Chapter 11
Risk Management
Risk Management
Contents
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-2
• Risk Management Overview
• Risk Management processes
• Tools/techniques/methods utilized in each
process
Risk Management
Objectives
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-3
By the end of this chapter, you should be able to:
1. Explain the importance of risk management on projects.
2. Name the Risk Management processes
3. Describe the tools and techniques used and activities
involved in each process
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-4
Project Risk Management
Processes
11.1 – Plan Risk
Management
11.2 –
Identify Risks
11.3 –
Perform Qualitative
Risk analysis
11.4 –
Perform Quantitative
Risk Analysis
11.5 –
Plan Risk
Responses
11.6 – Control
Risks
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-5
Review Quiz
Which one of the following is not a Risk
Management process?
A. Plan Risk Management
B. Resolve Risks
C. Perform Qualitative Risk Management
D. Control Risks
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-6
Project Risk Management
• What is a Risk?
• Risk is the possibility of suffering loss, injury, disadvantage,
or destruction. (Webster's Third New International Dictionary 1981)
OR
• An undesired event as a result of uncertainty, complexity,
constraint, or lack of resources – something that can go
wrong
– Risk Characteristics
• A risk may or may not happen. There is some probability of it
occurring
• If it is inevitable, it is not a risk
• a risk has unwanted consequences
• If there is no impact, its not a risk
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-7
Good Risk Management Practices
• Be a good risk manager or you will become a good crisis
manager (SITC)
• If you don't actively attack the risks, they will actively
attack you. (Tom Gilb)
• Projects that don't manage risk are at risk (ICE Corp)
• Risk management is not free; prepare to commit
resources, define a risk management process, and make
a risk reserve available.
• Risk in itself is not bad; risk is essential to progress
(Roger Van Scoy)
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-8
Project Risk Management
Threats and Opportunities
• A risk event is something that is identified in
advance that may or may not happen. If it does
not happen it can have a positive or negative
effect on the project
• A positive impact (good risks) risk is called
“Opportunities”.
• Up to 90 percent of threats that are identified
and investigated in the risk management
process can be eliminated.
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-9
Project Risk Management
Risk Factors
• The probability that it will occur (what)
• The range of possible outcomes (impact)
• When is it expected to happen (when)
• The frequency at which it will happen (how
often)
Risk Averse
• Someone who does not want to take risk (play it
safe)
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-10
Project Risk Management
Input to and output of Risk
Management
• Perform exercise on page 376, 377 on
Rita’s book.
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-11
Plan Risk Management
• Deciding how to approach and plan the risk management activities for a project.
• Risk management Plan may include:
– Methodology : Defines the approaches, tools and data sources that may be used to perform risk
management on the project.
– Roles and Responsibilities : Defines the lead, support and risk management team membership
for each type of action in the risk management plan.
– Budgeting : Establishes a budget for risk management for the project.
– Timing : Defines how often the risk management process will be performed throughout the project
life cycle.
– Risk Categories : Risks could be internal, external, technical, and unforeseeable.
– Risk Probability and Impact : What’s the probability of a risk event happening and its related
impact.
– Stakeholders Tolerance and thresholds : Stakeholders tolerance and thresholds criteria for risks
that will be acted upon, by whom, and in what manner.
– Scoring and Interpretation: Scoring and interpretation method appropriate for the type and timing
of the qualitative and quantitative risk analysis being performed.
– Reporting Formats: Describes the content and format of the risk response plan.
– Tracking : Documents how all the facets of risk activities will be recorded for the benefit of the
current project, future needs and lessons learned.
– Types of Risks : Business risks (Risk of a gain or loss) and Pure (insurable) risks .i.e. only a risk of
loss (i.e. fire, theft, personal injury, etc.)
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project
Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
4-12
Plan Risk Management
• Class Group Activity – 30 Minutes
– Divide Class into 3 groups (3 to 4 students in
each group)
– Discuss and brainstorm the inputs/outputs
– Present your inputs/outputs to the rest of the
teams
– Check and compare your inputs/outputs with
PMBOK
®
Guide 5th edition
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-13
Identify Risks
• Defined as “determining which risks might affect the project and documenting their characteristics”
• All stakeholders as well as experts from other parts of the company or outside the company may
be involved in indentifying the risks.
• The core team will begin the process and then the other members will become involved , making
risks identification an iterative process.
• Project Managers should start looking for risks as soon as possible.
Risk Categories
• Technical, quality , or performance risks – such as reliance on unproven or complex
technology, unrealistic performance goals, changes to the technology used or to the industry
standards during the project.
• Project Management Risks – such as poor allocation of resources, inadequate quality of the
project plan, poor use of the project management disciplines.
• Organizational risks – such as cost, time, and scope objectives that are internally inconsistent,
lack of prioritization of the projects, inadequacy or interruption of funding, and resource conflicts
with other projects in the organization.
• External Risks – such as shifting legal or regulatory environment, labor issues, changing owner
priorities, weather related risks (earthquake, flooding etc)
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project
Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
4-14
Identify Risks
• Class Group Activity – 30 Minutes
– Divide Class into 3 groups (3 to 4 students in
each group)
– Discuss and brainstorm the inputs/outputs
– Present your inputs/outputs to the rest of the
teams
– Check and compare your inputs/outputs with
PMBOK
®
Guide 5th edition
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-15
Risk Identification
Tools and Techniques
• Information Gathering Techniques:
– Brainstorming- Usually done in a meeting where one idea helps generate
another.
– Delphi technique - Way to reach a consensus of experts on a subject.
– Interviewing – Consists of a team or project manager interviewing an expert to
identify risks on the project or a specific element of work.
– Strengths, weaknesses, opportunities and threats (SWOT) Analysis – An
analysis that looks at the project to identify its strengths etc and thereby identify
risks.
– Checklist Analysis – Checklist is used to help identify specific risks within each
category.
– Assumptions Analysis – Analyzing what assumptions have been made on the
project which may help identity more risks.
– Diagramming Techniques – Similar diagramming techniques can be used to
identify risks as used in Quality Management.
• Triggers:
– Sometimes called risk symptoms or warning signs, are indications that a risk has
occurred or is about to occur. Example: Missing a deadline on an activity on
critical path means there is a chance that you will miss the project deadline.
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-16
Qualitative Risk Analysis
• Process of accessing the impact and likelihood of identified risks.
• Determine which risk events warrant a response.
• Document non-critical, or non-stop risks.
• Prioritizes risks according to their potential effect on project objectives.
• Probability and Impact:
– One of the ways to help rank risks is to analyze the probability of a risk occurring and the
effect of the risk on the project.
– Determine the probability of each risk occurring - usually in the form of taking and educated
guess. (e.g. low, medium, high)
– Determine the consequences of each risk occurring – also in the form of an educated guess.
(low, medium, high)
• Assumption Testing:
– “What assumptions have been made?”
– Before the project manager can use the risk information collected, assumptions made must
be identified.
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project
Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
4-17
Qualitative Risk Analysis
• Class Group Activity – 30 Minutes
– Divide Class into 3 groups (3 to 4 students in
each group)
– Discuss and brainstorm the inputs/outputs
– Present your inputs/outputs to the rest of the
teams
– Check and compare your inputs/outputs with
PMBOK
®
Guide 5th edition
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-18
Quantitative Risk Analysis
• Quantitative risk analysis process is to analyze numerically the
probability of each risk and its consequences on project objectives.
• Determine which risks warrant a response.
• Determine the quantified probability of meeting project objectives
e.g. “We only have an 80% chance of completing the project within 6
months.”
• Identify risks requiring most attention.
• Create realistic and achievable cost, schedule or scope targets.
• PMI suggests that quantitative method is preferable to
qualification because it is less subjective and is a better
approximations of actual probabilities and consequences.
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project
Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
4-19
Quantitative Risk Analysis
• Class Group Activity – 30 Minutes
– Divide Class into 3 groups (3 to 4 students in
each group)
– Discuss and brainstorm the inputs/outputs
– Present your inputs/outputs to the rest of the
teams
– Check and compare your inputs/outputs with
PMBOK
®
Guide 5th edition
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-20
Qualitative Risk Analysis
• Data Precision Ranking
– “How well understood is the risk?”
– Before the project manager can use the risk information collected, they must also analyze the
precision of the data – how good is the data?
• Risk Rating Matrix:
– In order to sort or rate risks so a determination can be made as to which risks will move on
through the risk process, a risk rating matrix may be used.
• Outputs from Qualitative Risk Analysis:
– Risk rating of the project.
– List of prioritized risks.
– List of risks created for additional analysis in risk quantification or risk response planning.
– Non-critical or non-stop risks documented for later revisit during risk monitoring and control.
– The project can be compared to the overall risks of other projects.
– The project could be selected, continued, or terminated.
– Resources could be moved between the projects.
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-21
Quantitative Risk Analysis
• Decision Tree:
– A decision tree takes into account future
events in trying to make a decision today.
– It calculates expected value (probability time
consequences) in more complex situations
than the expected value.
– Perform exercise Rita’s Pg 389/390
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-22
Quantitative Risk Analysis
• Monte Carlo Simulation:
– Evaluates the project and not the task.
– Provides the probability of completing the project on any specific day, or any specific account
of cost.
– Provides the probability of any task actually being on the critical path.
– Provides a percent probability that each task will be on the critical path.
– Translates uncertainties into impacts to the total project.
– Can be sue to assess cost and schedule impacts.
– Is usually done with a computer-based Monte Carol program.
– Results in a probability distribution.
• Outputs from Quantitative Risk Analysis:
– Prioritized list of quantified risks
– Forecasts of potential project costs or schedule.
– Listing of the possible project completion dates and costs with their confidence levels.
– Probability of achieving the required project cost or schedules objectives.
– Documented list of not-critical, not-top risks.
Review Question
Joe joined as a project manager in an organization
where his manager asks him to analysis of
risks for project giving a draft charter. What
should help Joe best in this situation?
A. A website for PM network
B. Enterprise environmental factor
C. Resource plan from project planning
D. Lesson learns document from the previous
project that failed earlier
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
Review Question
An output of Risk Identification is:
A. A risk register.
B. Expected monetary value of the risk
events.
C. Corrective actions.
D. The plan for mitigation.
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
Review Question
A thorough review of ______________will
help identify potential risks to the project.
A. Risk identification checklists based on
historical information and knowledge
B. The project’s change control system
C. The project’s mission statement
D. The project’s budget
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
Review Question
As an output of Quantitative Risk Analysis,
the risk register is updated. These updates
include:
A. Prioritized list of quantified risks
B. Probabilistic analysis of the threats to ignore and
opportunities to accept
C. Checklists, corrective actions, and quantified decision
trees
D. Direction, resources, and costs
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
Review Question
The Delphi technique has all of the following
characteristics EXCEPT:
A. It is a way to reach a consensus of experts on a subject such as
project risk.
B. It is a technique in which project risk experts participate
anonymously.
C. It helps reduce bias in the data and keeps any one person from
having undue influence on the outcome.
D. It is an ancient Greek technique to ensure that actions of
subordinates are aligned with the vision of senior executives.
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-28
Risk Response Planning
• Involves finding out ”What are we going to do about it”
• It involves finding ways to make the negative risk smaller or
eliminate it, as well as finding ways to make positive risks more
likely or greater in impact.
• Strategies are agreed upon by all parties.
• Primary and backup strategies are selected.
• Risks are assigned to individuals or group to take responsibilities.
• Risk Owner:
– Each risk must be assigned to someone who will help develop the risk
response and who will be assigned to carry it out or “own” the risk.
– The risk owner is then free to take predetermined action when risks
occur resulting in faster action, and less cost, time and other impacts on
the project.
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project
Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
4-29
Risk Response Planning
• Class Group Activity – 30 Minutes
– Divide Class into 3 groups (3 to 4 students in
each group)
– Discuss and brainstorm the inputs/outputs
– Present your inputs/outputs to the rest of the
teams
– Check and compare your inputs/outputs with
PMBOK
®
Guide 5th edition
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-30
Risk Response Planning
• Risk Response Strategies:
– Developing options and determining actions to enhance opportunities and reduce threats.
• Avoidance : Changing the project plan to eliminate the risk or condition or to protect objective from its
impact.
• Mitigation : Reduce the probability or the consequences of an adverse risk and increase the
probability or consequences of an opportunity.
• Acceptance : Do nothing and say. “If it happens it happens”. Active acceptance may include
developing a contingency plan to execute, should a risk occur. Passive acceptance requires no
action, leaving the project team to deal with the risks as they occur.
• Transference : Risk transference is seeking to shift the consequence of a risk to a third party together
with ownership of the response. Transferring the risk simply gives another party responsibility for its
management, it does not eliminate it. For e.g. purchasing of insurance, warranties, guarantees, or
outsourcing the work.
• Perform exercise Rita’s pg 394
• When Selecting risk strategies, it is important to remember:
– Strategies must be timely.
– The effort selected must be appropriate to the severity of the risk – avoid spending more
money preventing the risk than the impact of the risk would cost if it occurred.
– One response can be used to address more than one risk.
– Involve the team, stakeholders, and experts in selecting a strategy.
Review Quiz
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-31
Which one of the following is not a risk response
strategy?
A. Avoidance
B. Acceptance
C. Rejection
D. Mitigation
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-32
Risk Response Planning
Outputs from Risk Response
• Planning: Developing options and determining actions to enhance
opportunities and reduce threats.
– Residual Risks : Are those that remain after avoidance, transfer or mitigation
responses have been taken.
– Secondary Risks : Arise as a direct result of implementing a risk response.
– Contingency Planning : Planning the specific actions that will be taken if a risk
