SlideShare a Scribd company logo
1 of 13
Download to read offline
Amy I. Chen, Director of MWD Program
Dan Denham, Acting Director of Colorado River Program
Imported Water Committee
February 27, 2014
1
 Three key points
1. BDCP is a massive infrastructure project, will take
tremendous effort to implement, costs will likely go
up
2. How costs are allocated, and who will ultimately
commit to pay for the project are vitally important to
Water Authority’s ratepayers
3. Water Authority’s region has additional local
projects that may be explored to lessen the supply
impact, although at a cost, but with more local
control
2
3
Capacity 9,000 cfs 6,000 cfs 3,000 cfs
Primary type of
conveyance
pipelines/tunnels pipelines/tunnels pipelines/tunnels
Tunnel Twin Twin Twin Single a
Operations High
Outflow
Low
Outflow
High Outflow High
Outflow
High
Outflow
Total Export 4.7 MAF 5.6 MAF 4.5 MAF 4.2 MAF 4.2 MAF
BDCP Benefits b 1.2 MAF 1.7 MAF 1 MAF 740 TAF 740 TAF
Capital Cost c $14,344M $13,146M $10,821M $8,600M
O&M Cost c, d $1,456M $1,311M $1,118M
a BDCP Blog http://baydeltaconservationplan.com/news/blog/13-11-12/Revised_Capital_Cost_for_3_000_cfs_Single_Bore_Tunnel.aspx
b When compared against “no action” alternative as described in BDCP Chapter 9, Alternative to Take
c Value expressed in undiscounted 2012 dollars
d Source: Chapter 9.B “Take Alternatives Cost Estimation” Tables 9.B-9, -10, and -13. For ratio of annual O&M costs,
utilized same assumptions as the proposed action (40 years of facility operation and power and 30 years of replacement
cost).
Cost Estimate and Yield* Summary
*Export water yield from the “no action” alternative: 3.5 MAF– 3.9 MAF
 Project costs: escalation/overruns
 Construction schedule: delays
 Cost allocation:
 Unclear; Project costs to be shared by SWP and CVP
contractors, yet, allocation of cost obligations will not be
determined until “near the time that permits are issued for
BDCP”
 Financing costs
 Reduced yield from Decision Tree/Adaptive
Management
 State and federal funding doesn’t materialize
 “Funding estimates from state and federal agencies do not
represent commitment”
4
 MWD is the largest SWP contractor
 How costs are allocated among the contractors critical
 MWD could be exposed to between 25% to more than half of
total BDCP cost
 Supply benefit hinges on MWD’s ability to capture and store
wet-year supply for dry-year use
 Water Authority’s potential share: 25%-37%
 Based on MWD’s current cost allocation methodology
 Water supply benefit subject to MWD’s control
 MWD controls blend of supply to Water Authority
 MWD determines when supplies are stored and withdrawn
5
6
BDCP Yield
MWD 1
BDCP Yield
Water
Authority 2
Total Cost to
Water
Authority 3
Additional Common
Risks
9,000 cfs 4
(proposed
action)
302 taf – 428
taf
55 taf - 78 taf
$1,066M –
$2,208M
Construction estimate
Scheduling delay
Financing cost
Reduced yield from
Decision Tree / adaptive
management process
6,000 cfs 4 262 taf 48 taf $911M-1,885M
3,000 cfs 4 187 taf 34 taf
$612M-
$1,267M
1. Based on average of potential BDCP benefit when compared with “no action” as described in BDCP Chapter 9; yield
benefit is shared 55/45 SWP/CVP with MWD getting its Table A allocation
2. Based on Water Authority’s preferential right to MWD water as of 6/30/2013
3. In 2012$, based on cost allocation assumptions described in this memo, with Water Authority paying for 25% of
MWD share, based on MWD’s current cost allocation methodology
4. Modeling results for high outflow and low outflow are provided for 9,000 cfs only; export yields for other conveyance
capacity options included results from high outflow only.
BDCP Conveyance Alternatives Yields
and Costs to Water Authority
 To address potential supply gap, a selection of
local resources projects were investigated
 Projects were not included in 2010 UWMP as
“verifiable projects”
7
Potential Annual
Yield
Total Capital Cost to
Region
Unit Cost ($/af)
Seawater desal 1 56 taf-168 taf $1.43B-$3.2B $2,260-$2,860
Indirect Potable Reuse 2 93 taf $2.1B $2,175-$2,375
1. Based on cost estimates prepared for proposed Camp Pendleton Seawater Desalination Project (Oct/Nov 2013);
unit cost includes annual O&M costs; 30-year amortization @5% assumed
2. “Gross costs” based on city of San Diego Recycled Water Study (Integrated Reuse Alternatives); does not include
any potential avoided wastewater costs or potential offset savings such as grants, or low interest loans; project
may be scalable; unit cost includes annual O&M costs; 30-year amortization @5% assumed
 Scenarios based on contractors paying for
conveyance
 “Low” scenario assumes cost share between SWP
and CVP of 55 percent/45 percent, respectively
 MWD shares = Existing Table A allocation
 “High” scenario assumes urban and agricultural
split of 90 percent/10 percent, respectively
 MWD Shares = proportional share of urban deliveries
 Additional “risk premiums” are added to both low
and high scenarios
8
9
Risk Element Evaluation Assumptions
Construction Cost 50% increase applied to capital cost
estimates
Construction Delay 5-year delay in bond issuance
Cost of Funds 100 basis points added to project
financing
Failure of Public Financing Contractors pay for 100% of public
habitat funding
Decision Tree Impacts to
Operations
3% added to O&M costs 10 years after
project completion
10
Based on MWD’s Integrated Resources Plan sales projection of 1.8 MAF in 2025
11
 The Delta is broken and current operations are not
sustainable
 It is unclear if BDCP proposed action would secure
California’s water supply and improve the ecological
health of the Delta
 NRDC Portfolio and BDCP Plus alternatives produce
less Delta exports and require investments in storage
and local resources
 Investment in local resources in San Diego County
could fill supply gap widened by reduced exports
 Without clear and committed funding sources, the
Water Authority is faced with undefined cost exposure
12
13

