SlideShare a Scribd company logo
1 of 26
FACTORS AFFECTING
PERFORMANCE OF A SOLAR PV
PROJECTS
EnvironmentFirst Energy Services (P) Ltd.
“Privileged to Impart Knowledge”
There some factors which are beyond the control of Human efforts but certainly
there are other factors too which can be insured to have optimum out put of
energy. A Good design and operation practices save us from huge losses
The Annual amount of energy that will be produced by
a PV system depends on various conditions
IMPORTANT FACTORS
Solar radiation available at the
site
The orientation (azimuth) and
tilt (elevation) of PV arrays
The peak power rating of the
arrays
Energy Conversion Efficiency of
PV modules
Variation in the efficiency of
the Modules with Temperature
Power reducing effects of array
shading by trees, nearby
buildings
Accumulation of Dirt/Smog etc
The Efficiency of Inverter
Cable Thickness
System Design
Grid Operation & Reliability
The annual total quantity of solar
radiation available at the site
• This can be estimated from
meteorological data givng
the measured number of
kWh (or Gj) per square
meter per year incident on
the horizontal surface at the
nearest meteorological
station. In very sunny
conditions it can rise to well
over 2000 kWh m-2y-1.
The orientation (azimuth) and tilt
(elevation) of PV arrays
• For maximum energy
output, the arrays should
be oriented close to south
and with an elevation
roughly equal to latitude
of the site – although
deviation from these
optima does not have a
marked effect, and the
choice of tilt angle can be
varied according to the
seasonal output profile
desired.
The peak power rating of the arrays
• This alternatively can be
termed as area of the
arrays in square meters.
Each manufacturer of
PV panels provides a
data sheet, which will
specify the kWP or
"rated" amount of
power the solar panel
will produce.
Term "Peak Power" is a figure giving
the accuracy
• Many manufacturers
have a + or - of 10%
variation which
suggests a greater
variability in
performance.
• EnvironmentFirst
perform the onsite
analysis of actual power
Performance Warranty
• The second thing to look at … which is not
usually found on the manufacturer's data
sheet is the performance warranty. Typically,
the manufacturer will guarantee that the kWp
output of the panels will not be less than 90%
of the rated peak value (under standard
testing conditions) for the first 10 years, and
not less than 80% for the next 15 years.
Performance Guarantees
• performance guarantees are important to you
(and they certainly are if you are using bank
financing to pay for your installation), then
having re-insurance gives you a bit of extra
comfort on the performance side, and should
be something you should ask about.
The energy Conversion
Efficiency of PV modules:
Different modules have
different kind of materials,
doping type, doping
composition, impurities
etc. due to which their
efficiency varies. Therefore
it is recommended to use
high efficiency modules for
commercial operation so
that to have optimum
results.
The Variation in the efficiency of the
Modules with Temperature
• Solar cells work best at low temperatures, as
determined by their material properties. All
cell materials lose efficiency as the operating
temperature rises. Much of the light energy
shining on cells becomes heat, so it is good to
either match the cell material to the operation
temperature or continually cool the cell.
The Power reducing effects of array
shading by trees, nearby buildings
Accumulation of Dirt/Smog
The Efficiency of Inverter
• The Efficiency of Inverter used to convert the
DC power from the PV arrays into AC, and any
losses that occur in the wiring between PV
system and the final consumer of metering
point can amount to about 10% of the
electricity generated.
Natural Resistance
• The natural resistance to electron flow in a cell
decreases cell efficiency. These losses
predominantly occur in three places: in the
bulk of the primary solar material, in the thin
top layer typical of many devices, and at the
interface between the cell and the electrical
contacts leading to an external circuit.
Electrical Resistance
• Larger electrical contacts can minimize electrical resistance, but
covering a cell with large, opaque metallic contacts would block
too much incident light. Therefore, a trade off must be made
between loss due to resistance and loss due to shading effects.
Typically, top-surface contacts are designed as grids, with many
thin, conductive fingers spread over the cell's surface. However,
it is difficult to produce a grid that maintains good electrical