event occurs or planned response.
– Fallback Planning : Specific actions that will be taken if the contingency plan is
not effective.
– Risk Response Plan : A written document that captures the risks you identified
and what you plan to do about them. The project manager should also record
non-critical risks so that they can easily be revisited during the executed phase.
– Revised Project Plan : The efforts spent in risk management will result in
changes to the project plan. Tasks could be added, removed, or assigned to
different resources.
– Reserves : Formulating the amount of time or cost that needs to be added to the
project to account for risk.
Review Quiz
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-33
A secondary risk is defined as:
A. The second risk that occurs on the project
B. A risk that occurs as a result of implementing a
risk response
C. An unforeseen risk
D. An expected risk
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-34
Control Risks
• Keeping track of the identified risks
• Implementing risk responses
• Looking for the occurrence of risk triggers
• Monitoring residual risks
• Identifying new risks
• Ensuring the execution of risk plans.
• Evaluating the effectiveness of risk plans.
• Developing new risk responses.
• Communicating risk status and collecting risk status.
• Communicating with stakeholders about risks.
• Determining if assumptions are still valid.
• Revisiting low ranking or non-critical risks to see if risk responses need to be determined.
• Taking corrective action to adjust to the severity of actual risk events.
• Looking for any unexpected effects or consequences of risk events.
• Reevaluating risk identification, qualification, and quantification when the project deviates from the
baseline.
• Updating risk plans
• Making changes to the project plan when new risk responses are developed.
• Creating a database of risk data that may be used throughout the organization on other projects.
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project
Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
4-35
Control Risks
• Class Group Activity – 30 Minutes
– Divide Class into 3 groups (3 to 4 students in
each group)
– Discuss and brainstorm the inputs/outputs
– Present your inputs/outputs to the rest of the
teams
– Check and compare your inputs/outputs with
PMBOK
®
Guide 5th edition
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-36
Control Risks
• Risk Response Audits:
– Examining and documenting the effectiveness of the risk response and the person managing
the risk. This is an important step in order to see if the plans put in place are effective and if
changes are needed.
• Risk Reviews:
– Team needs to periodically review risk plans and adjust as required. Risk should be a major
topic at team meetings to keep focus on risks and to make sure plans remain appropriate.
• Outputs from Risk Monitoring and Control:
– Workarounds: Unplanned responses to risks or dealing with risks that you could not or did
not anticipate.
– Corrective action: consists of performing the contingency plans or workaround.
– Changes to the Project: Implementing contingency plans or workarounds frequently results
in a requirement to change the project plan to respond to risks.
– Updates to risk response plan: It is wise to always re-evaluate whether the plans need any
correcting or adjusting after each unidentified ir identified risk occurs.
– Risk Database: A repository that provides for collection, maintenance and analysis of data
gathered and used in the risk management process.
Chapter Summary
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-37
• Risk Management Overview
• Risk Management processes
• Plan Risk Management
• Identify Risks
• Perform Qualitative Risk Analysis
• Perform Quantitative Risk Analysis
• Plan Risk Responses
• Control Risks
• Tools and Techniques utilized in each process
End of Chapter Quiz
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-38
Question 1: After planning for all risks, the team
concludes that one risk is unavoidable. This risk
can be categorized as:
A. Inevitable risk
B. Unplanned risk
C. Remaining risk
D. Residual risk
End of Chapter Quiz
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-39
Question 2: One team member informs you that he
will miss a critical deadline. From a risk
management perspective, this is an example of:
A. Qualitative risk analysis
B. Unplanned risk
C. Risk Planning
D. Risk trigger
End of Chapter Quiz
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-40
Question 3: Although junior programmers outnumber
seniors programmers on the development team, you
decide to use a senior programmer due to the risk of using
an inexperienced programmer on a complex, high profile
project. This is an example of:
A. Risk tolerance
B. Risk avoidance
C. Risk planning
D. Risk strategy
End of Chapter Quiz
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-41
Question 4: A list of prioritized risks is an output of
which process?
A. Perform Qualitative Risk Analysis
B. Perform Quantitative Risk Analysis
C. Risk Response Planning
D. Control Risks
End of Chapter Quiz
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-42
Question 5: The project team is in a meeting on
risk identification. All the team members are
offering ideas that are being written on the board.
One idea leads to another idea. This technique is
known as:
A. Affinity diagrams
B. Delphi technique
C. Brainstorming
D. Interviewing
End of Chapter Quiz
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-43
Question 6: What would project manager do when
he receives a request for a change in the project
that increases project risk?
A. Call the team and analyses the impact
B. Discuss with the customer about the impact of
change
C. Use senility analysis of the risk with the team
D. Add expected monetary value of the risk
End of Chapter Quiz
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-44
Question 6: 2. Which of the strategies are for
negative risks?
A. Avoid, Mitigate, Transfer, Accept
B. Avoid, Transfer, Mitigate
C. Avoid, Transfer, Exploit, Mitigate
D. None of the above
Answer: A
End of Chapter Quiz
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-45
Question 7: Which of the strategies are for
negative risks?
A. Avoid, Mitigate, Transfer, Accept
B. Avoid, Transfer, Mitigate
C. Avoid, Transfer, Exploit, Mitigate
D. None of the above
End of Chapter Quiz
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-46
Question 8: To be successful, the organization
should be committed to addressing the
management of risk:
A. Just before a meeting with a client
B. Proactively and consistently throughout the
project
C. As soon as time and cost estimates are ready
D. Early in the execution phase
End of Chapter Quiz
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-47
Question 9: Outputs from Risk Response Planning
include all of the following EXCEPT:
A. Risk register updates
B. Corrective actions
C. Risk-related contractual agreements
D. Project management plan updates
End of Chapter Quiz
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-48
Question 10: The outputs from risk monitoring and
control include all of the following EXCEPT:
A. Requested changes
B. Work breakdown structure (WBS)
C. Recommended corrective actions
D. Updates to the risk register.
End of Chapter Quiz
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-49
Question 11: Decision tree analysis has all of the
following characteristics EXCEPT:
A. It is usually structured using a decision tree diagram that describes a
situation under consideration, and the implications of each of the
available choices and possible scenarios.
B. It incorporates the cost of each available choice, the probabilities of
each possible scenario, and the rewards of each alternative logical
path.
C. It is primarily a descriptive technique and cannot be effectively used
in quantitative risk analysis.
D. Solving the decision tree provides the expected monetary value for
each alternative, when all the rewards and subsequent decisions are
quantified.
End of Chapter Quiz
PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks
of Project Management Institute, Inc
Inov8Solutions Inc – Quality Educational Services For Professionals
www.Inov8Solutions.com
11-50
Question 12: Expected monetary value (EMV)
analysis has all of the following characteristics
EXCEPT:
A. It is a statistical concept that calculates the average outcome
when the future includes scenarios that may or may not happen.
B. The EMV of opportunities will generally be expressed as
positive values, while those of risks will be negative.
C. EMV analysis cannot be used effectively in decision tree
analysis.
D. EMV is calculated by multiplying the value of each possible
outcome by its probability of occurrence, and adding them
together.

