Renewables - funding for the future
1. WALES THIRD SECTOR FUNDING
CONFERENCE 2014
Making a better ask for funding
Renewables:
Funding for the future
Venue Cymru, Llandudno
2 October 2014
Jennifer Pride, Welsh Government
Vicky Davies, Ynniโr Fro Programme Manager, Welsh Government
Grant Peisley, Datblygiadau Egni Gwledig (DEG)
2. Why would communities
take on renewable energy
projects?
A long term, clean income stream
โขto invest as you decide
โขto attract match funding
Sale of electricity โ power purchase
agreements
Feed in Tariff (FIT)
Renewable Heat Incentive (RHI)
3. Antur Ynni Aelhaearn.
Pweruโr Gymuned Powering the Community.
โข Maeโr elw oโr cynllun yma iโw fuddsoddi ym
mhrosiectau Antur Aelhaearn aโr gymuned,
โข Bydd cyfle i brynu cyfranddaliadu yn y fenter.
โข The profit from this project will be invested in
Antur Aelhaearnโs and community projects.
โข There will be an opportunity to buy shares in the
venture.
4. Antur Aelhaearn project
Income Year 1 - 10
1 2 10
Incwm Income ยฃ391,739 ยฃ391,739 ยฃ391,739
Cyfanswm Costau Rhedeg + Gwasanaethu Cyllid
Total Running Costs + Servicing Finance ยฃ322,891 ยฃ280,865 ยฃ280,865
Elw Net
Net Surplus ยฃ68,848 ยฃ110,874 ยฃ110,874
5. Antur Aelhaearn
Income Year 11- 20
Blwyddyn 11 20
Incwm
Income Cyfanswm Costau Rhedeg + ยฃ391,739 ยฃ391,739
Gwasanaethu Cyllid ยฃ 1 7 8 , 7 3 4 .72 ยฃ178,734.72
Elw
Surplus ยฃ213,004.16 ยฃ213,004.16
20 year average annual profit = ยฃ159,838
6. Antur Aelhaearn
Investment
Cyllid Cyfalaf Capital
finance
Cyfran
Proportion Faint Sum
Llog
Interest
Cyfnod
Term
Blynyddol
Annual
Benthyciad banc Bank loan 47% ยฃ564,000 8.00% 10 ยฃ84,053
Benthyciad Ynni'r Fro loan 10% ยฃ120,000 8.24% 10 ยฃ18,078
Buddsoddiad partner Partner investment 20% ยฃ240,000
Cyfranddaliadau Share issue 20% ยฃ240,000 7.00% 20 ยฃ22,654
Grant 3% ยฃ36,000
Cyfanswm Total ยฃ1,200,000
8. Abergwyngregyn
Income: ยฃ200,000/year
Costs: ยฃ1,250,000
โข Project development costs ยฃ60,000
โข Project construction costs ยฃ1,055,000
โข Contingency ยฃ134,000
Share offer: ยฃ300,000
Has raised over ยฃ142k to date since
13 Sep launch
10. Penllegare Valley Woods
The Penllergare Trust:
โข 24kw Archimedes screw hydropower unit.
โข Provide an income to allow them to:
โข conserve and maintain the historic
landscape for enjoyment of the public.
โข Education and training โ outdoor
classroom
โข Enhance biodiversity
11. Penllegare Valley Woods
The Penllergare Trust:
โข 24kw Archimedes screw hydropower unit.
โข Total construction cost: ยฃ505,830
โข Ynniโr Fro grant ยฃ113,919
โข Annual generation of 73,936 KWh
โข Annual income forecast ยฃ16,180 from FITs
12. Dyffryn Crawnon Green Energy
16 kW high head micro hydro scheme in
Brecon Beacons National Park
โข Total construction costs ยฃ115,000
โข Ynniโr Fro loan ยฃ70,000
โข Annual income forecast of ยฃ17,000
โข Net profit of ยฃ3,600
โข Annual energy generation of 65,833 kWh
13. Groups are using the income for:
โข Reducing fuel bills
โข Insulating houses in the community
โข Heating community halls
โข Training members of the community, for
example to fit boilers or insulation
โข Building or buying local assets
15. Support
โข Ynniโr Fro and its successor scheme
โข Renew Wales http://www.renewwales.org.uk/
โข Robert Owen Community Banking Fund
(ROCBF) https://rocbf.co.uk/
โข Community Energy Development Fund
โข Business Wales
โข Wales Co-operative Centre
16. Over to you!
โขWould this be something that you could
see your group doing?
โขWhat support or help would you think
youโd need?
18. Renewables โ
Funding for the future
Thanks for listening!