contact with a cell while also resisting deterioration caused by
changes in temperature or humidity. Generally, the back-surface
contact of a cell is simpler, often being just a layer of metal.
Other designs for electrical contacts include placing everything
on the cell's back surface, or, as in some thin films, depositing a
thin layer of a transparent conducting oxide across the entire
cell.
Cable Thickness
While the size and length of
the cables is a matter of
system design and
installation, for the quality of
cables it is utmost important
that cables adhere to IEC
60227 / IS 694 or IEC 60502 /
IS 1554 (Part I & II). It pays to
familiarize what these
specification standards say. It
is important for a project
developer to know that what
quality of cables are being
installed at site as it could
affect the overall generation
of the plant.
Cable Thickness
• 20 meter is the length of cable between the panel and the
charge controller. A typical cable with 1.5 sq mm cross section
has resistance of about 0.012 ohms per meter of wire length. So
a 20 meter long wire will offer resistance of 20 x 0.012 = 0.24
ohms.
• If it is a 24V system and a 10 ampere current is flowing through
this wire, then from the Ohm’s law (V = IxR), we can calculate
voltage drop across this wire: 2.4V. It means the voltage at the
charge controller end of the cables will be 2.4V less than the
voltage produced by the panels if a 10 Amp current is flowing.
This 10% voltage drop is clearly unacceptable.
Cable Thickness
• What if we use a 6 sq mm cross section cable which has a
resistance of 0.003 ohms per meter. The total resistance for 20
meter long cable will now be 0.06 ohms; and the voltage drop,
10×0.06 or 0.6V. It is 2.5% voltage drop for a 24V system which
might be acceptable. But what about the increased cost of
thicker cable? Likewise, there would be wiring all around and
careful attention must be paid to know the impact on overall
system efficiency. Thus, cable length and size needs careful
attention right at the planning stage.
• Another way to reduce resistance loss is to raise the system
voltage, to say 48V. It will still give the same watt as above (48V x
5A = 240W). Doubling the system voltage reduces the voltage
drop by 1/4th.
System Design
Complexity lowers reliability and increases maintenance cost.
KEEPITSIMPLE
Determining the Performance
• At “EnvironmentFirst” we measure the
performance of a photovoltaic (PV) device to
predict the power the cell will produce. Current-
voltage (I-V) relationships, which measure the
electrical characteristics of PV devices, are
depicted by I-V curves. These I-V curves are
obtained by exposing the cell to a constant level
of light while maintaining a constant cell
temperature, varying the resistance of the load,
and measuring the current that is produced.
Determining the Performance
On an I-V plot, the vertical axis refers to current, and the horizontal axis refers to
voltage. The actual I-V curve typically passes through two significant points:
• The short-circuit current (Isc) is
the current produced when the
positive and negative terminals of
the cell are short-circuited and
the voltage between the
terminals is zero, which
corresponds to a load resistance
of zero.
• The open-circuit voltage (Voc) is
the voltage across the positive
and negative terminals under
open-circuit conditions when the
current is zero, which
corresponds to a load resistance
of infinity.
Determining the Performance
• The cell may be operated
over a range of voltages
and currents. By varying
the load resistance from
zero (a short circuit) to
infinity (an open circuit),
researchers can
determine the highest
efficiency as the point at
which the cell delivers
maximum power.
Determining the Performance
• Maximum power is
generated at only one
place on the power
curve, at about the
"knee" of the curve.
This point represents
the maximum efficiency
of the solar device at
converting sunlight into
electricity.
Grid Operation & Reliability
• This is the factor beyond
control but proper
planning can avoid later
problems. Therefore at
EnvironmentFirst we
collect the data of
nearest Grid at the design
phase itself to insure the
maximum reliability
Registered Office:
405 A, Prakrati Corporate, Y N Road, Indore (IN
452001 • +91-731-6007860
Chandigarh Office:
SCO 48, 2nd Floor, Opposite P.O., Sector-8,
Panchkula (INDIA) 134109 • +91-7696644244
Mumbai Office:
A1-1603, Runwal Garden City, Balkum, Thane (
Mumbai (INDIA) – 400607 •+91-9022437785
Other Representative Locations
Delhi, Chennai, Ahmadabad and Jaipur
Email ID: info@environmentfirst.in

