This PowerPoint helps students to consider the concept of infinity.
Stayer acc 560 week 8 quiz 6
1. STAYER ACC 560 Week 8 Quiz 6 (Chapter 11) NEW
Check this A+ tutorial guideline at
http://www.assignmentcloud.com/acc-560-stayer/acc-
560-week-8-quiz-6-new
For more classes visit
http://www.assignmentcloud.com
Question 1
If actual direct materials costs are greater than standard direct
materials costs, it means that
Question 2
The standard direct materials quantity does not include
allowances for
Question 3
Marburg Co. expects direct materials cost of $6 per unit for
100,000 units (a total of $600,000 of direct materials costs).
Marburg’s standard direct materials cost and budgeted direct
materials cost is
Question 4
2. If the labor quantity variance is unfavorable and the cause is
inefficient use of direct labor, the responsibility rests with the
Question 5
A managerial accountant
1. does not participate in the standard setting process.
2. provides knowledge of cost behaviors in the standard setting
process.
3. provides input of historical costs to the standard setting
process.
Question 6
Using standard costs
Question 7
An unfavorable materials quantity variance would occur if
Question 8
Hofburg’s standard quantities for 1 unit of product include 2
pounds of materials and 1.5 labor hours. The standard rates
are $2 per pound and $7 per hour. The standard overhead rate
is $8 per direct labor hour. The total standard cost of Hofburg’s
product is
Question 9
Scorpion Production Company planned to use 1 yard of plastic
per unit budgeted at $81 a yard. However, the plastic actually
cost $80 per yard. The company actually made 3,900 units,
although it had planned to make only 3,300 units. Total yards
used for production were 3,960. How much is the total
materials variance?
Question 10
Unfavorable materials price and quantity variances are