More Related Content

Similar to Risk Management.ppt

Enterprise 360 degree risk management
Enterprise 360 degree risk managementEnterprise 360 degree risk management
Enterprise 360 degree risk managementInfosys
 
Where do risks (threats and opportunities) arise from?, presented by Lynn Sta...
Where do risks (threats and opportunities) arise from?, presented by Lynn Sta...Where do risks (threats and opportunities) arise from?, presented by Lynn Sta...
Where do risks (threats and opportunities) arise from?, presented by Lynn Sta...Association for Project Management
 
Risk-Management-05012023-025512pm.ppt
Risk-Management-05012023-025512pm.pptRisk-Management-05012023-025512pm.ppt
Risk-Management-05012023-025512pm.pptYasirShaikh34
 
It_Club_NCP_Risk_Management_26_03_2013
It_Club_NCP_Risk_Management_26_03_2013It_Club_NCP_Risk_Management_26_03_2013
It_Club_NCP_Risk_Management_26_03_2013IT Club GTA
 
project_risk_mgmt_final 1.ppt
project_risk_mgmt_final 1.pptproject_risk_mgmt_final 1.ppt
project_risk_mgmt_final 1.pptBetshaTizazu2
 
11-Risk Management.pptx
11-Risk Management.pptx11-Risk Management.pptx
11-Risk Management.pptxSushant895574
 
Risk Management Presentation.pptx
Risk Management Presentation.pptxRisk Management Presentation.pptx
Risk Management Presentation.pptxPMIUKChapter
 
Fme project-risk
Fme project-riskFme project-risk
Fme project-risksahil mehta
 
Introduction to risk management
Introduction to risk managementIntroduction to risk management
Introduction to risk managements. Akhlaque
 
Software Engineering (Risk Management)
Software Engineering (Risk Management)Software Engineering (Risk Management)
Software Engineering (Risk Management)ShudipPal
 
Risk - ALL YOU NEED TO KNOW ABOUT PMI-RMP
Risk - ALL YOU NEED TO KNOW ABOUT PMI-RMPRisk - ALL YOU NEED TO KNOW ABOUT PMI-RMP
Risk - ALL YOU NEED TO KNOW ABOUT PMI-RMPAlcides Cabral PMP
 
Webinar - Building Team Efficiency and Effectiveness
Webinar - Building Team Efficiency and EffectivenessWebinar - Building Team Efficiency and Effectiveness
Webinar - Building Team Efficiency and EffectivenessInvensis Learning
 
Microsoft InfoSec for cloud and mobile
Microsoft InfoSec for cloud and mobileMicrosoft InfoSec for cloud and mobile
Microsoft InfoSec for cloud and mobileVijayananda Mohire
 
Risk Management
Risk ManagementRisk Management
Risk ManagementSaqib Raza
 
project_risk_mgmt_final.ppt
project_risk_mgmt_final.pptproject_risk_mgmt_final.ppt
project_risk_mgmt_final.pptavisha23
 
project_risk_mgmt_final.ppt
project_risk_mgmt_final.pptproject_risk_mgmt_final.ppt
project_risk_mgmt_final.pptAyidAlmgati
 
PMI project_risk_management_final_2022.ppt
PMI project_risk_management_final_2022.pptPMI project_risk_management_final_2022.ppt
PMI project_risk_management_final_2022.pptDorraLamouchi1
 

Similar to Risk Management.ppt (20)

Enterprise 360 degree risk management
Enterprise 360 degree risk managementEnterprise 360 degree risk management
Enterprise 360 degree risk management
 
P3M - Project, Program, Portfolio Management Framework
P3M - Project, Program, Portfolio Management FrameworkP3M - Project, Program, Portfolio Management Framework
P3M - Project, Program, Portfolio Management Framework
 
Where do risks (threats and opportunities) arise from?, presented by Lynn Sta...
Where do risks (threats and opportunities) arise from?, presented by Lynn Sta...Where do risks (threats and opportunities) arise from?, presented by Lynn Sta...
Where do risks (threats and opportunities) arise from?, presented by Lynn Sta...
 