More Related Content

What's hot

Bay-Delta Conservation Plan: Comparison of Estimated Yields - Sept. 26, 2013
Bay-Delta Conservation Plan: Comparison of Estimated Yields - Sept. 26, 2013Bay-Delta Conservation Plan: Comparison of Estimated Yields - Sept. 26, 2013
Bay-Delta Conservation Plan: Comparison of Estimated Yields - Sept. 26, 2013
San Diego County Water Authority
 
U.S. Marine Emissions Regulations: Compliance Assessment, Team Finland Future...
U.S. Marine Emissions Regulations: Compliance Assessment, Team Finland Future...U.S. Marine Emissions Regulations: Compliance Assessment, Team Finland Future...
U.S. Marine Emissions Regulations: Compliance Assessment, Team Finland Future...
Team Finland Future Watch
 
C Arias EA Current_WEM3 2015 Paddock Wood
C Arias EA Current_WEM3 2015 Paddock WoodC Arias EA Current_WEM3 2015 Paddock Wood
C Arias EA Current_WEM3 2015 Paddock Wood
Arias Christian
 

What's hot (20)

January 10, 2013
January 10, 2013January 10, 2013
January 10, 2013
 
RS-16-154 Nolan Creek Flood Protection Plan
RS-16-154 Nolan Creek Flood Protection PlanRS-16-154 Nolan Creek Flood Protection Plan
RS-16-154 Nolan Creek Flood Protection Plan
 
Bay-Delta Conservation Plan: Comparison of Estimated Yields - Sept. 26, 2013
Bay-Delta Conservation Plan: Comparison of Estimated Yields - Sept. 26, 2013Bay-Delta Conservation Plan: Comparison of Estimated Yields - Sept. 26, 2013
Bay-Delta Conservation Plan: Comparison of Estimated Yields - Sept. 26, 2013
 
Comparing the Costs of Submarine Maintenance at Public and Private Shipyards
Comparing the Costs of Submarine Maintenance at Public and Private ShipyardsComparing the Costs of Submarine Maintenance at Public and Private Shipyards
Comparing the Costs of Submarine Maintenance at Public and Private Shipyards
 
U.S. Marine Emissions Regulations: Compliance Assessment, Team Finland Future...
U.S. Marine Emissions Regulations: Compliance Assessment, Team Finland Future...U.S. Marine Emissions Regulations: Compliance Assessment, Team Finland Future...
U.S. Marine Emissions Regulations: Compliance Assessment, Team Finland Future...
 
