SlideShare a Scribd company logo
1 of 11
Download to read offline
Engineering Structures 24 (2002) 1397–1407 
www.elsevier.com/locate/engstruct 
Seismic rehabilitation of beam–column joint using GFRP sheets 
T. El-Amoury, A. Ghobarah ∗ 
Department of Civil Engineering, McMaster University, Hamilton, Ontario, Canada, L8S 4L7 
Received 13 July 2001; received in revised form 24 September 2001; accepted 24 May 2002 
Abstract 
Techniques for upgrading reinforced concrete beam–column joints are proposed. The test specimens represent a typical joint that 
was built in accordance to pre-1970s’ codes. The objective of the rehabilitation is to upgrade the shear strength of these joints and 
reduce the potential for bond-slip of the bottom bars of the beam. Glass fibre-reinforced polymer (GFRP) sheets are wrapped around 
the joint to prevent the joint shear failure. GFRP sheets are attached to the bottom beam face to replace the inadequately anchored 
steel bars. Three beam–column joints are tested; namely, a control specimen and two rehabilitated specimens. The specimens are 
tested under quasi-static load to failure. The control specimen showed combined brittle joint shear and bond failure modes while 
the rehabilitated specimens showed a more ductile failure mode. A simple design methodology for the rehabilitation scheme is 
proposed.  2002 Elsevier Science Ltd. All rights reserved. 
Keywords: Beam-column joints; Seismic rehabilitation; Joint shear strength; Bond-slip; Ductility; GFRP composites; Design 
1. Introduction 
Recent earthquakes in urban areas such as the 1994 
Northridge, the 1995 Hanshin-Awaji (Kobe) and the 
1999 Kocaeli (Turkey) have repeatedly demonstrated the 
vulnerability of existing structures to seismic defor-mation 
demands. These structures were designed and 
detailed for gravity loads and lateral forces that are lower 
than those specified by the current codes. Post-earth-quake 
examination of these structures showed that one 
of the weakest links in the lateral load-resisting system 
is the beam–column joint. Fig. 1 shows the exterior joint 
failure in a reinforced concrete building after the 1999 
Kocaeli earthquake. Exterior beam–column joints are 
more vulnerable than interior joints, which are partially 
confined by beams attached to four sides of the joint 
and contribute to the core confinement. There are some 
differences between the shear response of interior and 
exterior joints when subjected to earthquake ground 
motion due to joint confinement by beams. However, the 
bond-slip mode of failure of exterior and interior joints 
is similar. 
∗ Corresponding author. Tel.: +1-905-525-9140x124913; fax: +1- 
905-529-9688. 
E-mail address: ghobara@mcmaster.ca (A. Ghobarah). 
When built according to earlier code provisions, 
beam–column joints in reinforced concrete moment-resisting 
0141-0296/02/$ - see front matter  2002 Elsevier Science Ltd. All rights reserved. 
PII: S0141-0296(02)00081-0 
frames have inadequate or no transverse shear 
reinforcement, and the bottom reinforcement of the beam 
is anchored only 150 mm from the column face, with 
inadequate development length when the bars are in ten-sion. 
This was done under the assumption that the beam 
positive moment reinforcement at the column face is 
always in compression. Because of these deficiencies, 
the joint may experience shear or bond-slip failure 
modes. These brittle types of failure will significantly 
reduce the overall ductility of the structure. 
The objective of beam–column joint rehabilitation is 
to strengthen the shear and bond-slip resistance in order 
to eliminate these types of brittle failure and ensure 
instead that ductile flexural hinging in the beam will take 
place. Recent studies on the effect of shear and bond-slip 
rehabilitation on the behaviour of reinforced con-crete 
frame have shown significant improvements in the 
overall frame ductility [1,2]. It is important to develop 
effective and economic rehabilitation techniques for 
upgrading the vulnerable beam–column joints in exist-ing 
structures. 
Rehabilitation of existing structures has received 
much attention during the past two decades. The objec-tive 
is to upgrade the joint shear strength before it is 
subjected to an earthquake. An interior beam-column
1398 T. El-Amoury, A. Ghobarah / Engineering Structures 24 (2002) 1397–1407 
Fig. 1. Exterior joint failure during the 1999 Kocaeli (Turkey) earthquake. 
joint was rehabilitated and tested [3]. Steel plates were 
anchored to the beam bottom face at each side of the 
joint and connected together using threaded steel rods 
driven through the column. The idea is to replace the 
inadequately anchored steel bars with equivalent steel 
plates. Steel-plate jacketing was used to enhance the 
joint shear strength. Test results showed that joint jacket-ing 
was ineffective in improving the joint shear strength 
due to slippage of the steel plates. The specimen reached 
a drift of 4% without significant deterioration in strength. 
Flat steel plates were used to confine the joint in an 
attempt to prevent the spalling of concrete and to main-tain 
the concrete integrity [4,5]. Steel channels were 
attached to the beam bottom face to prevent slip of the 
bars. This scheme was found to be efficient in preventing 
the bars’ slippage, increasing the joint shear strength and 
reducing the rate of strength deterioration. 
Ghobarah et al. [6] used corrugated steel-sheet jacket-ing 
for joint confinement, leaving a gap between the con-crete 
and the jacket to be filled with grout. The shear 
strength of the rehabilitated joints was increased and the 
failure mode became flexural hinging in the beam. 
Carbon fibre-reinforced polymer (CFRP) materials 
were used to strengthen an external beam–column joint 
in shear [7]. The retrofitted specimen was wrapped with 
multiple layers of CFRP sheets. The joint shear capacity 
was increased by 25% and the specimens reached 5% 
drift. 
Ghobarah and Said [8] investigated the rehabilitation 
of beam–column joints using glass fibre-reinforced poly-mers 
(GFRP). One joint was tested as control specimen 
and two were tested after rehabilitation. The proposed 
rehabilitation scheme was to wrap the joint with U-shaped 
GFRP sheets. The ends of the composite sheets 
were tied together using two steel plates and four steel 
tie rods through the joint. The behaviour of the rehabili-tated 
specimen was significantly improved. The brittle 
shear failure of the beam–column joint was eliminated 
and instead ductile flexural hinging of the beam 
occurred. The joints tested in this research programme 
were designed with deficient shear strength but with 
adequate positive reinforcement anchoring in the joint. 
In other words, bond-slip failure was not included in the 
rehabilitation scheme. 
Limited testing was conducted on beam–column joints 
rehabilitated using composite rods to strengthen the col-umn 
flexural strength and fibre wrap to strengthen the 
joint shear [9]. Joint rehabilitation using fibre-reinforced 
polymers (FRP) has the advantages of simplicity of 
application and less need for skilled labour. The econ-omic 
advantages of FRP rehabilitation were evaluated 
by Ehlen and Marshall [10]. 
So far, most of the research conducted on beam– 
column joints has mainly been concerned with upgrading 
joint shear strength using steel plates, sheets and sections 
and FRP. However, the rehabilitation of bond-slip in 
reinforced concrete beam–column joints has not received 
much attention. 
The objective of the present research programme is to 
develop new rehabilitation systems for strengthening the 
shear resistance of beam–column joints and for upgrad-ing 
resistance to bond-slip of the positive reinforcement 
anchored in the joint. 
2. Experimental programme 
2.1. Test specimens 
Three reinforced concrete beam–column joints were 
tested: T0, TR1 and TR2. The specimens represent an 
exterior joint in a typical concrete frame that has been 
built before 1970 [11]. Exterior joints are selected 
because they are more vulnerable and are normally
T. El-Amoury, A. Ghobarah / Engineering Structures 24 (2002) 1397–1407 1399 
expected to fail first. If the rehabilitation system is suc-cessful, 
it can be easily adapted to interior joints as well. 
The beam–column joints are designed assuming that 
points of contra-flexure occur at the mid-height of col-umns 
and the mid-span of beams. The top longitudinal 
reinforcements in the beam are bent down into the col-umn, 
whereas the bottom reinforcement was anchored 
150 mm from the column face. No transverse reinforce-ment 
was installed in the joint region. The beam was 
reinforced using 4#20 as top and bottom longitudinal 
bars and #10 as transverse steel. The column was 
reinforced with 6#20 plus 2#15 as longitudinal bars and 
#10 ties spaced 200 mm. The dimensions and reinforce-ment 
details of all of the specimens are identical, as 
shown in Fig. 2. 
After testing the control specimen, T0, the cracked 
concrete was removed from the joint region and the 
adjacent parts of the columns and beam. The specimen 
was laid inside the wooden forms again and new con-crete 
was poured to replace the removed materials. The 
specimen was then rehabilitated and tested again as 
specimen TR1. However, specimen T2 is an original 
specimen that was retrofitted then tested. The concrete 
compressive strength on the test day was 30.6, 43.5 and 
39.5 MPa for the control specimen T0, the repair con-crete 
of specimen TR1 and for specimen TR2, respect-ively. 
The yield strength of the steel bars #10, #15 and 
#20 was 450, 408 and 425 MPa, respectively. 
Bi-directional GFRP material were used in the joint 
rehabilitation. The bi-directional material is woven in the 
±45° directions. The properties of the fibre sheets used 
in the current testing programme, as supplied by the 
manufacturer, are given in Table 1. 
2.2. Test set-up and instrumentation 
The specimens were tested in the column vertical pos-ition, 
hinged at the top and bottom column ends and sub-jected 
to a cyclic load applied at the beam tip as shown 
in Fig. 3. The beam-tip displacement and the column 
lateral displacement were measured using poten-tiometers. 
Two diagonal linear voltage differential trans-formers 
(LVDTs) were attached to the joint to measure 
the joint shear deformation. The displacement of the col-umn 
above and below the joint was measured using two 
additional LVDTs attached to the top and bottom of the 
beam, as shown in Fig. 3. Twelve strain gauges were 
installed on the reinforcement steel bars to measure the 
strains at different loading levels, as shown in Fig. 4. 
For the retrofitted specimens, 10 strain gauges were 
installed on the fibre sheets, two strain gauges were 
installed on the tie rods driven through the joint. 
A reversed quasi-static cyclic load was applied at the 
beam tip using a hydraulic actuator of ±250 mm stroke. 
The applied load was measured using a load cell. The 
loading routine consisted of two phases as shown in Fig. 
5. The first phase was load control, where the specimen 
was subjected to an increasing load up to the first yield 
of the steel bars. This phase of loading was used to deter-mine 
the displacement of the beam tip when first yield 
Fig. 2. Specimen dimensions and reinforcement details.
1400 T. El-Amoury, A. Ghobarah / Engineering Structures 24 (2002) 1397–1407 
Table 1 
Properties of the composite materials 
GFRP Tensile strength in 0° direction (MPa) Elongation at break (%) Tensile modulus (GPa) Thickness (mm) 
Bi-directional (±45°) 279 1.5 19 0.864 
Unidirectional 1700 2 71 0.353 
Fig. 3. Test set-up. 
of the steel occurs, y. After the beam steel bars reached 
the yield strain, the second loading phase was initiated 
which was displacement control. Multiples of the dis-placement 
corresponding to the bars’ first yield, y, were 
used to load the specimen. A constant axial load of 600 
kN was applied to the column, using another hydraulic 
