1. 9/7/2010
Alltec Modular Lifting Beams, patent pending,
were designed and manufactured in 2009 to
meet the needs within the petro‐chemical
industry to set modular components with ease.
Transportable system that accommodates a
Transportable system that accommodates a
variety of lifting arrangements.
James R Florey PE Transportable Quick Adjustments Variety of lifts with
Alltec Lifting Beam Design System to CG one setup
Alltec Lifting Systems
Quick Assembly Bolt‐Up Beam ASME BTH‐1‐2008
Quick Disassembly Calculator Code
Geometrical Design Geometrical Design Continued
Geometrical Design Continued
Transportable and Adjustable Transportable and Adjustable
Current Modular beams come in 7.5 ft and 15.5 ft Easily transportable between job sites
sections to accommodate 60’+ lengths Easily adjustable top sling and bottom sling
Bolt and pin connections (with link plate positions for various lifting locations
connection design)
i d i )
Geometrical Design Continued Implementation
Structural Rigging Detail Design
Dual Plate Design with centered top lug hole The Modular lifting beams allow for easy adjustment to
Allows for compression force to originate along centerline (no offset CG’s
eccentricity of compression force) With the lug geometry and lifting weight of the device to be lifted,
Allows all loading to be in‐line with center of beam geometry the arrangement of the beams in relation to the top and bottom
Stiffener pipes added to top and bottom of beam plates to slings can be adjusted and quickly validated for structural integrity
through the use of a computer program taking only a few minutes to
ensure adequate I values for weak axis buckling , g
run, saving time and money.y
considerations.
id i The designer can also take into consideration several different lifts
Flanged connection plates for stability and rigidity of and find the best arrangement to fit all similar lifts with the least
connection amount of adjustment, saving time and money.
1
2. 9/7/2010
Implementation (continued) Implementation (continued)
Analysis Analysis (continued)
Design of rigging arrangement considerations
Stress induced into the rigging and the deflection of the rigging Each lift is analyzed to
which in turn will induce stresses into the device that is to be lifted is ensure that all
a consideration that should be understood.
No structure is absolutely stiff components meet ASME
Areas of analysis: – BTH ‐1‐2008 code.
Shear stress
Shear stress
Bending Stress
Deflection
Symmetry of loading
Implementation (continued)
Analysis (continued)
Alltec’s Modular beam
program solves a 2
order indeterminate
beam column structure
beam column structure
by means of the “direct
displacement method”
It then checks the
results to ensure the
BTH‐1‐2008 code is met
Implementation (continued) Implementation (continued)
2
3. 9/7/2010
Implementation (continued) Implementation (continued)
Implementation (continued) Flint Hills Module Lifts
Flint Hills
60 + feet and up to 240 Tons
3 different Towers and Drums
7‐ Air coolers
1‐ Analyzer Shelter
3‐motor Control Centers
31‐ Different Modules
Flint Hills Module Lifts Flint Hills Module Lifts
3
4. 9/7/2010
Shaw Shaw
Design of modular systems to meet larger Design of modular
systems
lifts and maintain transportable and 1000 Ton System
adjustable systems which will eliminate 106 ft vertical
head room
long setup times and can be used for a
variety of different lifts
variety of different lifts
Alltec’s modular system designs can be constructed to
lift larger loads over longer spans, The same method
of design and analysis will be used on all of Alltec’s
modular systems.
James R Florey PE
Alltec Lifting Beam Design
Alltec Lifting Systems
4