2. The Problem:
The director and other authorized staff
members at the newly converted Agape Learning
Center need a place to quickly store and
retrieve a student’s data. This data also needs
to be protected from hackers and other
threats by security software.
3. Project Overview
This project will create a brand new system
that will track all student information that is
gathered by the learning center. It will then
give a progress report for each student to any
authorized staff member that requests it.
4. Objectives
this new system will provide the following for each student:
Subjects in which they are being tutored
The tutor assigned to the student
Number of session per week
Number of sessions per month
Accounting information
-balances, payments and payment method
-cash, check or charge
Emergency data
Students school information
Home information
A student progress report - Quarterly
5. Benefits
Saves a lot of employee time when looking
and storing data.
Increases accurate entry of student
information.
Reduces errors when storing or retrieving
information.
Increases the stored information’s overall
security.
19. Feasibility
The total system cost including installation is
projected to be around 50,000.00 USD. Shaun
Riordan, our company secretary, has already
bought all the software licenses. Every
software license needs to be renewed
individually every year.
21. Recurring Charges
License/Contract Yearly Cost
Technical support agreement $500
Microsoft ACCESS 2010 $100
CISCO network communication $200
UNDERSTAND IT™ $60
Words Plus Equalizer™ $150
Total $1,010
5yrs x $1,010 $5,050 total
22. For a system that will help solve information storage and tracking problems
by using database software over a secured network inside the building to
centralize and secure student billing, session, home, emergency and
progress information.
So…
$35,765 + $5,050 = $40,815 total Charges
Year Costs Cumulative Costs
0 $35,765 $35,765
1 $1,010 $36,775
2 $1,010 $37,785
3 $1,010 $38,795
4 $1,010 $39,805
5 $1,010 $40,815
Breakdown:
23. Schedules & Timelines
Analysis and Design 3 days
Installation 7 days
Software setup/testing 2 days
Training 2–8 days
Total 14 to 20 days
(depending on training)
24.
25.
26. TeamManagement
Fab 5 Technicians will be taking care of this
system. If any of them run into any problems
Mrs. Royal’s staff members are there to lend a
hand.
27.
28.
29. Since Agape’s goal is to grow into a worldwide chain of learning
centers it will need a website to advertise its business:
30. Finally…
The end product will be presented to the
site director, IT administrator and Electrician
about 8 days before the grand opening on July
1st, 2010. This leaves us with time to change
any non-satisfactions and errors.