Risk-Management-05012023-025512pm.ppt
Risk-Management-05012023-025512pm.pptRisk-Management-05012023-025512pm.ppt
Risk-Management-05012023-025512pm.ppt
 
8. project risk management
8. project risk management8. project risk management
8. project risk management
 
It_Club_NCP_Risk_Management_26_03_2013
It_Club_NCP_Risk_Management_26_03_2013It_Club_NCP_Risk_Management_26_03_2013
It_Club_NCP_Risk_Management_26_03_2013
 
project_risk_mgmt_final 1.ppt
project_risk_mgmt_final 1.pptproject_risk_mgmt_final 1.ppt
project_risk_mgmt_final 1.ppt
 
11-Risk Management.pptx
11-Risk Management.pptx11-Risk Management.pptx
11-Risk Management.pptx
 
Risk Management Presentation.pptx
Risk Management Presentation.pptxRisk Management Presentation.pptx
Risk Management Presentation.pptx
 
Fme project-risk
Fme project-riskFme project-risk
Fme project-risk
 
Introduction to risk management
Introduction to risk managementIntroduction to risk management
Introduction to risk management
 
Software Engineering (Risk Management)
Software Engineering (Risk Management)Software Engineering (Risk Management)
Software Engineering (Risk Management)
 
Risk - ALL YOU NEED TO KNOW ABOUT PMI-RMP
Risk - ALL YOU NEED TO KNOW ABOUT PMI-RMPRisk - ALL YOU NEED TO KNOW ABOUT PMI-RMP
Risk - ALL YOU NEED TO KNOW ABOUT PMI-RMP
 
Webinar - Building Team Efficiency and Effectiveness
Webinar - Building Team Efficiency and EffectivenessWebinar - Building Team Efficiency and Effectiveness
Webinar - Building Team Efficiency and Effectiveness
 
Microsoft InfoSec for cloud and mobile
Microsoft InfoSec for cloud and mobileMicrosoft InfoSec for cloud and mobile
Microsoft InfoSec for cloud and mobile
 
Pmi rmp-2020 - v6
Pmi rmp-2020 - v6Pmi rmp-2020 - v6
Pmi rmp-2020 - v6
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
project_risk_mgmt_final.ppt
project_risk_mgmt_final.pptproject_risk_mgmt_final.ppt
project_risk_mgmt_final.ppt
 
project_risk_mgmt_final.ppt
project_risk_mgmt_final.pptproject_risk_mgmt_final.ppt
project_risk_mgmt_final.ppt
 
PMI project_risk_management_final_2022.ppt
PMI project_risk_management_final_2022.pptPMI project_risk_management_final_2022.ppt
PMI project_risk_management_final_2022.ppt
 

Recently uploaded

VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdftbatkhuu1
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in managementchhavia330
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaShree Krishna Exports
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfOnline Income Engine
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsMichael W. Hawkins
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insightsseribangash
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 

Recently uploaded (20)

VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdf
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in management
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in India
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdf
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael Hawkins
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insights
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 