RWT_SYARIEF_43298608
RWT_SYARIEF_43298608RWT_SYARIEF_43298608
RWT_SYARIEF_43298608
 
TWCA Webinar - New “Waters of the United States” Rule
TWCA Webinar - New “Waters of the United States” RuleTWCA Webinar - New “Waters of the United States” Rule
TWCA Webinar - New “Waters of the United States” Rule
 
Njf redevelopment forum 2018 kumar
Njf redevelopment forum 2018 kumarNjf redevelopment forum 2018 kumar
Njf redevelopment forum 2018 kumar
 
Sanders, Richard: The Integrated Ocean Carbon Observing System
Sanders, Richard: The Integrated Ocean Carbon Observing SystemSanders, Richard: The Integrated Ocean Carbon Observing System
Sanders, Richard: The Integrated Ocean Carbon Observing System
 
Bay-Delta Update - Oct. 25, 2012
Bay-Delta Update - Oct. 25, 2012Bay-Delta Update - Oct. 25, 2012
Bay-Delta Update - Oct. 25, 2012
 
Lacey Hirschvogel, MDNR, Multiple Discharger Variance, Missouri Water Seminar...
Lacey Hirschvogel, MDNR, Multiple Discharger Variance, Missouri Water Seminar...Lacey Hirschvogel, MDNR, Multiple Discharger Variance, Missouri Water Seminar...
Lacey Hirschvogel, MDNR, Multiple Discharger Variance, Missouri Water Seminar...
 
Ecmhi m95 washburn
Ecmhi m95 washburnEcmhi m95 washburn
Ecmhi m95 washburn
 
Draft Delta Plan EIR - Jan. 26, 2012
Draft Delta Plan EIR - Jan. 26, 2012Draft Delta Plan EIR - Jan. 26, 2012
Draft Delta Plan EIR - Jan. 26, 2012
 
Only the Pipes Should be Hidden
Only the Pipes Should be HiddenOnly the Pipes Should be Hidden
Only the Pipes Should be Hidden
 
Acquisition of gulf coast natural gas assets final
Acquisition of gulf coast natural gas assets   finalAcquisition of gulf coast natural gas assets   final
Acquisition of gulf coast natural gas assets final
 
Badger Sheriff's Association Conference - Port Washington Police Department P...
Badger Sheriff's Association Conference - Port Washington Police Department P...Badger Sheriff's Association Conference - Port Washington Police Department P...
Badger Sheriff's Association Conference - Port Washington Police Department P...
 
C Arias EA Current_WEM3 2015 Paddock Wood
C Arias EA Current_WEM3 2015 Paddock WoodC Arias EA Current_WEM3 2015 Paddock Wood
C Arias EA Current_WEM3 2015 Paddock Wood
 
Example of IDEF 0 Diagram
Example of IDEF 0 Diagram Example of IDEF 0 Diagram
Example of IDEF 0 Diagram
 
Example IDEF 0 Flow Diagrams
Example IDEF 0 Flow DiagramsExample IDEF 0 Flow Diagrams
Example IDEF 0 Flow Diagrams
 
Sample-BCFerries natgas
Sample-BCFerries natgasSample-BCFerries natgas
Sample-BCFerries natgas
 

Similar to Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Water Authority - February 27, 2014

Economic Analyses Conducted on the Bay Delta Conservation Plan - David Sung, ...
Economic Analyses Conducted on the Bay Delta Conservation Plan - David Sung, ...Economic Analyses Conducted on the Bay Delta Conservation Plan - David Sung, ...
Economic Analyses Conducted on the Bay Delta Conservation Plan - David Sung, ...
San Diego County Water Authority
 
Is the Bay Delta Conservation Plan a Doable Deal? - Rodney T. Smith - Sept. 1...
Is the Bay Delta Conservation Plan a Doable Deal? - Rodney T. Smith - Sept. 1...Is the Bay Delta Conservation Plan a Doable Deal? - Rodney T. Smith - Sept. 1...
Is the Bay Delta Conservation Plan a Doable Deal? - Rodney T. Smith - Sept. 1...
San Diego County Water Authority
 