jack provided with a load cell to measure the applied 
load. This load represents the gravity load that acts on 
the column, and was approximately equal to 0.2Agfc, 
where Ag is the gross cross-sectional area and fc is the 
compressive strength of concrete. 
2.3. Rehabilitation schemes 
The proposed rehabilitation schemes consist of two 
systems. The first system is for upgrading the shear 
strength of the joint. The joint was wrapped with two 
U-shaped composite layers. The first layer was bi-direc-tional 
sheet and the second was unidirectional sheet. The 
ends of the sheets were anchored using steel plates and 
tie rods driven through the joint. This system was similar 
to previously tested systems [8] but differed in material 
design and details. The second system was for upgrading 
the steel bars’ bond-slip. This system is new and was 
Fig. 4. Location of strain gauges on the reinforcement steel bars. 
Fig. 5. Loading routine. 
being tested for the first time. In specimen TR1, four 
unidirectional glass fibre sheets were applied to the beam 
bottom face for a horizontal distance of 1000 mm and 
extended along the inner column face vertically for a 
distance of 500 mm, as shown in Fig. 6a. In specimen
T. El-Amoury, A. Ghobarah / Engineering Structures 24 (2002) 1397–1407 1401 
Fig. 6. Retrofitting schemes: (a) specimen TR1, (b) specimen TR2. 
TR2, eight unidirectional glass fibre sheets were applied 
to the bottom beam face and provided with two U-shaped 
3 mm thick steel plates to enhance the bond 
between the GFRP and the concrete, as shown in Fig. 
6b. Using the described configuration, the resultant of 
the tensile forces developed in the composite sheets may 
cause debonding of the sheets from the concrete surface 
at the beam–column corner. To overcome this potential 
problem, a steel angle was installed at the lower beam– 
column corner as shown in Fig. 6a. To install the angle 
in place, the beam bottom bars were exposed for a dis-tance 
of 150 mm from the column face and the heads 
of A375 steel bolts of diameter 20 mm were welded to 
the beam bars in two rows. For specimen TR1, four 28 
mm diameter and 170 mm depth holes were drilled in 
the column in two rows. The steel angle was fixed in 
place using washers and nuts to the bolts welded to the 
beam reinforcement and using Hilti HVA 5/8×6-5/8 
adhesive anchors to the column. For specimen TR2, four 
25 mm diameter external threaded rods with 
500 mm × 200 mm × 25 mm steel plate were used to tie 
the angle to the column as shown in Fig. 6b. 
3. Experimental results 
In this section, the behaviour of the control and 
rehabilitated specimens is described and the effective-ness 
of the rehabilitation schemes is evaluated. 
3.1. Specimen T0 
In the first loading cycle, the specimen was loaded up 
to 3.0 kN up and down to test the instrumentations. The 
first beam crack was observed during the second cycle 
at the column face at load of 7.7 kN up. In the fourth 
cycle, a load of 30.0 kN was applied up and down to the 
specimen; new flexural and flexural–shear cracks formed 
along the beam length. In the sixth cycle, vertical cracks 
formed in the joint region at beam-tip load of 35.5 kN 
due to bond-slip of the beam bottom bars. During the 
eighth cycle, diagonal shear cracks developed in the joint 
region, and the specimen reached a load of 60.0 kN at 
a beam-tip displacement of 20 mm. Repeating the same 
cycle, the beam reached the same displacement but at 
lower load level and the beam bars started to slip out of 
the joint with an associated reduction in the developed 
strain in the bars. The beam-tip displacement of 20 mm 
was used as a reference value for the displacement-con-trolled 
loading phase. In the following cycles the beam 
tip was displaced up and down by multiples of this value. 
The reason for selecting this arbitrary displacement as 
reference displacement in the test is that yield of the 
reinforcement steel is not expected to occur. When the 
specimen was pushed up, the bond-slip cracks opened 
and the lateral load-carrying capacity deteriorated sig-nificantly; 
however, when it was pulled down, the diag-onal 
shear cracks opened. This caused disintegration of 
the concrete, deterioration of the bond condition of the 
beam top bars and degradation of the lateral load-carry-ing 
capacity. The specimen reached a maximum load of
1402 T. El-Amoury, A. Ghobarah / Engineering Structures 24 (2002) 1397–1407 
60.0 kN up and 86.0 kN down, which is much less than 
the expected theoretical load at first steel yield of 
approximately 110.0 kN. The test was halted at displace-ment 
of 50 mm as the load-carrying capacity was greatly 
reduced. In effect, when pushing up on the beam, bond-slip 
failure of the beam bottom reinforcement occurred 
and when pulling down, joint shear failure occurred. The 
final failure pattern is shown in Fig. 7. A reduction in 
the column axial load up to 10% of the original load 
was recorded in the last cycles due to joint shear failure. 
Examining the hysteretic behaviour of the specimen 
showed considerable pinching, severe strength deterio-ration 
and stiffness degradation, as shown in Fig. 8. 
Bond slip was found to be a more brittle type of failure 
when compared with shear failure, as it occurred earlier 
and is associated with a higher rate of strength deterio-ration. 
In the figure, beam-tip displacement of 20 mm 
corresponds to 1.0 % storey drift. 
3.2. Specimen TR1 
Specimen TR1 was subjected to the same loading 
sequence as specimen T0. The first crack occurred dur- 
Fig. 7. Failure pattern of specimen T0. 
Fig. 8. Beam-tip load–displacement of specimen T0. 
ing the second cycle at load of 14.0 kN. The specimen 
was loaded at increments of 20.0 kN until reaching the 
first yield of the steel reinforcement. Before yielding, the 
behaviour of the specimen was almost elastic with no 
residual deformation observed. Examining the strain 
values showed that the fibre sheets attached to the beam 
face were carrying most of the developed tensile forces, 
indicating that the glass fibre fabric was working effec-tively. 
During the sixth cycle, vertical cracks appeared 
in the lower column under the joint region, due to the 
tensile forces developed in the adhesive anchors. These 
cracks caused a sudden drop in the beam-tip load from 
58.0 kN to 53.0 kN. During the test, FRP debonding was 
regularly checked by fingertip tapping on the composite 
sheets. During the eighth cycle, the wrapped laminates 
around the joint started to debond between the free edges 
and the steel plates. In the 10th cycle, the beam top steel 
bars reached the yield strain at beam displacement of 25 
mm and beam-tip load of 110.0 kN. This displacement 
was designated the yield displacement y, and the dis-placement- 
controlled loading phase was initiated. Dur-ing 
the 12th cycle, the specimen was displaced to 37.5 
mm up and down (1.5y). The fibre sheet attached to 
the bottom beam face reached a strain of 0.0045 when 
the specimen was pushed up. As the beam tip was pulled 
down, the fibre sheets buckled and started to debond 
from the beam face. In the following cycles, as the ten-sion 
in the fibres is lost due to debonding, the existing 
steel bars started to carry the developed tension force. 
The tension force in the bars was transferred to the col-umn 
by bonding, the welded bolts and the steel angle. 
The specimen showed increased load-carrying capacity 
as it was pulled down. During the 16th cycle, at displace-ment 
of 75 mm up and down (3.0y), the weld around 
the bolt heads fractured, the beam bars slipped out of 
the joint and sudden a drop in the beam load was 
observed. During the next cycle, the specimen experi-enced 
a loss of load-carrying capacity when pushed up, 
whereas it continued to carry the same load level when 
it was pulled down, indicating no shear failure in the 
joint region. The final failure condition is shown in Fig.
T. El-Amoury, A. Ghobarah / Engineering Structures 24 (2002) 1397–1407 1403 
Fig. 9. Failure pattern of specimen TR1. 
9. The composite sheets were completely debonded from 
the beam and column faces. Examining the hysteretic 
loops of the specimen showed that the behaviour 
remained almost elastic up to the first steel yield, as 
shown in Fig. 10. Severe pinching and stiffness degra-dation 
occurred in the last two cycles following the frac-ture 
of the weld. 
3.3. Specimen TR2 
Specimen TR2 was subjected to the same loading rou-tine 
as the previous specimens. The first crack occurred 
during the second cycle at load of 20.0 kN while it was 
being pulled down. During the following cycle, the first 
yield of the beam top bars occurred at beam displace-ment 
of 26.5 mm and beam-tip load of 114.5 kN. This 
displacement was designated the yield displacement y, 
and the displacement-controlled loading phase was 
initiated. Vertical cracks appeared in the lower column 
under the joint region at a beam-tip load of 75 kN. Dur-ing 
the sixth cycle, the wrapped laminates around the 
joint started to debond at the free edges. In the ninth 
cycle, the fibre attached to the column face started to 
Fig. 10. Beam-tip load–displacement of specimen TR1. 
delaminate behind the steel angle. The forces developed 
in the composite sheets were transferred to the column 
by the steel angle and the tie rods. This caused a 
reduction in the beam-tip load when the specimen was 
being pushed up accompanied with large deformations 
to the angle. In the 11th cycle, while the specimen was 
being pulled down, it reached its ultimate load of 131.0 
kN and displacement of 79.5 mm (3y). This high load 
caused new cracks in the column part above the joint 
and initiated joint shear failure. Degradation of the load-carrying 
capacity was observed in the following cycles. 
During the 16th cycle, the specimen displaced to 132.5 
mm (5y) was still able to carry load of 74.0 kN up and 
89.0 kN down, which are more than half of the yield 
load. 
The two U-shaped steel plates proved to be effective 
in preventing fibre debonding from the concrete face to 
the end of the test. The strain in the GFRP reached 
approximately 0.005 in both tension and compression. 
In the 17th cycle, the specimen was displaced to 159 
mm (6y); however, the load-carrying capacity deterio-rated 
to 52.0 kN. The test was halted after the 19th cycle 
where the specimen reached displacement of 185 mm 
(7y) and the load-carrying capacity deteriorated to 32.0 
kN. The specimen showed shear cracking in the joint 
region under the GFRP, as shown in Fig. 11. The load– 
displacement cycles are shown in Fig. 12. 
Although the final failure mode of specimen TR2 was 
due to joint shear high load-carrying capacity, the overall 
joint performance is much more ductile compared with 
the control specimen T0. During the test, it was con-firmed 
that the large plastic deformation of the steel 
angle provided significant ductility to the joint behav-iour. 
4. Discussion 
In this section, the hysteretic behaviour, energy dissi-pation, 
stiffness degradation, joint strength and ductility 
levels of the tested specimens are discussed. 
The envelopes of the hysteretic loops of the tested 
specimens are shown in Fig. 13. Specimen TR1 showed 
almost 100% increase in the load-carrying capacity com-pared 
with specimen T0. Specimen TR2 reached a higher 
load level and maintained the load-carrying capacity at 
displacement levels much higher than those of the other 
two specimens. The pinching effect is severe in speci-men 
T0 as compared with the rehabilitated specimens. 
The top steel in the beam of specimen T0 did not reach 
its yield stress. On the other hand, in the rehabilitated 
specimens, the yield of the top beam reinforcement was 
exceeded. This indicates the effectiveness of the shear 
rehabilitation scheme in strengthening the joint shear 
capacity and maintaining the joint concrete integrity 
by confinement.
1404 T. El-Amoury, A. Ghobarah / Engineering Structures 24 (2002) 1397–1407 
Fig. 11. Failure pattern of specimen TR2. 