More Related Content

Viewers also liked

Photovoltaic Training - Session 1 - Design
Photovoltaic Training - Session 1 - DesignPhotovoltaic Training - Session 1 - Design
Photovoltaic Training - Session 1 - DesignLeonardo ENERGY
 
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...Harish Sharma
 
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IV
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IVRfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IV
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IVHarish Sharma
 
053013 pv system site assessment (1)
053013 pv system site assessment (1)053013 pv system site assessment (1)
053013 pv system site assessment (1)solpowerpeople
 
Webinar 03 electrical installation of pv system
Webinar 03 electrical installation of pv system Webinar 03 electrical installation of pv system
Webinar 03 electrical installation of pv system solpowerpeople
 

Viewers also liked (9)

Inspecting Photovoltaic (PV) Systems for Code Compliance
Inspecting Photovoltaic (PV) Systems for Code ComplianceInspecting Photovoltaic (PV) Systems for Code Compliance
Inspecting Photovoltaic (PV) Systems for Code Compliance
 
Photovoltaic Training - Session 1 - Design
Photovoltaic Training - Session 1 - DesignPhotovoltaic Training - Session 1 - Design
Photovoltaic Training - Session 1 - Design
 
CUF vs PR
CUF vs PRCUF vs PR
CUF vs PR
 
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...
 
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IV
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IVRfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IV
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IV
 
Designing Solar PV Systems ( Utility Scale)
Designing Solar PV Systems ( Utility Scale)Designing Solar PV Systems ( Utility Scale)
Designing Solar PV Systems ( Utility Scale)
 
053013 pv system site assessment (1)
053013 pv system site assessment (1)053013 pv system site assessment (1)
053013 pv system site assessment (1)
 
Webinar 03 electrical installation of pv system
Webinar 03 electrical installation of pv system Webinar 03 electrical installation of pv system
Webinar 03 electrical installation of pv system
 
Phases of Construction - Solar Project
Phases of Construction - Solar ProjectPhases of Construction - Solar Project
Phases of Construction - Solar Project
 

More from Harish Sharma

MNRE recomendations to States for the Solar Street Lighting Systems
MNRE recomendations to States for the Solar Street Lighting SystemsMNRE recomendations to States for the Solar Street Lighting Systems
MNRE recomendations to States for the Solar Street Lighting SystemsHarish Sharma
 
MNRE Clarification on the capacity with respect to inverter and eligibility o...
MNRE Clarification on the capacity with respect to inverter and eligibility o...MNRE Clarification on the capacity with respect to inverter and eligibility o...
MNRE Clarification on the capacity with respect to inverter and eligibility o...Harish Sharma
 
MNRE Guidelines for off-grid and grid connected Solar DC System
MNRE Guidelines for off-grid and grid connected Solar DC SystemMNRE Guidelines for off-grid and grid connected Solar DC System
MNRE Guidelines for off-grid and grid connected Solar DC SystemHarish Sharma
 
Future of solar Power Projects in India
Future of solar Power Projects in IndiaFuture of solar Power Projects in India
Future of solar Power Projects in IndiaHarish Sharma
 
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-IIIRfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-IIIHarish Sharma
 
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESHRfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESHHarish Sharma
 
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...Harish Sharma
 
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...Harish Sharma
 
PPA draft for the development of solar power project in the state of Karnataka
PPA draft for the development of solar power project in the state of KarnatakaPPA draft for the development of solar power project in the state of Karnataka
PPA draft for the development of solar power project in the state of KarnatakaHarish Sharma
 
