SlideShare a Scribd company logo
1 of 22
Download to read offline
- 1 -
District Court
New South Wales
Case Title: Fordham v Dewsash Pty Ltd t/as S.P. & W.
Hobson
Medium Neutral Citation: [2012] NSWDC 109
Hearing Date(s): 25/05/2012 and 28/05/2012
Decision Date: 27 July 2012
Jurisdiction:
Before: P Taylor SC DCJ
Decision:
1. Allow the appeal.
2. Set aside the orders of the Tribunal.
3. Remit the matter to the Tribunal for a
rehearing in accordance with these reasons,
pursuant to ss 67(3)(b) and (4) of the CTTT
Act.
4. Order that the plaintiff's costs of the
appeal be costs of the proceedings in the
Tribunal.
Catchwords: Appeal from Tribunal - question with respect
to matter of law - no evidence - agreement -
mitigation of loss - quantum of damages -
estoppel - costs
Legislation Cited: Consumer, Trader and Tenancy Tribunal
Act 2001
Cases Cited: Kostas v HIA Insurance Services Pty
Limited [2010] HCA 32
Mahlo & Ors v Westpac Banking
Corporation Ltd [1999] NSWCA 358
Pavey & Matthews v Paul (1987) 162 CLR
221
Texts Cited:
Category: Principal judgment
- 2 -
Parties: James Arthur Fordham (plaintiff)
Dewsash Pty Limited t/as S.P. & W. Hobson
(defendant)
Representation
- Counsel: Mr J Young (plaintiff)
Mr S V Shepherd (defendant)
- Solicitors: Blackwell Short Lawyers (plaintiff)
Creaghe Lisle Solicitors (defendant)
File number(s): 2011/165234
Decision Under Appeal
- Court / Tribunal:
- Before: Tribunal Member S Smith
- Date of Decision: 17 March 2011
- Citation:
- Court File Number(s) HB 09/25483; HB 10/21874
Publication Restriction: No
JUDGMENT
A. Introduction
1 This is an appeal from a decision of the Consumer, Trader and Tenancy
Tribunal ("the Tribunal") under s 67 of the Consumer, Trader and Tenancy
Tribunal Act 2001 ("the CTTT Act"), in respect of a building dispute.
B. Background
2 The facts as found by the Tribunal were as follows.
- 3 -
3 Mr Fordham, the plaintiff, owned some rural land at Bendick Murrell in the
central west of New South Wales. He had plans to build a cottage. He
negotiated with Mr Hobson, the owner of the defendant's building
company, and on 25 June 2002 the parties entered a standard HIA
contract for the building of the house. The contract provided for a price of
$187,000 with no deposit, and a schedule of progress payments
commencing with $50,000 when the slab and underfloor plumbing were
complete.
4 Site work commenced in November 2002, and after many inspections and
rectifications the main part of the slab was poured on 13 May 2003.
5 In April 2003, shortly before the slab was poured, the defendant presented
the plaintiff with invoices totalling $36,000. As the slab had not been
poured, the plaintiff may have been within his rights to make no payment
until all works referable to the first progress payment were substantially
complete. In any event, on about 28 April 2003 the plaintiff paid the
defendant $29,000.
6 After the slab was poured, a further dispute arose between the parties
concerning the adequacy of the slab. Experts were retained. After some
debate those experts, Mr Simpson for the defendant, and Mr Noonan for
the plaintiff, agreed on a rectification procedure whereby a concrete
topping would be put on the existing slab to allow for a shower set down
and to provide some stiffening of the overall structure.
7 Ultimately, no concrete topping was installed. The plaintiff engaged a new
builder, and demolished the existing slab.
C. The Tribunalproceedings
- 4 -
8 The Tribunal member determined that the matter required him to
determine three issues:
(a) Was the slab as built a breach of the building
contract;
(b) Did the plaintiff mitigate his loss if there was a
breach; and
(c) Which party had the right to terminate the contract.
9 In the course of dealing with these three issues, the Tribunal member
made findings which can be summarized as follows:
(i) Contrary to the defendant's contention, there
was no agreement prior to 28 April 2003
(when the invoices were supplied) that
$36,000 was payable upon the pouring of
the main slab with the veranda slab to be
poured separately.
(ii) On about 28 April 2003 the contract was
varied by agreement (or by the plaintiff
allowing the defendant to imagine that he
agreed) so that a further amount of $7,000
(in addition to the $29,000 paid on that day)
was to be paid on completion of the slab.
(iii) The refusal by the plaintiff to pay the
additional $7,000 indicated an unwillingness
by the plaintiff to be bound by the contract
as agreed and empowered the builder to
stop work.
(iv) This variation of the contract was an
informal variation, such that the builder
could not assert a right to payment under
the contract but was entitled to rely on a
quantum meruit.
(v) The plaintiff was estopped from disputing
that the value of the slab was an additional
$7,000 in addition to the $29,000 already
paid.
(vi) The builder was entitled to succeed on the
cross-claim for $7,000.
(vii) There is an argument that the slab satisfied
the contractual requirements, but because
other aspects of the case are fatal to the
- 5 -
plaintiff's claim the question of breach of
contract need not be decided.
(viii) The compromise reached between the
experts about a topping slab was binding on
the parties, and governed their rights and
responsibilities.
(ix) The need to strengthen the slab was a
consequence of the way the builder
constructed the slab and so the builder must
bear the cost of the extra works.
(x) The only evidence of the value of the extra
works was Mr Simpson's estimate of $8,000,
which was accepted.
(xi) Were there a breach of contract by the
builder, the plaintiff had a duty to take all
reasonable steps to mitigate his loss, by
selecting the cheapest solutions reasonably
available.
(xii) The plaintiff's expert, Mr Noonan, withdrew
his approval to the slab topping even though
he had agreed previously. It was possible he
had succumbed to pressure from the
plaintiff, and as a result, little weight could
be given to Mr Noonan in measuring
reasonableness. Mr Simpson seemed
ready, willing and able to certify the slab
topping, and his evidence was preferred to
Mr Noonan's.
(xiii) The plaintiff unreasonably refused to
proceed with the topping slab and failed to
mitigate his loss, which would otherwise be
$8,000.
(xiv) The plaintiff should pay the defendant's
costs.
D. The Appeal
10 The plaintiff appealed from the Tribunal decision pursuant to section 67 of
the CTTT Act. Section 67 contains the following provisions:
- 6 -
"(1) If, in respect of any proceedings, the Tribunal decides a
question with respect to a matter of law, a party in the proceedings
who is dissatisfied with the decision may, subject to this section,
appeal to the District Court against the decision.
...
(3) After deciding the question the subject of such an appeal, the
District Court may, unless it affirms the decision of the Tribunal on
the question:
(a) make such order in relation to the proceedings in which
the question arose as, in its opinion, should have been
made by the Tribunal, or
(b) remit its decision on the question to the Tribunal and
order a rehearing of the proceedings by the Tribunal.
(4) If such a rehearing is held, the Tribunal is not to proceed in a
manner, or make an order or a decision, that is inconsistent with
the decision of the District Court remitted to the Tribunal."
11 The plaintiff may have commenced the appeal shortly after the prescribed
statutory period, without leave. The defendant did not oppose an order for
leave to be granted, and accordingly I granted an extension of time for the
filing of the appeal to the date of the filing of the appeal.
12 In Kostas v HIA Insurance Services Pty Limited [2010] HCA 32, French CJ
at [25] held that:
"The words "question with respect to a matter of law" are wide
enough to encompass a question of mixed law and fact. Questions
of fact and law are often closely intertwined."
13 The plurality in Kostas (Hayne, Heydon, Crennan, Bell JJ) determined at
[90] and [91]:
"It is sufficient, for present purposes, to determine that the ground
usually described as a "no evidence ground" raises a question of
law...
Whether there was no evidence to support a factual finding is a
question of law, not a question of fact...What amounts to material
that could support a factual finding is ultimately a question for
judicial decision. It is a question of law."
14 The plurality declined at [88] to determine in the abstract the precise ambit
of the words "question with respect to a matter of law".
- 7 -
15 The plaintiff asserted the following errors by the Tribunal:
"1 The finding that the there was an agreement for the Plaintiff to
pay $36,000 on completion of the slab.
2 The finding that the Defendant is entitled to a quantum meruit.
3 The finding that the Plaintiff is estopped from asserting that the
value of the work related to the completion of the slab was other
than $7,000.
4 The finding that the Defendant was entitled to stop work until the
$7,000 was paid.
5 The Tribunal failed to make any finding as to Plaintiff's claim for
breach of contract.
6 The finding without evidence that Mr Simpson would have
certified the slab as built and will certify the slab as augmented.
7 The finding that there was a compromise agreement binding on
the parties.
8 The finding without evidence that Mr Noonan resiled from his
previous opinion offered.
9 The finding without evidence that Mr Simpson had designed the
topping slab and was ready, willing and able to certify it.
10 The finding without evidence that the Plaintiff's entitlement to a
quantum of loss of $8,000.
11 The finding that the Plaintiff had failed to mitigate his loss.
12 The finding without evidence that the Plaintiff's claim demolition
and reconstruction was (as pleaded) $91,000 in round figures.
13 The Tribunal treated the hearing as a final hearing when it was
a hearing on liability and part of quantum only."
Ground 1: The agreement to pay $36,000.
16 This ground relates to finding (i) and (ii) of the Tribunal set out in
paragraph 10 above.
17 The plaintiff alleges that the finding of an agreement falls within s 67 on
two bases: it is a mixed question of fact and law, and in any event there
was no evidence to support the finding. It is clear from Kostas that the
second basis falls with the ambit of the appeal jurisdiction created by s 67.
I am also of the view that in the circumstances of this case, a finding of an
agreement is a mixed question of fact and law, which would fall within the
ambit of s 67 according to the decision of the Chief Justice in Kostas at
[25].
- 8 -
18 The undisputed evidence was that on or about 28th April 2003, before the
slab was poured, the defendant gave the plaintiff three documents, these
being:
(a) Tax Invoice 0184 for $36,000;
(b) Part A Progress Claim No. 1 for $29,000 dated 27th
April 2003; and
(c) Part B Progress Claim No. 1 for $7,000 dated 27th
April 2003.
19 On 28 or 29 April 2003, the plaintiff paid the defendant $29,000. The
plaintiff's evidence as to the circumstances under which this amount was
paid is set out in detail in Annexure "K" to his witness statement dated 30
November 2009 filed with the Tribunal and adhered to under cross-
examination at T28/7/2010 p 23.5:
Q: I mean the reality is, Mr Fordham, if you haven't paid the builder
the $29,000, he wouldn't have poured the slab.
A: Would have been good if he hadn't.
Q: But he wouldn't have poured it if you hadn't paid it.
A: Paul rang me a couple of days before that date that I paid, and
asked me, because of the delay in time, and the fact that his
contract - he couldn't pay his contractors, he'd outlaid a lot of
money and he couldn't pay his contractors, the kids were - their
kids were starving, could I make an advance on progress payment
number 1, and I agreed to that. He couldn't tell me how much he
wanted upon that date. Three or four days later when he turned up
on the Sunday, he had these payments already - progress
payments already made out, and I was astounded at the amount,
because the amount of work that had been done to that date didn't
amount to $29,000. Nevertheless, I paid him the $29,000 which is
what he asked for, and then when I saw the second progress
payment, number 2B or whatever he called, for $7,000, that's
when I said, "No, that's $21,000, its not due until the veranda slabs
are done and all that sort of thing".
Q: Would he have poured the slab if you hadn't paid him the
$29,000?
A: I doubt it, I'm sure that he wouldn't have.
20 This evidence denies an agreement to pay the further sum of $7,000. The
defendant asserted that it was open to the Tribunal to reject the plaintiff's
evidence, and, in that event, the Tribunal's finding of an agreement to pay
a total of $36,000 was not so illogical or against the weight of the evidence
as to constitute an error of law.
- 9 -
21 The difficulty with the defendant's submission is that the rejection of the
plaintiff's evidence does not operate to supply the contrary evidence. The
Tribunal accepted that the sum of $50,000 was due under the contract
when the slabs were complete. I accept that the invoices delivered to the
plaintiff constitute evidence of an offer by the builder for a variation to the
effect that $29,000 be paid on 28 April 2003 and that $7,000 be paid after
the pouring of the main slab.
22 However, I do not think that the payment of $29,000, without more, is
sufficient to support a finding of an agreement that a further $7,000 would
be paid after the main slab was poured.
23 The evidence of Mr Hobson was as follows (T29/7/2010 pp 6.45-7.11):
Q: What you were saying yesterday is the contract says, "slab
complete $50,000". You were saying, "Oh no, that's what it might
say, but in my mind, slab complete means the home and the
house slab because I built the veranda later". Mr. Shepherd led
evidence from you yesterday to indicate that there was a variation
to that $50,000, based on conversations which allowed you then to
submit a claim for $36,000, remember that?
A: Mm-hmm.
Q: Why was it necessary to have a variation if the contract said
$50,000 on completion of slab, and you, in your mind, had
completed the slab that you thought was included in that $50,000?
A: The word variation, wasn't actually a variation. Like it was - it
was just - the figures were all there, and because the time lapse
went on for so long, I had made a claim for the money that I
actually put into the place at that time, and that came to that
amount for the slab, and the difference was for the veranda slab.
Now, to me, a variation is when there's a plus or minus cost, and
there's no plus or minus, I was just requesting a payment for what
I've done.
And at T28/7/2010 p 63.45-63.50:
Q: If the contract was to be varied by postponing the construction
of the veranda, why did you not document it as you did with the
three minor variations?
A: Possibly because I didn't believe it as a variation because no
money is going to be on it, plus or minus. Like to me, it's not a
variation, it's just a different program of work. Wasn't going to cost
me any money or Mr. Fordham.
- 10 -
24 This evidence does not seem to me to support a variation of the
agreement to require a payment of a total of $36,000 after the pouring of
the main slab. The Tribunal member noted that no claim of duress or lack
of consideration was maintained by the plaintiff in respect of the variation
but the absence of such a claim does not supply evidence of acceptance
by the plaintiff of the obligation to pay a further $7,000. There is no
conduct or words by the plaintiff in any of the evidence that indicates an
acceptance of the proposal by the defendant. I do not regard invoices sent
after the event as supplying evidence of an agreement.
25 Accordingly, I find that there was no foundation for any findings of a varied
agreement by the Tribunal other than an agreement to pay $29,000 in late
April 2003. To some extent this lack of evidence is recognized by the
Tribunal by its alternative finding of "allowing Mr Hobson to imagine that he
agreed". This alternative finding suggests that there was no acceptance,
rather that the conduct of the plaintiff gave rise to some form of estoppel.
An estoppel by conduct requires that there be evidence of the conduct
giving rise to an assumption, or reliance, by the defendant so as to act to
its detriment. These are not matters the subject of findings by the Tribunal,
and do not appear to be supported by evidence. I do not regard the finding
quoted earlier in this paragraph as sufficient to establish an estoppel.
26 It follows that ground 1 is established: the finding by the Tribunal of an
agreement between the parties for the plaintiff to pay a further $7,000 on
the pouring of the slab is an erroneous finding with respect to a matter of
law.
Ground 2: the defendant is entitled to a quantum meruit
27 The Tribunal also relied upon quantum meruit and the decision in Pavey &
Matthews v Paul (1987) 162 CLR 221 (see finding (iv) in paragraph 9
above.
- 11 -
28 An action in indebitatus assumpsit for the value of the work done and
materials supplied, otherwise known as an action on a quantum meruit,
depends on proof by the builder that he did the work and that the owner
accepted the work without paying the agreed remuneration: Pavey v
Matthews at 228.
29 In the present case, it is not in dispute that the builder did the work, but the
owner's acceptance of the work and the agreed remuneration remain
matters in dispute. I have already decided that there was no evidence of
an agreed remuneration upon the pouring of the primary slab. Nor do I
think, in circumstances where the parties have been found to have agreed
upon the need for a topping slab, that there was acceptance of the work
done, at least not without rectification.
30 The defendant submitted (at [53] of its submissions):
"...the position as at the time the applicant terminated the contract
was that the common ground was that the builder had completed
this work and therefore must be entitled to payment for what he
had done as at the time the contract was terminated. Any putative
entitlement to damages for breach of the contract must
nevertheless account for the builder's entitlement to payment for
work done."
31 Of course, the owner must give credit for any work done. But if the owner
has terminated the contract for breach, the builder is only entitled to
payment for work done to the extent that the costs to complete the work
(including payments already made to the builder) are less than the contract
value. So much was provided for in clause 36.4 of the contract which
stated:
36.4 If the costs incurred by the owner are:
(a) more than the unpaid balance of the contract price the
builder must pay the difference to the owner within 7
working days of receiving the notice from the owner; or
(b) less than the unpaid balance of the contract price the
owner must pay the difference when giving the notice as a