Fig. 12. Beam-tip load–displacement of specimen TR2. 
The area enclosed by a hysteretic loop at a given cycle 
represents the energy dissipated by the specimen during 
this cycle. The capability of a structure to dissipate 
energy has a strong influence on its response to an earth-quake 
loading. The total energy dissipated by a structure 
consists of (1) energy dissipated by the steel reinforce-ment; 
(2) energy dissipated by friction along existing 
cracks in concrete; and (3) energy dissipated during the 
formation of new cracks. Fig. 14 shows the cumulative 
energy dissipated by the three beam–column joints. It is 
observed that the rehabilitated specimen TR1 had the 
ability to dissipate three times the energy dissipated by 
Fig. 13. Hysteretic loop envelopes of the test specimens. 
Fig. 14. Cumulative energy dissipated by the tested specimens. 
the specimen T0, while specimen TR2 dissipated almost 
six times the energy dissipated by the control speci-men 
T0. 
The beam–column joint stiffness was approximated as 
the slope of the peak-to-peak line in each loop. Test 
results indicated that stiffness degradation was due to 
various factors such as non-linear deformations, flexural 
and shear cracking, distortion of the joint panel, slippage 
of reinforcement, and loss of cover. The control speci-men 
T0 showed high initial stiffness compared with 
specimen TR1 because of the pre-cracking of the 
rehabilitated specimen TR1 before repair. Specimen 
TR2, which was tested for the first time after rehabili-tation, 
showed also high initial stiffness. Comparing the 
peak-to-peak stiffness of the tested joints shows that the 
stiffness degradation of the control joint T0 was higher 
than that of the rehabilitated specimens TR1 and TR2, 
as shown in Fig. 15. 
While the control specimen did not reach the steel 
yield due to bond-slip and shear failure, the rehabilitated 
specimens TR1 and TR2 reached higher ductility levels 
than the control specimen T0. 
5. Design of GFRP sheets 
The design approach is based on providing fibre 
reinforcement to replace the missing joint shear
T. El-Amoury, A. Ghobarah / Engineering Structures 24 (2002) 1397–1407 1405 
Fig. 15. Degradation of stiffness with storey drift. 
reinforcement or the inadequately anchored steel 
reinforcement. 
5.1. Flexural strengthening sheets 
The fibre is used to replace the inadequately anchored 
bottom steel bars of the beam. In the design process, 
fibre sheets are provided to develop the same design 
flexural moment of the reinforced concrete beam section. 
This moment limit is imposed on the flexural strengthen-ing 
system to avoid creating a beam that is stronger than 
the column. 
5.1.1. The beam flexural moment 
The moment capacity of the beam section is determ-ined 
according to the provisions of CSA A23.3-94 [12]. 
To account for overstrength in steel, the tensile force in 
the steel is calculated using the actual yield strength, 
which equals the nominal yield strength increased by 
25%, 
Ts  1.25fyAs, (1) 
where 
Ts is the tension force in the bottom steel bars 
As is the area of the tension steel bars. 
fy is the nominal yield strength of the steel 
The concrete compression block depth “a” can be calcu-lated 
using the force equilibrium expression: 
Ts  Cc  Cs  a1fcab  AsEses, (2) 
where 
Cc is the concrete compression force 
Cs is the steel compression force 
a1 is the equivalent compression block reduction factor 
[12], a1  0.85–0.0015 for fc 0.67 
fc is the concrete compression strength 
b is the beam width 
As is the area of the compression steel 
Es is the modulus of elasticity of the steel 
es is the strain in the compression steel. 
The resisting positive moment of the section at the face 
of the column, Mr, is: 
Mr  Cc(da/2)  Cs(dd), (3) 
where 
d is the effective beam depth 
d is the concrete cover above the top steel. 
In the particular case of joint T0, Eq. (1) gives the ten-sion 
force in the steel bars to be Ts  600 kN, and Eq. 
(2) gives the depth of the concrete block to be a  
61.0 mm. The resisting moment capacity given by Eq. 
(3) is Mr  187.32 kN m. 
5.1.2. Required number of GFRP layers 
The design objective is to achieve the same flexural 
capacity of the adequately anchored section. In this 
design procedure, three assumptions are made: 
 strain compatibility between the different materials 
is assumed; 
 the ultimate concrete strain in compression is taken 
as 0.0035; and 
 the contribution of the existing steel bars is ignored. 
The tensile force developed in the fibre sheets can be 
estimated as 
Tfrp  efrpEfrpAfrp, (4) 
where efrp is the strain developed in the GFRP sheets, 
which should be less than the ultimate strain, and could 
be derived from the geometry, as shown in Fig. 16; Efrp 
is the modulus of elasticity of the GFRP and Afrp is the 
area of the GFRP sheets. 
The depth of the concrete compression block “a” can 
be calculated from the moment equilibrium equation: 
Mr  a1fcab(ta/2)  AsesEs(td). (5) 
The strain in the fibre can be written as: 
efrp  ec 
tc 
c 
, (6) 
where ec is the compression strain in concrete and c is 
the location of the neutral axis. From the equilibrium 
of forces: 
Tfrp  Cc  Cs (7) 
Tfrp  efrpEfrpnfrptfrpb. (8) 
Using the same resisting moment capacity of joint T0, 
Mr  187.32 kN m, Eq. (5) gives the depth of the con-crete 
block to be a  55.95 mm. Eqs. (6) to (8) give the
1406 T. El-Amoury, A. Ghobarah / Engineering Structures 24 (2002) 1397–1407 
Fig. 16. Calculation of the required number of GFRP sheets. 
strain in the fibre efrp  0.0189 with the number of 
GFRP layers, nfrp, as 4.35. 
In specimen TR1, the number of GFRP layers, nfrp, is 
taken as 4, while in specimen TR2 the nfrp is taken as 8. 
5.2. Joint shear strengthening 
The developed joint shear force is calculated as 
[12,13]: 
Vj  1.25AsfyVcol, (9) 
where 
Vj is the developed joint shear force 
Vcol is the shear force in the column. 
The total shear resistance consists of the concrete 
resistance, the resistance of the ties and the resistance 
provided by the composite sheets: 
Vj  Vc  Vs  Vfrp. (10) 
The concrete shear resistance can be estimated using 
ACI 352 [14] provision to be: 
Vc  0.3fc(1  0.3fcol)bjdj, (11) 
where 
fcol is the axial stress applied to the column 
bj is the joint width 
dj is the joint effective width. 
As there are no ties provided in the joint, Vs is taken to 
be zero. 
The fibre contribution, Vfrp, is estimated to be: 
Vfrp  AfrpefrpEfrp. (12) 
For the rehabilitated specimen TR2, the column shear 
force is obtained by dividing the nominal moment 
capacity by the shear arm, which is equal to 2850 mm: 
Vcol  187.32/ 2.85  65.73 kN. 
Eq. (9) gives the total joint shear as Vj  534.27 kN. Eq. 
(11) gives Vc  276.06 kN. From Eq. (10), the required 
shear resistance contributed by the fibre is Vfrp  
258.21 kN. 
The shear strength provided using one bi-directional 
and one unidirectional layers can be estimated from Eq. 
(12), by assuming that both sheets will reach the same 
strain level of 1.0%, which is equal to 2/3 of the smallest 
maximum strains of the two composite sheet types. This 
gives the provided shear resistance by the FRP, Vr  
290.35 kN, which is greater than the required fibre 
resistance Vfrp. 
6. Conclusions 
Based on the experimental results, the following con-clusions 
can be made. 
 The control specimen with no shear reinforcement in 
the joint and with inadequate anchorage for the beam 
bottom steel bars showed a brittle joint shear failure 
accompanied by slippage of the beam bottom bars. 
 The bond conditions of the beam top bars were affec-ted 
by the disintegration of the concrete in the control 
joint, leading to a significant reduction in the load-carrying 
capacity and the ductility of the joint. Using 
GFRP jacketing maintained the concrete integrity by 
confinement and significantly improved the ductility 
and the load-carrying capacity of the rehabilitated 
joint. 
 Comparison between the control and the rehabilitated 
specimens emphasized the effectiveness of the 
rehabilitation schemes. The joint rehabilitation elim-inated 
the brittle joint shear failure, improved the 
bond conditions of the beam top reinforcement, 
delayed the slippage of the bottom steel bars, 
increased the energy dissipated by the specimen and 
reduced the stiffness degradation of the joint. 
 In specimen TR1, the fibre debonded from the con-crete 
surface when it reached a strain of 0.004, which 
is approximately 25% of the proposed strain by the 
design methodology. However, specimen TR1
T. El-Amoury, A. Ghobarah / Engineering Structures 24 (2002) 1397–1407 1407 
reached the proposed strength due to the contribution 
of the existing steel bars, which was ignored in the 
design. 
 In specimen TR2, use of U-shaped steel plates to 
restrain the GFRP eliminated debonding of the GFRP 
from the concrete surface. The FRP reached a strain 
that is approximately 1/3 of its ultimate strain in both 
tension and compression without failure. The rehabili-tated 
joint achieved 52% higher load-carrying 
capacity and dissipated six times the energy dissipated 
by the control specimen. 
Acknowledgements 
The authors are grateful to Fyfe Co. and R.J. Watson, 
Inc. for providing the GFRP material used in the tests, 
and to ISIS Canada for supporting the research pro-gramme. 
References 
[1] Ghobarah A, Biddah A. Dynamic analysis of reinforced concrete 
frames including joint shear deformation. Eng. Struct. 
1999;21:971–87. 
[2] Ghobarah A, Youssef, M. Response of an existing RC building 
including concrete crushing and bond slip effects. In: Proceedings 
of 8th Canadian Conference on Earthquake Engineering, Canad-ian 
Association for Earthquake Engineering, Vancouver, BC, 
1999. p. 427–32. 
[3] Estrada JI. Use of steel elements to strengthen a reinforced con-crete 
building. M.Sc. thesis, University of Texas at Austin, 1990. 
[4] Beres A, White RN, Gergely P. Seismic performance of interior 
and exterior beam-to-column reinforced concrete frame buildings. 
Detailed experimental results. In: Report No. 92-06. Ithaca, NY: 
Department of Structural Engineering, Cornell University, 1992. 
[5] Beres A, El-Borgi S, White RN, Gergely P. Experimental results 
of repaired and retrofitted beam–column joint tests in lightly 
reinforced concrete frame buildings. In: Report No, NCEER-92- 
25. Buffalo (NY): National Center for Earthquake Engineering 
Research, State University of New York at Buffalo, 1992. 
[6] Ghobarah A, Aziz TS, Biddah A. Seismic rehabilitation of 
reinforced concrete beam–column connections. Earthquake Spec-tra 
1996;12(4):761–80. 
[7] Pantelides C, Clyde C, Dreaveley L. Rehabilitation of R/C build-ing 
joints with FRP composites. Proceedings of the 12th World 
Conference on Earthquake Engineering, New Zealand Society for 
Earthquake Engineering, Silverstream, Upper Hutt, New Zealand, 
2000. Paper no. 2306. 
[8] Ghobarah A, Said A. Seismic rehabilitation of beam–column 
joints using FRP laminates. J. Earthquake Eng. 2001;5(1):113– 
29. 
[9] Prota A, Nanni A, Manfredi G, Cosenza E. Seismic upgrade of 
beam–column joints with FRP reinforcement. In: FRPRCS5. Pro-ceedings 
of 5th Non-Metallic Reinforcement for Concrete Struc-tures, 
Thomas Telford Ltd, UK. 2001. paper # 339. 
[10] Ehlen MA, Marshall HE. The economics of new-technology 
materials: a case study of FRP bridge decking. In: National Insti-tute 
of Standards and Technology Report NISTIR 5864. Gaithers-burg 
(MD): Office of Applied Economics, Building and Fire 
Research Laboratory, 1996. 
[11] ACI-318 Building code requirements for reinforced concrete. 
Detroit (MI): American Concrete Institute, 1963. 
[12] CSA A23.3 Design of concrete structures. Rexdale, Ontario: Can-adian 
Standards Association, 1994. 
[13] Park R, Paulay T. Reinforced concrete structures. New York: 
John Wiley  Sons, 1975. 
[14] ACI 352 Recommendation for design of beam–column joints in 
monolithic reinforced concrete structures. Detroit (MI): American 
Concrete Institute, 1976.