Risk Management.ppt

  • 1. PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-1 Chapter 11 Risk Management
  • 2. Risk Management Contents PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-2 • Risk Management Overview • Risk Management processes • Tools/techniques/methods utilized in each process
  • 3. Risk Management Objectives PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-3 By the end of this chapter, you should be able to: 1. Explain the importance of risk management on projects. 2. Name the Risk Management processes 3. Describe the tools and techniques used and activities involved in each process
  • 4. PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-4 Project Risk Management Processes 11.1 – Plan Risk Management 11.2 – Identify Risks 11.3 – Perform Qualitative Risk analysis 11.4 – Perform Quantitative Risk Analysis 11.5 – Plan Risk Responses 11.6 – Control Risks
  • 5. PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-5 Review Quiz Which one of the following is not a Risk Management process? A. Plan Risk Management B. Resolve Risks C. Perform Qualitative Risk Management D. Control Risks
  • 6. PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-6 Project Risk Management • What is a Risk? • Risk is the possibility of suffering loss, injury, disadvantage, or destruction. (Webster's Third New International Dictionary 1981) OR • An undesired event as a result of uncertainty, complexity, constraint, or lack of resources – something that can go wrong – Risk Characteristics • A risk may or may not happen. There is some probability of it occurring • If it is inevitable, it is not a risk • a risk has unwanted consequences • If there is no impact, its not a risk
  • 7. PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-7 Good Risk Management Practices • Be a good risk manager or you will become a good crisis manager (SITC) • If you don't actively attack the risks, they will actively attack you. (Tom Gilb) • Projects that don't manage risk are at risk (ICE Corp) • Risk management is not free; prepare to commit resources, define a risk management process, and make a risk reserve available. • Risk in itself is not bad; risk is essential to progress (Roger Van Scoy)
  • 8. PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-8 Project Risk Management Threats and Opportunities • A risk event is something that is identified in advance that may or may not happen. If it does not happen it can have a positive or negative effect on the project • A positive impact (good risks) risk is called “Opportunities”. • Up to 90 percent of threats that are identified and investigated in the risk management process can be eliminated.
  • 9. PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-9 Project Risk Management Risk Factors • The probability that it will occur (what) • The range of possible outcomes (impact) • When is it expected to happen (when) • The frequency at which it will happen (how often) Risk Averse • Someone who does not want to take risk (play it safe)
  • 10. PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-10 Project Risk Management Input to and output of Risk Management • Perform exercise on page 376, 377 on Rita’s book.
  • 11. PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-11 Plan Risk Management • Deciding how to approach and plan the risk management activities for a project. • Risk management Plan may include: – Methodology : Defines the approaches, tools and data sources that may be used to perform risk management on the project. – Roles and Responsibilities : Defines the lead, support and risk management team membership for each type of action in the risk management plan. – Budgeting : Establishes a budget for risk management for the project. – Timing : Defines how often the risk management process will be performed throughout the project life cycle. – Risk Categories : Risks could be internal, external, technical, and unforeseeable. – Risk Probability and Impact : What’s the probability of a risk event happening and its related impact. – Stakeholders Tolerance and thresholds : Stakeholders tolerance and thresholds criteria for risks that will be acted upon, by whom, and in what manner. – Scoring and Interpretation: Scoring and interpretation method appropriate for the type and timing of the qualitative and quantitative risk analysis being performed. – Reporting Formats: Describes the content and format of the risk response plan. – Tracking : Documents how all the facets of risk activities will be recorded for the benefit of the current project, future needs and lessons learned. – Types of Risks : Business risks (Risk of a gain or loss) and Pure (insurable) risks .i.e. only a risk of loss (i.e. fire, theft, personal injury, etc.)
  • 12. PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 4-12 Plan Risk Management • Class Group Activity – 30 Minutes – Divide Class into 3 groups (3 to 4 students in each group) – Discuss and brainstorm the inputs/outputs – Present your inputs/outputs to the rest of the teams – Check and compare your inputs/outputs with PMBOK ® Guide 5th edition
  • 13. PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-13 Identify Risks • Defined as “determining which risks might affect the project and documenting their characteristics” • All stakeholders as well as experts from other parts of the company or outside the company may be involved in indentifying the risks. • The core team will begin the process and then the other members will become involved , making risks identification an iterative process. • Project Managers should start looking for risks as soon as possible. Risk Categories • Technical, quality , or performance risks – such as reliance on unproven or complex technology, unrealistic performance goals, changes to the technology used or to the industry standards during the project. • Project Management Risks – such as poor allocation of resources, inadequate quality of the project plan, poor use of the project management disciplines. • Organizational risks – such as cost, time, and scope objectives that are internally inconsistent, lack of prioritization of the projects, inadequacy or interruption of funding, and resource conflicts with other projects in the organization. • External Risks – such as shifting legal or regulatory environment, labor issues, changing owner priorities, weather related risks (earthquake, flooding etc)
  • 14. PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 4-14 Identify Risks • Class Group Activity – 30 Minutes – Divide Class into 3 groups (3 to 4 students in each group) – Discuss and brainstorm the inputs/outputs – Present your inputs/outputs to the rest of the teams – Check and compare your inputs/outputs with PMBOK ® Guide 5th edition
  • 15. PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-15 Risk Identification Tools and Techniques • Information Gathering Techniques: – Brainstorming- Usually done in a meeting where one idea helps generate another. – Delphi technique - Way to reach a consensus of experts on a subject. – Interviewing – Consists of a team or project manager interviewing an expert to identify risks on the project or a specific element of work. – Strengths, weaknesses, opportunities and threats (SWOT) Analysis – An analysis that looks at the project to identify its strengths etc and thereby identify risks. – Checklist Analysis – Checklist is used to help identify specific risks within each category. – Assumptions Analysis – Analyzing what assumptions have been made on the project which may help identity more risks. – Diagramming Techniques – Similar diagramming techniques can be used to identify risks as used in Quality Management. • Triggers: – Sometimes called risk symptoms or warning signs, are indications that a risk has occurred or is about to occur. Example: Missing a deadline on an activity on critical path means there is a chance that you will miss the project deadline.
  • 16. PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-16 Qualitative Risk Analysis • Process of accessing the impact and likelihood of identified risks. • Determine which risk events warrant a response. • Document non-critical, or non-stop risks. • Prioritizes risks according to their potential effect on project objectives. • Probability and Impact: – One of the ways to help rank risks is to analyze the probability of a risk occurring and the effect of the risk on the project. – Determine the probability of each risk occurring - usually in the form of taking and educated guess. (e.g. low, medium, high) – Determine the consequences of each risk occurring – also in the form of an educated guess. (low, medium, high) • Assumption Testing: – “What assumptions have been made?” – Before the project manager can use the risk information collected, assumptions made must be identified.