Q3 2014 Growth Initiatives Update
Q3 2014 Growth Initiatives UpdateQ3 2014 Growth Initiatives Update
Q3 2014 Growth Initiatives Update
EnLinkMidstreamLLC
 
THE ART OF REDUCING LEAKAGE – BLENDING SMART ANALYTICS WITH SIMPLICITY
THE ART OF REDUCING LEAKAGE – BLENDING SMART ANALYTICS WITH SIMPLICITYTHE ART OF REDUCING LEAKAGE – BLENDING SMART ANALYTICS WITH SIMPLICITY
THE ART OF REDUCING LEAKAGE – BLENDING SMART ANALYTICS WITH SIMPLICITY
iQHub
 

Similar to Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Water Authority - February 27, 2014 (20)

State Treasurer's Assessment of the Affordability and Financing Consideration...
State Treasurer's Assessment of the Affordability and Financing Consideration...State Treasurer's Assessment of the Affordability and Financing Consideration...
State Treasurer's Assessment of the Affordability and Financing Consideration...
 
Bay-Delta Conservation Plan: Preliminary Assessment of Financing Risk Paramet...
Bay-Delta Conservation Plan: Preliminary Assessment of Financing Risk Paramet...Bay-Delta Conservation Plan: Preliminary Assessment of Financing Risk Paramet...
Bay-Delta Conservation Plan: Preliminary Assessment of Financing Risk Paramet...
 
Bay-Delta Conservation Plan (BDCP) Supply and Demand Risk Assessment - Jan. 9...
Bay-Delta Conservation Plan (BDCP) Supply and Demand Risk Assessment - Jan. 9...Bay-Delta Conservation Plan (BDCP) Supply and Demand Risk Assessment - Jan. 9...
Bay-Delta Conservation Plan (BDCP) Supply and Demand Risk Assessment - Jan. 9...
 
Master Plan EIR CAP Presentation - March 27, 2014
Master Plan EIR CAP Presentation - March 27, 2014Master Plan EIR CAP Presentation - March 27, 2014
Master Plan EIR CAP Presentation - March 27, 2014
 
State Treasurer's Assessment of the Affordability and Financing Consideration...
State Treasurer's Assessment of the Affordability and Financing Consideration...State Treasurer's Assessment of the Affordability and Financing Consideration...
State Treasurer's Assessment of the Affordability and Financing Consideration...
 
Economic Analyses Conducted on the Bay Delta Conservation Plan - David Sung, ...
Economic Analyses Conducted on the Bay Delta Conservation Plan - David Sung, ...Economic Analyses Conducted on the Bay Delta Conservation Plan - David Sung, ...
Economic Analyses Conducted on the Bay Delta Conservation Plan - David Sung, ...
 
Is the Bay Delta Conservation Plan a Doable Deal? - Rodney T. Smith - Sept. 1...
Is the Bay Delta Conservation Plan a Doable Deal? - Rodney T. Smith - Sept. 1...Is the Bay Delta Conservation Plan a Doable Deal? - Rodney T. Smith - Sept. 1...
Is the Bay Delta Conservation Plan a Doable Deal? - Rodney T. Smith - Sept. 1...
 
The Rate Setting Process
The Rate Setting ProcessThe Rate Setting Process
The Rate Setting Process
 
Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...
Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...
Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...
 
Q3 2014 Growth Initiatives Update
Q3 2014 Growth Initiatives UpdateQ3 2014 Growth Initiatives Update
Q3 2014 Growth Initiatives Update
 
THE ART OF REDUCING LEAKAGE – BLENDING SMART ANALYTICS WITH SIMPLICITY
THE ART OF REDUCING LEAKAGE – BLENDING SMART ANALYTICS WITH SIMPLICITYTHE ART OF REDUCING LEAKAGE – BLENDING SMART ANALYTICS WITH SIMPLICITY
THE ART OF REDUCING LEAKAGE – BLENDING SMART ANALYTICS WITH SIMPLICITY
 
9/9 FRI 11:00 | Water Woes, Cash Flow Woes & Future Growth
9/9 FRI 11:00 | Water Woes, Cash Flow Woes & Future Growth9/9 FRI 11:00 | Water Woes, Cash Flow Woes & Future Growth
9/9 FRI 11:00 | Water Woes, Cash Flow Woes & Future Growth
 