More Related Content

What's hot

MODELS FOR CONFINED CONCRETE COLUMNS WITH FIBER COMPOSITES
MODELS FOR CONFINED CONCRETE COLUMNS WITH FIBER COMPOSITESMODELS FOR CONFINED CONCRETE COLUMNS WITH FIBER COMPOSITES
MODELS FOR CONFINED CONCRETE COLUMNS WITH FIBER COMPOSITESIAEME Publication
 
Study on Steel Beam Column Joint using Different Connections – State of Art
Study on Steel Beam Column Joint using Different Connections – State of ArtStudy on Steel Beam Column Joint using Different Connections – State of Art
Study on Steel Beam Column Joint using Different Connections – State of ArtIRJET Journal
 
Effect of width and layers of GFRP strips on deflection of Reinforced Concret...
Effect of width and layers of GFRP strips on deflection of Reinforced Concret...Effect of width and layers of GFRP strips on deflection of Reinforced Concret...
Effect of width and layers of GFRP strips on deflection of Reinforced Concret...inventionjournals
 
Kinerja RBS Balok Kastella akibat beban siklik
Kinerja RBS Balok Kastella akibat beban siklikKinerja RBS Balok Kastella akibat beban siklik
Kinerja RBS Balok Kastella akibat beban siklikNini Aswad
 
IRJET- Experimental Investigation on Seismic Retrofitting of RCC Structures
IRJET- Experimental Investigation on Seismic Retrofitting of RCC StructuresIRJET- Experimental Investigation on Seismic Retrofitting of RCC Structures
IRJET- Experimental Investigation on Seismic Retrofitting of RCC StructuresIRJET Journal
 
Capacity of strengthened Reinforced concrete columns
Capacity of strengthened Reinforced concrete columnsCapacity of strengthened Reinforced concrete columns
Capacity of strengthened Reinforced concrete columnsKhaled Mahmoud
 
retrofitting
retrofittingretrofitting
retrofittingSRUTHI K
 
IRJETI Comparison of RC Beam-Column Joint with GFRC Beam-Column Joint using S...
IRJETI Comparison of RC Beam-Column Joint with GFRC Beam-Column Joint using S...IRJETI Comparison of RC Beam-Column Joint with GFRC Beam-Column Joint using S...
IRJETI Comparison of RC Beam-Column Joint with GFRC Beam-Column Joint using S...IRJET Journal
 
IRJET- Fea & Experimental Analysis of Three Point Bending Test of Thin Walled...
IRJET- Fea & Experimental Analysis of Three Point Bending Test of Thin Walled...IRJET- Fea & Experimental Analysis of Three Point Bending Test of Thin Walled...
IRJET- Fea & Experimental Analysis of Three Point Bending Test of Thin Walled...IRJET Journal
 
IRJET - Experimental Study on Performance of Buckling Restrained Bracings
IRJET - Experimental Study on Performance of Buckling Restrained BracingsIRJET - Experimental Study on Performance of Buckling Restrained Bracings
IRJET - Experimental Study on Performance of Buckling Restrained BracingsIRJET Journal
 
Analysis of Concrete Filled Double Skin Steel Tube (CFDST) column with FRP wr...
Analysis of Concrete Filled Double Skin Steel Tube (CFDST) column with FRP wr...Analysis of Concrete Filled Double Skin Steel Tube (CFDST) column with FRP wr...
Analysis of Concrete Filled Double Skin Steel Tube (CFDST) column with FRP wr...IRJET Journal
 
IRJET- Behaviour of Castellated Beam with Coupled Stiffener
IRJET-  	  Behaviour of Castellated Beam with Coupled StiffenerIRJET-  	  Behaviour of Castellated Beam with Coupled Stiffener
IRJET- Behaviour of Castellated Beam with Coupled StiffenerIRJET Journal
 
IRJET-Cyclic Response of Perforated Beam in Steel Column Joints
IRJET-Cyclic Response of Perforated Beam in Steel Column JointsIRJET-Cyclic Response of Perforated Beam in Steel Column Joints
IRJET-Cyclic Response of Perforated Beam in Steel Column JointsIRJET Journal
 
Strengthening of reinforced concrete beam using steel fiber at different dept...
Strengthening of reinforced concrete beam using steel fiber at different dept...Strengthening of reinforced concrete beam using steel fiber at different dept...
Strengthening of reinforced concrete beam using steel fiber at different dept...eSAT Journals
 

What's hot (19)

MODELS FOR CONFINED CONCRETE COLUMNS WITH FIBER COMPOSITES
MODELS FOR CONFINED CONCRETE COLUMNS WITH FIBER COMPOSITESMODELS FOR CONFINED CONCRETE COLUMNS WITH FIBER COMPOSITES
MODELS FOR CONFINED CONCRETE COLUMNS WITH FIBER COMPOSITES
 
Study on Steel Beam Column Joint using Different Connections – State of Art
Study on Steel Beam Column Joint using Different Connections – State of ArtStudy on Steel Beam Column Joint using Different Connections – State of Art
Study on Steel Beam Column Joint using Different Connections – State of Art
 
Effect of width and layers of GFRP strips on deflection of Reinforced Concret...
Effect of width and layers of GFRP strips on deflection of Reinforced Concret...Effect of width and layers of GFRP strips on deflection of Reinforced Concret...
Effect of width and layers of GFRP strips on deflection of Reinforced Concret...
 
Kinerja RBS Balok Kastella akibat beban siklik
Kinerja RBS Balok Kastella akibat beban siklikKinerja RBS Balok Kastella akibat beban siklik
Kinerja RBS Balok Kastella akibat beban siklik
 
IRJET- Experimental Investigation on Seismic Retrofitting of RCC Structures
IRJET- Experimental Investigation on Seismic Retrofitting of RCC StructuresIRJET- Experimental Investigation on Seismic Retrofitting of RCC Structures
IRJET- Experimental Investigation on Seismic Retrofitting of RCC Structures
 
Capacity of strengthened Reinforced concrete columns
Capacity of strengthened Reinforced concrete columnsCapacity of strengthened Reinforced concrete columns
Capacity of strengthened Reinforced concrete columns
 
retrofitting
retrofittingretrofitting
retrofitting
 
Strengthening of RC Arches
Strengthening of RC ArchesStrengthening of RC Arches
Strengthening of RC Arches
 
Sub.ass.2
Sub.ass.2Sub.ass.2
Sub.ass.2
 
Retrofitting Reinforced Concrete
Retrofitting Reinforced Concrete Retrofitting Reinforced Concrete
Retrofitting Reinforced Concrete
 
IRJETI Comparison of RC Beam-Column Joint with GFRC Beam-Column Joint using S...
IRJETI Comparison of RC Beam-Column Joint with GFRC Beam-Column Joint using S...IRJETI Comparison of RC Beam-Column Joint with GFRC Beam-Column Joint using S...
IRJETI Comparison of RC Beam-Column Joint with GFRC Beam-Column Joint using S...
 
20320130406005
2032013040600520320130406005
20320130406005
 
IRJET- Fea & Experimental Analysis of Three Point Bending Test of Thin Walled...
IRJET- Fea & Experimental Analysis of Three Point Bending Test of Thin Walled...IRJET- Fea & Experimental Analysis of Three Point Bending Test of Thin Walled...
IRJET- Fea & Experimental Analysis of Three Point Bending Test of Thin Walled...
 
IRJET - Experimental Study on Performance of Buckling Restrained Bracings
IRJET - Experimental Study on Performance of Buckling Restrained BracingsIRJET - Experimental Study on Performance of Buckling Restrained Bracings
IRJET - Experimental Study on Performance of Buckling Restrained Bracings
 
Analysis of Concrete Filled Double Skin Steel Tube (CFDST) column with FRP wr...
Analysis of Concrete Filled Double Skin Steel Tube (CFDST) column with FRP wr...Analysis of Concrete Filled Double Skin Steel Tube (CFDST) column with FRP wr...
Analysis of Concrete Filled Double Skin Steel Tube (CFDST) column with FRP wr...
 
IRJET- Behaviour of Castellated Beam with Coupled Stiffener
IRJET-  	  Behaviour of Castellated Beam with Coupled StiffenerIRJET-  	  Behaviour of Castellated Beam with Coupled Stiffener
IRJET- Behaviour of Castellated Beam with Coupled Stiffener
 
Ijciet 10 01_012
Ijciet 10 01_012Ijciet 10 01_012
Ijciet 10 01_012
 
IRJET-Cyclic Response of Perforated Beam in Steel Column Joints
IRJET-Cyclic Response of Perforated Beam in Steel Column JointsIRJET-Cyclic Response of Perforated Beam in Steel Column Joints
IRJET-Cyclic Response of Perforated Beam in Steel Column Joints
 
Strengthening of reinforced concrete beam using steel fiber at different dept...
Strengthening of reinforced concrete beam using steel fiber at different dept...Strengthening of reinforced concrete beam using steel fiber at different dept...
Strengthening of reinforced concrete beam using steel fiber at different dept...
 