debt due and payable. [emphasis omitted]
- 12 -
32 It follows that the value of the work done by the builder must take account
of the cost of the remedial topping slab, and, potentially, the cost to
complete the work. It was an error for the Tribunal to ignore these costs
and simply award the builder the $7,000 as the additional value of the work
done to date.
Ground 3: the plaintiff is estopped from asserting the value of completing
the slab was other than $7,000.
33 This finding of the Tribunal ((v) in paragraph 9 above) is dependent upon
the finding of an agreement. The Tribunal member found:
"I note that at least one count in the builder's claim was founded
on an estoppel. In my opinion the part played by estoppel in this
matter goes to the amount of the quantum meruit being the value
of the work done. Because Mr Hobson acted to his detriment on
the promise of Mr Fordham to pay the outstanding balance of
$7,000 for the completion of house slab, I do not think he can be
heard now to say that its value is other than $7,000.00 and that it
is payable forthwith."
34 The Tribunal's reasons indicate that the estoppel claim is not an alternative
to the agreement, but an addendum: there was an agreement to pay for
the value of the work on completion of the slab, and the plaintiff is
estopped from denying (for the purposes of that agreement) that the value
of the slab is a further $7,000.
35 If there is no evidence of agreement, this finding also must be in error.
36 Further, an estoppel by conduct requires a party to act to its detriment. The
detriment in this case was alleged to be the pouring of the slab.
37 There was evidence from Mr Fordham that the builder would not (or would
not likely) have poured the slab if the $29,000 was not paid. But there was
no evidence from either party that the builder would not have poured the
slab if the owner had not promised to pay a further $7,000 on completion
of the slab, and no questions to that effect were directed to the owner. I do
- 13 -
not accept that the mere tendering of an invoice for $7,000 by the builder
can be conduct sufficient to support an estoppel, in circumstances where
there was discussion and agreement in respect of payment of the invoice
for $29,000 in return for the pouring of the slab.
38 The builder submits that it was:
"...entirely open to the tribunal to conclude that the applicant
encouraged the respondent to act on an assumption that a contact
would come into existence or a promise be performed by the
applicant (i.e. payment of $36,000) and the applicant intended the
respondent to act on that assumption (by part performance of that
promise in paying $29,000) and the respondent did act on that
assumption to his detriment in that work was performed that
otherwise would not have been done and he has not been paid the
outstanding amount for which he undertook that work."
39 To make out this submission, there needed to be some evidence, perhaps
from the builder, to the effect that he poured the slab because of some
conduct of the owner in respect of the invoice for $36,000, or the invoice
for $7,000. No such evidence was identified. In the absence of evidence of
"encouragement" or "acting on an assumption", there was no basis for the
Tribunal's finding. I have already found that the mere tender of an invoice
is insufficient.
Ground 4: the defendant could stop work until the $7,000 was paid.
40 Again, finding (iii) in [9] above is dependent upon an agreement in respect
of the $7,000, which I have rejected on the basis that there was no
evidence to support it. It follows that there was no evidence to support an
entitlement in the builder to stop work until the $7,000 was paid.
Ground 5: failure to make a finding of breach of contract by the builder.
41 It is correct that the Tribunal did not make a finding in respect of breach of
contract and expressly reserved that question. However, the Tribunal's
finding (based on the finding of a varied agreement) that the builder was
- 14 -
"empowered to stop work" precluded a finding of breach by the builder in
so doing.
42 In the absence of a valid variation, the Tribunal would need to determine
whether either party was in breach of the agreement.
Conclusion to Grounds (1) - (5)
43 All of these grounds arise out of the Tribunal's decision that there was an
agreement between the plaintiff and the defendant to pay $7,000 on
completion of the pouring of the main slab. I have found that there is no
evidence to support such an agreement, so these grounds are made out. It
follows that findings (ii) to (vii) are not supported by any evidence and must
be rejected.
Grounds 6 and 9: Mr Simpson designed and would have certified the
topping slab
44 These grounds concern finding (xii) in [9] above.
45 Mr Noonan, the plaintiff's expert, wrote on 5 August 2007:
"The topping slab rectifications proposal by Mr Simpson is a
suitable strength rectification provided it is designed and installed
correctly."
46 On 24 August 2007, Mr Simpson noted that he was:
"...preparing a rectification plan and specification. The plan will
involve a systematic inspection of the underside of the edge beam,
the removal of any soft plant material found; the refilling of any
gaps with compacted granite or high strength concrete slurry: the
machine grinding/roughening of the slab surface; the installation of
[unreadable] placing of reinforcing mesh and the pouring of a
topping slab in two or three segments."
"The structural characteristics of the new slab are intended to
easily accommodate any movements in the founding soil through
settlement or moisture content related shrinking and levelling. In
reality the rectified slab will be far stiffer than the original design."
- 15 -
47 The evidence also included a facsimile to Mr Fordham from Mr Simpson
dated 28 October 2007 which comprised a topping slab plan with notes
and specifications, a rectification procedure, and detailed sections at the
edges of the existing slab and at the construction joint.
48 Mr Noonan responded on 19 November 2007, writing:
"We therefore advise that method of rectification is acceptable
provided the additional notes are included in the design drawings
for the edge beam rectification."
49 In these circumstances it seems clear to me that there was evidence on
which the Tribunal could conclude that Mr Simpson had designed the slab
and was willing to certify as built. I therefore reject grounds 6 and 9 of the
appeal.
Ground 7: there was a compromise agreement concerning the slab
rectification which was binding on the parties
50 This ground concerns finding (viii) in [9] above.
51 I refer to the evidence quoted under the previous ground. That evidence
supports a finding that there was a compromise agreement concerning the
slab rectification, which was binding upon the parties. The plaintiff did not
appear to submit otherwise. The primary submission on this ground was
that it did not relieve the Tribunal of the need to determine breach (a
matter dealt with under another ground of appeal):
"If, as it appears, the Tribunal found that there was a compromise
agreement between the parties that would govern the way the
rectification of the slab progressed, then the Tribunal did not then
go to decide which party was in breach of that compromise
agreement. This was an error with respect to a matter of law."
52 The plaintiff also submitted that no final plans were prepared. The
evidence indicates that an updated plan was to be prepared which might
not have been completed, but I think the plans provided at pages 105-106
of the Blue Appeal Book, together with the specifications and rectification
- 16 -
procedure recorded thereon, were sufficient to enable a finding that a
compromise agreement had been reached.
53 Accordingly, I reject ground 7 of the grounds of appeal.
Ground 8: Mr Noonan resiled from his previous opinion.
54 This ground concerns finding (xii) in [9] above.
55 It does not appear to be in contest that Mr Noonan did resile from his
previous opinion of agreement with Mr Simpson's slab topping proposal. At
least Mr Noonan thought that, for reasons which he set out, demolition of
the slab was a preferable course.
56 Save for one matter, which is dealt with below, I do not find any errors with
the way the Tribunal dealt with Mr Noonan's evidence. Mr Noonan
withdrew his approval of the agreed topping slab solution, as the Tribunal
found. Also, as the Tribunal found, Mr Noonan's reasons for so doing were
not relevantly technical. Mr Noonan did not find that the topping slab would
be defective or inappropriate in some way, but was concerned with matters
of liability and costs.
57 I think it was open to the Tribunal to adopt Mr Simpson's topping slab
solution, as a reasonable and cost effective procedure, on the basis that
Mr Noonan had once agreed with it but subsequently changed his mind.
However, the Tribunal did not proceed on this basis. Rather, it found that
there was a "possibility that Mr Noonan succumbed to pressure from Mr
Fordham", and that "as a result" Mr Noonan's revised opinion was given
little weight.
58 The defendant refers to a letter from the plaintiff's solicitor (Blue AB 492-3)
as "evidence to support that the change of opinion had been encouraged
by the plaintiff's solicitors". Although that may be so, I do not think it was
- 17 -
open to the Tribunal to attribute this possible motivation for Mr Noonan's
change of mind and to reject his evidence because of it, in circumstances
where Mr Noonan was not cross-examined and the possibility was not put
to him. The Tribunal must be cautious before attributing an extraneous
motive to an expert, and should not do so unless there is some factual
foundation for it.
59 Notwithstanding this error, as I have said, the ultimate finding of the
Tribunal on the reasonable rectification procedure was open to it. It would
be a matter for the Tribunal to decide whether it now makes the same
finding in circumstances where (in the absence of further evidence) it was
not entitled to reject Mr Noonan's revised view on the basis of the alleged
possibility that Mr Noonan had succumbed to pressure from Mr Fordham.
Ground 10: plaintiff entitled to $8,000 only
60 The plaintiff submits that there was no evidence to support the finding that
the cost of rectification of the slab was $8,000 (see finding (x) in [9]
above).
61 The Tribunal found:
"As it turns out, Mr Simpson's estimate of the cost of rectification
was the only one before me. He indicated the cost at about $8,000
and I accept that estimate".
and
"In the circumstances of the present case I am well satisfied that
Mr Fordham has not acted reasonably in rejecting the topping slab
and has failed to mitigate his loss which would otherwise be
$8,000."
62 The basis of this finding is that in re-examination of Mr Simpson on the
topic of the topping slab, the following exchange occurred:
"Q. Would that have been cheap?
A. Without doing the - work, it would have been in the ballpark of
$8,000 to $10,000, maybe $12,000."
- 18 -
63 It may be that the Tribunal has elevated the evidence of the cost of a slab
topping to a level slightly higher than it bore. However, I think the evidence
of Mr Simpson is some evidence that the cost of the slab may be $8,000.
The fact that a finding of a cost of $9,000 or $10,000 may sit more
comfortably with that evidence is not sufficient, in my view, to allow a
finding by this court that the cost of $8,000 for the topping slab as found by
the Tribunal had no evidentiary basis.
64 The question whether the cost of the topping slab was the proper amount
of the plaintiff's damage under the contract, if any, is another matter. I
have already dealt with this issue under grounds 1 to 5. I should note that
the Tribunal did not find that the plaintiff's loss was $8,000, rather that if
there was a breach of contract, "it would sound in damages equal to the
homeowners loss according to law, here the $8,000 for the topping slab".
Ground 11: the plaintiff failed to mitigate his loss.
65 The finding at (xiii) in [9] above is criticised by the plaintiff on the basis that:
"such a finding is relevant where a breach of contract is
established [but that] the Member...expressly stated that he was
making no finding of breach by the defendant."
66 I accept the plaintiff's submission that the question of a failure to mitigate
loss only arises where the Tribunal is endeavouring to assess the damage
consequent upon a breach of contract. In the absence of a finding of
breach of contract, a finding of a failure to mitigate loss is unnecessary.
However, that does not assist the plaintiff on this appeal. If anything, it may
support an argument that the $8,000 awarded to the plaintiff could not be
sustained.
67 This is another reason (or perhaps the same reason expressed another
way) as to why the Tribunal needed to make a finding about breach of
contract by the defendant. Unless it did so, there was no cause of action
- 19 -
established which justified an award of $8,000 or some other sum, in
favour of the plaintiff.
68 However, there was a basis (as set out above with respect to grounds 6 to
10) for the Tribunal to find that by not installing a topping slab the plaintiff
had failed to mitigate any loss to which he was entitled. I would therefore
not reject this finding of the Tribunal.
Ground 12: the plaintiff's claim was for $91,000.
69 On 19 October 2009, Member Durie noted:
"That the owner has now obtained an owner/builder license and is
proceeding with works. It may be necessary (with the consent of
the parties) to have an initial hearing on liability and part of the
quantum, and a later hearing on the balance of quantum."
and on 19 November 2009, Tribunal Member Rossa noted:
"The Tribunal further notes that the parties are agreed that the
hearing of the application will be in two parts, with liability and part
of the quantum to be determined initially, with the balance of the
quantum to be determined at a later stage (if liability is
established)."
70 It was proposed that, as the Plaintiff submitted:
"...the hearing was to determine liability on all issues and, subject
to that decision on liability, then go on to determine quantum for
the limited component of demolition and reconstruction of the
slab."
71 It is not readily apparent to me how the Commissioner could determine
"part of the quantum". The difference between the cost of the slab, and the
amount paid by the plaintiff to the defendant, is not a proper amount of
damage. Certainly the cost of the slab is a component of the overall cost,
and the amount paid to the builder is a relevant component of the
calculation of the damages to which the plaintiff may become entitled. But
the proposal by the parties to separate the cost of the slab from the
amount of damages suffered by the plaintiff was misconceived, and seems
likely to have contributed to the error made by the Tribunal.
- 20 -
72 In the result, nothing turns on this ground, other than perhaps the question
of costs. The plaintiff argued that on the question of costs:
"...the amount awarded of $8,000 has been compared to the total
claim of $91,129.91 instead of the amount referable to the more
limited claim for the defective slab claim of $58,790.91. This has
had an effect on the costs analysis".
73 I do not accept this submission. Although the Tribunal member noted the
claim for $95,000 in deciding the question of costs, the Tribunal member
reserved liberty to the parties to make submissions on costs.
74 The Tribunal member revisited the question of costs on 21 April 2011, and
gave a decision which, although not in the Blue Appeal Book, was
annexed to an affidavit of the plaintiff's solicitor read on the appeal and
was thus part of the evidence before the court.
75 The Tribunal member decided:
"In response to orders and reasons published on 17 March 2011
the parties have filed and served detailed submissions on the
question of costs.
I have considered those submissions in deciding the question of
costs.
As I indicated in my written reasons, the builder has achieved
substantial success in his claim but the homeowner's claim in the
final analysis was more like $50,000.00, not over $90,000.00 as
mentioned in my reasons. While that may be so, the claim as
pleaded was in the higher amount and the bulk of the litigation was
conducted on that basis. In any event, the difference between the
two amounts in relation to the whole of the case and its outcome
would have little effect on the exercise of the costs discretion."
76 In the circumstances, I do not think that the Tribunal's decision on costs
miscarried because of a failure to recognise that the claim was for $58,000
approximately rather than $91,000. The final decision by the Tribunal in
respect of costs contemplated the lower value of the claim.
- 21 -
77 However, the decision on costs was affected by the findings considered
under grounds 1 to 5 above, which I have found to be in error. Accordingly,
the question of costs will need to be revisited by the Tribunal.
Ground 13: not a final hearing
78 I have dealt with this matter above. The Tribunal needed to determine
whether there was a breach of contract in order to determine whether the
plaintiff was entitled to an award of $8,000 on the primary claim. Such an
award would have an impact on the appropriate costs order. Generally a
plaintiff is entitled to the costs of a successful claim and the defendant
would be entitled to the costs of the successful cross-claim, but the costs
of a cross-claim would only be those costs which were in addition to those
which were incurred in the primary claim: see Mahlo & Ors v Westpac
Banking Corporation Ltd [1999] NSWCA 358 at [88]. Whether that general
rule should apply in this particular case would be a matter for the Tribunal.
Conclusion
79 The parties jointly submitted that if the Tribunal's decision was in error
such that the orders could not be affirmed, I should send the matter back
to the Tribunal for further consideration. In view of my findings in respect of
grounds 1 to 5 of the appeal, the findings of the Tribunal must be set
aside, and the matter remitted to the Tribunal for further consideration in
accordance with these reasons. In accordance with s 67(7) of the CTTT
Act, further evidence "may be given on the rehearing".
80 As to the question of costs, the plaintiff has had some success on the
appeal but not on all points. In these circumstances I propose to order that
the plaintiff's costs on the appeal be costs of the proceedings in the
Tribunal.
E. Conclusion and orders
- 22 -
81 Accordingly, the orders are:
1. Allow the appeal.
2. Set aside the orders of the Tribunal.
3. Remit the matter to the Tribunal for a rehearing in accordance with
these reasons, pursuant to ss 67(3)(b) and (4) of the CTTT Act.
4. Order that the plaintiff's costs of the appeal be costs of the proceedings
in the Tribunal.
**********