RfP for tariff based competitive bidding by KREDL for the installation of 240...
RfP for tariff based competitive bidding by KREDL for the installation of 240...RfP for tariff based competitive bidding by KREDL for the installation of 240...
RfP for tariff based competitive bidding by KREDL for the installation of 240...Harish Sharma
 
RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...
RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...
RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...Harish Sharma
 
RfP for 1200 MW SOLAR POWER PROJECTS IN KARNATAKA
RfP for 1200 MW SOLAR  POWER PROJECTS IN KARNATAKARfP for 1200 MW SOLAR  POWER PROJECTS IN KARNATAKA
RfP for 1200 MW SOLAR POWER PROJECTS IN KARNATAKAHarish Sharma
 
Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.
Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.
Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.Harish Sharma
 
Rfp for tariff based competitive bidding for upto 170 mw solar power plant by...
Rfp for tariff based competitive bidding for upto 170 mw solar power plant by...Rfp for tariff based competitive bidding for upto 170 mw solar power plant by...
Rfp for tariff based competitive bidding for upto 170 mw solar power plant by...Harish Sharma
 
Scheme for Allocation of Solar Power Projects to Land Owning Farmers in Punjab
Scheme for Allocation of Solar Power Projects to Land Owning Farmers in PunjabScheme for Allocation of Solar Power Projects to Land Owning Farmers in Punjab
Scheme for Allocation of Solar Power Projects to Land Owning Farmers in PunjabHarish Sharma
 
Request for Proposal (RfP) For Installation of 2 MW Canal Top Grid connecte...
Request for Proposal (RfP)  For  Installation of 2 MW Canal Top Grid connecte...Request for Proposal (RfP)  For  Installation of 2 MW Canal Top Grid connecte...
Request for Proposal (RfP) For Installation of 2 MW Canal Top Grid connecte...Harish Sharma
 
Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...
Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...
Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...Harish Sharma
 
250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...
250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...
250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...Harish Sharma
 
RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...
RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...
RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...Harish Sharma
 
Draft scheme for allocation of solar power projects for land owning farmers
Draft scheme for allocation of solar power projects for land owning farmersDraft scheme for allocation of solar power projects for land owning farmers
Draft scheme for allocation of solar power projects for land owning farmersHarish Sharma
 

More from Harish Sharma (20)

MNRE recomendations to States for the Solar Street Lighting Systems
MNRE recomendations to States for the Solar Street Lighting SystemsMNRE recomendations to States for the Solar Street Lighting Systems
MNRE recomendations to States for the Solar Street Lighting Systems
 
MNRE Clarification on the capacity with respect to inverter and eligibility o...
MNRE Clarification on the capacity with respect to inverter and eligibility o...MNRE Clarification on the capacity with respect to inverter and eligibility o...
MNRE Clarification on the capacity with respect to inverter and eligibility o...
 
MNRE Guidelines for off-grid and grid connected Solar DC System
MNRE Guidelines for off-grid and grid connected Solar DC SystemMNRE Guidelines for off-grid and grid connected Solar DC System
MNRE Guidelines for off-grid and grid connected Solar DC System
 
Future of solar Power Projects in India
Future of solar Power Projects in IndiaFuture of solar Power Projects in India
Future of solar Power Projects in India
 
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-IIIRfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
 
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESHRfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
 
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...
 
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...
 
PPA draft for the development of solar power project in the state of Karnataka
PPA draft for the development of solar power project in the state of KarnatakaPPA draft for the development of solar power project in the state of Karnataka
PPA draft for the development of solar power project in the state of Karnataka
 
RfP for tariff based competitive bidding by KREDL for the installation of 240...
RfP for tariff based competitive bidding by KREDL for the installation of 240...RfP for tariff based competitive bidding by KREDL for the installation of 240...
RfP for tariff based competitive bidding by KREDL for the installation of 240...
 
RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...
RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...
RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...
 
