The Norwegian Road PPP Programme
– Experiences with the E18 Project –
Dirk Söhngen, Co-CEO Bilfinger Berger Project Investments, Berlin, 24. April 2012
• National Transport Plan 2002-2011 was approved
in February 2001
• The projects were identified as pilot projects
• PPP was meant to increase efficiency in the
implementation of major projects
• All three projects were implemented and opened to
traffic latest August 2009
• Important project criteria:
o Availability
o Operation and Maintenance
o Traffic Safety
Concept and targets
page 2
Implementation
page 3
Project E39 E39 E18
Sponsors Skanska,
Laing
Veidekke,
Sundt
Pihl, Sundt,
Bilfinger
Berger
Construction
Volume
(in EUR)
170 Mio. 155 Mio. 400 Mio.
Implementation
period
2003-
2005
2004-
2006
2006-
2009
• Efficiency improvements achieved?
o Construction time
o Construction price
o Traffic Safety
o Risk allocation
• Outlook?
First conclusions and outlook
page 4

The Norwegian Road PPP Programme - Söhngen.pdf

  • 1.
    The Norwegian RoadPPP Programme – Experiences with the E18 Project – Dirk Söhngen, Co-CEO Bilfinger Berger Project Investments, Berlin, 24. April 2012
  • 2.
    • National TransportPlan 2002-2011 was approved in February 2001 • The projects were identified as pilot projects • PPP was meant to increase efficiency in the implementation of major projects • All three projects were implemented and opened to traffic latest August 2009 • Important project criteria: o Availability o Operation and Maintenance o Traffic Safety Concept and targets page 2
  • 3.
    Implementation page 3 Project E39E39 E18 Sponsors Skanska, Laing Veidekke, Sundt Pihl, Sundt, Bilfinger Berger Construction Volume (in EUR) 170 Mio. 155 Mio. 400 Mio. Implementation period 2003- 2005 2004- 2006 2006- 2009
  • 4.
    • Efficiency improvementsachieved? o Construction time o Construction price o Traffic Safety o Risk allocation • Outlook? First conclusions and outlook page 4