More Related Content

What's hot

FLSA Litigation - Federal Court - MDFL Tampa - Fee Entitlement & Mootness
FLSA Litigation - Federal Court - MDFL Tampa - Fee Entitlement & MootnessFLSA Litigation - Federal Court - MDFL Tampa - Fee Entitlement & Mootness
FLSA Litigation - Federal Court - MDFL Tampa - Fee Entitlement & MootnessPollard PLLC
 
123552920 shinryo-v-rrn
123552920 shinryo-v-rrn123552920 shinryo-v-rrn
123552920 shinryo-v-rrnhomeworkping9
 
UK Adjudicators January 2022 Newsletter
UK Adjudicators January 2022 NewsletterUK Adjudicators January 2022 Newsletter
UK Adjudicators January 2022 NewsletterSeanGibbs12
 
FORECLOSURE Response to JP Morgan Chase Foreclosure
FORECLOSURE Response to JP Morgan Chase ForeclosureFORECLOSURE Response to JP Morgan Chase Foreclosure
FORECLOSURE Response to JP Morgan Chase Foreclosurelauren tratar
 
Hutka v. Aitchison et al, 2006 BSCS 1169
Hutka v. Aitchison et al, 2006 BSCS 1169Hutka v. Aitchison et al, 2006 BSCS 1169
Hutka v. Aitchison et al, 2006 BSCS 1169Rolf Warburton
 
NY Court of Appeals Motion to Accept Town of Dryden Ban Case
NY Court of Appeals Motion to Accept Town of Dryden Ban CaseNY Court of Appeals Motion to Accept Town of Dryden Ban Case
NY Court of Appeals Motion to Accept Town of Dryden Ban CaseMarcellus Drilling News
 
Loughman v EQT - Decision Rejecting Landowner Request to Sever Production Lea...
Loughman v EQT - Decision Rejecting Landowner Request to Sever Production Lea...Loughman v EQT - Decision Rejecting Landowner Request to Sever Production Lea...
Loughman v EQT - Decision Rejecting Landowner Request to Sever Production Lea...Marcellus Drilling News
 