Energy Choices - Sept 17 2014
Energy Choices - Sept 17 2014Energy Choices - Sept 17 2014
Energy Choices - Sept 17 2014
 
WELLS FARGO SECURITIES RESEARCH, ECONOMICS AND STRATEGY 2014 ENERGY SYMPOSIUM
WELLS FARGO SECURITIES RESEARCH, ECONOMICS AND STRATEGY 2014 ENERGY SYMPOSIUMWELLS FARGO SECURITIES RESEARCH, ECONOMICS AND STRATEGY 2014 ENERGY SYMPOSIUM
WELLS FARGO SECURITIES RESEARCH, ECONOMICS AND STRATEGY 2014 ENERGY SYMPOSIUM
 
assignmenttutorhelp.com
assignmenttutorhelp.comassignmenttutorhelp.com
assignmenttutorhelp.com
 
Efficient Use of Water - Drew Beckwith, Western Resources Associates
Efficient Use of Water - Drew Beckwith, Western Resources AssociatesEfficient Use of Water - Drew Beckwith, Western Resources Associates
Efficient Use of Water - Drew Beckwith, Western Resources Associates
 
Clean Air Partnership Green Infrastructure CAC Meeting - Don Mills Channel Fl...
Clean Air Partnership Green Infrastructure CAC Meeting - Don Mills Channel Fl...Clean Air Partnership Green Infrastructure CAC Meeting - Don Mills Channel Fl...
Clean Air Partnership Green Infrastructure CAC Meeting - Don Mills Channel Fl...
 
Citi conference presentation final - 8.20.14
Citi conference presentation   final - 8.20.14Citi conference presentation   final - 8.20.14
Citi conference presentation final - 8.20.14
 
Simplifying stormwater design is costing us money - a short case study
Simplifying stormwater design is costing us money - a short case studySimplifying stormwater design is costing us money - a short case study
Simplifying stormwater design is costing us money - a short case study
 
Creating Green Infrastructure
Creating Green Infrastructure  Creating Green Infrastructure
Creating Green Infrastructure
 

More from San Diego County Water Authority

More from San Diego County Water Authority (20)

Session 2 presentation
Session 2 presentationSession 2 presentation
Session 2 presentation
 
Update on Supply Conditions and Drought Response Activities - September 24, 2015
Update on Supply Conditions and Drought Response Activities - September 24, 2015Update on Supply Conditions and Drought Response Activities - September 24, 2015
Update on Supply Conditions and Drought Response Activities - September 24, 2015
 
Update on Supply Conditions and Drought Response Activities - June 25, 2015
Update on Supply Conditions and Drought Response Activities - June 25, 2015 Update on Supply Conditions and Drought Response Activities - June 25, 2015
Update on Supply Conditions and Drought Response Activities - June 25, 2015
 
Update on Supply Conditions and Drought Response Activities - October 22, 2015
Update on Supply Conditions and Drought Response Activities - October 22, 2015Update on Supply Conditions and Drought Response Activities - October 22, 2015
Update on Supply Conditions and Drought Response Activities - October 22, 2015
 
Update on Supply Conditions and Drought Response Activities - December 10, 2015
Update on Supply Conditions and Drought Response Activities - December 10, 2015Update on Supply Conditions and Drought Response Activities - December 10, 2015
Update on Supply Conditions and Drought Response Activities - December 10, 2015
 
Update on Supply Conditions and Drought Response Activities - February 25, 2016
Update on Supply Conditions and Drought Response Activities - February 25, 2016Update on Supply Conditions and Drought Response Activities - February 25, 2016
Update on Supply Conditions and Drought Response Activities - February 25, 2016
 
Update on Supply Conditions and Drought Response Activities - August 27, 2015
Update on Supply Conditions and Drought Response Activities - August 27, 2015Update on Supply Conditions and Drought Response Activities - August 27, 2015
Update on Supply Conditions and Drought Response Activities - August 27, 2015
 
Update on Supply Conditions and Drought Response Activities - July 23, 2015
Update on Supply Conditions and Drought Response Activities - July 23, 2015 Update on Supply Conditions and Drought Response Activities - July 23, 2015
Update on Supply Conditions and Drought Response Activities - July 23, 2015
 
