SlideShare a Scribd company logo
1 of 12
OPERATION RESEARCH

***PRESENTED BY***
Jacob John Panicker
PRESENTATION OUTLINE
•
•
•
•
•
•

Project time cost trade off
Project crashing
Time cost trade off procedure
Resource allocation
Resource leveling
Resource smoothing
PROJECT TIME COST TRADE OFF

 Project time can be reduced by crashing
 Normal time reduced, budget increase
 Use additional resource to complete on time
PROJECT CRASHING
Crashing number of activities to reduce
duration of project
Cost increases more quickly when time is
reduced
Relationship between normal time and cost
and crash time and time is linear
TIME COST TRADE OFF PROCEDURE
1. Determine normal project completion time
and associated critical path
2. Identify critical activities and compute cost
slope
cost slope= crash cost - normal cost
crash time - normal time
3. Identify and crash an activity time on critical
path
4. If the critical path is still critical, return to
step 3
5. Terminate the procedure after each critical
activity crashed to its lower possible time
RESOURCE ALLOCATION
Resources are:men, money, material, machinery etc..,
Network analysis PERT/CPM is carried out
using unlimited resources
Resources may not be uniform throughout the
project
RESOURCE LEVELLING
 Stabilize rate of resource utilization without
changing project duration
 Total float of non-critical activity
 Shift non-critical activity between earliest start
time and latest allowable time can lower
maximum resource requirement
i. Total float=free float can be scheduled between
earliest start and latest times
ii. Total float>free float starting time can be
delayed
RESOURCE SMOOTHING
Reduce peak demand for resources and
reallocate them and shortest duration
I. Calculate earliest start and latest finish
times, draw time scaled network
II. Draw resource histogram
III. Shift the start time of those non-critical
activities
CONCLUSION
I conclude by saying that to reduce the
time duration the cost of the project will be
increased. The crash point is the point beyond
which the time cannot be reduced nor the
cost can be increased.
THANK YOU

More Related Content

Similar to Operation research

Time management pressent
Time management pressentTime management pressent
Time management pressentiklil fairuz
 
Allocating Resources To The Project
Allocating Resources To The ProjectAllocating Resources To The Project
Allocating Resources To The ProjectJeff Brooks
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost ManagementBhuWan Khadka
 
05 Project Monitoring & Cost Control
05 Project Monitoring & Cost Control05 Project Monitoring & Cost Control
05 Project Monitoring & Cost Controlakashpadole
 
Time cost trade off
Time cost trade offTime cost trade off
Time cost trade offzollatrix
 
Pert cpm-120421125920-phpapp02
Pert cpm-120421125920-phpapp02Pert cpm-120421125920-phpapp02
Pert cpm-120421125920-phpapp02kongara
 
unit-3 POM.pptx
unit-3 POM.pptxunit-3 POM.pptx
unit-3 POM.pptxjaya315652
 
time cost trade off
 time cost trade off time cost trade off
time cost trade offbriankirui9
 
9-180307064518 (1).pptx
9-180307064518 (1).pptx9-180307064518 (1).pptx
9-180307064518 (1).pptxRenvic
 
Scheduling of a five story residential apartment project
Scheduling of a five story residential apartment project Scheduling of a five story residential apartment project
Scheduling of a five story residential apartment project kaishwarya3
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertRaj J Das
 
Test folder.pptx
Test folder.pptxTest folder.pptx
Test folder.pptxCons11
 
ABIJU_Software _project _scheduling.pptx
ABIJU_Software _project _scheduling.pptxABIJU_Software _project _scheduling.pptx
ABIJU_Software _project _scheduling.pptxBVimala1
 
Mba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aMba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aRai University
 
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_siesOm lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_siesvideoaakash15
 

Similar to Operation research (20)

Time management pressent
Time management pressentTime management pressent
Time management pressent
 
Allocating Resources To The Project
Allocating Resources To The ProjectAllocating Resources To The Project
Allocating Resources To The Project
 
EpM
EpMEpM
EpM
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 
05 Project Monitoring & Cost Control
05 Project Monitoring & Cost Control05 Project Monitoring & Cost Control
05 Project Monitoring & Cost Control
 