Armstrong v. Chesapeake Exploration Court Decision
Armstrong v. Chesapeake Exploration Court DecisionArmstrong v. Chesapeake Exploration Court Decision
Armstrong v. Chesapeake Exploration Court DecisionMarcellus Drilling News
 
Writing Sample - Sealing Records Memo
Writing Sample - Sealing Records MemoWriting Sample - Sealing Records Memo
Writing Sample - Sealing Records Memoatsherwi
 
BANK OF AMERICA FORECLOSURE, ANSWER, AFFIRMATIVE DEFENSES, COUNTERCLAIM
BANK OF AMERICA FORECLOSURE, ANSWER, AFFIRMATIVE DEFENSES, COUNTERCLAIMBANK OF AMERICA FORECLOSURE, ANSWER, AFFIRMATIVE DEFENSES, COUNTERCLAIM
BANK OF AMERICA FORECLOSURE, ANSWER, AFFIRMATIVE DEFENSES, COUNTERCLAIMlauren tratar
 
Declaración por escrito del Estado Plurinacional de Bolivia en la excepción p...
Declaración por escrito del Estado Plurinacional de Bolivia en la excepción p...Declaración por escrito del Estado Plurinacional de Bolivia en la excepción p...
Declaración por escrito del Estado Plurinacional de Bolivia en la excepción p...Miguel Angel De La Roca
 
Defence of Residential Dwellings at Law
Defence of Residential Dwellings at LawDefence of Residential Dwellings at Law
Defence of Residential Dwellings at Lawinventionjournals
 
Doc876 robbins tapp cobb & assoc accountants_work done_final comp
Doc876 robbins tapp cobb & assoc accountants_work done_final comp Doc876 robbins tapp cobb & assoc accountants_work done_final comp
Doc876 robbins tapp cobb & assoc accountants_work done_final comp malp2009
 
Dewing v. Abarta Oil & Gas Co. - PA Superior Court Ruling
Dewing v. Abarta Oil & Gas Co. - PA Superior Court RulingDewing v. Abarta Oil & Gas Co. - PA Superior Court Ruling
Dewing v. Abarta Oil & Gas Co. - PA Superior Court RulingMarcellus Drilling News
 

What's hot (20)

FLSA Litigation - Federal Court - MDFL Tampa - Fee Entitlement & Mootness
FLSA Litigation - Federal Court - MDFL Tampa - Fee Entitlement & MootnessFLSA Litigation - Federal Court - MDFL Tampa - Fee Entitlement & Mootness
FLSA Litigation - Federal Court - MDFL Tampa - Fee Entitlement & Mootness
 
10000000010
1000000001010000000010
10000000010
 
123552920 shinryo-v-rrn
123552920 shinryo-v-rrn123552920 shinryo-v-rrn
123552920 shinryo-v-rrn
 
UK Adjudicators January 2022 Newsletter
UK Adjudicators January 2022 NewsletterUK Adjudicators January 2022 Newsletter
UK Adjudicators January 2022 Newsletter
 
FORECLOSURE Response to JP Morgan Chase Foreclosure
FORECLOSURE Response to JP Morgan Chase ForeclosureFORECLOSURE Response to JP Morgan Chase Foreclosure
FORECLOSURE Response to JP Morgan Chase Foreclosure
 
Hutka v. Aitchison et al, 2006 BSCS 1169
Hutka v. Aitchison et al, 2006 BSCS 1169Hutka v. Aitchison et al, 2006 BSCS 1169
Hutka v. Aitchison et al, 2006 BSCS 1169
 
NY Court of Appeals Motion to Accept Town of Dryden Ban Case
NY Court of Appeals Motion to Accept Town of Dryden Ban CaseNY Court of Appeals Motion to Accept Town of Dryden Ban Case
NY Court of Appeals Motion to Accept Town of Dryden Ban Case
 
Loughman v EQT - Decision Rejecting Landowner Request to Sever Production Lea...
Loughman v EQT - Decision Rejecting Landowner Request to Sever Production Lea...Loughman v EQT - Decision Rejecting Landowner Request to Sever Production Lea...
Loughman v EQT - Decision Rejecting Landowner Request to Sever Production Lea...
 
10000000031
1000000003110000000031
10000000031
 
Armstrong v. Chesapeake Exploration Court Decision
Armstrong v. Chesapeake Exploration Court DecisionArmstrong v. Chesapeake Exploration Court Decision
Armstrong v. Chesapeake Exploration Court Decision
 
Writing Sample - Sealing Records Memo
Writing Sample - Sealing Records MemoWriting Sample - Sealing Records Memo
Writing Sample - Sealing Records Memo
 
BANK OF AMERICA FORECLOSURE, ANSWER, AFFIRMATIVE DEFENSES, COUNTERCLAIM
BANK OF AMERICA FORECLOSURE, ANSWER, AFFIRMATIVE DEFENSES, COUNTERCLAIMBANK OF AMERICA FORECLOSURE, ANSWER, AFFIRMATIVE DEFENSES, COUNTERCLAIM
BANK OF AMERICA FORECLOSURE, ANSWER, AFFIRMATIVE DEFENSES, COUNTERCLAIM
 
10000000032
1000000003210000000032
10000000032
 
Declaración por escrito del Estado Plurinacional de Bolivia en la excepción p...
Declaración por escrito del Estado Plurinacional de Bolivia en la excepción p...Declaración por escrito del Estado Plurinacional de Bolivia en la excepción p...
Declaración por escrito del Estado Plurinacional de Bolivia en la excepción p...
 
Defence of Residential Dwellings at Law
Defence of Residential Dwellings at LawDefence of Residential Dwellings at Law
Defence of Residential Dwellings at Law
 
10000001237
1000000123710000001237
10000001237
 
10000001240
1000000124010000001240
10000001240
 
Supreme Court Opinion
Supreme Court OpinionSupreme Court Opinion
Supreme Court Opinion
 
Doc876 robbins tapp cobb & assoc accountants_work done_final comp
Doc876 robbins tapp cobb & assoc accountants_work done_final comp Doc876 robbins tapp cobb & assoc accountants_work done_final comp
Doc876 robbins tapp cobb & assoc accountants_work done_final comp
 
Dewing v. Abarta Oil & Gas Co. - PA Superior Court Ruling
Dewing v. Abarta Oil & Gas Co. - PA Superior Court RulingDewing v. Abarta Oil & Gas Co. - PA Superior Court Ruling
Dewing v. Abarta Oil & Gas Co. - PA Superior Court Ruling
 

Viewers also liked

From UFOs to UDCs: building research collections in a new era
From UFOs to UDCs: building research collections in a new eraFrom UFOs to UDCs: building research collections in a new era
From UFOs to UDCs: building research collections in a new eraUniversity College Cork
 
4th Workshop on Strategic Crisis Management, Presentation, Panel 1 - Horizon ...
4th Workshop on Strategic Crisis Management, Presentation, Panel 1 - Horizon ...4th Workshop on Strategic Crisis Management, Presentation, Panel 1 - Horizon ...
4th Workshop on Strategic Crisis Management, Presentation, Panel 1 - Horizon ...OECD Governance
 
Witchcraft spells for wishes
Witchcraft spells for wishesWitchcraft spells for wishes
Witchcraft spells for wishesMeenal Sharma
 
JavaScript: Implementations And Applications
JavaScript: Implementations And ApplicationsJavaScript: Implementations And Applications
JavaScript: Implementations And ApplicationsPragya Pai
 
ITNEW Wake smart alarm
ITNEW Wake smart alarmITNEW Wake smart alarm
ITNEW Wake smart alarmJidapa Kam
 
4th Workshop on Strategic Crisis Management, Panel 1 - Risk and crisis antici...
4th Workshop on Strategic Crisis Management, Panel 1 - Risk and crisis antici...4th Workshop on Strategic Crisis Management, Panel 1 - Risk and crisis antici...
4th Workshop on Strategic Crisis Management, Panel 1 - Risk and crisis antici...OECD Governance
 
Koofi La-Yoofi 2
Koofi La-Yoofi 2Koofi La-Yoofi 2
Koofi La-Yoofi 2Wajid Malik
 
4th Workshop on Strategic Crisis Management, Keynote Presentation - Strategic...
4th Workshop on Strategic Crisis Management, Keynote Presentation - Strategic...4th Workshop on Strategic Crisis Management, Keynote Presentation - Strategic...
4th Workshop on Strategic Crisis Management, Keynote Presentation - Strategic...OECD Governance
 
35 Mitigating Factors by MitigationAssistant.com
35 Mitigating Factors by MitigationAssistant.com35 Mitigating Factors by MitigationAssistant.com
35 Mitigating Factors by MitigationAssistant.comgemusli23
 

Viewers also liked (15)

From UFOs to UDCs: building research collections in a new era
From UFOs to UDCs: building research collections in a new eraFrom UFOs to UDCs: building research collections in a new era
From UFOs to UDCs: building research collections in a new era
 
Bicol Christian College
Bicol Christian CollegeBicol Christian College
Bicol Christian College
 
4th Workshop on Strategic Crisis Management, Presentation, Panel 1 - Horizon ...
4th Workshop on Strategic Crisis Management, Presentation, Panel 1 - Horizon ...4th Workshop on Strategic Crisis Management, Presentation, Panel 1 - Horizon ...
4th Workshop on Strategic Crisis Management, Presentation, Panel 1 - Horizon ...
 
Shailesh Gosavi. (2015)
Shailesh Gosavi. (2015)Shailesh Gosavi. (2015)
Shailesh Gosavi. (2015)
 
Witchcraft spells for wishes
Witchcraft spells for wishesWitchcraft spells for wishes
Witchcraft spells for wishes
 
Microcontrollers
MicrocontrollersMicrocontrollers
Microcontrollers
 
JavaScript: Implementations And Applications
JavaScript: Implementations And ApplicationsJavaScript: Implementations And Applications
JavaScript: Implementations And Applications
 
ITNEW Wake smart alarm
ITNEW Wake smart alarmITNEW Wake smart alarm
ITNEW Wake smart alarm
 
4th Workshop on Strategic Crisis Management, Panel 1 - Risk and crisis antici...
4th Workshop on Strategic Crisis Management, Panel 1 - Risk and crisis antici...4th Workshop on Strategic Crisis Management, Panel 1 - Risk and crisis antici...
4th Workshop on Strategic Crisis Management, Panel 1 - Risk and crisis antici...
 
Koofi La-Yoofi 2
Koofi La-Yoofi 2Koofi La-Yoofi 2
Koofi La-Yoofi 2
 
4th Workshop on Strategic Crisis Management, Keynote Presentation - Strategic...
4th Workshop on Strategic Crisis Management, Keynote Presentation - Strategic...4th Workshop on Strategic Crisis Management, Keynote Presentation - Strategic...
4th Workshop on Strategic Crisis Management, Keynote Presentation - Strategic...
 