Bay Delta Conservation Plan/California WaterFix
Bay Delta Conservation Plan/California WaterFixBay Delta Conservation Plan/California WaterFix
Bay Delta Conservation Plan/California WaterFix
 
Bay Delta Conservation Plan/California WaterFix
Bay Delta Conservation Plan/California WaterFixBay Delta Conservation Plan/California WaterFix
Bay Delta Conservation Plan/California WaterFix
 
Bay-Delta Activities Update
Bay-Delta Activities UpdateBay-Delta Activities Update
Bay-Delta Activities Update
 
2015-2016 Bay-Delta Workplan - February 26, 2015
2015-2016 Bay-Delta Workplan - February 26, 20152015-2016 Bay-Delta Workplan - February 26, 2015
2015-2016 Bay-Delta Workplan - February 26, 2015
 
Bay-Delta Conservation Plan: Supplemental Draft EIR/EIS Comment Letter - July...
Bay-Delta Conservation Plan: Supplemental Draft EIR/EIS Comment Letter - July...Bay-Delta Conservation Plan: Supplemental Draft EIR/EIS Comment Letter - July...
Bay-Delta Conservation Plan: Supplemental Draft EIR/EIS Comment Letter - July...
 
Bay-Delta Conservation Plan: Draft EIR/EIS Comment Letter - March 27, 2014
Bay-Delta Conservation Plan: Draft EIR/EIS Comment Letter - March 27, 2014Bay-Delta Conservation Plan: Draft EIR/EIS Comment Letter - March 27, 2014
Bay-Delta Conservation Plan: Draft EIR/EIS Comment Letter - March 27, 2014
 
Update on Supply Conditions and Drought Response Activities
Update on Supply Conditions and Drought Response ActivitiesUpdate on Supply Conditions and Drought Response Activities
Update on Supply Conditions and Drought Response Activities
 
Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...
Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...
Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...
 
Update on Supply Conditions and Drought Response Actions
Update on Supply Conditions and Drought Response ActionsUpdate on Supply Conditions and Drought Response Actions
Update on Supply Conditions and Drought Response Actions
 
Water Supply and Drought Management Update - Feb. 26, 2015
Water Supply and Drought Management Update - Feb. 26, 2015Water Supply and Drought Management Update - Feb. 26, 2015
Water Supply and Drought Management Update - Feb. 26, 2015
 
Update on Water Supply Conditions and Drought Response Activities - March 26,...
Update on Water Supply Conditions and Drought Response Activities - March 26,...Update on Water Supply Conditions and Drought Response Activities - March 26,...
Update on Water Supply Conditions and Drought Response Activities - March 26,...
 
Water Supply and Drought Management Update - Nov. 20, 2014
Water Supply and Drought Management Update - Nov. 20, 2014Water Supply and Drought Management Update - Nov. 20, 2014
Water Supply and Drought Management Update - Nov. 20, 2014
 

Recently uploaded

Unique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdfUnique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdf
ScottMeyers35
 

Recently uploaded (20)

31st World Press Freedom Day - A Press for the Planet: Journalism in the face...
31st World Press Freedom Day - A Press for the Planet: Journalism in the face...31st World Press Freedom Day - A Press for the Planet: Journalism in the face...
31st World Press Freedom Day - A Press for the Planet: Journalism in the face...
 
Unique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdfUnique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdf
 
2024 UNESCO/Guillermo Cano World Press Freedom Prize
2024 UNESCO/Guillermo Cano World Press Freedom Prize2024 UNESCO/Guillermo Cano World Press Freedom Prize
2024 UNESCO/Guillermo Cano World Press Freedom Prize
 
Finance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCCFinance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCC
 
An Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCCAn Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCC
 
World Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - PosterWorld Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - Poster
 
Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)
 
NAP Expo - Delivering effective and adequate adaptation.pptx
NAP Expo - Delivering effective and adequate adaptation.pptxNAP Expo - Delivering effective and adequate adaptation.pptx
NAP Expo - Delivering effective and adequate adaptation.pptx
 
Dating Call Girls inBaloda Bazar Bhatapara 9332606886Call Girls Advance Cash...
Dating Call Girls inBaloda Bazar Bhatapara  9332606886Call Girls Advance Cash...Dating Call Girls inBaloda Bazar Bhatapara  9332606886Call Girls Advance Cash...
Dating Call Girls inBaloda Bazar Bhatapara 9332606886Call Girls Advance Cash...
 