Viewers also liked

Analytical study on stress strain behaviour of reinforced concrete column
Analytical study on stress strain behaviour of reinforced concrete columnAnalytical study on stress strain behaviour of reinforced concrete column
Analytical study on stress strain behaviour of reinforced concrete columnIAEME Publication
 
Hysteresis models otani
Hysteresis models otaniHysteresis models otani
Hysteresis models otaniManuel Miranda
 
3.4 pushover analysis
3.4 pushover analysis3.4 pushover analysis
3.4 pushover analysisNASRIN AFROZ
 
Cable stay bridges, summary of a lecture delivered at Uni of Surrey, UK
Cable stay bridges, summary of a lecture delivered at Uni of Surrey, UKCable stay bridges, summary of a lecture delivered at Uni of Surrey, UK
Cable stay bridges, summary of a lecture delivered at Uni of Surrey, UKDavid Collings
 
Composite structures of steel and concrete
Composite structures of steel and concreteComposite structures of steel and concrete
Composite structures of steel and concretePashtoon Khan
 

Viewers also liked (8)

Analytical study on stress strain behaviour of reinforced concrete column
Analytical study on stress strain behaviour of reinforced concrete columnAnalytical study on stress strain behaviour of reinforced concrete column
Analytical study on stress strain behaviour of reinforced concrete column
 
Hysteresis models otani
Hysteresis models otaniHysteresis models otani
Hysteresis models otani
 
Hysteresis
HysteresisHysteresis
Hysteresis
 
Short Composite Columns - thesis
Short Composite Columns - thesis Short Composite Columns - thesis
Short Composite Columns - thesis
 
Modelos de histeresis Dr.Otani (traducción personal)
Modelos de histeresis Dr.Otani (traducción personal)Modelos de histeresis Dr.Otani (traducción personal)
Modelos de histeresis Dr.Otani (traducción personal)
 
3.4 pushover analysis
3.4 pushover analysis3.4 pushover analysis
3.4 pushover analysis
 
Cable stay bridges, summary of a lecture delivered at Uni of Surrey, UK
Cable stay bridges, summary of a lecture delivered at Uni of Surrey, UKCable stay bridges, summary of a lecture delivered at Uni of Surrey, UK
Cable stay bridges, summary of a lecture delivered at Uni of Surrey, UK
 
Composite structures of steel and concrete
Composite structures of steel and concreteComposite structures of steel and concrete
Composite structures of steel and concrete
 

Similar to Seismic rehabilitation of beam column joint using gfrp sheets-2002

Retrofitting of RC Beam Column Joint
Retrofitting of RC Beam Column JointRetrofitting of RC Beam Column Joint
Retrofitting of RC Beam Column JointDishamk
 
Retrofitting and Strengthening of Damaged Reinforced Concrete Columns Using S...
Retrofitting and Strengthening of Damaged Reinforced Concrete Columns Using S...Retrofitting and Strengthening of Damaged Reinforced Concrete Columns Using S...
Retrofitting and Strengthening of Damaged Reinforced Concrete Columns Using S...IJMER
 
IRJET- Experimental Evaluation of Strength of Damaged RCC Beam Repaired us...
IRJET- 	  Experimental Evaluation of Strength of Damaged RCC Beam Repaired us...IRJET- 	  Experimental Evaluation of Strength of Damaged RCC Beam Repaired us...
IRJET- Experimental Evaluation of Strength of Damaged RCC Beam Repaired us...IRJET Journal
 
STRENGTHENING OF PRECAST BEAM-COLUMN JOINT USING STEEL ENCASEMENT
STRENGTHENING OF PRECAST BEAM-COLUMN JOINT USING STEEL ENCASEMENTSTRENGTHENING OF PRECAST BEAM-COLUMN JOINT USING STEEL ENCASEMENT
STRENGTHENING OF PRECAST BEAM-COLUMN JOINT USING STEEL ENCASEMENTIRJET Journal
 
J0324056065
J0324056065J0324056065
J0324056065theijes
 
Paper id 36201532
Paper id 36201532Paper id 36201532
Paper id 36201532IJRAT
 
Steve Gregan -The Fatigue Performance Assessment of Corrosion Damaged RC Beam...
Steve Gregan -The Fatigue Performance Assessment of Corrosion Damaged RC Beam...Steve Gregan -The Fatigue Performance Assessment of Corrosion Damaged RC Beam...
Steve Gregan -The Fatigue Performance Assessment of Corrosion Damaged RC Beam...Steve Gregan
 
IRJET- Review on Reinforced Concrete Beam-Column Joint
IRJET- Review on Reinforced Concrete Beam-Column JointIRJET- Review on Reinforced Concrete Beam-Column Joint
IRJET- Review on Reinforced Concrete Beam-Column JointIRJET Journal
 
Behaviour of Steel Fibre Reinforced Concrete Beam under Cyclic Loading
Behaviour of Steel Fibre Reinforced Concrete Beam under Cyclic LoadingBehaviour of Steel Fibre Reinforced Concrete Beam under Cyclic Loading
Behaviour of Steel Fibre Reinforced Concrete Beam under Cyclic LoadingIOSR Journals
 
Study Of High Strength Fibre Reinforced Concrete Beams With Fibre Reinforced ...
Study Of High Strength Fibre Reinforced Concrete Beams With Fibre Reinforced ...Study Of High Strength Fibre Reinforced Concrete Beams With Fibre Reinforced ...
Study Of High Strength Fibre Reinforced Concrete Beams With Fibre Reinforced ...IRJET Journal
 
IRJET- Review on Steel Concrete Composite Column
IRJET-  	  Review on Steel Concrete Composite ColumnIRJET-  	  Review on Steel Concrete Composite Column
IRJET- Review on Steel Concrete Composite ColumnIRJET Journal
 
Final paper for thesis on Steel tubular column
Final paper for thesis on Steel tubular columnFinal paper for thesis on Steel tubular column
Final paper for thesis on Steel tubular columnAL AMIN AZIZ
 
COMPARATIVE STUDY ON RETEROFITTING OF RCC BEAM AND COLUMN JOINT BY USING FERR...
COMPARATIVE STUDY ON RETEROFITTING OF RCC BEAM AND COLUMN JOINT BY USING FERR...COMPARATIVE STUDY ON RETEROFITTING OF RCC BEAM AND COLUMN JOINT BY USING FERR...
COMPARATIVE STUDY ON RETEROFITTING OF RCC BEAM AND COLUMN JOINT BY USING FERR...IRJET Journal
 
Numerical Study on Retrofitting Of Beam Column Joint Strengthened With CFRP
Numerical Study on Retrofitting Of Beam Column Joint Strengthened With CFRPNumerical Study on Retrofitting Of Beam Column Joint Strengthened With CFRP
Numerical Study on Retrofitting Of Beam Column Joint Strengthened With CFRPIRJET Journal
 
Experimental Behavior of RC Beams Strengthened by Externally Bonded CFRP with...
Experimental Behavior of RC Beams Strengthened by Externally Bonded CFRP with...Experimental Behavior of RC Beams Strengthened by Externally Bonded CFRP with...
Experimental Behavior of RC Beams Strengthened by Externally Bonded CFRP with...IJERDJOURNAL
 

Similar to Seismic rehabilitation of beam column joint using gfrp sheets-2002 (20)

Retrofitting of RC Beam Column Joint
Retrofitting of RC Beam Column JointRetrofitting of RC Beam Column Joint
Retrofitting of RC Beam Column Joint
 
AJCE 1151
AJCE 1151AJCE 1151
AJCE 1151
 
Retrofitting and Strengthening of Damaged Reinforced Concrete Columns Using S...
Retrofitting and Strengthening of Damaged Reinforced Concrete Columns Using S...Retrofitting and Strengthening of Damaged Reinforced Concrete Columns Using S...
Retrofitting and Strengthening of Damaged Reinforced Concrete Columns Using S...
 
IRJET- Experimental Evaluation of Strength of Damaged RCC Beam Repaired us...
IRJET- 	  Experimental Evaluation of Strength of Damaged RCC Beam Repaired us...IRJET- 	  Experimental Evaluation of Strength of Damaged RCC Beam Repaired us...
IRJET- Experimental Evaluation of Strength of Damaged RCC Beam Repaired us...
 
STRENGTHENING OF PRECAST BEAM-COLUMN JOINT USING STEEL ENCASEMENT
STRENGTHENING OF PRECAST BEAM-COLUMN JOINT USING STEEL ENCASEMENTSTRENGTHENING OF PRECAST BEAM-COLUMN JOINT USING STEEL ENCASEMENT
STRENGTHENING OF PRECAST BEAM-COLUMN JOINT USING STEEL ENCASEMENT
 
J0324056065
J0324056065J0324056065
J0324056065
 
Paper id 36201532
Paper id 36201532Paper id 36201532
Paper id 36201532
 
Steve Gregan -The Fatigue Performance Assessment of Corrosion Damaged RC Beam...
Steve Gregan -The Fatigue Performance Assessment of Corrosion Damaged RC Beam...Steve Gregan -The Fatigue Performance Assessment of Corrosion Damaged RC Beam...
Steve Gregan -The Fatigue Performance Assessment of Corrosion Damaged RC Beam...
 
IRJET- Review on Reinforced Concrete Beam-Column Joint
IRJET- Review on Reinforced Concrete Beam-Column JointIRJET- Review on Reinforced Concrete Beam-Column Joint
IRJET- Review on Reinforced Concrete Beam-Column Joint
 
Behaviour of Steel Fibre Reinforced Concrete Beam under Cyclic Loading
Behaviour of Steel Fibre Reinforced Concrete Beam under Cyclic LoadingBehaviour of Steel Fibre Reinforced Concrete Beam under Cyclic Loading
Behaviour of Steel Fibre Reinforced Concrete Beam under Cyclic Loading
 
Study Of High Strength Fibre Reinforced Concrete Beams With Fibre Reinforced ...
Study Of High Strength Fibre Reinforced Concrete Beams With Fibre Reinforced ...Study Of High Strength Fibre Reinforced Concrete Beams With Fibre Reinforced ...
Study Of High Strength Fibre Reinforced Concrete Beams With Fibre Reinforced ...
 
IRJET- Review on Steel Concrete Composite Column
IRJET-  	  Review on Steel Concrete Composite ColumnIRJET-  	  Review on Steel Concrete Composite Column
IRJET- Review on Steel Concrete Composite Column
 
Final paper for thesis on Steel tubular column
Final paper for thesis on Steel tubular columnFinal paper for thesis on Steel tubular column
Final paper for thesis on Steel tubular column
 
V01226139142
V01226139142V01226139142
V01226139142
 
COMPARATIVE STUDY ON RETEROFITTING OF RCC BEAM AND COLUMN JOINT BY USING FERR...
COMPARATIVE STUDY ON RETEROFITTING OF RCC BEAM AND COLUMN JOINT BY USING FERR...COMPARATIVE STUDY ON RETEROFITTING OF RCC BEAM AND COLUMN JOINT BY USING FERR...
COMPARATIVE STUDY ON RETEROFITTING OF RCC BEAM AND COLUMN JOINT BY USING FERR...
 
