SlideShare a Scribd company logo
1 of 42
Download to read offline
Reliability Case Studies
• Reza Emami, P.Eng, PMP
1
Reza Emami
P. Eng, PMP
Currently, Engineering Specialist – Oil & Gas Industry, North America
12 years with Flowserve in various aftermarket roles: Applications
Engineer, Project Engineer, Service & Repair Engineer, Senior Technical
Services Engineer and Engineering Manager
3 years with Bartar Pumps company, Involved in re-engineering and
applications engineering.
2 years with Tarh Negasht company, Design engineer involved in
Computational Fluid Dynamics (CFD) for 3D simulation of flow in
Automotive torque convertors
MSc from Tehran University (Mechanical Engineering)
Presenter
2
Presentation Content
• Failures (they happen…)
• Maintenance Practice Strategies
• Case Studies
3
• RCA for Reliability Based Maintenance
Failures (they happen …)
Key Parameters:
Maintenance
Design
Installation
Manufacturing
Upset Condition
…..
Failures can affect:
Safety
Production
Additional Damages
Additional Spare Parts Cost
Unnecessary Overtime
……
4
Maintenance Practice Strategies
Graph Source: http://www.maintenanceonline.co.uk/article.asp?id=10286
Reliability based
maintenance
RCA (Root cause
analysis) &
appropriate upgrade
solutions to eliminate
the issue
OEE (Overall Equipment Effectiveness) Improvement
OEE Availability x Performance x Quality
5
RCA for Reliability Based Maintenance
RCA (Root cause analysis) & appropriate upgrade solutions for defect elimination
5 Why Concept
https://www.qualitydigest.com/inside/health-care-column/dig-5-whys.html
6
Case Studies
• Case 1 - High Vibration issue – Shipping pump
• Case 2 - Material Upgrade for Erosive Service
• Case 3 - Bearing Upgrade (CH design)
• Case 4 - Multi Stage pump in Amine Service
• Case 5 - Vertical Can Pump –Hydrocarbon Condensate
7
Case 1 - Shipping Pump Vibration
BB3 pump – 10 stages
- Butane / Propane Shipping
Problem:
- High vibration at vane passing
frequency (5X)
- Frequent failures due to
inconsistent abnormal high
vibration.
8
Shipping propane/butane pumps:
- Feed from GL1K ( “cryogenic” LNG)
- Feed from RA1K (refinery GPL )
Two pumps installed
- Pump was sent to factory for repair & tests then shipped back to site & restarted
showing high thrust & radial bearing vibrations at 5X (250 hz) when pumping
butane ~1 hour (colder product) from successful start-up
Case 1 - Shipping Pump Vibration
9
Pump B. tests in Factory (Water Ambient )
Vibration level at 5X (250hz) was very
low in the full operation range
(including minimum flow and minimum
suction pressure).
Case 1 - Shipping Pump Vibration
10
Test on site
Case 1 - Shipping Pump Vibration
11
Test on site
Case 1 - Shipping Pump Vibration
12
Influence of process temperature on Vibration
Possible Causes?
Case 1 - Shipping Pump Vibration
13
5 Vanes
Impellers
Long Cross-Over
All other impellers are 3 Vanes
Case 1 - Shipping Pump Vibration
14
Hz (Acoustic Frequency) =
C (Speed of sound) / WL
(wavelength)
C depends of Fluid property, Passage
dimensions / material
Acoustic Resonance?
Acoustic resonance data are calculated
basis cross over length and speed of sound
in various products:
Acoustic Frequency
- Water 20° 331 Hz
- Butane 20° 221 Hz
- Butane 10° 232 Hz
- Butane 4° 240 Hz
5 vanes x 50 Hz running = 250
Case 1 - Shipping Pump Vibration
15
Conclusions:
- In water (on test platform), the 5X component did not exist.
- In butane
• At start-up, pumping hot product with a critical acoustic frequency below 5X,
no amplification occurs
• As soon as the product becomes colder, the critical acoustic frequency
increases and reaches the 5X frequency causing the measured high pump
vibration by amplification
It was proposed to change to 7 vanes impellers