Time cost trade off
Time cost trade offTime cost trade off
Time cost trade off
 
Pert cpm-120421125920-phpapp02
Pert cpm-120421125920-phpapp02Pert cpm-120421125920-phpapp02
Pert cpm-120421125920-phpapp02
 
unit-3 POM.pptx
unit-3 POM.pptxunit-3 POM.pptx
unit-3 POM.pptx
 
time cost trade off
 time cost trade off time cost trade off
time cost trade off
 
9-180307064518 (1).pptx
9-180307064518 (1).pptx9-180307064518 (1).pptx
9-180307064518 (1).pptx
 
Allocating resources
Allocating resourcesAllocating resources
Allocating resources
 
Scheduling of a five story residential apartment project
Scheduling of a five story residential apartment project Scheduling of a five story residential apartment project
Scheduling of a five story residential apartment project
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gert
 
Test folder.pptx
Test folder.pptxTest folder.pptx
Test folder.pptx
 
ABIJU_Software _project _scheduling.pptx
ABIJU_Software _project _scheduling.pptxABIJU_Software _project _scheduling.pptx
ABIJU_Software _project _scheduling.pptx
 
Mba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aMba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management a
 
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_siesOm lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
 
vk1
vk1vk1
vk1
 
Unit IV-Project Management
Unit IV-Project ManagementUnit IV-Project Management
Unit IV-Project Management
 
Final Review
Final ReviewFinal Review
Final Review
 

More from Jacob John Panicker (17)

Promotion mix
Promotion mixPromotion mix
Promotion mix
 
Environent and its components
Environent  and its componentsEnvironent  and its components
Environent and its components
 
Environmental Management
Environmental Management Environmental Management
Environmental Management
 
Financial Agencies
Financial AgenciesFinancial Agencies
Financial Agencies
 
Scaling technique
Scaling techniqueScaling technique
Scaling technique
 
Chi square
Chi squareChi square
Chi square
 
Retro marketing
Retro marketingRetro marketing
Retro marketing
 
Management
ManagementManagement
Management
 
Leadershp presentation
Leadershp presentationLeadershp presentation
Leadershp presentation
 
Insurance sector
Insurance sectorInsurance sector
Insurance sector
 
The industrial dispute act 1947
The industrial dispute act 1947The industrial dispute act 1947
The industrial dispute act 1947
 
Intervention strategies
Intervention strategiesIntervention strategies
Intervention strategies
 
Identification of training and development needs
Identification of training and development needsIdentification of training and development needs
Identification of training and development needs
 
Executive information
Executive informationExecutive information
Executive information
 
Environmental laws
Environmental lawsEnvironmental laws
Environmental laws
 
Emerging concept
Emerging conceptEmerging concept
Emerging concept
 
Attitude
AttitudeAttitude
Attitude
 

Operation research

  • 2. PRESENTATION OUTLINE • • • • • • Project time cost trade off Project crashing Time cost trade off procedure Resource allocation Resource leveling Resource smoothing
  • 3. PROJECT TIME COST TRADE OFF  Project time can be reduced by crashing  Normal time reduced, budget increase  Use additional resource to complete on time
  • 4. PROJECT CRASHING Crashing number of activities to reduce duration of project Cost increases more quickly when time is reduced Relationship between normal time and cost and crash time and time is linear
  • 5.
  • 6. TIME COST TRADE OFF PROCEDURE 1. Determine normal project completion time and associated critical path 2. Identify critical activities and compute cost slope cost slope= crash cost - normal cost crash time - normal time
  • 7. 3. Identify and crash an activity time on critical path 4. If the critical path is still critical, return to step 3 5. Terminate the procedure after each critical activity crashed to its lower possible time
  • 8. RESOURCE ALLOCATION Resources are:men, money, material, machinery etc.., Network analysis PERT/CPM is carried out using unlimited resources Resources may not be uniform throughout the project
  • 9. RESOURCE LEVELLING  Stabilize rate of resource utilization without changing project duration  Total float of non-critical activity  Shift non-critical activity between earliest start time and latest allowable time can lower maximum resource requirement i. Total float=free float can be scheduled between earliest start and latest times ii. Total float>free float starting time can be delayed
  • 10. RESOURCE SMOOTHING Reduce peak demand for resources and reallocate them and shortest duration I. Calculate earliest start and latest finish times, draw time scaled network II. Draw resource histogram III. Shift the start time of those non-critical activities
  • 11. CONCLUSION I conclude by saying that to reduce the time duration the cost of the project will be increased. The crash point is the point beyond which the time cannot be reduced nor the cost can be increased.