SlideShare a Scribd company logo
1 of 14
Download to read offline
Opening Remarks – Technical Briefing (21/3/2011)

1. Current Situation
We are seeing some steady improvements, but the overall situation at the Fukushima Daiichi
nuclear power plant remains very serious. High levels of contamination have been measured
in the locality of the plant.
The restoration of electrical power to Unit 2, which we reported yesterday, is good news. AC
power is available and an electrical load check to pumps etc. is currently on-going. Work on
the restoration of off-site power to Units 3 and 4 is also underway.
Seawater is still being injected into the reactor pressure vessels of Units 1, 2 and 3.
Pressure in the reactor pressure vessel and the containment vessel drywell at Unit 3, which
had been rising yesterday, has again fallen.
Water is being sprayed periodically into the spent fuel pools at Units 2, 3 and 4. The Agency
still lacks data on water levels and temperatures in the spent fuel pools at Units 1, 2, 3 and 4.
Following the restoration of cooling at Units 5 and 6, temperatures in the spent fuel pools
continue to decline.


2. Radiation Monitoring
As I reported yesterday, the IAEA radiation monitoring team took measurements at distances
from 56 to 200 km from the Fukushima nuclear power plant. At two locations in Fukushima
Prefecture gamma dose rate and beta-gamma contamination measurements have been
repeated. These measurements showed high beta-gamma contamination levels. Measurements
by the IAEA and the Japanese authorities were taken at the same time and locations. The
Japanese and independent IAEA measurements gave comparable results.
Measurement of gamma dose rate and beta-gamma contamination were taken on 20 March at
more locations. The dose-rate results ranged from 2-160 microsieverts per hour, which
compares to a typical natural background level of around 0.1 microsieverts per hour. High-
levels of beta-gamma contamination have been measured between 16-58 km from the plant.
Available results show contamination ranging from 0.2-0.9 MBq per square metre.
Further measurements are needed to assess possible contamination beyond the area currently
monitored – both closer to the facility and further way. We have no contamination
measurements showing that that contamination levels are high at greater distances than 58 km
from the plant, but this cannot be excluded.
I have no further information available regarding the measurement of alpha radiation. As I
reported yesterday, from the measurements taken within the evacuation zone (20 km), no
significant alpha radiation had been detected at that time.
In the coming days, the IAEA monitoring team will continue to take measurements in the
Fukushima prefecture. We are seeking data from Japan on radioactivity contamination
measurements for the rest of Japan.
Some results on the monitoring of foodstuffs have been made available by Japan to the IAEA
and FAO. Results provided recently by the Japanese authorities range up to 55,000 Bq per kg
of I-131 in samples of Spinach taken in in the Ibaraki Prefecture. These high values are
significantly above Japanese limits for restricting food consumption (i.e. 2,000 Bq/kg). I
understand that the Japanese Government is actively considering relevant precautionary
measures and has instructed four Prefectures (Ibaraki, Totigi, Gunma, Fukushima) to refrain,
for the time being, from distributing two types of vegetables (spinach and kakina) from these
Prefectures and milk from Fukshima.


3. Agency Activities
The Director General briefed the Board of Governors today on the outcome of his visit to
Tokyo.
Unit                        1                       2                        3                       4

Power (MWe /MWth)                  460/1380                 784/2381               784/2381                784/2381
Type of Reactor                    BWR-3                    BWR-4                   BWR-4                     BWR-4

                          In service – auto        In service – auto        In service – auto
Status at time of EQ                                                                                 Outage
                          shutdown                 shutdown                 shutdown

Core and fuel integrity   Damaged                  Damaged                  Damaged                  No fuel in the Reactor

RPV & RCS integrity       Unknown                  Unknown                  Unknown
                                                                                                     Not applicable due to
Containment integrity     Not Damaged              Damage suspected         No information           outage plant status

                                                   AC Power available –
AC Power                  Substation connected                              Not available            Not available
                                                   Load check is ongoing

Building                  Severe damage            Slight damage            Severe damage            Severe damage

                          Around half of Fuel is   Around half of Fuel is   Around half of Fuel is
Water level of RPV
                          uncovered (Stable)       uncovered (Stable)       uncovered (Stable)

Pressure of RPV           Stabilized               Unreliable Readings      Decreased                Not applicable due to
CV Pressure Drywell       Stable                   Stable                   Decreased                outage plant status

Water injection to RPV    Seawater                 Seawater                 Seawater

Water injection to CV     No information           No information           No information
                                                   Periodic spraying from   Periodic spraying from   Periodic spraying
Spent Fuel Pool Status    No information
                                                   outside                  outside                  from outside
3/21/2011 07:00 AM
Unit                            5                           6
  Power                                 784/2381                    1100/3293