It was also recommended to change the source of product to RA1K (LPG from
refinery at higher temperature) if possible
Case 1 - Shipping Pump Vibration
16
Re-test with butane at 25°C
Source = RA1K
Half day after start-up
Butane temperature = 25 ̊ C
Vibrations are around 1 mm/s !!!!
17
Case 1 - Shipping Pump Vibration
Site Test Results
18
Case 1 - Shipping Pump Vibration
Case 2 - Erosive Service
Single stage OH pump
- FCC bottom
Problem:
- Existing casing needs replacement every month due
to severe erosion
Possible Causes?
19
EXISTING NEW
Flow (gpm) 790 980
Differential Head (ft) 200 232
Suction pressure
(psig)
27 (29 max) 27 (29 max)
NPSH available (ft) 15 15
Liquid FCC Main Fractionator Bottoms
Oper Temp (°F) 675 (690 max) 675 (690 max)
Viscosity <0.5 cSt <0.5 cSt
Originally Rated Condition
(3x50%)
New Condition (2x100%)
20
Case 2 - Erosive Service
Operating range reviewed and noted
pumps are running toward left of the
curve due to increased demand
Half Flow
Non modified impeller
21
Case 2 - Erosive Service
Generally wear rate is proportional to
the increase of the particle velocity
cubed
Hydraulic Re-rate (Diffuser
Design) proposed along with
material upgrade
Drop-in replacement upgraded
with:
- The casing will not be subject
to high velocities However was
coated with HVOF line of sight
- Future repairs will be limited to
replacement of the wear kit
Upgraded Hydraulics
Upgraded Bearing Frame
22
Case 2 - Erosive Service
Case 3 - Bearing Upgrade
Coker Charge Pump
Problem:
- Ball thrust bearing
failure
23
Root Cause:
- Transient upset
condition could not
be avoided
24
Case 3 - Bearing Upgrade
Self contained CH bearing assembly (Thrust)
25
Case 3 - Bearing Upgrade
C bearing assembly (Radial)
- Not required for this case
26
Case 3 - Bearing Upgrade
Self contained (C & CH) bearing operation
27
Case 3 - Bearing Upgrade
Upgraded pump
28
Case 3 - Bearing Upgrade
Another example
29
Case 3 - Bearing Upgrade
Case 4 - Pump in Amine Service
BB3 Pump – 5 stages
- Amine Service
Problem:
- Unable to reach
the duty point
- Lower Head /
Higher Power
30
Materials:
- 316 SS Impellers
- 410 SS Shaft
- CS casing (Meeting API Specs…)
Inspection notes:
- Casing parting flange eroded
- Casing bores eroded
- Casing volute lips heavily eroded
31
Case 4 - Pump in Amine Service
Upgrades:
- Recommended for replacement
casing in SS material. Not
implemented.
- Casing weld with SS material
- Re-boring & facing
- 316 SS volute lip welds
- Complete performance test and field
test (Successful)
32
Case 4 - Pump in Amine Service
Notes for Services with dissolved gases:
Gas scrubbing, by chemical
absorption process.
- MEA, DEA,TEA, DGA, DIPA, MDEA
….
- Benfield, Potassium, Carbonate, …
33
Case 4 - Pump in Amine Service
Notes for Services with dissolved gases:
- NPSH margin (Could be a factor in loss of performance)
NPSHA/NPSHR ratio 1.3 – 2.0
34
Case 4 - Pump in Amine Service
Notes for Services with dissolved gases:
- Range of operations
Off Range operation
Recirculation
Gas Release
35
Case 4 - Pump in Amine Service
Notes for Services with dissolved gases:
- Materials
CA6NM Impellers in good condition
C.S. Diffusers severely pitted
36
Case 4 - Pump in Amine Service
Recommended:
- API class A-7 or A-8
- API class C-6 conforming to NACE requirements
Case 5 - Vertical Can Pump
VS6 Pump– 10 stage
- Hydrocarbon Condensate
- Vapor Pressure at PT =61 bar = 896 Psi
Problem:
- Frequent seal & bearing failure with
excessive vibration & bearing wear
- Failure every 6 month
37
Observations (Venting)
38
Case 5 - Vertical Can Pump
Observations (Duty)
Re rate needed
39
Case 5 - Vertical Can Pump
Upgrade (Re-bowling)
Replaced with smaller
hydraulics
40
Case 5 - Vertical Can Pump
Last test Nov. 2011
41
Case 5 - Vertical Can Pump
Questions ?
42