FinalReport
FinalReportFinalReport
FinalReport
 
Numerical Study on Retrofitting Of Beam Column Joint Strengthened With CFRP
Numerical Study on Retrofitting Of Beam Column Joint Strengthened With CFRPNumerical Study on Retrofitting Of Beam Column Joint Strengthened With CFRP
Numerical Study on Retrofitting Of Beam Column Joint Strengthened With CFRP
 
J013127179
J013127179J013127179
J013127179
 
Experimental Behavior of RC Beams Strengthened by Externally Bonded CFRP with...
Experimental Behavior of RC Beams Strengthened by Externally Bonded CFRP with...Experimental Behavior of RC Beams Strengthened by Externally Bonded CFRP with...
Experimental Behavior of RC Beams Strengthened by Externally Bonded CFRP with...
 
K012456697
K012456697K012456697
K012456697
 

Seismic rehabilitation of beam column joint using gfrp sheets-2002

  • 1. Engineering Structures 24 (2002) 1397–1407 www.elsevier.com/locate/engstruct Seismic rehabilitation of beam–column joint using GFRP sheets T. El-Amoury, A. Ghobarah ∗ Department of Civil Engineering, McMaster University, Hamilton, Ontario, Canada, L8S 4L7 Received 13 July 2001; received in revised form 24 September 2001; accepted 24 May 2002 Abstract Techniques for upgrading reinforced concrete beam–column joints are proposed. The test specimens represent a typical joint that was built in accordance to pre-1970s’ codes. The objective of the rehabilitation is to upgrade the shear strength of these joints and reduce the potential for bond-slip of the bottom bars of the beam. Glass fibre-reinforced polymer (GFRP) sheets are wrapped around the joint to prevent the joint shear failure. GFRP sheets are attached to the bottom beam face to replace the inadequately anchored steel bars. Three beam–column joints are tested; namely, a control specimen and two rehabilitated specimens. The specimens are tested under quasi-static load to failure. The control specimen showed combined brittle joint shear and bond failure modes while the rehabilitated specimens showed a more ductile failure mode. A simple design methodology for the rehabilitation scheme is proposed.  2002 Elsevier Science Ltd. All rights reserved. Keywords: Beam-column joints; Seismic rehabilitation; Joint shear strength; Bond-slip; Ductility; GFRP composites; Design 1. Introduction Recent earthquakes in urban areas such as the 1994 Northridge, the 1995 Hanshin-Awaji (Kobe) and the 1999 Kocaeli (Turkey) have repeatedly demonstrated the vulnerability of existing structures to seismic defor-mation demands. These structures were designed and detailed for gravity loads and lateral forces that are lower than those specified by the current codes. Post-earth-quake examination of these structures showed that one of the weakest links in the lateral load-resisting system is the beam–column joint. Fig. 1 shows the exterior joint failure in a reinforced concrete building after the 1999 Kocaeli earthquake. Exterior beam–column joints are more vulnerable than interior joints, which are partially confined by beams attached to four sides of the joint and contribute to the core confinement. There are some differences between the shear response of interior and exterior joints when subjected to earthquake ground motion due to joint confinement by beams. However, the bond-slip mode of failure of exterior and interior joints is similar. ∗ Corresponding author. Tel.: +1-905-525-9140x124913; fax: +1- 905-529-9688. E-mail address: ghobara@mcmaster.ca (A. Ghobarah). When built according to earlier code provisions, beam–column joints in reinforced concrete moment-resisting 0141-0296/02/$ - see front matter  2002 Elsevier Science Ltd. All rights reserved. PII: S0141-0296(02)00081-0 frames have inadequate or no transverse shear reinforcement, and the bottom reinforcement of the beam is anchored only 150 mm from the column face, with inadequate development length when the bars are in ten-sion. This was done under the assumption that the beam positive moment reinforcement at the column face is always in compression. Because of these deficiencies, the joint may experience shear or bond-slip failure modes. These brittle types of failure will significantly reduce the overall ductility of the structure. The objective of beam–column joint rehabilitation is to strengthen the shear and bond-slip resistance in order to eliminate these types of brittle failure and ensure instead that ductile flexural hinging in the beam will take place. Recent studies on the effect of shear and bond-slip rehabilitation on the behaviour of reinforced con-crete frame have shown significant improvements in the overall frame ductility [1,2]. It is important to develop effective and economic rehabilitation techniques for upgrading the vulnerable beam–column joints in exist-ing structures. Rehabilitation of existing structures has received much attention during the past two decades. The objec-tive is to upgrade the joint shear strength before it is subjected to an earthquake. An interior beam-column
  • 2. 1398 T. El-Amoury, A. Ghobarah / Engineering Structures 24 (2002) 1397–1407 Fig. 1. Exterior joint failure during the 1999 Kocaeli (Turkey) earthquake. joint was rehabilitated and tested [3]. Steel plates were anchored to the beam bottom face at each side of the joint and connected together using threaded steel rods driven through the column. The idea is to replace the inadequately anchored steel bars with equivalent steel plates. Steel-plate jacketing was used to enhance the joint shear strength. Test results showed that joint jacket-ing was ineffective in improving the joint shear strength due to slippage of the steel plates. The specimen reached a drift of 4% without significant deterioration in strength. Flat steel plates were used to confine the joint in an attempt to prevent the spalling of concrete and to main-tain the concrete integrity [4,5]. Steel channels were attached to the beam bottom face to prevent slip of the bars. This scheme was found to be efficient in preventing the bars’ slippage, increasing the joint shear strength and reducing the rate of strength deterioration. Ghobarah et al. [6] used corrugated steel-sheet jacket-ing for joint confinement, leaving a gap between the con-crete and the jacket to be filled with grout. The shear strength of the rehabilitated joints was increased and the failure mode became flexural hinging in the beam. Carbon fibre-reinforced polymer (CFRP) materials were used to strengthen an external beam–column joint in shear [7]. The retrofitted specimen was wrapped with multiple layers of CFRP sheets. The joint shear capacity was increased by 25% and the specimens reached 5% drift. Ghobarah and Said [8] investigated the rehabilitation of beam–column joints using glass fibre-reinforced poly-mers (GFRP). One joint was tested as control specimen and two were tested after rehabilitation. The proposed rehabilitation scheme was to wrap the joint with U-shaped GFRP sheets. The ends of the composite sheets were tied together using two steel plates and four steel tie rods through the joint. The behaviour of the rehabili-tated specimen was significantly improved. The brittle shear failure of the beam–column joint was eliminated and instead ductile flexural hinging of the beam occurred. The joints tested in this research programme were designed with deficient shear strength but with adequate positive reinforcement anchoring in the joint. In other words, bond-slip failure was not included in the rehabilitation scheme. Limited testing was conducted on beam–column joints rehabilitated using composite rods to strengthen the col-umn flexural strength and fibre wrap to strengthen the joint shear [9]. Joint rehabilitation using fibre-reinforced polymers (FRP) has the advantages of simplicity of application and less need for skilled labour. The econ-omic advantages of FRP rehabilitation were evaluated by Ehlen and Marshall [10]. So far, most of the research conducted on beam– column joints has mainly been concerned with upgrading joint shear strength using steel plates, sheets and sections and FRP. However, the rehabilitation of bond-slip in reinforced concrete beam–column joints has not received much attention. The objective of the present research programme is to develop new rehabilitation systems for strengthening the shear resistance of beam–column joints and for upgrad-ing resistance to bond-slip of the positive reinforcement anchored in the joint. 2. Experimental programme 2.1. Test specimens Three reinforced concrete beam–column joints were tested: T0, TR1 and TR2. The specimens represent an exterior joint in a typical concrete frame that has been built before 1970 [11]. Exterior joints are selected because they are more vulnerable and are normally
  • 3. T. El-Amoury, A. Ghobarah / Engineering Structures 24 (2002) 1397–1407 1399 expected to fail first. If the rehabilitation system is suc-cessful, it can be easily adapted to interior joints as well. The beam–column joints are designed assuming that points of contra-flexure occur at the mid-height of col-umns and the mid-span of beams. The top longitudinal reinforcements in the beam are bent down into the col-umn, whereas the bottom reinforcement was anchored 150 mm from the column face. No transverse reinforce-ment was installed in the joint region. The beam was reinforced using 4#20 as top and bottom longitudinal bars and #10 as transverse steel. The column was reinforced with 6#20 plus 2#15 as longitudinal bars and #10 ties spaced 200 mm. The dimensions and reinforce-ment details of all of the specimens are identical, as shown in Fig. 2. After testing the control specimen, T0, the cracked concrete was removed from the joint region and the adjacent parts of the columns and beam. The specimen was laid inside the wooden forms again and new con-crete was poured to replace the removed materials. The specimen was then rehabilitated and tested again as specimen TR1. However, specimen T2 is an original specimen that was retrofitted then tested. The concrete compressive strength on the test day was 30.6, 43.5 and 39.5 MPa for the control specimen T0, the repair con-crete of specimen TR1 and for specimen TR2, respect-ively. The yield strength of the steel bars #10, #15 and #20 was 450, 408 and 425 MPa, respectively. Bi-directional GFRP material were used in the joint rehabilitation. The bi-directional material is woven in the ±45° directions. The properties of the fibre sheets used in the current testing programme, as supplied by the manufacturer, are given in Table 1. 2.2. Test set-up and instrumentation The specimens were tested in the column vertical pos-ition, hinged at the top and bottom column ends and sub-jected to a cyclic load applied at the beam tip as shown in Fig. 3. The beam-tip displacement and the column lateral displacement were measured using poten-tiometers. Two diagonal linear voltage differential trans-formers (LVDTs) were attached to the joint to measure the joint shear deformation. The displacement of the col-umn above and below the joint was measured using two additional LVDTs attached to the top and bottom of the beam, as shown in Fig. 3. Twelve strain gauges were installed on the reinforcement steel bars to measure the strains at different loading levels, as shown in Fig. 4. For the retrofitted specimens, 10 strain gauges were installed on the fibre sheets, two strain gauges were installed on the tie rods driven through the joint. A reversed quasi-static cyclic load was applied at the beam tip using a hydraulic actuator of ±250 mm stroke. The applied load was measured using a load cell. The loading routine consisted of two phases as shown in Fig. 5. The first phase was load control, where the specimen was subjected to an increasing load up to the first yield of the steel bars. This phase of loading was used to deter-mine the displacement of the beam tip when first yield Fig. 2. Specimen dimensions and reinforcement details.