31st World Press Freedom Day Conference in Santiago.
31st World Press Freedom Day Conference in Santiago.31st World Press Freedom Day Conference in Santiago.
31st World Press Freedom Day Conference in Santiago.
 
1935 CONSTITUTION REPORT IN RIPH FINALLS
1935 CONSTITUTION REPORT IN RIPH FINALLS1935 CONSTITUTION REPORT IN RIPH FINALLS
1935 CONSTITUTION REPORT IN RIPH FINALLS
 
3 May, Journalism in the face of the Environmental Crisis.
3 May, Journalism in the face of the Environmental Crisis.3 May, Journalism in the face of the Environmental Crisis.
3 May, Journalism in the face of the Environmental Crisis.
 
A Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental CrisisA Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental Crisis
 
Kolkata Call Girls Halisahar 💯Call Us 🔝 8005736733 🔝 💃 Top Class Call Girl ...
Kolkata Call Girls Halisahar  💯Call Us 🔝 8005736733 🔝 💃  Top Class Call Girl ...Kolkata Call Girls Halisahar  💯Call Us 🔝 8005736733 🔝 💃  Top Class Call Girl ...
Kolkata Call Girls Halisahar 💯Call Us 🔝 8005736733 🔝 💃 Top Class Call Girl ...
 
Just Call VIP Call Girls In Bangalore Kr Puram ☎️ 6378878445 Independent Fem...
Just Call VIP Call Girls In  Bangalore Kr Puram ☎️ 6378878445 Independent Fem...Just Call VIP Call Girls In  Bangalore Kr Puram ☎️ 6378878445 Independent Fem...
Just Call VIP Call Girls In Bangalore Kr Puram ☎️ 6378878445 Independent Fem...
 
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and NumberCall Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
 
Financing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCFinancing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCC
 
74th Amendment of India PPT by Piyush(IC).pptx
74th Amendment of India PPT by Piyush(IC).pptx74th Amendment of India PPT by Piyush(IC).pptx
74th Amendment of India PPT by Piyush(IC).pptx
 
2024: The FAR, Federal Acquisition Regulations, Part 32
2024: The FAR, Federal Acquisition Regulations, Part 322024: The FAR, Federal Acquisition Regulations, Part 32
2024: The FAR, Federal Acquisition Regulations, Part 32
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
 

Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Water Authority - February 27, 2014