More Related Content

Similar to PPT Centrifugal Pumps Reliability Case Studies.pdf

Methane Steam Reformer Re-tube Studies
Methane Steam Reformer Re-tube StudiesMethane Steam Reformer Re-tube Studies
Methane Steam Reformer Re-tube StudiesGerard B. Hawkins
 
Filling machine reduced laminar flow tunnel assembled by adhesive bonding and...
Filling machine reduced laminar flow tunnel assembled by adhesive bonding and...Filling machine reduced laminar flow tunnel assembled by adhesive bonding and...
Filling machine reduced laminar flow tunnel assembled by adhesive bonding and...Confindustria Emilia-Romagna Ricerca
 
Axial Thrust Failure investigation
Axial Thrust Failure investigationAxial Thrust Failure investigation
Axial Thrust Failure investigationRory McKay
 
Centrifugal pump health check up before start
Centrifugal pump health check up before startCentrifugal pump health check up before start
Centrifugal pump health check up before startssuser0edfd7
 
Optimum overhaul of pumps 2014
Optimum overhaul of pumps 2014Optimum overhaul of pumps 2014
Optimum overhaul of pumps 2014Ray Beebe
 
Louis Bosch AMSA VDBP
Louis Bosch AMSA VDBPLouis Bosch AMSA VDBP
Louis Bosch AMSA VDBP7391456
 
Revamps for Modern Hydrogen Plants
Revamps for Modern Hydrogen PlantsRevamps for Modern Hydrogen Plants
Revamps for Modern Hydrogen PlantsGerard B. Hawkins
 
Removing metal fatigue for wind turnbine operators
Removing metal fatigue for wind turnbine operatorsRemoving metal fatigue for wind turnbine operators
Removing metal fatigue for wind turnbine operatorsDermott Reilly
 
BE Chemical Engineering Design Project Production Of Propylene Oxide
BE Chemical Engineering Design Project   Production Of Propylene OxideBE Chemical Engineering Design Project   Production Of Propylene Oxide
BE Chemical Engineering Design Project Production Of Propylene Oxidepatrickconneran
 
Case Study: Resin Reactor Vent Analysis
Case Study: Resin Reactor Vent AnalysisCase Study: Resin Reactor Vent Analysis
Case Study: Resin Reactor Vent AnalysisFlex Process
 
Computational Fluid Dynamics (CFD) Modelling for Designing & Troubleshooting ...
Computational Fluid Dynamics (CFD) Modelling for Designing & Troubleshooting ...Computational Fluid Dynamics (CFD) Modelling for Designing & Troubleshooting ...
Computational Fluid Dynamics (CFD) Modelling for Designing & Troubleshooting ...AmarvirChilka
 
Computational Fluid Dynamics (CFD) Modelling for Designing & Troubleshooting ...
Computational Fluid Dynamics (CFD) Modelling for Designing & Troubleshooting ...Computational Fluid Dynamics (CFD) Modelling for Designing & Troubleshooting ...
Computational Fluid Dynamics (CFD) Modelling for Designing & Troubleshooting ...Chandra Prakash Lohia
 
design_fyp_slide.ppt
design_fyp_slide.pptdesign_fyp_slide.ppt
design_fyp_slide.pptAhmad Firdaus
 
Optimising Efficiency & Capacity Sep 04 Rev 0
Optimising Efficiency & Capacity Sep 04 Rev 0Optimising Efficiency & Capacity Sep 04 Rev 0
Optimising Efficiency & Capacity Sep 04 Rev 0Raja Ratnam
 
Heat Exchanger Tube Rupture Scenario Evaluation using Aspen HYSYS Dynamics
Heat Exchanger Tube Rupture Scenario Evaluation using Aspen HYSYS DynamicsHeat Exchanger Tube Rupture Scenario Evaluation using Aspen HYSYS Dynamics
Heat Exchanger Tube Rupture Scenario Evaluation using Aspen HYSYS DynamicsProcess Ecology Inc
 
Case Study: API Recovery Process
Case Study: API Recovery ProcessCase Study: API Recovery Process
Case Study: API Recovery ProcessFlex Process
 

Similar to PPT Centrifugal Pumps Reliability Case Studies.pdf (20)

Methane Steam Reformer Re-tube Studies
Methane Steam Reformer Re-tube StudiesMethane Steam Reformer Re-tube Studies
Methane Steam Reformer Re-tube Studies
 
annalee-1207
annalee-1207annalee-1207
annalee-1207
 
Filling machine reduced laminar flow tunnel assembled by adhesive bonding and...
Filling machine reduced laminar flow tunnel assembled by adhesive bonding and...Filling machine reduced laminar flow tunnel assembled by adhesive bonding and...
Filling machine reduced laminar flow tunnel assembled by adhesive bonding and...
 
