S/no Hurdles Things Required
1 RTA NOC+WATER NOC
Portacabins+Entry door+Store+Steel
Area+Signboard+Roadbase for access road
2
DM Sand Transfer Noc+Excavation Noc DDA+confirmation letter
from soil laboratory
Shovel+Compactor+theodolite+Compaction
test+safety signs+safety officer+Shoes and
Helmet+HSE PLAN
3
Dewatering NOC+Waste Skip+Surveyor to fix Bolts and base
plate
Shuttering+Subcontractors+Ready Mix
Designs+Steel test result and confirmation from
consutlant+Testing Apparatus+Dewatering Sub-
contractor
4
5
6
7
8
AL AMEERA FOOD FACTORY
ROOF SHEETING
Description of activity
MOBILIZATION
EXCAVATION
SUBSTRUCTURE
SUPERSTRUCTURE
STEEL STRUCTURE
BLOCK WORK
PLASTER AND PAINT WORK
9
10
11
12
13
14
15
16
17
18
19
20
21
COMMISSIONING
FIREFIGHTING WORKS
WATER SUPPLY
MISCELLANEOUS WORK
SITE CLEANING & HANDOVER
TILE & MARBLE WORK
PLUMBING WORK
JOINERY WORK
EXTERNAL FINISHING
AC WORKS
INFRASTRUCTURE WORK
ALUMINIUM WORK
ELECTRICAL WORK

work schedule 2.pdf

  • 1.
    S/no Hurdles ThingsRequired 1 RTA NOC+WATER NOC Portacabins+Entry door+Store+Steel Area+Signboard+Roadbase for access road 2 DM Sand Transfer Noc+Excavation Noc DDA+confirmation letter from soil laboratory Shovel+Compactor+theodolite+Compaction test+safety signs+safety officer+Shoes and Helmet+HSE PLAN 3 Dewatering NOC+Waste Skip+Surveyor to fix Bolts and base plate Shuttering+Subcontractors+Ready Mix Designs+Steel test result and confirmation from consutlant+Testing Apparatus+Dewatering Sub- contractor 4 5 6 7 8 AL AMEERA FOOD FACTORY ROOF SHEETING Description of activity MOBILIZATION EXCAVATION SUBSTRUCTURE SUPERSTRUCTURE STEEL STRUCTURE BLOCK WORK PLASTER AND PAINT WORK
  • 2.
    9 10 11 12 13 14 15 16 17 18 19 20 21 COMMISSIONING FIREFIGHTING WORKS WATER SUPPLY MISCELLANEOUSWORK SITE CLEANING & HANDOVER TILE & MARBLE WORK PLUMBING WORK JOINERY WORK EXTERNAL FINISHING AC WORKS INFRASTRUCTURE WORK ALUMINIUM WORK ELECTRICAL WORK