  • 17. PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 4-17 Qualitative Risk Analysis • Class Group Activity – 30 Minutes – Divide Class into 3 groups (3 to 4 students in each group) – Discuss and brainstorm the inputs/outputs – Present your inputs/outputs to the rest of the teams – Check and compare your inputs/outputs with PMBOK ® Guide 5th edition
  • 18. PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-18 Quantitative Risk Analysis • Quantitative risk analysis process is to analyze numerically the probability of each risk and its consequences on project objectives. • Determine which risks warrant a response. • Determine the quantified probability of meeting project objectives e.g. “We only have an 80% chance of completing the project within 6 months.” • Identify risks requiring most attention. • Create realistic and achievable cost, schedule or scope targets. • PMI suggests that quantitative method is preferable to qualification because it is less subjective and is a better approximations of actual probabilities and consequences.
  • 19. PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 4-19 Quantitative Risk Analysis • Class Group Activity – 30 Minutes – Divide Class into 3 groups (3 to 4 students in each group) – Discuss and brainstorm the inputs/outputs – Present your inputs/outputs to the rest of the teams – Check and compare your inputs/outputs with PMBOK ® Guide 5th edition
  • 20. PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-20 Qualitative Risk Analysis • Data Precision Ranking – “How well understood is the risk?” – Before the project manager can use the risk information collected, they must also analyze the precision of the data – how good is the data? • Risk Rating Matrix: – In order to sort or rate risks so a determination can be made as to which risks will move on through the risk process, a risk rating matrix may be used. • Outputs from Qualitative Risk Analysis: – Risk rating of the project. – List of prioritized risks. – List of risks created for additional analysis in risk quantification or risk response planning. – Non-critical or non-stop risks documented for later revisit during risk monitoring and control. – The project can be compared to the overall risks of other projects. – The project could be selected, continued, or terminated. – Resources could be moved between the projects.
  • 21. PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-21 Quantitative Risk Analysis • Decision Tree: – A decision tree takes into account future events in trying to make a decision today. – It calculates expected value (probability time consequences) in more complex situations than the expected value. – Perform exercise Rita’s Pg 389/390
  • 22. PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-22 Quantitative Risk Analysis • Monte Carlo Simulation: – Evaluates the project and not the task. – Provides the probability of completing the project on any specific day, or any specific account of cost. – Provides the probability of any task actually being on the critical path. – Provides a percent probability that each task will be on the critical path. – Translates uncertainties into impacts to the total project. – Can be sue to assess cost and schedule impacts. – Is usually done with a computer-based Monte Carol program. – Results in a probability distribution. • Outputs from Quantitative Risk Analysis: – Prioritized list of quantified risks – Forecasts of potential project costs or schedule. – Listing of the possible project completion dates and costs with their confidence levels. – Probability of achieving the required project cost or schedules objectives. – Documented list of not-critical, not-top risks.
  • 23. Review Question Joe joined as a project manager in an organization where his manager asks him to analysis of risks for project giving a draft charter. What should help Joe best in this situation? A. A website for PM network B. Enterprise environmental factor C. Resource plan from project planning D. Lesson learns document from the previous project that failed earlier PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com
  • 24. Review Question An output of Risk Identification is: A. A risk register. B. Expected monetary value of the risk events. C. Corrective actions. D. The plan for mitigation. PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com
  • 25. Review Question A thorough review of ______________will help identify potential risks to the project. A. Risk identification checklists based on historical information and knowledge B. The project’s change control system C. The project’s mission statement D. The project’s budget PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com
  • 26. Review Question As an output of Quantitative Risk Analysis, the risk register is updated. These updates include: A. Prioritized list of quantified risks B. Probabilistic analysis of the threats to ignore and opportunities to accept C. Checklists, corrective actions, and quantified decision trees D. Direction, resources, and costs PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com
  • 27. Review Question The Delphi technique has all of the following characteristics EXCEPT: A. It is a way to reach a consensus of experts on a subject such as project risk. B. It is a technique in which project risk experts participate anonymously. C. It helps reduce bias in the data and keeps any one person from having undue influence on the outcome. D. It is an ancient Greek technique to ensure that actions of subordinates are aligned with the vision of senior executives. PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com
  • 28. PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-28 Risk Response Planning • Involves finding out ”What are we going to do about it” • It involves finding ways to make the negative risk smaller or eliminate it, as well as finding ways to make positive risks more likely or greater in impact. • Strategies are agreed upon by all parties. • Primary and backup strategies are selected. • Risks are assigned to individuals or group to take responsibilities. • Risk Owner: – Each risk must be assigned to someone who will help develop the risk response and who will be assigned to carry it out or “own” the risk. – The risk owner is then free to take predetermined action when risks occur resulting in faster action, and less cost, time and other impacts on the project.
  • 29. PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 4-29 Risk Response Planning • Class Group Activity – 30 Minutes – Divide Class into 3 groups (3 to 4 students in each group) – Discuss and brainstorm the inputs/outputs – Present your inputs/outputs to the rest of the teams – Check and compare your inputs/outputs with PMBOK ® Guide 5th edition
  • 30. PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-30 Risk Response Planning • Risk Response Strategies: – Developing options and determining actions to enhance opportunities and reduce threats. • Avoidance : Changing the project plan to eliminate the risk or condition or to protect objective from its impact. • Mitigation : Reduce the probability or the consequences of an adverse risk and increase the probability or consequences of an opportunity. • Acceptance : Do nothing and say. “If it happens it happens”. Active acceptance may include developing a contingency plan to execute, should a risk occur. Passive acceptance requires no action, leaving the project team to deal with the risks as they occur. • Transference : Risk transference is seeking to shift the consequence of a risk to a third party together with ownership of the response. Transferring the risk simply gives another party responsibility for its management, it does not eliminate it. For e.g. purchasing of insurance, warranties, guarantees, or outsourcing the work. • Perform exercise Rita’s pg 394 • When Selecting risk strategies, it is important to remember: – Strategies must be timely. – The effort selected must be appropriate to the severity of the risk – avoid spending more money preventing the risk than the impact of the risk would cost if it occurred. – One response can be used to address more than one risk. – Involve the team, stakeholders, and experts in selecting a strategy.
  • 31. Review Quiz PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-31 Which one of the following is not a risk response strategy? A. Avoidance B. Acceptance C. Rejection D. Mitigation