Engineering & Design - January
Engineering & Design - JanuaryEngineering & Design - January
Engineering & Design - January
 
Engineering and Design Webinar - September
Engineering and Design Webinar - SeptemberEngineering and Design Webinar - September
Engineering and Design Webinar - September
 
Axial Thrust Failure investigation
Axial Thrust Failure investigationAxial Thrust Failure investigation
Axial Thrust Failure investigation
 
Centrifugal pump health check up before start
Centrifugal pump health check up before startCentrifugal pump health check up before start
Centrifugal pump health check up before start
 
Optimum overhaul of pumps 2014
Optimum overhaul of pumps 2014Optimum overhaul of pumps 2014
Optimum overhaul of pumps 2014
 
Louis Bosch AMSA VDBP
Louis Bosch AMSA VDBPLouis Bosch AMSA VDBP
Louis Bosch AMSA VDBP
 
Revamps for Modern Hydrogen Plants
Revamps for Modern Hydrogen PlantsRevamps for Modern Hydrogen Plants
Revamps for Modern Hydrogen Plants
 
Removing metal fatigue for wind turnbine operators
Removing metal fatigue for wind turnbine operatorsRemoving metal fatigue for wind turnbine operators
Removing metal fatigue for wind turnbine operators
 
BE Chemical Engineering Design Project Production Of Propylene Oxide
BE Chemical Engineering Design Project   Production Of Propylene OxideBE Chemical Engineering Design Project   Production Of Propylene Oxide
BE Chemical Engineering Design Project Production Of Propylene Oxide
 
Case Study: Resin Reactor Vent Analysis
Case Study: Resin Reactor Vent AnalysisCase Study: Resin Reactor Vent Analysis
Case Study: Resin Reactor Vent Analysis
 
Porject final review
Porject final reviewPorject final review
Porject final review
 
Computational Fluid Dynamics (CFD) Modelling for Designing & Troubleshooting ...
Computational Fluid Dynamics (CFD) Modelling for Designing & Troubleshooting ...Computational Fluid Dynamics (CFD) Modelling for Designing & Troubleshooting ...
Computational Fluid Dynamics (CFD) Modelling for Designing & Troubleshooting ...
 
Computational Fluid Dynamics (CFD) Modelling for Designing & Troubleshooting ...
Computational Fluid Dynamics (CFD) Modelling for Designing & Troubleshooting ...Computational Fluid Dynamics (CFD) Modelling for Designing & Troubleshooting ...
Computational Fluid Dynamics (CFD) Modelling for Designing & Troubleshooting ...
 
design_fyp_slide.ppt
design_fyp_slide.pptdesign_fyp_slide.ppt
design_fyp_slide.ppt
 
Optimising Efficiency & Capacity Sep 04 Rev 0
Optimising Efficiency & Capacity Sep 04 Rev 0Optimising Efficiency & Capacity Sep 04 Rev 0
Optimising Efficiency & Capacity Sep 04 Rev 0
 
Heat Exchanger Tube Rupture Scenario Evaluation using Aspen HYSYS Dynamics
Heat Exchanger Tube Rupture Scenario Evaluation using Aspen HYSYS DynamicsHeat Exchanger Tube Rupture Scenario Evaluation using Aspen HYSYS Dynamics
Heat Exchanger Tube Rupture Scenario Evaluation using Aspen HYSYS Dynamics
 
Case Study: API Recovery Process
Case Study: API Recovery ProcessCase Study: API Recovery Process
Case Study: API Recovery Process
 

Recently uploaded

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Recently uploaded (20)