RfP for 1200 MW SOLAR POWER PROJECTS IN KARNATAKA
RfP for 1200 MW SOLAR  POWER PROJECTS IN KARNATAKARfP for 1200 MW SOLAR  POWER PROJECTS IN KARNATAKA
RfP for 1200 MW SOLAR POWER PROJECTS IN KARNATAKA
 
Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.
Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.
Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.
 
Rfp for tariff based competitive bidding for upto 170 mw solar power plant by...
Rfp for tariff based competitive bidding for upto 170 mw solar power plant by...Rfp for tariff based competitive bidding for upto 170 mw solar power plant by...
Rfp for tariff based competitive bidding for upto 170 mw solar power plant by...
 
Scheme for Allocation of Solar Power Projects to Land Owning Farmers in Punjab
Scheme for Allocation of Solar Power Projects to Land Owning Farmers in PunjabScheme for Allocation of Solar Power Projects to Land Owning Farmers in Punjab
Scheme for Allocation of Solar Power Projects to Land Owning Farmers in Punjab
 
Request for Proposal (RfP) For Installation of 2 MW Canal Top Grid connecte...
Request for Proposal (RfP)  For  Installation of 2 MW Canal Top Grid connecte...Request for Proposal (RfP)  For  Installation of 2 MW Canal Top Grid connecte...
Request for Proposal (RfP) For Installation of 2 MW Canal Top Grid connecte...
 
Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...
Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...
Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...
 
250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...
250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...
250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...
 
RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...
RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...
RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...
 
Draft scheme for allocation of solar power projects for land owning farmers
Draft scheme for allocation of solar power projects for land owning farmersDraft scheme for allocation of solar power projects for land owning farmers
Draft scheme for allocation of solar power projects for land owning farmers
 

Recently uploaded

Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1kcpayne
 
PARK STREET 💋 Call Girl 9827461493 Call Girls in Escort service book now
PARK STREET 💋 Call Girl 9827461493 Call Girls in  Escort service book nowPARK STREET 💋 Call Girl 9827461493 Call Girls in  Escort service book now
PARK STREET 💋 Call Girl 9827461493 Call Girls in Escort service book nowkapoorjyoti4444
 
GUWAHATI 💋 Call Girl 9827461493 Call Girls in Escort service book now
GUWAHATI 💋 Call Girl 9827461493 Call Girls in  Escort service book nowGUWAHATI 💋 Call Girl 9827461493 Call Girls in  Escort service book now
GUWAHATI 💋 Call Girl 9827461493 Call Girls in Escort service book nowkapoorjyoti4444
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon investment
 
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGpr788182
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Timegargpaaro
 
Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...
Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...
Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...pujan9679
 
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGpr788182
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 MonthsIndeedSEO
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...daisycvs
 
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Adnet Communications
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwaitdaisycvs
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfAdmir Softic
 
Cannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 UpdatedCannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 UpdatedCannaBusinessPlans
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPanhandleOilandGas
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizharallensay1
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting
 
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGParadip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGpr788182
 
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...meghakumariji156
 

Recently uploaded (20)

Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
PARK STREET 💋 Call Girl 9827461493 Call Girls in Escort service book now
PARK STREET 💋 Call Girl 9827461493 Call Girls in  Escort service book nowPARK STREET 💋 Call Girl 9827461493 Call Girls in  Escort service book now
PARK STREET 💋 Call Girl 9827461493 Call Girls in Escort service book now
 
GUWAHATI 💋 Call Girl 9827461493 Call Girls in Escort service book now
GUWAHATI 💋 Call Girl 9827461493 Call Girls in  Escort service book nowGUWAHATI 💋 Call Girl 9827461493 Call Girls in  Escort service book now
GUWAHATI 💋 Call Girl 9827461493 Call Girls in Escort service book now
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
 
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
 
Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...
Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...
Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...
 
WheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond InsightsWheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond Insights
 
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
Cannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 UpdatedCannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 Updated
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation Final
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGParadip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
 

Factors affecting performance of a solar pv project

  • 1. FACTORS AFFECTING PERFORMANCE OF A SOLAR PV PROJECTS EnvironmentFirst Energy Services (P) Ltd. “Privileged to Impart Knowledge”
  • 2. There some factors which are beyond the control of Human efforts but certainly there are other factors too which can be insured to have optimum out put of energy. A Good design and operation practices save us from huge losses The Annual amount of energy that will be produced by a PV system depends on various conditions
  • 3. IMPORTANT FACTORS Solar radiation available at the site The orientation (azimuth) and tilt (elevation) of PV arrays The peak power rating of the arrays Energy Conversion Efficiency of PV modules Variation in the efficiency of the Modules with Temperature Power reducing effects of array shading by trees, nearby buildings Accumulation of Dirt/Smog etc The Efficiency of Inverter Cable Thickness System Design Grid Operation & Reliability
  • 4. The annual total quantity of solar radiation available at the site • This can be estimated from meteorological data givng the measured number of kWh (or Gj) per square meter per year incident on the horizontal surface at the nearest meteorological station. In very sunny conditions it can rise to well over 2000 kWh m-2y-1.
  • 5. The orientation (azimuth) and tilt (elevation) of PV arrays • For maximum energy output, the arrays should be oriented close to south and with an elevation roughly equal to latitude of the site – although deviation from these optima does not have a marked effect, and the choice of tilt angle can be varied according to the seasonal output profile desired.
  • 6. The peak power rating of the arrays • This alternatively can be termed as area of the arrays in square meters. Each manufacturer of PV panels provides a data sheet, which will specify the kWP or "rated" amount of power the solar panel will produce.
  • 7. Term "Peak Power" is a figure giving the accuracy • Many manufacturers have a + or - of 10% variation which suggests a greater variability in performance. • EnvironmentFirst perform the onsite analysis of actual power
  • 8. Performance Warranty • The second thing to look at … which is not usually found on the manufacturer's data sheet is the performance warranty. Typically, the manufacturer will guarantee that the kWp output of the panels will not be less than 90% of the rated peak value (under standard testing conditions) for the first 10 years, and not less than 80% for the next 15 years.
  • 9. Performance Guarantees • performance guarantees are important to you (and they certainly are if you are using bank financing to pay for your installation), then having re-insurance gives you a bit of extra comfort on the performance side, and should be something you should ask about.
  • 10. The energy Conversion Efficiency of PV modules: Different modules have different kind of materials, doping type, doping composition, impurities etc. due to which their efficiency varies. Therefore it is recommended to use high efficiency modules for commercial operation so that to have optimum results.
  • 11. The Variation in the efficiency of the Modules with Temperature • Solar cells work best at low temperatures, as determined by their material properties. All cell materials lose efficiency as the operating temperature rises. Much of the light energy shining on cells becomes heat, so it is good to either match the cell material to the operation temperature or continually cool the cell.
  • 12. The Power reducing effects of array shading by trees, nearby buildings
  • 14. The Efficiency of Inverter • The Efficiency of Inverter used to convert the DC power from the PV arrays into AC, and any losses that occur in the wiring between PV system and the final consumer of metering point can amount to about 10% of the electricity generated.
  • 15. Natural Resistance • The natural resistance to electron flow in a cell decreases cell efficiency. These losses predominantly occur in three places: in the bulk of the primary solar material, in the thin top layer typical of many devices, and at the interface between the cell and the electrical contacts leading to an external circuit.