Los 25 pueblos mas bonitos de europa1
Los 25 pueblos mas bonitos de europa1Los 25 pueblos mas bonitos de europa1
Los 25 pueblos mas bonitos de europa1
 
variable aleatoria
variable aleatoriavariable aleatoria
variable aleatoria
 
35 Mitigating Factors by MitigationAssistant.com
35 Mitigating Factors by MitigationAssistant.com35 Mitigating Factors by MitigationAssistant.com
35 Mitigating Factors by MitigationAssistant.com
 
Analisis software
Analisis softwareAnalisis software
Analisis software
 

Similar to NSW District Court Overturns Tribunal Ruling in Building Dispute

1. For the short essay questions write your answers in the space pro.docx
1. For the short essay questions write your answers in the space pro.docx1. For the short essay questions write your answers in the space pro.docx
1. For the short essay questions write your answers in the space pro.docxSONU61709
 
Adjudication: Challenging the Adjudicator's Jurisdiction
Adjudication: Challenging the Adjudicator's JurisdictionAdjudication: Challenging the Adjudicator's Jurisdiction
Adjudication: Challenging the Adjudicator's JurisdictionFrancis Ho
 
5 a law and ethics discharge of contract, remedies and injunctions
5 a law and ethics discharge of contract, remedies and injunctions5 a law and ethics discharge of contract, remedies and injunctions
5 a law and ethics discharge of contract, remedies and injunctionsmsstephanielord
 
Miles v. deutsche bank national trust company | find law
Miles v. deutsche bank national trust company | find lawMiles v. deutsche bank national trust company | find law
Miles v. deutsche bank national trust company | find lawJustin Gluesing
 
The Lord of Law: Major Nourhaghighi's Factum before the Court of Appeal for O...
The Lord of Law: Major Nourhaghighi's Factum before the Court of Appeal for O...The Lord of Law: Major Nourhaghighi's Factum before the Court of Appeal for O...
The Lord of Law: Major Nourhaghighi's Factum before the Court of Appeal for O...nourhaghighi
 
citimortgage robo signers
citimortgage robo signerscitimortgage robo signers
citimortgage robo signerstsimmonsia
 
DUBAI-DIAC Request For Arbitration in Construction Contracts Disputes (Real C...
DUBAI-DIAC Request For Arbitration in Construction Contracts Disputes (Real C...DUBAI-DIAC Request For Arbitration in Construction Contracts Disputes (Real C...
DUBAI-DIAC Request For Arbitration in Construction Contracts Disputes (Real C...César del Riego y Fuentes
 
Cases on discharge of contract
Cases on discharge of contractCases on discharge of contract
Cases on discharge of contractLe Hong Phong
 
King county-superior-court-order-on-rha-v-city-of-seattle-22421
King county-superior-court-order-on-rha-v-city-of-seattle-22421King county-superior-court-order-on-rha-v-city-of-seattle-22421
King county-superior-court-order-on-rha-v-city-of-seattle-22421Roger Valdez
 
Doc1037 robert oneil paul ballard_todd hickman_seeking approval_settlement & ...
Doc1037 robert oneil paul ballard_todd hickman_seeking approval_settlement & ...Doc1037 robert oneil paul ballard_todd hickman_seeking approval_settlement & ...
Doc1037 robert oneil paul ballard_todd hickman_seeking approval_settlement & ...malp2009
 
UK Adjudicators Newsletter November 2021
UK Adjudicators  Newsletter November 2021UK Adjudicators  Newsletter November 2021
UK Adjudicators Newsletter November 2021SeanGibbs12
 
Year In Review (Nov. 29)
Year In Review (Nov. 29)Year In Review (Nov. 29)
Year In Review (Nov. 29)bradsugarman
 
How to Prepare for Small Claims Court to Collect Rental Debt in San Diego
How to Prepare for Small Claims Court to Collect Rental Debt in San DiegoHow to Prepare for Small Claims Court to Collect Rental Debt in San Diego
How to Prepare for Small Claims Court to Collect Rental Debt in San DiegoMadisonWilliamson2
 

Similar to NSW District Court Overturns Tribunal Ruling in Building Dispute (20)

QDC03-148
QDC03-148QDC03-148
QDC03-148
 
1. For the short essay questions write your answers in the space pro.docx
1. For the short essay questions write your answers in the space pro.docx1. For the short essay questions write your answers in the space pro.docx
1. For the short essay questions write your answers in the space pro.docx
 
Lecture 13 duress - cases
Lecture 13   duress - casesLecture 13   duress - cases
Lecture 13 duress - cases
 
Adjudication: Challenging the Adjudicator's Jurisdiction
Adjudication: Challenging the Adjudicator's JurisdictionAdjudication: Challenging the Adjudicator's Jurisdiction
Adjudication: Challenging the Adjudicator's Jurisdiction
 
5 a law and ethics discharge of contract, remedies and injunctions
5 a law and ethics discharge of contract, remedies and injunctions5 a law and ethics discharge of contract, remedies and injunctions
5 a law and ethics discharge of contract, remedies and injunctions
 
Miles v. deutsche bank national trust company | find law
Miles v. deutsche bank national trust company | find lawMiles v. deutsche bank national trust company | find law
Miles v. deutsche bank national trust company | find law
 
The Lord of Law: Major Nourhaghighi's Factum before the Court of Appeal for O...
The Lord of Law: Major Nourhaghighi's Factum before the Court of Appeal for O...The Lord of Law: Major Nourhaghighi's Factum before the Court of Appeal for O...
The Lord of Law: Major Nourhaghighi's Factum before the Court of Appeal for O...
 
Lecture 12 privity - notes
Lecture 12   privity - notesLecture 12   privity - notes
Lecture 12 privity - notes
 
Mistake
MistakeMistake
Mistake
 
citimortgage robo signers
citimortgage robo signerscitimortgage robo signers
citimortgage robo signers
 
DUBAI-DIAC Request For Arbitration in Construction Contracts Disputes (Real C...
DUBAI-DIAC Request For Arbitration in Construction Contracts Disputes (Real C...DUBAI-DIAC Request For Arbitration in Construction Contracts Disputes (Real C...
DUBAI-DIAC Request For Arbitration in Construction Contracts Disputes (Real C...
 
Cases on discharge of contract
Cases on discharge of contractCases on discharge of contract
Cases on discharge of contract
 
King county-superior-court-order-on-rha-v-city-of-seattle-22421
King county-superior-court-order-on-rha-v-city-of-seattle-22421King county-superior-court-order-on-rha-v-city-of-seattle-22421
King county-superior-court-order-on-rha-v-city-of-seattle-22421
 
Doc1037 robert oneil paul ballard_todd hickman_seeking approval_settlement & ...
Doc1037 robert oneil paul ballard_todd hickman_seeking approval_settlement & ...Doc1037 robert oneil paul ballard_todd hickman_seeking approval_settlement & ...
Doc1037 robert oneil paul ballard_todd hickman_seeking approval_settlement & ...
 
UK Adjudicators Newsletter November 2021
UK Adjudicators  Newsletter November 2021UK Adjudicators  Newsletter November 2021
UK Adjudicators Newsletter November 2021
 
Bad Faith Nov2013 covenant judgments
Bad Faith Nov2013 covenant judgments Bad Faith Nov2013 covenant judgments
Bad Faith Nov2013 covenant judgments
 
TORT II [remedy notes]
TORT II [remedy notes]TORT II [remedy notes]
TORT II [remedy notes]
 
Geosource Case Study
Geosource Case StudyGeosource Case Study
Geosource Case Study
 
Year In Review (Nov. 29)
Year In Review (Nov. 29)Year In Review (Nov. 29)
Year In Review (Nov. 29)
 
How to Prepare for Small Claims Court to Collect Rental Debt in San Diego
How to Prepare for Small Claims Court to Collect Rental Debt in San DiegoHow to Prepare for Small Claims Court to Collect Rental Debt in San Diego
How to Prepare for Small Claims Court to Collect Rental Debt in San Diego
 

More from Alec Rendell [NBPR-2]

McKenzie v Dean T.as T & D Dean Building [2003] NSWCTTT 386
McKenzie v Dean T.as T & D Dean Building [2003] NSWCTTT 386McKenzie v Dean T.as T & D Dean Building [2003] NSWCTTT 386
McKenzie v Dean T.as T & D Dean Building [2003] NSWCTTT 386Alec Rendell [NBPR-2]
 
Dwyer v Kelly (Home Building) [2007] NSWCTTT 442
Dwyer v Kelly (Home Building) [2007] NSWCTTT 442Dwyer v Kelly (Home Building) [2007] NSWCTTT 442
Dwyer v Kelly (Home Building) [2007] NSWCTTT 442Alec Rendell [NBPR-2]
 
Ultra Developments Pty Ltd v Nagle (Home Building) [2012] NSWCTTT 518
Ultra Developments Pty Ltd v Nagle (Home Building) [2012] NSWCTTT 518Ultra Developments Pty Ltd v Nagle (Home Building) [2012] NSWCTTT 518
Ultra Developments Pty Ltd v Nagle (Home Building) [2012] NSWCTTT 518Alec Rendell [NBPR-2]
 
FORDHAM #1 of 3; Fordham v Hobson (Home Building) [2011] NSWCTTT 164
FORDHAM #1 of 3; Fordham v Hobson (Home Building) [2011] NSWCTTT 164FORDHAM #1 of 3; Fordham v Hobson (Home Building) [2011] NSWCTTT 164
FORDHAM #1 of 3; Fordham v Hobson (Home Building) [2011] NSWCTTT 164Alec Rendell [NBPR-2]
 
Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61
Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61
Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61Alec Rendell [NBPR-2]
 
Tyler & Miller v Rawson Homes P.L (Home Building) [2005] NSWCTTT 153
Tyler & Miller v Rawson Homes P.L (Home Building) [2005] NSWCTTT 153Tyler & Miller v Rawson Homes P.L (Home Building) [2005] NSWCTTT 153
Tyler & Miller v Rawson Homes P.L (Home Building) [2005] NSWCTTT 153Alec Rendell [NBPR-2]
 
Gugliemino v Advance Flooring Co P.L (Home Building) [2005] NSWCTTT 162
Gugliemino v Advance Flooring Co P.L (Home Building) [2005] NSWCTTT 162Gugliemino v Advance Flooring Co P.L (Home Building) [2005] NSWCTTT 162
Gugliemino v Advance Flooring Co P.L (Home Building) [2005] NSWCTTT 162Alec Rendell [NBPR-2]
 
Rich v Fair Trading Administration Corporation [2000] NSWFTT 10
Rich v Fair Trading Administration Corporation [2000] NSWFTT 10Rich v Fair Trading Administration Corporation [2000] NSWFTT 10
Rich v Fair Trading Administration Corporation [2000] NSWFTT 10Alec Rendell [NBPR-2]
 
'Arlie' Private Residence; Lyndhurst NSW
'Arlie' Private Residence; Lyndhurst NSW'Arlie' Private Residence; Lyndhurst NSW
'Arlie' Private Residence; Lyndhurst NSWAlec Rendell [NBPR-2]
 

More from Alec Rendell [NBPR-2] (20)

McKenzie v Dean T.as T & D Dean Building [2003] NSWCTTT 386
McKenzie v Dean T.as T & D Dean Building [2003] NSWCTTT 386McKenzie v Dean T.as T & D Dean Building [2003] NSWCTTT 386
McKenzie v Dean T.as T & D Dean Building [2003] NSWCTTT 386
 
Dwyer v Kelly (Home Building) [2007] NSWCTTT 442
Dwyer v Kelly (Home Building) [2007] NSWCTTT 442Dwyer v Kelly (Home Building) [2007] NSWCTTT 442
Dwyer v Kelly (Home Building) [2007] NSWCTTT 442
 
Ultra Developments Pty Ltd v Nagle (Home Building) [2012] NSWCTTT 518
Ultra Developments Pty Ltd v Nagle (Home Building) [2012] NSWCTTT 518Ultra Developments Pty Ltd v Nagle (Home Building) [2012] NSWCTTT 518
Ultra Developments Pty Ltd v Nagle (Home Building) [2012] NSWCTTT 518
 
FORDHAM #1 of 3; Fordham v Hobson (Home Building) [2011] NSWCTTT 164
FORDHAM #1 of 3; Fordham v Hobson (Home Building) [2011] NSWCTTT 164FORDHAM #1 of 3; Fordham v Hobson (Home Building) [2011] NSWCTTT 164
FORDHAM #1 of 3; Fordham v Hobson (Home Building) [2011] NSWCTTT 164
 
Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61
Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61
Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61
 
Tyler & Miller v Rawson Homes P.L (Home Building) [2005] NSWCTTT 153
Tyler & Miller v Rawson Homes P.L (Home Building) [2005] NSWCTTT 153Tyler & Miller v Rawson Homes P.L (Home Building) [2005] NSWCTTT 153
Tyler & Miller v Rawson Homes P.L (Home Building) [2005] NSWCTTT 153
 
Gugliemino v Advance Flooring Co P.L (Home Building) [2005] NSWCTTT 162
Gugliemino v Advance Flooring Co P.L (Home Building) [2005] NSWCTTT 162Gugliemino v Advance Flooring Co P.L (Home Building) [2005] NSWCTTT 162
Gugliemino v Advance Flooring Co P.L (Home Building) [2005] NSWCTTT 162
 
Rich v Fair Trading Administration Corporation [2000] NSWFTT 10
Rich v Fair Trading Administration Corporation [2000] NSWFTT 10Rich v Fair Trading Administration Corporation [2000] NSWFTT 10
Rich v Fair Trading Administration Corporation [2000] NSWFTT 10
 
MOLONG CENTRAL SCHOOL CAPITAL WORKS
MOLONG CENTRAL SCHOOL CAPITAL WORKSMOLONG CENTRAL SCHOOL CAPITAL WORKS
MOLONG CENTRAL SCHOOL CAPITAL WORKS
 
Orphan Rocker; Katoomba
Orphan Rocker; KatoombaOrphan Rocker; Katoomba
Orphan Rocker; Katoomba
 
Coonabarabran Hospital Upgrade
Coonabarabran Hospital Upgrade Coonabarabran Hospital Upgrade
Coonabarabran Hospital Upgrade
 
Gundagai High School
Gundagai High SchoolGundagai High School
Gundagai High School
 
RSL Club; Dubbo NSW
RSL Club; Dubbo NSWRSL Club; Dubbo NSW
RSL Club; Dubbo NSW
 
Katoomba Public School; NSW
Katoomba Public School; NSWKatoomba Public School; NSW
Katoomba Public School; NSW
 
Supa K-Mart; Katoomba. NSW
Supa K-Mart; Katoomba. NSWSupa K-Mart; Katoomba. NSW
Supa K-Mart; Katoomba. NSW
 
Lithgow Tafe; Lithgow. NSW
Lithgow Tafe; Lithgow. NSWLithgow Tafe; Lithgow. NSW
Lithgow Tafe; Lithgow. NSW
 
Calvary Hospital; Wagga Wagga NSW
Calvary Hospital; Wagga Wagga NSWCalvary Hospital; Wagga Wagga NSW
Calvary Hospital; Wagga Wagga NSW
 
Public School; Menindee NSW
Public School; Menindee NSWPublic School; Menindee NSW
Public School; Menindee NSW
 
Band Club Restoration; St Marys NSW
Band Club Restoration; St Marys NSWBand Club Restoration; St Marys NSW
Band Club Restoration; St Marys NSW
 
'Arlie' Private Residence; Lyndhurst NSW
'Arlie' Private Residence; Lyndhurst NSW'Arlie' Private Residence; Lyndhurst NSW
'Arlie' Private Residence; Lyndhurst NSW
 