  • 1. Amy I. Chen, Director of MWD Program Dan Denham, Acting Director of Colorado River Program Imported Water Committee February 27, 2014 1
  • 2.  Three key points 1. BDCP is a massive infrastructure project, will take tremendous effort to implement, costs will likely go up 2. How costs are allocated, and who will ultimately commit to pay for the project are vitally important to Water Authority’s ratepayers 3. Water Authority’s region has additional local projects that may be explored to lessen the supply impact, although at a cost, but with more local control 2
  • 3. 3 Capacity 9,000 cfs 6,000 cfs 3,000 cfs Primary type of conveyance pipelines/tunnels pipelines/tunnels pipelines/tunnels Tunnel Twin Twin Twin Single a Operations High Outflow Low Outflow High Outflow High Outflow High Outflow Total Export 4.7 MAF 5.6 MAF 4.5 MAF 4.2 MAF 4.2 MAF BDCP Benefits b 1.2 MAF 1.7 MAF 1 MAF 740 TAF 740 TAF Capital Cost c $14,344M $13,146M $10,821M $8,600M O&M Cost c, d $1,456M $1,311M $1,118M a BDCP Blog http://baydeltaconservationplan.com/news/blog/13-11-12/Revised_Capital_Cost_for_3_000_cfs_Single_Bore_Tunnel.aspx b When compared against “no action” alternative as described in BDCP Chapter 9, Alternative to Take c Value expressed in undiscounted 2012 dollars d Source: Chapter 9.B “Take Alternatives Cost Estimation” Tables 9.B-9, -10, and -13. For ratio of annual O&M costs, utilized same assumptions as the proposed action (40 years of facility operation and power and 30 years of replacement cost). Cost Estimate and Yield* Summary *Export water yield from the “no action” alternative: 3.5 MAF– 3.9 MAF
  • 4.  Project costs: escalation/overruns  Construction schedule: delays  Cost allocation:  Unclear; Project costs to be shared by SWP and CVP contractors, yet, allocation of cost obligations will not be determined until “near the time that permits are issued for BDCP”  Financing costs  Reduced yield from Decision Tree/Adaptive Management  State and federal funding doesn’t materialize  “Funding estimates from state and federal agencies do not represent commitment” 4
  • 5.  MWD is the largest SWP contractor  How costs are allocated among the contractors critical  MWD could be exposed to between 25% to more than half of total BDCP cost  Supply benefit hinges on MWD’s ability to capture and store wet-year supply for dry-year use  Water Authority’s potential share: 25%-37%  Based on MWD’s current cost allocation methodology  Water supply benefit subject to MWD’s control  MWD controls blend of supply to Water Authority  MWD determines when supplies are stored and withdrawn 5
  • 6. 6 BDCP Yield MWD 1 BDCP Yield Water Authority 2 Total Cost to Water Authority 3 Additional Common Risks 9,000 cfs 4 (proposed action) 302 taf – 428 taf 55 taf - 78 taf $1,066M – $2,208M Construction estimate Scheduling delay Financing cost Reduced yield from Decision Tree / adaptive management process 6,000 cfs 4 262 taf 48 taf $911M-1,885M 3,000 cfs 4 187 taf 34 taf $612M- $1,267M 1. Based on average of potential BDCP benefit when compared with “no action” as described in BDCP Chapter 9; yield benefit is shared 55/45 SWP/CVP with MWD getting its Table A allocation 2. Based on Water Authority’s preferential right to MWD water as of 6/30/2013 3. In 2012$, based on cost allocation assumptions described in this memo, with Water Authority paying for 25% of MWD share, based on MWD’s current cost allocation methodology 4. Modeling results for high outflow and low outflow are provided for 9,000 cfs only; export yields for other conveyance capacity options included results from high outflow only. BDCP Conveyance Alternatives Yields and Costs to Water Authority
  • 7.  To address potential supply gap, a selection of local resources projects were investigated  Projects were not included in 2010 UWMP as “verifiable projects” 7 Potential Annual Yield Total Capital Cost to Region Unit Cost ($/af) Seawater desal 1 56 taf-168 taf $1.43B-$3.2B $2,260-$2,860 Indirect Potable Reuse 2 93 taf $2.1B $2,175-$2,375 1. Based on cost estimates prepared for proposed Camp Pendleton Seawater Desalination Project (Oct/Nov 2013); unit cost includes annual O&M costs; 30-year amortization @5% assumed 2. “Gross costs” based on city of San Diego Recycled Water Study (Integrated Reuse Alternatives); does not include any potential avoided wastewater costs or potential offset savings such as grants, or low interest loans; project may be scalable; unit cost includes annual O&M costs; 30-year amortization @5% assumed
  • 8.  Scenarios based on contractors paying for conveyance  “Low” scenario assumes cost share between SWP and CVP of 55 percent/45 percent, respectively  MWD shares = Existing Table A allocation  “High” scenario assumes urban and agricultural split of 90 percent/10 percent, respectively  MWD Shares = proportional share of urban deliveries  Additional “risk premiums” are added to both low and high scenarios 8
  • 9. 9 Risk Element Evaluation Assumptions Construction Cost 50% increase applied to capital cost estimates Construction Delay 5-year delay in bond issuance Cost of Funds 100 basis points added to project financing Failure of Public Financing Contractors pay for 100% of public habitat funding Decision Tree Impacts to Operations 3% added to O&M costs 10 years after project completion
  • 10. 10 Based on MWD’s Integrated Resources Plan sales projection of 1.8 MAF in 2025
  • 11. 11
  • 12.  The Delta is broken and current operations are not sustainable  It is unclear if BDCP proposed action would secure California’s water supply and improve the ecological health of the Delta  NRDC Portfolio and BDCP Plus alternatives produce less Delta exports and require investments in storage and local resources  Investment in local resources in San Diego County could fill supply gap widened by reduced exports  Without clear and committed funding sources, the Water Authority is faced with undefined cost exposure 12
  • 13. 13