nzebr+success+cases
Ne zer+ d2+2+nzebr+success+casesNe zer+ d2+2+nzebr+success+cases
Ne zer+ d2+2+nzebr+success+cases
 
How to design and construct a 18ha commercial nursery
How to design and construct a 18ha commercial nurseryHow to design and construct a 18ha commercial nursery
How to design and construct a 18ha commercial nursery
 
Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...
Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...
Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...
 
Experiences in Barcelona: Energy-efficient refurbishment in residential build...
Experiences in Barcelona: Energy-efficient refurbishment in residential build...Experiences in Barcelona: Energy-efficient refurbishment in residential build...
Experiences in Barcelona: Energy-efficient refurbishment in residential build...
 
Innovation Forum @ Klimainfisso | Roberto Lollini (EURAC)
Innovation Forum @ Klimainfisso | Roberto Lollini (EURAC)Innovation Forum @ Klimainfisso | Roberto Lollini (EURAC)
Innovation Forum @ Klimainfisso | Roberto Lollini (EURAC)
 
Office fit out from Dribuild
Office fit out from DribuildOffice fit out from Dribuild
Office fit out from Dribuild
 
MicroVent: Energy-Efficient, Façade-Integrated Ventilation Systems with Heat ...
MicroVent: Energy-Efficient, Façade-Integrated Ventilation Systems with Heat ...MicroVent: Energy-Efficient, Façade-Integrated Ventilation Systems with Heat ...
MicroVent: Energy-Efficient, Façade-Integrated Ventilation Systems with Heat ...
 
Ppt5 exp lonodn - kevin cope & alex yakimov ( imperial college ) data cent...
Ppt5   exp lonodn - kevin cope & alex yakimov ( imperial college )  data cent...Ppt5   exp lonodn - kevin cope & alex yakimov ( imperial college )  data cent...
Ppt5 exp lonodn - kevin cope & alex yakimov ( imperial college ) data cent...
 

More from Alessandro Annunziata

More from Alessandro Annunziata (12)

MKUH X-Ray room 3 & 4 - After works
MKUH X-Ray room 3 & 4 - After worksMKUH X-Ray room 3 & 4 - After works
MKUH X-Ray room 3 & 4 - After works
 
MKUH X-Ray room 3 & 4 - Before works
MKUH X-Ray room 3 & 4 - Before worksMKUH X-Ray room 3 & 4 - Before works
MKUH X-Ray room 3 & 4 - Before works
 
MKUH Cook Chill project - Before & after works
MKUH Cook Chill project - Before & after worksMKUH Cook Chill project - Before & after works
MKUH Cook Chill project - Before & after works
 
MKUH Barium project -After works
MKUH Barium project -After worksMKUH Barium project -After works
MKUH Barium project -After works
 
MKUH Barium project - Before works
MKUH Barium project - Before worksMKUH Barium project - Before works
MKUH Barium project - Before works
 
MKUH Physiotherapy Hydropool refurbishment - After works
MKUH Physiotherapy Hydropool refurbishment - After worksMKUH Physiotherapy Hydropool refurbishment - After works
MKUH Physiotherapy Hydropool refurbishment - After works
 
MKUH Physiotherapy Hydropool refurbishment - Before works
MKUH Physiotherapy Hydropool refurbishment - Before worksMKUH Physiotherapy Hydropool refurbishment - Before works
MKUH Physiotherapy Hydropool refurbishment - Before works
 
Maternity Murray ward - After works
Maternity Murray ward - After worksMaternity Murray ward - After works
Maternity Murray ward - After works
 
Maternity Murray ward - Before refurbishment
Maternity Murray ward - Before refurbishmentMaternity Murray ward - Before refurbishment
Maternity Murray ward - Before refurbishment
 
TB Clinic After
TB Clinic AfterTB Clinic After
TB Clinic After
 
TB Clinic Before
TB Clinic BeforeTB Clinic Before
TB Clinic Before
 
TB Clinic Proposed Layout
TB Clinic Proposed LayoutTB Clinic Proposed Layout
TB Clinic Proposed Layout
 

MKUH Physiotherapy Hydropool refurbishment Project Fact Sheet 2015

  • 1. Project Fact Sheet Project Name: Physiotherapy Hydropool refurbishment – Budget code OT0006 Location: Physiotherapy Department Stage: Delivered Client representative: Ann Dring - Therapy Services Manager & AHP Lead Core Clinical & Support Services Division Senior Project Manager (Capital): Alessandro Annunziata Head of Capital Projects: John Brierley Director of Estates: Phil Eagles Project Update: • Project completed in May 2016 • In Defects until May 2017 Project Brief: In 2015, Milton Keynes University Hospital NHS Foundation Trust stated its intentions that the hydrotherapy pool was very dated and the changing rooms were small and not easily disabled accessible. Radiators & pipe work were rusty, window seals were hanging down, poolside floor was not up to latest non slip standards, blown plaster due to leaking showers and water drips into pool from leaking roof. Construction works to create adequate areas for effective and efficient use of the hydropool include as follows: • Alteration of partition walls to reconfigure the layout of both changing rooms. • New mechanical ventilation with hygienic air grilles and heat recovery • Hot and cold water services for clinical sink and showers • New windows with triple glazed • New high levels luminaries in LED • New clear rooflights in triple skins • New insulation at roof level to reduce condensation and heating cost • Presence Detectors (PIR sensors) designed to switch off lights if an area is unoccupied • New wireless emergency call system • New hygienic Glass Reinforced Polyester (GRP) doors • New wall cladding in tiles • New flooring in antislip ceramic tiles Construction Project Team: Project Manager: Alessandro Annunziata Lead Designer Alessandro Annunziata Main Contractor Parias Commercial Interiors Ltd Roofing Contractor Fenland Flat Roofing Ltd Project Facts & Figures: Budget: £230,000.00 Funding Source: Capital Tendering: single stage with priced schedule of works Contract: JCT Minor works 2nd Tendering for roofing works only.