NSW District Court Overturns Tribunal Ruling in Building Dispute

  • 1. - 1 - District Court New South Wales Case Title: Fordham v Dewsash Pty Ltd t/as S.P. & W. Hobson Medium Neutral Citation: [2012] NSWDC 109 Hearing Date(s): 25/05/2012 and 28/05/2012 Decision Date: 27 July 2012 Jurisdiction: Before: P Taylor SC DCJ Decision: 1. Allow the appeal. 2. Set aside the orders of the Tribunal. 3. Remit the matter to the Tribunal for a rehearing in accordance with these reasons, pursuant to ss 67(3)(b) and (4) of the CTTT Act. 4. Order that the plaintiff's costs of the appeal be costs of the proceedings in the Tribunal. Catchwords: Appeal from Tribunal - question with respect to matter of law - no evidence - agreement - mitigation of loss - quantum of damages - estoppel - costs Legislation Cited: Consumer, Trader and Tenancy Tribunal Act 2001 Cases Cited: Kostas v HIA Insurance Services Pty Limited [2010] HCA 32 Mahlo & Ors v Westpac Banking Corporation Ltd [1999] NSWCA 358 Pavey & Matthews v Paul (1987) 162 CLR 221 Texts Cited: Category: Principal judgment
  • 2. - 2 - Parties: James Arthur Fordham (plaintiff) Dewsash Pty Limited t/as S.P. & W. Hobson (defendant) Representation - Counsel: Mr J Young (plaintiff) Mr S V Shepherd (defendant) - Solicitors: Blackwell Short Lawyers (plaintiff) Creaghe Lisle Solicitors (defendant) File number(s): 2011/165234 Decision Under Appeal - Court / Tribunal: - Before: Tribunal Member S Smith - Date of Decision: 17 March 2011 - Citation: - Court File Number(s) HB 09/25483; HB 10/21874 Publication Restriction: No JUDGMENT A. Introduction 1 This is an appeal from a decision of the Consumer, Trader and Tenancy Tribunal ("the Tribunal") under s 67 of the Consumer, Trader and Tenancy Tribunal Act 2001 ("the CTTT Act"), in respect of a building dispute. B. Background 2 The facts as found by the Tribunal were as follows.
  • 3. - 3 - 3 Mr Fordham, the plaintiff, owned some rural land at Bendick Murrell in the central west of New South Wales. He had plans to build a cottage. He negotiated with Mr Hobson, the owner of the defendant's building company, and on 25 June 2002 the parties entered a standard HIA contract for the building of the house. The contract provided for a price of $187,000 with no deposit, and a schedule of progress payments commencing with $50,000 when the slab and underfloor plumbing were complete. 4 Site work commenced in November 2002, and after many inspections and rectifications the main part of the slab was poured on 13 May 2003. 5 In April 2003, shortly before the slab was poured, the defendant presented the plaintiff with invoices totalling $36,000. As the slab had not been poured, the plaintiff may have been within his rights to make no payment until all works referable to the first progress payment were substantially complete. In any event, on about 28 April 2003 the plaintiff paid the defendant $29,000. 6 After the slab was poured, a further dispute arose between the parties concerning the adequacy of the slab. Experts were retained. After some debate those experts, Mr Simpson for the defendant, and Mr Noonan for the plaintiff, agreed on a rectification procedure whereby a concrete topping would be put on the existing slab to allow for a shower set down and to provide some stiffening of the overall structure. 7 Ultimately, no concrete topping was installed. The plaintiff engaged a new builder, and demolished the existing slab. C. The Tribunalproceedings
  • 4. - 4 - 8 The Tribunal member determined that the matter required him to determine three issues: (a) Was the slab as built a breach of the building contract; (b) Did the plaintiff mitigate his loss if there was a breach; and (c) Which party had the right to terminate the contract. 9 In the course of dealing with these three issues, the Tribunal member made findings which can be summarized as follows: (i) Contrary to the defendant's contention, there was no agreement prior to 28 April 2003 (when the invoices were supplied) that $36,000 was payable upon the pouring of the main slab with the veranda slab to be poured separately. (ii) On about 28 April 2003 the contract was varied by agreement (or by the plaintiff allowing the defendant to imagine that he agreed) so that a further amount of $7,000 (in addition to the $29,000 paid on that day) was to be paid on completion of the slab. (iii) The refusal by the plaintiff to pay the additional $7,000 indicated an unwillingness by the plaintiff to be bound by the contract as agreed and empowered the builder to stop work. (iv) This variation of the contract was an informal variation, such that the builder could not assert a right to payment under the contract but was entitled to rely on a quantum meruit. (v) The plaintiff was estopped from disputing that the value of the slab was an additional $7,000 in addition to the $29,000 already paid. (vi) The builder was entitled to succeed on the cross-claim for $7,000. (vii) There is an argument that the slab satisfied the contractual requirements, but because other aspects of the case are fatal to the
  • 5. - 5 - plaintiff's claim the question of breach of contract need not be decided. (viii) The compromise reached between the experts about a topping slab was binding on the parties, and governed their rights and responsibilities. (ix) The need to strengthen the slab was a consequence of the way the builder constructed the slab and so the builder must bear the cost of the extra works. (x) The only evidence of the value of the extra works was Mr Simpson's estimate of $8,000, which was accepted. (xi) Were there a breach of contract by the builder, the plaintiff had a duty to take all reasonable steps to mitigate his loss, by selecting the cheapest solutions reasonably available. (xii) The plaintiff's expert, Mr Noonan, withdrew his approval to the slab topping even though he had agreed previously. It was possible he had succumbed to pressure from the plaintiff, and as a result, little weight could be given to Mr Noonan in measuring reasonableness. Mr Simpson seemed ready, willing and able to certify the slab topping, and his evidence was preferred to Mr Noonan's. (xiii) The plaintiff unreasonably refused to proceed with the topping slab and failed to mitigate his loss, which would otherwise be $8,000. (xiv) The plaintiff should pay the defendant's costs. D. The Appeal 10 The plaintiff appealed from the Tribunal decision pursuant to section 67 of the CTTT Act. Section 67 contains the following provisions:
  • 6. - 6 - "(1) If, in respect of any proceedings, the Tribunal decides a question with respect to a matter of law, a party in the proceedings who is dissatisfied with the decision may, subject to this section, appeal to the District Court against the decision. ... (3) After deciding the question the subject of such an appeal, the District Court may, unless it affirms the decision of the Tribunal on the question: (a) make such order in relation to the proceedings in which the question arose as, in its opinion, should have been made by the Tribunal, or (b) remit its decision on the question to the Tribunal and order a rehearing of the proceedings by the Tribunal. (4) If such a rehearing is held, the Tribunal is not to proceed in a manner, or make an order or a decision, that is inconsistent with the decision of the District Court remitted to the Tribunal." 11 The plaintiff may have commenced the appeal shortly after the prescribed statutory period, without leave. The defendant did not oppose an order for leave to be granted, and accordingly I granted an extension of time for the filing of the appeal to the date of the filing of the appeal. 12 In Kostas v HIA Insurance Services Pty Limited [2010] HCA 32, French CJ at [25] held that: "The words "question with respect to a matter of law" are wide enough to encompass a question of mixed law and fact. Questions of fact and law are often closely intertwined." 13 The plurality in Kostas (Hayne, Heydon, Crennan, Bell JJ) determined at [90] and [91]: "It is sufficient, for present purposes, to determine that the ground usually described as a "no evidence ground" raises a question of law... Whether there was no evidence to support a factual finding is a question of law, not a question of fact...What amounts to material that could support a factual finding is ultimately a question for judicial decision. It is a question of law." 14 The plurality declined at [88] to determine in the abstract the precise ambit of the words "question with respect to a matter of law".
  • 7. - 7 - 15 The plaintiff asserted the following errors by the Tribunal: "1 The finding that the there was an agreement for the Plaintiff to pay $36,000 on completion of the slab. 2 The finding that the Defendant is entitled to a quantum meruit. 3 The finding that the Plaintiff is estopped from asserting that the value of the work related to the completion of the slab was other than $7,000. 4 The finding that the Defendant was entitled to stop work until the $7,000 was paid. 5 The Tribunal failed to make any finding as to Plaintiff's claim for breach of contract. 6 The finding without evidence that Mr Simpson would have certified the slab as built and will certify the slab as augmented. 7 The finding that there was a compromise agreement binding on the parties. 8 The finding without evidence that Mr Noonan resiled from his previous opinion offered. 9 The finding without evidence that Mr Simpson had designed the topping slab and was ready, willing and able to certify it. 10 The finding without evidence that the Plaintiff's entitlement to a quantum of loss of $8,000. 11 The finding that the Plaintiff had failed to mitigate his loss. 12 The finding without evidence that the Plaintiff's claim demolition and reconstruction was (as pleaded) $91,000 in round figures. 13 The Tribunal treated the hearing as a final hearing when it was a hearing on liability and part of quantum only." Ground 1: The agreement to pay $36,000. 16 This ground relates to finding (i) and (ii) of the Tribunal set out in paragraph 10 above. 17 The plaintiff alleges that the finding of an agreement falls within s 67 on two bases: it is a mixed question of fact and law, and in any event there was no evidence to support the finding. It is clear from Kostas that the second basis falls with the ambit of the appeal jurisdiction created by s 67. I am also of the view that in the circumstances of this case, a finding of an agreement is a mixed question of fact and law, which would fall within the ambit of s 67 according to the decision of the Chief Justice in Kostas at [25].
  • 8. - 8 - 18 The undisputed evidence was that on or about 28th April 2003, before the slab was poured, the defendant gave the plaintiff three documents, these being: (a) Tax Invoice 0184 for $36,000; (b) Part A Progress Claim No. 1 for $29,000 dated 27th April 2003; and (c) Part B Progress Claim No. 1 for $7,000 dated 27th April 2003. 19 On 28 or 29 April 2003, the plaintiff paid the defendant $29,000. The plaintiff's evidence as to the circumstances under which this amount was paid is set out in detail in Annexure "K" to his witness statement dated 30 November 2009 filed with the Tribunal and adhered to under cross- examination at T28/7/2010 p 23.5: Q: I mean the reality is, Mr Fordham, if you haven't paid the builder the $29,000, he wouldn't have poured the slab. A: Would have been good if he hadn't. Q: But he wouldn't have poured it if you hadn't paid it. A: Paul rang me a couple of days before that date that I paid, and asked me, because of the delay in time, and the fact that his contract - he couldn't pay his contractors, he'd outlaid a lot of money and he couldn't pay his contractors, the kids were - their kids were starving, could I make an advance on progress payment number 1, and I agreed to that. He couldn't tell me how much he wanted upon that date. Three or four days later when he turned up on the Sunday, he had these payments already - progress payments already made out, and I was astounded at the amount, because the amount of work that had been done to that date didn't amount to $29,000. Nevertheless, I paid him the $29,000 which is what he asked for, and then when I saw the second progress payment, number 2B or whatever he called, for $7,000, that's when I said, "No, that's $21,000, its not due until the veranda slabs are done and all that sort of thing". Q: Would he have poured the slab if you hadn't paid him the $29,000? A: I doubt it, I'm sure that he wouldn't have. 20 This evidence denies an agreement to pay the further sum of $7,000. The defendant asserted that it was open to the Tribunal to reject the plaintiff's evidence, and, in that event, the Tribunal's finding of an agreement to pay a total of $36,000 was not so illogical or against the weight of the evidence as to constitute an error of law.
  • 9. - 9 - 21 The difficulty with the defendant's submission is that the rejection of the plaintiff's evidence does not operate to supply the contrary evidence. The Tribunal accepted that the sum of $50,000 was due under the contract when the slabs were complete. I accept that the invoices delivered to the plaintiff constitute evidence of an offer by the builder for a variation to the effect that $29,000 be paid on 28 April 2003 and that $7,000 be paid after the pouring of the main slab. 22 However, I do not think that the payment of $29,000, without more, is sufficient to support a finding of an agreement that a further $7,000 would be paid after the main slab was poured. 23 The evidence of Mr Hobson was as follows (T29/7/2010 pp 6.45-7.11): Q: What you were saying yesterday is the contract says, "slab complete $50,000". You were saying, "Oh no, that's what it might say, but in my mind, slab complete means the home and the house slab because I built the veranda later". Mr. Shepherd led evidence from you yesterday to indicate that there was a variation to that $50,000, based on conversations which allowed you then to submit a claim for $36,000, remember that? A: Mm-hmm. Q: Why was it necessary to have a variation if the contract said $50,000 on completion of slab, and you, in your mind, had completed the slab that you thought was included in that $50,000? A: The word variation, wasn't actually a variation. Like it was - it was just - the figures were all there, and because the time lapse went on for so long, I had made a claim for the money that I actually put into the place at that time, and that came to that amount for the slab, and the difference was for the veranda slab. Now, to me, a variation is when there's a plus or minus cost, and there's no plus or minus, I was just requesting a payment for what I've done. And at T28/7/2010 p 63.45-63.50: Q: If the contract was to be varied by postponing the construction of the veranda, why did you not document it as you did with the three minor variations? A: Possibly because I didn't believe it as a variation because no money is going to be on it, plus or minus. Like to me, it's not a variation, it's just a different program of work. Wasn't going to cost me any money or Mr. Fordham.
  • 10. - 10 - 24 This evidence does not seem to me to support a variation of the agreement to require a payment of a total of $36,000 after the pouring of the main slab. The Tribunal member noted that no claim of duress or lack of consideration was maintained by the plaintiff in respect of the variation but the absence of such a claim does not supply evidence of acceptance by the plaintiff of the obligation to pay a further $7,000. There is no conduct or words by the plaintiff in any of the evidence that indicates an acceptance of the proposal by the defendant. I do not regard invoices sent after the event as supplying evidence of an agreement. 25 Accordingly, I find that there was no foundation for any findings of a varied agreement by the Tribunal other than an agreement to pay $29,000 in late April 2003. To some extent this lack of evidence is recognized by the Tribunal by its alternative finding of "allowing Mr Hobson to imagine that he agreed". This alternative finding suggests that there was no acceptance, rather that the conduct of the plaintiff gave rise to some form of estoppel. An estoppel by conduct requires that there be evidence of the conduct giving rise to an assumption, or reliance, by the defendant so as to act to its detriment. These are not matters the subject of findings by the Tribunal, and do not appear to be supported by evidence. I do not regard the finding quoted earlier in this paragraph as sufficient to establish an estoppel. 26 It follows that ground 1 is established: the finding by the Tribunal of an agreement between the parties for the plaintiff to pay a further $7,000 on the pouring of the slab is an erroneous finding with respect to a matter of law. Ground 2: the defendant is entitled to a quantum meruit 27 The Tribunal also relied upon quantum meruit and the decision in Pavey & Matthews v Paul (1987) 162 CLR 221 (see finding (iv) in paragraph 9 above.
  • 11. - 11 - 28 An action in indebitatus assumpsit for the value of the work done and materials supplied, otherwise known as an action on a quantum meruit, depends on proof by the builder that he did the work and that the owner accepted the work without paying the agreed remuneration: Pavey v Matthews at 228. 29 In the present case, it is not in dispute that the builder did the work, but the owner's acceptance of the work and the agreed remuneration remain matters in dispute. I have already decided that there was no evidence of an agreed remuneration upon the pouring of the primary slab. Nor do I think, in circumstances where the parties have been found to have agreed upon the need for a topping slab, that there was acceptance of the work done, at least not without rectification. 30 The defendant submitted (at [53] of its submissions): "...the position as at the time the applicant terminated the contract was that the common ground was that the builder had completed this work and therefore must be entitled to payment for what he had done as at the time the contract was terminated. Any putative entitlement to damages for breach of the contract must nevertheless account for the builder's entitlement to payment for work done." 31 Of course, the owner must give credit for any work done. But if the owner has terminated the contract for breach, the builder is only entitled to payment for work done to the extent that the costs to complete the work (including payments already made to the builder) are less than the contract value. So much was provided for in clause 36.4 of the contract which stated: 36.4 If the costs incurred by the owner are: (a) more than the unpaid balance of the contract price the builder must pay the difference to the owner within 7 working days of receiving the notice from the owner; or (b) less than the unpaid balance of the contract price the owner must pay the difference when giving the notice as a debt due and payable. [emphasis omitted]
