Dynamics CRM Implementation
Weekly Status Report
July 2, 2015
Phase 1 – Original Schedule w/ Variation Timeline
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Initiation &
Planning
12/01 –
01/30
Requirements / Data Prep
02/02 – 03/27
Pre-Production QA / UAT
06/22– 08/21
GO-
LIVE
11/13
Final UAT
08/24– 10/30
Migration Staging / Dry Runs
04/13– 06/19
Variation 1
<=15 days
Analysis Design Develop Deploy Ops
Initiation &
Planning
02/02 –
2/28
Installation
Set Up
03/02 –
03/31
Soft Launch /
Beta Testing /
Workflows
5/01 – 6/05
Produ
ction
10/15
Pre Production UAT/
Integration CRM
6/08 – 07/31
Pre-Launch
/ Code
Freeze
04/01 –
04/30
Final UAT w/ CRM
8/03 - 10/09
Variation 2
<=10 days
Variation 3
<=15 days
DYNAMICS CRM
BYTE LOS
Phase 1 – Updated Schedule w/ Variation Timeline
Jun Jul Aug Sep Oct Nov
GO-LIVE
10/16
UAT / Training
9/14 – 10/16
Config / Migration / Dry Runs
7/13 – 9/11
Develop Deploy Ops
Initiation & Planning
6/30 – 7/12
Eloqua Kickoff / Integration
Testing
7/13 – 8/21
UAT/ Training
8/24– 10/16
DYNAMICS CRM
ELOQUA
GO-LIVE
10/16
CRM Project – Architecture
 up
 up
 up
CRM Project – Weekly Status
CRM Project – Weekly Status
Reference Log Sheet

More Related Content

Viewers also liked

CRM Desktop Typical Implementation Project by InvisibleCRM
CRM Desktop Typical Implementation Project by InvisibleCRMCRM Desktop Typical Implementation Project by InvisibleCRM
CRM Desktop Typical Implementation Project by InvisibleCRMInvisibleCRM
 
Writing a Report (Tips and Sample of Reports)
Writing a Report (Tips and Sample of Reports)Writing a Report (Tips and Sample of Reports)
Writing a Report (Tips and Sample of Reports)Po Po Tun
 
The Top Skills That Can Get You Hired in 2017
The Top Skills That Can Get You Hired in 2017The Top Skills That Can Get You Hired in 2017
The Top Skills That Can Get You Hired in 2017LinkedIn
 

Viewers also liked (6)

Crm assessment template
Crm assessment templateCrm assessment template
Crm assessment template
 
CRM Desktop Typical Implementation Project by InvisibleCRM
CRM Desktop Typical Implementation Project by InvisibleCRMCRM Desktop Typical Implementation Project by InvisibleCRM
CRM Desktop Typical Implementation Project by InvisibleCRM
 
How to Write a Weekly Report
How to Write a Weekly ReportHow to Write a Weekly Report
How to Write a Weekly Report
 
Writing a Report (Tips and Sample of Reports)
Writing a Report (Tips and Sample of Reports)Writing a Report (Tips and Sample of Reports)
Writing a Report (Tips and Sample of Reports)
 
CRM Strategy and Implementation
CRM Strategy and ImplementationCRM Strategy and Implementation
CRM Strategy and Implementation
 
The Top Skills That Can Get You Hired in 2017
The Top Skills That Can Get You Hired in 2017The Top Skills That Can Get You Hired in 2017
The Top Skills That Can Get You Hired in 2017
 

Similar to Weekly Project Status Report_070215

Similar to Weekly Project Status Report_070215 (9)

R squared weekly-status_03012010[1]
R squared  weekly-status_03012010[1]R squared  weekly-status_03012010[1]
R squared weekly-status_03012010[1]
 
Acbsi pacing chart 2nd semester -14-15
Acbsi pacing chart   2nd semester -14-15Acbsi pacing chart   2nd semester -14-15
Acbsi pacing chart 2nd semester -14-15
 
SOC-2 Compliance Status Report sample v10.0
SOC-2 Compliance Status Report   sample v10.0SOC-2 Compliance Status Report   sample v10.0
SOC-2 Compliance Status Report sample v10.0
 
Rovi bit dashboard
Rovi bit dashboard Rovi bit dashboard
Rovi bit dashboard
 
Software Management in a Lean and Agile World
Software Management in a Lean and Agile WorldSoftware Management in a Lean and Agile World
Software Management in a Lean and Agile World
 
Projects Handled
Projects HandledProjects Handled
Projects Handled
 
DRAFT LHD-2 PEMT SKED V - Portfolio Example
DRAFT LHD-2 PEMT SKED V - Portfolio ExampleDRAFT LHD-2 PEMT SKED V - Portfolio Example
DRAFT LHD-2 PEMT SKED V - Portfolio Example
 
Project Portfolio Francois Bourcier
Project Portfolio Francois BourcierProject Portfolio Francois Bourcier
Project Portfolio Francois Bourcier
 
CPM155_154.pptx
CPM155_154.pptxCPM155_154.pptx
CPM155_154.pptx
 

Weekly Project Status Report_070215

  • 1. Dynamics CRM Implementation Weekly Status Report July 2, 2015
  • 2. Phase 1 – Original Schedule w/ Variation Timeline Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Initiation & Planning 12/01 – 01/30 Requirements / Data Prep 02/02 – 03/27 Pre-Production QA / UAT 06/22– 08/21 GO- LIVE 11/13 Final UAT 08/24– 10/30 Migration Staging / Dry Runs 04/13– 06/19 Variation 1 <=15 days Analysis Design Develop Deploy Ops Initiation & Planning 02/02 – 2/28 Installation Set Up 03/02 – 03/31 Soft Launch / Beta Testing / Workflows 5/01 – 6/05 Produ ction 10/15 Pre Production UAT/ Integration CRM 6/08 – 07/31 Pre-Launch / Code Freeze 04/01 – 04/30 Final UAT w/ CRM 8/03 - 10/09 Variation 2 <=10 days Variation 3 <=15 days DYNAMICS CRM BYTE LOS
  • 3. Phase 1 – Updated Schedule w/ Variation Timeline Jun Jul Aug Sep Oct Nov GO-LIVE 10/16 UAT / Training 9/14 – 10/16 Config / Migration / Dry Runs 7/13 – 9/11 Develop Deploy Ops Initiation & Planning 6/30 – 7/12 Eloqua Kickoff / Integration Testing 7/13 – 8/21 UAT/ Training 8/24– 10/16 DYNAMICS CRM ELOQUA GO-LIVE 10/16
  • 4. CRM Project – Architecture  up  up  up
  • 5. CRM Project – Weekly Status
  • 6. CRM Project – Weekly Status Reference Log Sheet