  • 4. 1400 T. El-Amoury, A. Ghobarah / Engineering Structures 24 (2002) 1397–1407 Table 1 Properties of the composite materials GFRP Tensile strength in 0° direction (MPa) Elongation at break (%) Tensile modulus (GPa) Thickness (mm) Bi-directional (±45°) 279 1.5 19 0.864 Unidirectional 1700 2 71 0.353 Fig. 3. Test set-up. of the steel occurs, y. After the beam steel bars reached the yield strain, the second loading phase was initiated which was displacement control. Multiples of the dis-placement corresponding to the bars’ first yield, y, were used to load the specimen. A constant axial load of 600 kN was applied to the column, using another hydraulic jack provided with a load cell to measure the applied load. This load represents the gravity load that acts on the column, and was approximately equal to 0.2Agfc, where Ag is the gross cross-sectional area and fc is the compressive strength of concrete. 2.3. Rehabilitation schemes The proposed rehabilitation schemes consist of two systems. The first system is for upgrading the shear strength of the joint. The joint was wrapped with two U-shaped composite layers. The first layer was bi-direc-tional sheet and the second was unidirectional sheet. The ends of the sheets were anchored using steel plates and tie rods driven through the joint. This system was similar to previously tested systems [8] but differed in material design and details. The second system was for upgrading the steel bars’ bond-slip. This system is new and was Fig. 4. Location of strain gauges on the reinforcement steel bars. Fig. 5. Loading routine. being tested for the first time. In specimen TR1, four unidirectional glass fibre sheets were applied to the beam bottom face for a horizontal distance of 1000 mm and extended along the inner column face vertically for a distance of 500 mm, as shown in Fig. 6a. In specimen
  • 5. T. El-Amoury, A. Ghobarah / Engineering Structures 24 (2002) 1397–1407 1401 Fig. 6. Retrofitting schemes: (a) specimen TR1, (b) specimen TR2. TR2, eight unidirectional glass fibre sheets were applied to the bottom beam face and provided with two U-shaped 3 mm thick steel plates to enhance the bond between the GFRP and the concrete, as shown in Fig. 6b. Using the described configuration, the resultant of the tensile forces developed in the composite sheets may cause debonding of the sheets from the concrete surface at the beam–column corner. To overcome this potential problem, a steel angle was installed at the lower beam– column corner as shown in Fig. 6a. To install the angle in place, the beam bottom bars were exposed for a dis-tance of 150 mm from the column face and the heads of A375 steel bolts of diameter 20 mm were welded to the beam bars in two rows. For specimen TR1, four 28 mm diameter and 170 mm depth holes were drilled in the column in two rows. The steel angle was fixed in place using washers and nuts to the bolts welded to the beam reinforcement and using Hilti HVA 5/8×6-5/8 adhesive anchors to the column. For specimen TR2, four 25 mm diameter external threaded rods with 500 mm × 200 mm × 25 mm steel plate were used to tie the angle to the column as shown in Fig. 6b. 3. Experimental results In this section, the behaviour of the control and rehabilitated specimens is described and the effective-ness of the rehabilitation schemes is evaluated. 3.1. Specimen T0 In the first loading cycle, the specimen was loaded up to 3.0 kN up and down to test the instrumentations. The first beam crack was observed during the second cycle at the column face at load of 7.7 kN up. In the fourth cycle, a load of 30.0 kN was applied up and down to the specimen; new flexural and flexural–shear cracks formed along the beam length. In the sixth cycle, vertical cracks formed in the joint region at beam-tip load of 35.5 kN due to bond-slip of the beam bottom bars. During the eighth cycle, diagonal shear cracks developed in the joint region, and the specimen reached a load of 60.0 kN at a beam-tip displacement of 20 mm. Repeating the same cycle, the beam reached the same displacement but at lower load level and the beam bars started to slip out of the joint with an associated reduction in the developed strain in the bars. The beam-tip displacement of 20 mm was used as a reference value for the displacement-con-trolled loading phase. In the following cycles the beam tip was displaced up and down by multiples of this value. The reason for selecting this arbitrary displacement as reference displacement in the test is that yield of the reinforcement steel is not expected to occur. When the specimen was pushed up, the bond-slip cracks opened and the lateral load-carrying capacity deteriorated sig-nificantly; however, when it was pulled down, the diag-onal shear cracks opened. This caused disintegration of the concrete, deterioration of the bond condition of the beam top bars and degradation of the lateral load-carry-ing capacity. The specimen reached a maximum load of
  • 6. 1402 T. El-Amoury, A. Ghobarah / Engineering Structures 24 (2002) 1397–1407 60.0 kN up and 86.0 kN down, which is much less than the expected theoretical load at first steel yield of approximately 110.0 kN. The test was halted at displace-ment of 50 mm as the load-carrying capacity was greatly reduced. In effect, when pushing up on the beam, bond-slip failure of the beam bottom reinforcement occurred and when pulling down, joint shear failure occurred. The final failure pattern is shown in Fig. 7. A reduction in the column axial load up to 10% of the original load was recorded in the last cycles due to joint shear failure. Examining the hysteretic behaviour of the specimen showed considerable pinching, severe strength deterio-ration and stiffness degradation, as shown in Fig. 8. Bond slip was found to be a more brittle type of failure when compared with shear failure, as it occurred earlier and is associated with a higher rate of strength deterio-ration. In the figure, beam-tip displacement of 20 mm corresponds to 1.0 % storey drift. 3.2. Specimen TR1 Specimen TR1 was subjected to the same loading sequence as specimen T0. The first crack occurred dur- Fig. 7. Failure pattern of specimen T0. Fig. 8. Beam-tip load–displacement of specimen T0. ing the second cycle at load of 14.0 kN. The specimen was loaded at increments of 20.0 kN until reaching the first yield of the steel reinforcement. Before yielding, the behaviour of the specimen was almost elastic with no residual deformation observed. Examining the strain values showed that the fibre sheets attached to the beam face were carrying most of the developed tensile forces, indicating that the glass fibre fabric was working effec-tively. During the sixth cycle, vertical cracks appeared in the lower column under the joint region, due to the tensile forces developed in the adhesive anchors. These cracks caused a sudden drop in the beam-tip load from 58.0 kN to 53.0 kN. During the test, FRP debonding was regularly checked by fingertip tapping on the composite sheets. During the eighth cycle, the wrapped laminates around the joint started to debond between the free edges and the steel plates. In the 10th cycle, the beam top steel bars reached the yield strain at beam displacement of 25 mm and beam-tip load of 110.0 kN. This displacement was designated the yield displacement y, and the dis-placement- controlled loading phase was initiated. Dur-ing the 12th cycle, the specimen was displaced to 37.5 mm up and down (1.5y). The fibre sheet attached to the bottom beam face reached a strain of 0.0045 when the specimen was pushed up. As the beam tip was pulled down, the fibre sheets buckled and started to debond from the beam face. In the following cycles, as the ten-sion in the fibres is lost due to debonding, the existing steel bars started to carry the developed tension force. The tension force in the bars was transferred to the col-umn by bonding, the welded bolts and the steel angle. The specimen showed increased load-carrying capacity as it was pulled down. During the 16th cycle, at displace-ment of 75 mm up and down (3.0y), the weld around the bolt heads fractured, the beam bars slipped out of the joint and sudden a drop in the beam load was observed. During the next cycle, the specimen experi-enced a loss of load-carrying capacity when pushed up, whereas it continued to carry the same load level when it was pulled down, indicating no shear failure in the joint region. The final failure condition is shown in Fig.
  • 7. T. El-Amoury, A. Ghobarah / Engineering Structures 24 (2002) 1397–1407 1403 Fig. 9. Failure pattern of specimen TR1. 9. The composite sheets were completely debonded from the beam and column faces. Examining the hysteretic loops of the specimen showed that the behaviour remained almost elastic up to the first steel yield, as shown in Fig. 10. Severe pinching and stiffness degra-dation occurred in the last two cycles following the frac-ture of the weld. 3.3. Specimen TR2 Specimen TR2 was subjected to the same loading rou-tine as the previous specimens. The first crack occurred during the second cycle at load of 20.0 kN while it was being pulled down. During the following cycle, the first yield of the beam top bars occurred at beam displace-ment of 26.5 mm and beam-tip load of 114.5 kN. This displacement was designated the yield displacement y, and the displacement-controlled loading phase was initiated. Vertical cracks appeared in the lower column under the joint region at a beam-tip load of 75 kN. Dur-ing the sixth cycle, the wrapped laminates around the joint started to debond at the free edges. In the ninth cycle, the fibre attached to the column face started to Fig. 10. Beam-tip load–displacement of specimen TR1. delaminate behind the steel angle. The forces developed in the composite sheets were transferred to the column by the steel angle and the tie rods. This caused a reduction in the beam-tip load when the specimen was being pushed up accompanied with large deformations to the angle. In the 11th cycle, while the specimen was being pulled down, it reached its ultimate load of 131.0 kN and displacement of 79.5 mm (3y). This high load caused new cracks in the column part above the joint and initiated joint shear failure. Degradation of the load-carrying capacity was observed in the following cycles. During the 16th cycle, the specimen displaced to 132.5 mm (5y) was still able to carry load of 74.0 kN up and 89.0 kN down, which are more than half of the yield load. The two U-shaped steel plates proved to be effective in preventing fibre debonding from the concrete face to the end of the test. The strain in the GFRP reached approximately 0.005 in both tension and compression. In the 17th cycle, the specimen was displaced to 159 mm (6y); however, the load-carrying capacity deterio-rated to 52.0 kN. The test was halted after the 19th cycle where the specimen reached displacement of 185 mm (7y) and the load-carrying capacity deteriorated to 32.0 kN. The specimen showed shear cracking in the joint region under the GFRP, as shown in Fig. 11. The load– displacement cycles are shown in Fig. 12. Although the final failure mode of specimen TR2 was due to joint shear high load-carrying capacity, the overall joint performance is much more ductile compared with the control specimen T0. During the test, it was con-firmed that the large plastic deformation of the steel angle provided significant ductility to the joint behav-iour. 4. Discussion In this section, the hysteretic behaviour, energy dissi-pation, stiffness degradation, joint strength and ductility levels of the tested specimens are discussed. The envelopes of the hysteretic loops of the tested specimens are shown in Fig. 13. Specimen TR1 showed almost 100% increase in the load-carrying capacity com-pared with specimen T0. Specimen TR2 reached a higher load level and maintained the load-carrying capacity at displacement levels much higher than those of the other two specimens. The pinching effect is severe in speci-men T0 as compared with the rehabilitated specimens. The top steel in the beam of specimen T0 did not reach its yield stress. On the other hand, in the rehabilitated specimens, the yield of the top beam reinforcement was exceeded. This indicates the effectiveness of the shear rehabilitation scheme in strengthening the joint shear capacity and maintaining the joint concrete integrity by confinement.