  • 32. PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-32 Risk Response Planning Outputs from Risk Response • Planning: Developing options and determining actions to enhance opportunities and reduce threats. – Residual Risks : Are those that remain after avoidance, transfer or mitigation responses have been taken. – Secondary Risks : Arise as a direct result of implementing a risk response. – Contingency Planning : Planning the specific actions that will be taken if a risk event occurs or planned response. – Fallback Planning : Specific actions that will be taken if the contingency plan is not effective. – Risk Response Plan : A written document that captures the risks you identified and what you plan to do about them. The project manager should also record non-critical risks so that they can easily be revisited during the executed phase. – Revised Project Plan : The efforts spent in risk management will result in changes to the project plan. Tasks could be added, removed, or assigned to different resources. – Reserves : Formulating the amount of time or cost that needs to be added to the project to account for risk.
  • 33. Review Quiz PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-33 A secondary risk is defined as: A. The second risk that occurs on the project B. A risk that occurs as a result of implementing a risk response C. An unforeseen risk D. An expected risk
  • 34. PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-34 Control Risks • Keeping track of the identified risks • Implementing risk responses • Looking for the occurrence of risk triggers • Monitoring residual risks • Identifying new risks • Ensuring the execution of risk plans. • Evaluating the effectiveness of risk plans. • Developing new risk responses. • Communicating risk status and collecting risk status. • Communicating with stakeholders about risks. • Determining if assumptions are still valid. • Revisiting low ranking or non-critical risks to see if risk responses need to be determined. • Taking corrective action to adjust to the severity of actual risk events. • Looking for any unexpected effects or consequences of risk events. • Reevaluating risk identification, qualification, and quantification when the project deviates from the baseline. • Updating risk plans • Making changes to the project plan when new risk responses are developed. • Creating a database of risk data that may be used throughout the organization on other projects.
  • 35. PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 4-35 Control Risks • Class Group Activity – 30 Minutes – Divide Class into 3 groups (3 to 4 students in each group) – Discuss and brainstorm the inputs/outputs – Present your inputs/outputs to the rest of the teams – Check and compare your inputs/outputs with PMBOK ® Guide 5th edition
  • 36. PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-36 Control Risks • Risk Response Audits: – Examining and documenting the effectiveness of the risk response and the person managing the risk. This is an important step in order to see if the plans put in place are effective and if changes are needed. • Risk Reviews: – Team needs to periodically review risk plans and adjust as required. Risk should be a major topic at team meetings to keep focus on risks and to make sure plans remain appropriate. • Outputs from Risk Monitoring and Control: – Workarounds: Unplanned responses to risks or dealing with risks that you could not or did not anticipate. – Corrective action: consists of performing the contingency plans or workaround. – Changes to the Project: Implementing contingency plans or workarounds frequently results in a requirement to change the project plan to respond to risks. – Updates to risk response plan: It is wise to always re-evaluate whether the plans need any correcting or adjusting after each unidentified ir identified risk occurs. – Risk Database: A repository that provides for collection, maintenance and analysis of data gathered and used in the risk management process.
  • 37. Chapter Summary PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-37 • Risk Management Overview • Risk Management processes • Plan Risk Management • Identify Risks • Perform Qualitative Risk Analysis • Perform Quantitative Risk Analysis • Plan Risk Responses • Control Risks • Tools and Techniques utilized in each process
  • 38. End of Chapter Quiz PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-38 Question 1: After planning for all risks, the team concludes that one risk is unavoidable. This risk can be categorized as: A. Inevitable risk B. Unplanned risk C. Remaining risk D. Residual risk
  • 39. End of Chapter Quiz PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-39 Question 2: One team member informs you that he will miss a critical deadline. From a risk management perspective, this is an example of: A. Qualitative risk analysis B. Unplanned risk C. Risk Planning D. Risk trigger
  • 40. End of Chapter Quiz PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-40 Question 3: Although junior programmers outnumber seniors programmers on the development team, you decide to use a senior programmer due to the risk of using an inexperienced programmer on a complex, high profile project. This is an example of: A. Risk tolerance B. Risk avoidance C. Risk planning D. Risk strategy
  • 41. End of Chapter Quiz PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-41 Question 4: A list of prioritized risks is an output of which process? A. Perform Qualitative Risk Analysis B. Perform Quantitative Risk Analysis C. Risk Response Planning D. Control Risks
  • 42. End of Chapter Quiz PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-42 Question 5: The project team is in a meeting on risk identification. All the team members are offering ideas that are being written on the board. One idea leads to another idea. This technique is known as: A. Affinity diagrams B. Delphi technique C. Brainstorming D. Interviewing
  • 43. End of Chapter Quiz PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-43 Question 6: What would project manager do when he receives a request for a change in the project that increases project risk? A. Call the team and analyses the impact B. Discuss with the customer about the impact of change C. Use senility analysis of the risk with the team D. Add expected monetary value of the risk
  • 44. End of Chapter Quiz PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-44 Question 6: 2. Which of the strategies are for negative risks? A. Avoid, Mitigate, Transfer, Accept B. Avoid, Transfer, Mitigate C. Avoid, Transfer, Exploit, Mitigate D. None of the above Answer: A
  • 45. End of Chapter Quiz PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-45 Question 7: Which of the strategies are for negative risks? A. Avoid, Mitigate, Transfer, Accept B. Avoid, Transfer, Mitigate C. Avoid, Transfer, Exploit, Mitigate D. None of the above
  • 46. End of Chapter Quiz PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-46 Question 8: To be successful, the organization should be committed to addressing the management of risk: A. Just before a meeting with a client B. Proactively and consistently throughout the project C. As soon as time and cost estimates are ready D. Early in the execution phase
  • 47. End of Chapter Quiz PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-47 Question 9: Outputs from Risk Response Planning include all of the following EXCEPT: A. Risk register updates B. Corrective actions C. Risk-related contractual agreements D. Project management plan updates
  • 48. End of Chapter Quiz PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-48 Question 10: The outputs from risk monitoring and control include all of the following EXCEPT: A. Requested changes B. Work breakdown structure (WBS) C. Recommended corrective actions D. Updates to the risk register.
  • 49. End of Chapter Quiz PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-49 Question 11: Decision tree analysis has all of the following characteristics EXCEPT: A. It is usually structured using a decision tree diagram that describes a situation under consideration, and the implications of each of the available choices and possible scenarios. B. It incorporates the cost of each available choice, the probabilities of each possible scenario, and the rewards of each alternative logical path. C. It is primarily a descriptive technique and cannot be effectively used in quantitative risk analysis. D. Solving the decision tree provides the expected monetary value for each alternative, when all the rewards and subsequent decisions are quantified.
  • 50. End of Chapter Quiz PMP, CAPM, PgMP, PMI-SP , PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services For Professionals www.Inov8Solutions.com 11-50 Question 12: Expected monetary value (EMV) analysis has all of the following characteristics EXCEPT: A. It is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen. B. The EMV of opportunities will generally be expressed as positive values, while those of risks will be negative. C. EMV analysis cannot be used effectively in decision tree analysis. D. EMV is calculated by multiplying the value of each possible outcome by its probability of occurrence, and adding them together.