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 

PPT Centrifugal Pumps Reliability Case Studies.pdf

  • 1. Reliability Case Studies • Reza Emami, P.Eng, PMP 1
  • 2. Reza Emami P. Eng, PMP Currently, Engineering Specialist – Oil & Gas Industry, North America 12 years with Flowserve in various aftermarket roles: Applications Engineer, Project Engineer, Service & Repair Engineer, Senior Technical Services Engineer and Engineering Manager 3 years with Bartar Pumps company, Involved in re-engineering and applications engineering. 2 years with Tarh Negasht company, Design engineer involved in Computational Fluid Dynamics (CFD) for 3D simulation of flow in Automotive torque convertors MSc from Tehran University (Mechanical Engineering) Presenter 2
  • 3. Presentation Content • Failures (they happen…) • Maintenance Practice Strategies • Case Studies 3 • RCA for Reliability Based Maintenance
  • 4. Failures (they happen …) Key Parameters: Maintenance Design Installation Manufacturing Upset Condition ….. Failures can affect: Safety Production Additional Damages Additional Spare Parts Cost Unnecessary Overtime …… 4
  • 5. Maintenance Practice Strategies Graph Source: http://www.maintenanceonline.co.uk/article.asp?id=10286 Reliability based maintenance RCA (Root cause analysis) & appropriate upgrade solutions to eliminate the issue OEE (Overall Equipment Effectiveness) Improvement OEE Availability x Performance x Quality 5
  • 6. RCA for Reliability Based Maintenance RCA (Root cause analysis) & appropriate upgrade solutions for defect elimination 5 Why Concept https://www.qualitydigest.com/inside/health-care-column/dig-5-whys.html 6
  • 7. Case Studies • Case 1 - High Vibration issue – Shipping pump • Case 2 - Material Upgrade for Erosive Service • Case 3 - Bearing Upgrade (CH design) • Case 4 - Multi Stage pump in Amine Service • Case 5 - Vertical Can Pump –Hydrocarbon Condensate 7
  • 8. Case 1 - Shipping Pump Vibration BB3 pump – 10 stages - Butane / Propane Shipping Problem: - High vibration at vane passing frequency (5X) - Frequent failures due to inconsistent abnormal high vibration. 8
  • 9. Shipping propane/butane pumps: - Feed from GL1K ( “cryogenic” LNG) - Feed from RA1K (refinery GPL ) Two pumps installed - Pump was sent to factory for repair & tests then shipped back to site & restarted showing high thrust & radial bearing vibrations at 5X (250 hz) when pumping butane ~1 hour (colder product) from successful start-up Case 1 - Shipping Pump Vibration 9
  • 10. Pump B. tests in Factory (Water Ambient ) Vibration level at 5X (250hz) was very low in the full operation range (including minimum flow and minimum suction pressure). Case 1 - Shipping Pump Vibration 10
  • 11. Test on site Case 1 - Shipping Pump Vibration 11
  • 12. Test on site Case 1 - Shipping Pump Vibration 12
  • 13. Influence of process temperature on Vibration Possible Causes? Case 1 - Shipping Pump Vibration 13
  • 14. 5 Vanes Impellers Long Cross-Over All other impellers are 3 Vanes Case 1 - Shipping Pump Vibration 14
  • 15. Hz (Acoustic Frequency) = C (Speed of sound) / WL (wavelength) C depends of Fluid property, Passage dimensions / material Acoustic Resonance? Acoustic resonance data are calculated basis cross over length and speed of sound in various products: Acoustic Frequency - Water 20° 331 Hz - Butane 20° 221 Hz - Butane 10° 232 Hz - Butane 4° 240 Hz 5 vanes x 50 Hz running = 250 Case 1 - Shipping Pump Vibration 15
  • 16. Conclusions: - In water (on test platform), the 5X component did not exist. - In butane • At start-up, pumping hot product with a critical acoustic frequency below 5X, no amplification occurs • As soon as the product becomes colder, the critical acoustic frequency increases and reaches the 5X frequency causing the measured high pump vibration by amplification It was proposed to change to 7 vanes impellers It was also recommended to change the source of product to RA1K (LPG from refinery at higher temperature) if possible Case 1 - Shipping Pump Vibration 16
