Originally presented at the Gartner PPM & IT Governance Summit 2013, Ulrich Aigner from Austrian Airlines discusses driving innovation via advanced PPM.
How to Drive Innovation Via Advanced Project Portfolio Management
1. Gartner PPM & IT Governance Summit
How to drive Innovation
via Advanced
Project Portfolio Management
Ulrich.Aigner@austrian.com
2013-06-04, LON
Austrian Airlines
2. Agenda
Brief Company & PMO Profile
Methodology
& Project
Management
Project
Portfolio
Management
• how to do it
• doing
projects right
• what to do
• doing the
right projects
www.austrian.com
Tool
facilitate PM
work, control
(content,
progress,
budget)
• are we doing
well
• delivering the
outcome?
2
3. Austrian Airlines Profile
We fly to 130 destinations worldwide
thereof 41 destinations to Central & Eastern Europe
Our home base is the hub Vienna
We carried 11,5 million passengers
in 2012 in total
Our turnover in 2012 was 2,2 bn EUR
We operate a fleet of 74 aircrafts
• 64 short and medium haul aircrafts
• 10 long haul aircrafts
We’ve been part of Lufthansa Group since 2009
www.austrian.com
3
5. Agenda
Brief Company & PMO Profile
Methodology
& Project
Management
Project
Portfolio
Management
• how to do it
• doing
projects right
• what to do
• doing the
right projects
www.austrian.com
Tool
facilitate PM
work, control
(content,
progress,
budget)
• are we doing
well
• delivering the
outcome?
5
6. A to B without Innovation?
A
B
www.austrian.com
6
7. PMO Goals & Requirements
Drive innovation via project management
Support top management to make the right
decisions regarding projects and project portfolio
Help management to get relevant information
regarding their projects
Help to focus on company not business units
Support the project managers through project
coaches
www.austrian.com
7
8. Hard Facts to Select
Idea derives from Business Unit
PMO checks:
Strategy
Allignment
Earnings
+
NPV
(40%P)
Priority
=
ROI
(20%P)
40%
60%
100%
PMO checks further on parallel projects
PMO filters non relevant projects
PMO provides projects for approval by top mgt
www.austrian.com
8
9. PPM-Monitoring Cycle
Project Controlling
Project Manager + PM-Coach + Controller
Action
Tracking
Clarifications
on Actions
PMO
Coach, PjMgr,
Project Owner/VP
Controlling
Project Portfolio
Prepare
Project Portfolio
Board of Directors
every trimester
with according VP
PMO
www.austrian.com
9
10. Agenda
Brief Company & PMO Profile
Methodology
& Project
Management
Project
Portfolio
Management
• how to do it
• doing
projects right
• what to do
• doing the
right projects
www.austrian.com
Tool
facilitate PM
work, control
(content,
progress,
budget)
• are we doing
well
• delivering the
outcome?
10
11. Be a fool without a tool…
PMO assures:
plan
monitor
select
RIGHT
Projects
control
measure
www.austrian.com
11