  • 8. 1404 T. El-Amoury, A. Ghobarah / Engineering Structures 24 (2002) 1397–1407 Fig. 11. Failure pattern of specimen TR2. Fig. 12. Beam-tip load–displacement of specimen TR2. The area enclosed by a hysteretic loop at a given cycle represents the energy dissipated by the specimen during this cycle. The capability of a structure to dissipate energy has a strong influence on its response to an earth-quake loading. The total energy dissipated by a structure consists of (1) energy dissipated by the steel reinforce-ment; (2) energy dissipated by friction along existing cracks in concrete; and (3) energy dissipated during the formation of new cracks. Fig. 14 shows the cumulative energy dissipated by the three beam–column joints. It is observed that the rehabilitated specimen TR1 had the ability to dissipate three times the energy dissipated by Fig. 13. Hysteretic loop envelopes of the test specimens. Fig. 14. Cumulative energy dissipated by the tested specimens. the specimen T0, while specimen TR2 dissipated almost six times the energy dissipated by the control speci-men T0. The beam–column joint stiffness was approximated as the slope of the peak-to-peak line in each loop. Test results indicated that stiffness degradation was due to various factors such as non-linear deformations, flexural and shear cracking, distortion of the joint panel, slippage of reinforcement, and loss of cover. The control speci-men T0 showed high initial stiffness compared with specimen TR1 because of the pre-cracking of the rehabilitated specimen TR1 before repair. Specimen TR2, which was tested for the first time after rehabili-tation, showed also high initial stiffness. Comparing the peak-to-peak stiffness of the tested joints shows that the stiffness degradation of the control joint T0 was higher than that of the rehabilitated specimens TR1 and TR2, as shown in Fig. 15. While the control specimen did not reach the steel yield due to bond-slip and shear failure, the rehabilitated specimens TR1 and TR2 reached higher ductility levels than the control specimen T0. 5. Design of GFRP sheets The design approach is based on providing fibre reinforcement to replace the missing joint shear
  • 9. T. El-Amoury, A. Ghobarah / Engineering Structures 24 (2002) 1397–1407 1405 Fig. 15. Degradation of stiffness with storey drift. reinforcement or the inadequately anchored steel reinforcement. 5.1. Flexural strengthening sheets The fibre is used to replace the inadequately anchored bottom steel bars of the beam. In the design process, fibre sheets are provided to develop the same design flexural moment of the reinforced concrete beam section. This moment limit is imposed on the flexural strengthen-ing system to avoid creating a beam that is stronger than the column. 5.1.1. The beam flexural moment The moment capacity of the beam section is determ-ined according to the provisions of CSA A23.3-94 [12]. To account for overstrength in steel, the tensile force in the steel is calculated using the actual yield strength, which equals the nominal yield strength increased by 25%, Ts 1.25fyAs, (1) where Ts is the tension force in the bottom steel bars As is the area of the tension steel bars. fy is the nominal yield strength of the steel The concrete compression block depth “a” can be calcu-lated using the force equilibrium expression: Ts Cc Cs a1fcab AsEses, (2) where Cc is the concrete compression force Cs is the steel compression force a1 is the equivalent compression block reduction factor [12], a1 0.85–0.0015 for fc 0.67 fc is the concrete compression strength b is the beam width As is the area of the compression steel Es is the modulus of elasticity of the steel es is the strain in the compression steel. The resisting positive moment of the section at the face of the column, Mr, is: Mr Cc(da/2) Cs(dd), (3) where d is the effective beam depth d is the concrete cover above the top steel. In the particular case of joint T0, Eq. (1) gives the ten-sion force in the steel bars to be Ts 600 kN, and Eq. (2) gives the depth of the concrete block to be a 61.0 mm. The resisting moment capacity given by Eq. (3) is Mr 187.32 kN m. 5.1.2. Required number of GFRP layers The design objective is to achieve the same flexural capacity of the adequately anchored section. In this design procedure, three assumptions are made: strain compatibility between the different materials is assumed; the ultimate concrete strain in compression is taken as 0.0035; and the contribution of the existing steel bars is ignored. The tensile force developed in the fibre sheets can be estimated as Tfrp efrpEfrpAfrp, (4) where efrp is the strain developed in the GFRP sheets, which should be less than the ultimate strain, and could be derived from the geometry, as shown in Fig. 16; Efrp is the modulus of elasticity of the GFRP and Afrp is the area of the GFRP sheets. The depth of the concrete compression block “a” can be calculated from the moment equilibrium equation: Mr a1fcab(ta/2) AsesEs(td). (5) The strain in the fibre can be written as: efrp ec tc c , (6) where ec is the compression strain in concrete and c is the location of the neutral axis. From the equilibrium of forces: Tfrp Cc Cs (7) Tfrp efrpEfrpnfrptfrpb. (8) Using the same resisting moment capacity of joint T0, Mr 187.32 kN m, Eq. (5) gives the depth of the con-crete block to be a 55.95 mm. Eqs. (6) to (8) give the
  • 10. 1406 T. El-Amoury, A. Ghobarah / Engineering Structures 24 (2002) 1397–1407 Fig. 16. Calculation of the required number of GFRP sheets. strain in the fibre efrp 0.0189 with the number of GFRP layers, nfrp, as 4.35. In specimen TR1, the number of GFRP layers, nfrp, is taken as 4, while in specimen TR2 the nfrp is taken as 8. 5.2. Joint shear strengthening The developed joint shear force is calculated as [12,13]: Vj 1.25AsfyVcol, (9) where Vj is the developed joint shear force Vcol is the shear force in the column. The total shear resistance consists of the concrete resistance, the resistance of the ties and the resistance provided by the composite sheets: Vj Vc Vs Vfrp. (10) The concrete shear resistance can be estimated using ACI 352 [14] provision to be: Vc 0.3fc(1 0.3fcol)bjdj, (11) where fcol is the axial stress applied to the column bj is the joint width dj is the joint effective width. As there are no ties provided in the joint, Vs is taken to be zero. The fibre contribution, Vfrp, is estimated to be: Vfrp AfrpefrpEfrp. (12) For the rehabilitated specimen TR2, the column shear force is obtained by dividing the nominal moment capacity by the shear arm, which is equal to 2850 mm: Vcol 187.32/ 2.85 65.73 kN. Eq. (9) gives the total joint shear as Vj 534.27 kN. Eq. (11) gives Vc 276.06 kN. From Eq. (10), the required shear resistance contributed by the fibre is Vfrp 258.21 kN. The shear strength provided using one bi-directional and one unidirectional layers can be estimated from Eq. (12), by assuming that both sheets will reach the same strain level of 1.0%, which is equal to 2/3 of the smallest maximum strains of the two composite sheet types. This gives the provided shear resistance by the FRP, Vr 290.35 kN, which is greater than the required fibre resistance Vfrp. 6. Conclusions Based on the experimental results, the following con-clusions can be made. The control specimen with no shear reinforcement in the joint and with inadequate anchorage for the beam bottom steel bars showed a brittle joint shear failure accompanied by slippage of the beam bottom bars. The bond conditions of the beam top bars were affec-ted by the disintegration of the concrete in the control joint, leading to a significant reduction in the load-carrying capacity and the ductility of the joint. Using GFRP jacketing maintained the concrete integrity by confinement and significantly improved the ductility and the load-carrying capacity of the rehabilitated joint. Comparison between the control and the rehabilitated specimens emphasized the effectiveness of the rehabilitation schemes. The joint rehabilitation elim-inated the brittle joint shear failure, improved the bond conditions of the beam top reinforcement, delayed the slippage of the bottom steel bars, increased the energy dissipated by the specimen and reduced the stiffness degradation of the joint. In specimen TR1, the fibre debonded from the con-crete surface when it reached a strain of 0.004, which is approximately 25% of the proposed strain by the design methodology. However, specimen TR1
  • 11. T. El-Amoury, A. Ghobarah / Engineering Structures 24 (2002) 1397–1407 1407 reached the proposed strength due to the contribution of the existing steel bars, which was ignored in the design. In specimen TR2, use of U-shaped steel plates to restrain the GFRP eliminated debonding of the GFRP from the concrete surface. The FRP reached a strain that is approximately 1/3 of its ultimate strain in both tension and compression without failure. The rehabili-tated joint achieved 52% higher load-carrying capacity and dissipated six times the energy dissipated by the control specimen. Acknowledgements The authors are grateful to Fyfe Co. and R.J. Watson, Inc. for providing the GFRP material used in the tests, and to ISIS Canada for supporting the research pro-gramme. References [1] Ghobarah A, Biddah A. Dynamic analysis of reinforced concrete frames including joint shear deformation. Eng. Struct. 1999;21:971–87. [2] Ghobarah A, Youssef, M. Response of an existing RC building including concrete crushing and bond slip effects. In: Proceedings of 8th Canadian Conference on Earthquake Engineering, Canad-ian Association for Earthquake Engineering, Vancouver, BC, 1999. p. 427–32. [3] Estrada JI. Use of steel elements to strengthen a reinforced con-crete building. M.Sc. thesis, University of Texas at Austin, 1990. [4] Beres A, White RN, Gergely P. Seismic performance of interior and exterior beam-to-column reinforced concrete frame buildings. Detailed experimental results. In: Report No. 92-06. Ithaca, NY: Department of Structural Engineering, Cornell University, 1992. [5] Beres A, El-Borgi S, White RN, Gergely P. Experimental results of repaired and retrofitted beam–column joint tests in lightly reinforced concrete frame buildings. In: Report No, NCEER-92- 25. Buffalo (NY): National Center for Earthquake Engineering Research, State University of New York at Buffalo, 1992. [6] Ghobarah A, Aziz TS, Biddah A. Seismic rehabilitation of reinforced concrete beam–column connections. Earthquake Spec-tra 1996;12(4):761–80. [7] Pantelides C, Clyde C, Dreaveley L. Rehabilitation of R/C build-ing joints with FRP composites. Proceedings of the 12th World Conference on Earthquake Engineering, New Zealand Society for Earthquake Engineering, Silverstream, Upper Hutt, New Zealand, 2000. Paper no. 2306. [8] Ghobarah A, Said A. Seismic rehabilitation of beam–column joints using FRP laminates. J. Earthquake Eng. 2001;5(1):113– 29. [9] Prota A, Nanni A, Manfredi G, Cosenza E. Seismic upgrade of beam–column joints with FRP reinforcement. In: FRPRCS5. Pro-ceedings of 5th Non-Metallic Reinforcement for Concrete Struc-tures, Thomas Telford Ltd, UK. 2001. paper # 339. [10] Ehlen MA, Marshall HE. The economics of new-technology materials: a case study of FRP bridge decking. In: National Insti-tute of Standards and Technology Report NISTIR 5864. Gaithers-burg (MD): Office of Applied Economics, Building and Fire Research Laboratory, 1996. [11] ACI-318 Building code requirements for reinforced concrete. Detroit (MI): American Concrete Institute, 1963. [12] CSA A23.3 Design of concrete structures. Rexdale, Ontario: Can-adian Standards Association, 1994. [13] Park R, Paulay T. Reinforced concrete structures. New York: John Wiley Sons, 1975. [14] ACI 352 Recommendation for design of beam–column joints in monolithic reinforced concrete structures. Detroit (MI): American Concrete Institute, 1976.