  • 12. - 12 - 32 It follows that the value of the work done by the builder must take account of the cost of the remedial topping slab, and, potentially, the cost to complete the work. It was an error for the Tribunal to ignore these costs and simply award the builder the $7,000 as the additional value of the work done to date. Ground 3: the plaintiff is estopped from asserting the value of completing the slab was other than $7,000. 33 This finding of the Tribunal ((v) in paragraph 9 above) is dependent upon the finding of an agreement. The Tribunal member found: "I note that at least one count in the builder's claim was founded on an estoppel. In my opinion the part played by estoppel in this matter goes to the amount of the quantum meruit being the value of the work done. Because Mr Hobson acted to his detriment on the promise of Mr Fordham to pay the outstanding balance of $7,000 for the completion of house slab, I do not think he can be heard now to say that its value is other than $7,000.00 and that it is payable forthwith." 34 The Tribunal's reasons indicate that the estoppel claim is not an alternative to the agreement, but an addendum: there was an agreement to pay for the value of the work on completion of the slab, and the plaintiff is estopped from denying (for the purposes of that agreement) that the value of the slab is a further $7,000. 35 If there is no evidence of agreement, this finding also must be in error. 36 Further, an estoppel by conduct requires a party to act to its detriment. The detriment in this case was alleged to be the pouring of the slab. 37 There was evidence from Mr Fordham that the builder would not (or would not likely) have poured the slab if the $29,000 was not paid. But there was no evidence from either party that the builder would not have poured the slab if the owner had not promised to pay a further $7,000 on completion of the slab, and no questions to that effect were directed to the owner. I do
  • 13. - 13 - not accept that the mere tendering of an invoice for $7,000 by the builder can be conduct sufficient to support an estoppel, in circumstances where there was discussion and agreement in respect of payment of the invoice for $29,000 in return for the pouring of the slab. 38 The builder submits that it was: "...entirely open to the tribunal to conclude that the applicant encouraged the respondent to act on an assumption that a contact would come into existence or a promise be performed by the applicant (i.e. payment of $36,000) and the applicant intended the respondent to act on that assumption (by part performance of that promise in paying $29,000) and the respondent did act on that assumption to his detriment in that work was performed that otherwise would not have been done and he has not been paid the outstanding amount for which he undertook that work." 39 To make out this submission, there needed to be some evidence, perhaps from the builder, to the effect that he poured the slab because of some conduct of the owner in respect of the invoice for $36,000, or the invoice for $7,000. No such evidence was identified. In the absence of evidence of "encouragement" or "acting on an assumption", there was no basis for the Tribunal's finding. I have already found that the mere tender of an invoice is insufficient. Ground 4: the defendant could stop work until the $7,000 was paid. 40 Again, finding (iii) in [9] above is dependent upon an agreement in respect of the $7,000, which I have rejected on the basis that there was no evidence to support it. It follows that there was no evidence to support an entitlement in the builder to stop work until the $7,000 was paid. Ground 5: failure to make a finding of breach of contract by the builder. 41 It is correct that the Tribunal did not make a finding in respect of breach of contract and expressly reserved that question. However, the Tribunal's finding (based on the finding of a varied agreement) that the builder was
  • 14. - 14 - "empowered to stop work" precluded a finding of breach by the builder in so doing. 42 In the absence of a valid variation, the Tribunal would need to determine whether either party was in breach of the agreement. Conclusion to Grounds (1) - (5) 43 All of these grounds arise out of the Tribunal's decision that there was an agreement between the plaintiff and the defendant to pay $7,000 on completion of the pouring of the main slab. I have found that there is no evidence to support such an agreement, so these grounds are made out. It follows that findings (ii) to (vii) are not supported by any evidence and must be rejected. Grounds 6 and 9: Mr Simpson designed and would have certified the topping slab 44 These grounds concern finding (xii) in [9] above. 45 Mr Noonan, the plaintiff's expert, wrote on 5 August 2007: "The topping slab rectifications proposal by Mr Simpson is a suitable strength rectification provided it is designed and installed correctly." 46 On 24 August 2007, Mr Simpson noted that he was: "...preparing a rectification plan and specification. The plan will involve a systematic inspection of the underside of the edge beam, the removal of any soft plant material found; the refilling of any gaps with compacted granite or high strength concrete slurry: the machine grinding/roughening of the slab surface; the installation of [unreadable] placing of reinforcing mesh and the pouring of a topping slab in two or three segments." "The structural characteristics of the new slab are intended to easily accommodate any movements in the founding soil through settlement or moisture content related shrinking and levelling. In reality the rectified slab will be far stiffer than the original design."
  • 15. - 15 - 47 The evidence also included a facsimile to Mr Fordham from Mr Simpson dated 28 October 2007 which comprised a topping slab plan with notes and specifications, a rectification procedure, and detailed sections at the edges of the existing slab and at the construction joint. 48 Mr Noonan responded on 19 November 2007, writing: "We therefore advise that method of rectification is acceptable provided the additional notes are included in the design drawings for the edge beam rectification." 49 In these circumstances it seems clear to me that there was evidence on which the Tribunal could conclude that Mr Simpson had designed the slab and was willing to certify as built. I therefore reject grounds 6 and 9 of the appeal. Ground 7: there was a compromise agreement concerning the slab rectification which was binding on the parties 50 This ground concerns finding (viii) in [9] above. 51 I refer to the evidence quoted under the previous ground. That evidence supports a finding that there was a compromise agreement concerning the slab rectification, which was binding upon the parties. The plaintiff did not appear to submit otherwise. The primary submission on this ground was that it did not relieve the Tribunal of the need to determine breach (a matter dealt with under another ground of appeal): "If, as it appears, the Tribunal found that there was a compromise agreement between the parties that would govern the way the rectification of the slab progressed, then the Tribunal did not then go to decide which party was in breach of that compromise agreement. This was an error with respect to a matter of law." 52 The plaintiff also submitted that no final plans were prepared. The evidence indicates that an updated plan was to be prepared which might not have been completed, but I think the plans provided at pages 105-106 of the Blue Appeal Book, together with the specifications and rectification
  • 16. - 16 - procedure recorded thereon, were sufficient to enable a finding that a compromise agreement had been reached. 53 Accordingly, I reject ground 7 of the grounds of appeal. Ground 8: Mr Noonan resiled from his previous opinion. 54 This ground concerns finding (xii) in [9] above. 55 It does not appear to be in contest that Mr Noonan did resile from his previous opinion of agreement with Mr Simpson's slab topping proposal. At least Mr Noonan thought that, for reasons which he set out, demolition of the slab was a preferable course. 56 Save for one matter, which is dealt with below, I do not find any errors with the way the Tribunal dealt with Mr Noonan's evidence. Mr Noonan withdrew his approval of the agreed topping slab solution, as the Tribunal found. Also, as the Tribunal found, Mr Noonan's reasons for so doing were not relevantly technical. Mr Noonan did not find that the topping slab would be defective or inappropriate in some way, but was concerned with matters of liability and costs. 57 I think it was open to the Tribunal to adopt Mr Simpson's topping slab solution, as a reasonable and cost effective procedure, on the basis that Mr Noonan had once agreed with it but subsequently changed his mind. However, the Tribunal did not proceed on this basis. Rather, it found that there was a "possibility that Mr Noonan succumbed to pressure from Mr Fordham", and that "as a result" Mr Noonan's revised opinion was given little weight. 58 The defendant refers to a letter from the plaintiff's solicitor (Blue AB 492-3) as "evidence to support that the change of opinion had been encouraged by the plaintiff's solicitors". Although that may be so, I do not think it was
  • 17. - 17 - open to the Tribunal to attribute this possible motivation for Mr Noonan's change of mind and to reject his evidence because of it, in circumstances where Mr Noonan was not cross-examined and the possibility was not put to him. The Tribunal must be cautious before attributing an extraneous motive to an expert, and should not do so unless there is some factual foundation for it. 59 Notwithstanding this error, as I have said, the ultimate finding of the Tribunal on the reasonable rectification procedure was open to it. It would be a matter for the Tribunal to decide whether it now makes the same finding in circumstances where (in the absence of further evidence) it was not entitled to reject Mr Noonan's revised view on the basis of the alleged possibility that Mr Noonan had succumbed to pressure from Mr Fordham. Ground 10: plaintiff entitled to $8,000 only 60 The plaintiff submits that there was no evidence to support the finding that the cost of rectification of the slab was $8,000 (see finding (x) in [9] above). 61 The Tribunal found: "As it turns out, Mr Simpson's estimate of the cost of rectification was the only one before me. He indicated the cost at about $8,000 and I accept that estimate". and "In the circumstances of the present case I am well satisfied that Mr Fordham has not acted reasonably in rejecting the topping slab and has failed to mitigate his loss which would otherwise be $8,000." 62 The basis of this finding is that in re-examination of Mr Simpson on the topic of the topping slab, the following exchange occurred: "Q. Would that have been cheap? A. Without doing the - work, it would have been in the ballpark of $8,000 to $10,000, maybe $12,000."
  • 18. - 18 - 63 It may be that the Tribunal has elevated the evidence of the cost of a slab topping to a level slightly higher than it bore. However, I think the evidence of Mr Simpson is some evidence that the cost of the slab may be $8,000. The fact that a finding of a cost of $9,000 or $10,000 may sit more comfortably with that evidence is not sufficient, in my view, to allow a finding by this court that the cost of $8,000 for the topping slab as found by the Tribunal had no evidentiary basis. 64 The question whether the cost of the topping slab was the proper amount of the plaintiff's damage under the contract, if any, is another matter. I have already dealt with this issue under grounds 1 to 5. I should note that the Tribunal did not find that the plaintiff's loss was $8,000, rather that if there was a breach of contract, "it would sound in damages equal to the homeowners loss according to law, here the $8,000 for the topping slab". Ground 11: the plaintiff failed to mitigate his loss. 65 The finding at (xiii) in [9] above is criticised by the plaintiff on the basis that: "such a finding is relevant where a breach of contract is established [but that] the Member...expressly stated that he was making no finding of breach by the defendant." 66 I accept the plaintiff's submission that the question of a failure to mitigate loss only arises where the Tribunal is endeavouring to assess the damage consequent upon a breach of contract. In the absence of a finding of breach of contract, a finding of a failure to mitigate loss is unnecessary. However, that does not assist the plaintiff on this appeal. If anything, it may support an argument that the $8,000 awarded to the plaintiff could not be sustained. 67 This is another reason (or perhaps the same reason expressed another way) as to why the Tribunal needed to make a finding about breach of contract by the defendant. Unless it did so, there was no cause of action
  • 19. - 19 - established which justified an award of $8,000 or some other sum, in favour of the plaintiff. 68 However, there was a basis (as set out above with respect to grounds 6 to 10) for the Tribunal to find that by not installing a topping slab the plaintiff had failed to mitigate any loss to which he was entitled. I would therefore not reject this finding of the Tribunal. Ground 12: the plaintiff's claim was for $91,000. 69 On 19 October 2009, Member Durie noted: "That the owner has now obtained an owner/builder license and is proceeding with works. It may be necessary (with the consent of the parties) to have an initial hearing on liability and part of the quantum, and a later hearing on the balance of quantum." and on 19 November 2009, Tribunal Member Rossa noted: "The Tribunal further notes that the parties are agreed that the hearing of the application will be in two parts, with liability and part of the quantum to be determined initially, with the balance of the quantum to be determined at a later stage (if liability is established)." 70 It was proposed that, as the Plaintiff submitted: "...the hearing was to determine liability on all issues and, subject to that decision on liability, then go on to determine quantum for the limited component of demolition and reconstruction of the slab." 71 It is not readily apparent to me how the Commissioner could determine "part of the quantum". The difference between the cost of the slab, and the amount paid by the plaintiff to the defendant, is not a proper amount of damage. Certainly the cost of the slab is a component of the overall cost, and the amount paid to the builder is a relevant component of the calculation of the damages to which the plaintiff may become entitled. But the proposal by the parties to separate the cost of the slab from the amount of damages suffered by the plaintiff was misconceived, and seems likely to have contributed to the error made by the Tribunal.
  • 20. - 20 - 72 In the result, nothing turns on this ground, other than perhaps the question of costs. The plaintiff argued that on the question of costs: "...the amount awarded of $8,000 has been compared to the total claim of $91,129.91 instead of the amount referable to the more limited claim for the defective slab claim of $58,790.91. This has had an effect on the costs analysis". 73 I do not accept this submission. Although the Tribunal member noted the claim for $95,000 in deciding the question of costs, the Tribunal member reserved liberty to the parties to make submissions on costs. 74 The Tribunal member revisited the question of costs on 21 April 2011, and gave a decision which, although not in the Blue Appeal Book, was annexed to an affidavit of the plaintiff's solicitor read on the appeal and was thus part of the evidence before the court. 75 The Tribunal member decided: "In response to orders and reasons published on 17 March 2011 the parties have filed and served detailed submissions on the question of costs. I have considered those submissions in deciding the question of costs. As I indicated in my written reasons, the builder has achieved substantial success in his claim but the homeowner's claim in the final analysis was more like $50,000.00, not over $90,000.00 as mentioned in my reasons. While that may be so, the claim as pleaded was in the higher amount and the bulk of the litigation was conducted on that basis. In any event, the difference between the two amounts in relation to the whole of the case and its outcome would have little effect on the exercise of the costs discretion." 76 In the circumstances, I do not think that the Tribunal's decision on costs miscarried because of a failure to recognise that the claim was for $58,000 approximately rather than $91,000. The final decision by the Tribunal in respect of costs contemplated the lower value of the claim.
  • 21. - 21 - 77 However, the decision on costs was affected by the findings considered under grounds 1 to 5 above, which I have found to be in error. Accordingly, the question of costs will need to be revisited by the Tribunal. Ground 13: not a final hearing 78 I have dealt with this matter above. The Tribunal needed to determine whether there was a breach of contract in order to determine whether the plaintiff was entitled to an award of $8,000 on the primary claim. Such an award would have an impact on the appropriate costs order. Generally a plaintiff is entitled to the costs of a successful claim and the defendant would be entitled to the costs of the successful cross-claim, but the costs of a cross-claim would only be those costs which were in addition to those which were incurred in the primary claim: see Mahlo & Ors v Westpac Banking Corporation Ltd [1999] NSWCA 358 at [88]. Whether that general rule should apply in this particular case would be a matter for the Tribunal. Conclusion 79 The parties jointly submitted that if the Tribunal's decision was in error such that the orders could not be affirmed, I should send the matter back to the Tribunal for further consideration. In view of my findings in respect of grounds 1 to 5 of the appeal, the findings of the Tribunal must be set aside, and the matter remitted to the Tribunal for further consideration in accordance with these reasons. In accordance with s 67(7) of the CTTT Act, further evidence "may be given on the rehearing". 80 As to the question of costs, the plaintiff has had some success on the appeal but not on all points. In these circumstances I propose to order that the plaintiff's costs on the appeal be costs of the proceedings in the Tribunal. E. Conclusion and orders
  • 22. - 22 - 81 Accordingly, the orders are: 1. Allow the appeal. 2. Set aside the orders of the Tribunal. 3. Remit the matter to the Tribunal for a rehearing in accordance with these reasons, pursuant to ss 67(3)(b) and (4) of the CTTT Act. 4. Order that the plaintiff's costs of the appeal be costs of the proceedings in the Tribunal. **********