  • 16. Electrical Resistance • Larger electrical contacts can minimize electrical resistance, but covering a cell with large, opaque metallic contacts would block too much incident light. Therefore, a trade off must be made between loss due to resistance and loss due to shading effects. Typically, top-surface contacts are designed as grids, with many thin, conductive fingers spread over the cell's surface. However, it is difficult to produce a grid that maintains good electrical contact with a cell while also resisting deterioration caused by changes in temperature or humidity. Generally, the back-surface contact of a cell is simpler, often being just a layer of metal. Other designs for electrical contacts include placing everything on the cell's back surface, or, as in some thin films, depositing a thin layer of a transparent conducting oxide across the entire cell.
  • 17. Cable Thickness While the size and length of the cables is a matter of system design and installation, for the quality of cables it is utmost important that cables adhere to IEC 60227 / IS 694 or IEC 60502 / IS 1554 (Part I & II). It pays to familiarize what these specification standards say. It is important for a project developer to know that what quality of cables are being installed at site as it could affect the overall generation of the plant.
  • 18. Cable Thickness • 20 meter is the length of cable between the panel and the charge controller. A typical cable with 1.5 sq mm cross section has resistance of about 0.012 ohms per meter of wire length. So a 20 meter long wire will offer resistance of 20 x 0.012 = 0.24 ohms. • If it is a 24V system and a 10 ampere current is flowing through this wire, then from the Ohm’s law (V = IxR), we can calculate voltage drop across this wire: 2.4V. It means the voltage at the charge controller end of the cables will be 2.4V less than the voltage produced by the panels if a 10 Amp current is flowing. This 10% voltage drop is clearly unacceptable.
  • 19. Cable Thickness • What if we use a 6 sq mm cross section cable which has a resistance of 0.003 ohms per meter. The total resistance for 20 meter long cable will now be 0.06 ohms; and the voltage drop, 10×0.06 or 0.6V. It is 2.5% voltage drop for a 24V system which might be acceptable. But what about the increased cost of thicker cable? Likewise, there would be wiring all around and careful attention must be paid to know the impact on overall system efficiency. Thus, cable length and size needs careful attention right at the planning stage. • Another way to reduce resistance loss is to raise the system voltage, to say 48V. It will still give the same watt as above (48V x 5A = 240W). Doubling the system voltage reduces the voltage drop by 1/4th.
  • 20. System Design Complexity lowers reliability and increases maintenance cost. KEEPITSIMPLE
  • 21. Determining the Performance • At “EnvironmentFirst” we measure the performance of a photovoltaic (PV) device to predict the power the cell will produce. Current- voltage (I-V) relationships, which measure the electrical characteristics of PV devices, are depicted by I-V curves. These I-V curves are obtained by exposing the cell to a constant level of light while maintaining a constant cell temperature, varying the resistance of the load, and measuring the current that is produced.
  • 22. Determining the Performance On an I-V plot, the vertical axis refers to current, and the horizontal axis refers to voltage. The actual I-V curve typically passes through two significant points: • The short-circuit current (Isc) is the current produced when the positive and negative terminals of the cell are short-circuited and the voltage between the terminals is zero, which corresponds to a load resistance of zero. • The open-circuit voltage (Voc) is the voltage across the positive and negative terminals under open-circuit conditions when the current is zero, which corresponds to a load resistance of infinity.
  • 23. Determining the Performance • The cell may be operated over a range of voltages and currents. By varying the load resistance from zero (a short circuit) to infinity (an open circuit), researchers can determine the highest efficiency as the point at which the cell delivers maximum power.
  • 24. Determining the Performance • Maximum power is generated at only one place on the power curve, at about the "knee" of the curve. This point represents the maximum efficiency of the solar device at converting sunlight into electricity.
  • 25. Grid Operation & Reliability • This is the factor beyond control but proper planning can avoid later problems. Therefore at EnvironmentFirst we collect the data of nearest Grid at the design phase itself to insure the maximum reliability
  • 26. Registered Office: 405 A, Prakrati Corporate, Y N Road, Indore (IN 452001 • +91-731-6007860 Chandigarh Office: SCO 48, 2nd Floor, Opposite P.O., Sector-8, Panchkula (INDIA) 134109 • +91-7696644244 Mumbai Office: A1-1603, Runwal Garden City, Balkum, Thane ( Mumbai (INDIA) – 400607 •+91-9022437785 Other Representative Locations Delhi, Chennai, Ahmadabad and Jaipur Email ID: info@environmentfirst.in