  • 17. Re-test with butane at 25°C Source = RA1K Half day after start-up Butane temperature = 25 ̊ C Vibrations are around 1 mm/s !!!! 17 Case 1 - Shipping Pump Vibration
  • 18. Site Test Results 18 Case 1 - Shipping Pump Vibration
  • 19. Case 2 - Erosive Service Single stage OH pump - FCC bottom Problem: - Existing casing needs replacement every month due to severe erosion Possible Causes? 19
  • 20. EXISTING NEW Flow (gpm) 790 980 Differential Head (ft) 200 232 Suction pressure (psig) 27 (29 max) 27 (29 max) NPSH available (ft) 15 15 Liquid FCC Main Fractionator Bottoms Oper Temp (°F) 675 (690 max) 675 (690 max) Viscosity <0.5 cSt <0.5 cSt Originally Rated Condition (3x50%) New Condition (2x100%) 20 Case 2 - Erosive Service
  • 21. Operating range reviewed and noted pumps are running toward left of the curve due to increased demand Half Flow Non modified impeller 21 Case 2 - Erosive Service Generally wear rate is proportional to the increase of the particle velocity cubed
  • 22. Hydraulic Re-rate (Diffuser Design) proposed along with material upgrade Drop-in replacement upgraded with: - The casing will not be subject to high velocities However was coated with HVOF line of sight - Future repairs will be limited to replacement of the wear kit Upgraded Hydraulics Upgraded Bearing Frame 22 Case 2 - Erosive Service
  • 23. Case 3 - Bearing Upgrade Coker Charge Pump Problem: - Ball thrust bearing failure 23 Root Cause: - Transient upset condition could not be avoided
  • 24. 24 Case 3 - Bearing Upgrade
  • 25. Self contained CH bearing assembly (Thrust) 25 Case 3 - Bearing Upgrade
  • 26. C bearing assembly (Radial) - Not required for this case 26 Case 3 - Bearing Upgrade
  • 27. Self contained (C & CH) bearing operation 27 Case 3 - Bearing Upgrade
  • 28. Upgraded pump 28 Case 3 - Bearing Upgrade
  • 29. Another example 29 Case 3 - Bearing Upgrade
  • 30. Case 4 - Pump in Amine Service BB3 Pump – 5 stages - Amine Service Problem: - Unable to reach the duty point - Lower Head / Higher Power 30
  • 31. Materials: - 316 SS Impellers - 410 SS Shaft - CS casing (Meeting API Specs…) Inspection notes: - Casing parting flange eroded - Casing bores eroded - Casing volute lips heavily eroded 31 Case 4 - Pump in Amine Service
  • 32. Upgrades: - Recommended for replacement casing in SS material. Not implemented. - Casing weld with SS material - Re-boring & facing - 316 SS volute lip welds - Complete performance test and field test (Successful) 32 Case 4 - Pump in Amine Service
  • 33. Notes for Services with dissolved gases: Gas scrubbing, by chemical absorption process. - MEA, DEA,TEA, DGA, DIPA, MDEA …. - Benfield, Potassium, Carbonate, … 33 Case 4 - Pump in Amine Service
  • 34. Notes for Services with dissolved gases: - NPSH margin (Could be a factor in loss of performance) NPSHA/NPSHR ratio 1.3 – 2.0 34 Case 4 - Pump in Amine Service
  • 35. Notes for Services with dissolved gases: - Range of operations Off Range operation Recirculation Gas Release 35 Case 4 - Pump in Amine Service
  • 36. Notes for Services with dissolved gases: - Materials CA6NM Impellers in good condition C.S. Diffusers severely pitted 36 Case 4 - Pump in Amine Service Recommended: - API class A-7 or A-8 - API class C-6 conforming to NACE requirements
  • 37. Case 5 - Vertical Can Pump VS6 Pump– 10 stage - Hydrocarbon Condensate - Vapor Pressure at PT =61 bar = 896 Psi Problem: - Frequent seal & bearing failure with excessive vibration & bearing wear - Failure every 6 month 37
  • 38. Observations (Venting) 38 Case 5 - Vertical Can Pump
  • 39. Observations (Duty) Re rate needed 39 Case 5 - Vertical Can Pump
  • 40. Upgrade (Re-bowling) Replaced with smaller hydraulics 40 Case 5 - Vertical Can Pump
  • 41. Last test Nov. 2011 41 Case 5 - Vertical Can Pump