  Type of Reactor                          BWR-4                       BWR-5

  Status at the EQ occurred   Outage                      Outage

  Core and Fuel               Cold Shutdown               Cold Shutdown                   Severe condition
  RPV & RCS integrity         Intact                      Intact

  Containment int.            No damage expected          No damage expected              Concern
  AC Power                    2nd Emergency diesel from   Emergency diesel
                              Unit 6                      Off-site power being restored   No immediate
                                                                                          concern
  Building                    No damage reported          No damage reported

  Water level of RPV          Above fuel                  Above fuel

  Pressure of RPV             Cooling restored            Cooling restored

  Containment Pressure        No information              No information

  Water injection to RPV      Injection in Progress       Injection in Progress

  Water injection to CV       Not needed now              Not needed now

  Spent Fuel Pool Status      Cooling restored            Cooling restored


3/21/2011 07:00 AM
Technical Briefing on the
Radiological Situation in Japan



      21 March 2011




                   IAEA
         International Atomic Energy Agency
Daiichi NPP On-Site gamma dose rate
(updated)




   IAEA
Evolution of gamma dose rates after radioactive releases
surrounding Daiichi NPP since 15 March 2011
(Selected monitoring posts)




      IAEA
                              Information provided by MEXT-Japan
Gamma dose rates North of Daiichi NPP
Japan (microSv/h), 15-20 March




   IAEA
Gamma dose rates between Tokyo and Daiichi
NPP (microSv/h), 15-20 March




   IAEA
Gamma dose rates close to Tokyo, (microSv/h),
15-20 March




   IAEA
Measurements by the IAEA monitoring team on
 20 March 2011
      Location         Distanc   Time, JST   Dose rate    Alpha        beta +             Contamination
                         e to      (24h)      micro      (counts      gamma        Becquerel per      Mega‐
                        NPP                    Sv/h        per      (counts per        cm 2         Becquerel 
                        (km)                             second)      second)                         per m2
Mini Stop near 
Kawamata Hospital        58       10:32         5.7         0          3440           58.5           0.585
Nihonmatsu‐Towa‐
cho                      52       10:55         4.2         0          2368           40.3           0.403
Towa‐cho Michino‐
eki                      49       11:05         3.1         0          1270           21.6           0.216
At crossing of Road 
349 and Road 50          46       11:30         1.9         0          1973           33.5           0.335
Suichuji bus stop        43       11:42         2           0          2260           38.4           0.384
JA Tamura                39       11:57         2.6         0          2265           38.5           0.385
Border between 
Kuzuo‐mura and           34       12:09        11.7         0          3152           53.6           0.536
Tamura‐shi
Kuzuo village office     29       13:47        11.2         0          4874           82.9           0.829
Road 50                  28       15:25         7.2         0          5030           85.5           0.855
Border between 
Namie town and           20       14:55        161          0        overload          na              na
Kuzuo village
Gate of Ogaki‐dam 
management office        16       14:31         83          0        overload          na              na

            IAEA                                                                                                 7
Measurements by the IAEA monitoring team on
 19 March 2011
Location          Time,  Distance     Dose      Alpha      beta +          Contamination
                   JST     from        rate    (counts    gamma
                  (24h) Fukushim     (micro      per    (counts per 
                             a        Sv/h)    second)    second)      Becquerel         Mega‐
                          Daiichi                                       per cm2         Becquerel 
                         NPP (km)                                                        per m2

    Saitama 
   Prefecture
Hasuda            17:00    200       0.04         0         27             ‐        -
     Tochigi  
   Prefecture 
Sano              17:27    180       0.16        0          150           2.5             0.03
Kamikochi         18:17    140       0.18      0.2 *)       240          4.1              0.04
Nasukogem         20:17    220       2.9         0         2300          39.3             0.39
   Fukushimi 
   Prefecture
Abukuma           21:05     60        3.5      0.08*)      3750           64              0.64
Gohyakugawa       21:58     56         3          0        3900          66.3             0.66
           IAEA                                                                                      8
Maps with prefectures where foodstuffs
were measured




   IAEA                                  9
Ibaraki: Results from measurements of
radionuclides in foodstuffs
  Name        Sampling Date     Spniach & other leafy vegs       Spring Onion               Milk (unprocessed)        UNITS
                          JST      I‐131         Cs‐137      I‐131         Cs‐137   I‐131           Cs‐137     Cs‐134
Kitaibaraki            18‐Mar    24000           690         350           ND        ‐               ‐          ‐    (Bq/kg)
Kamisu                 17‐Mar      56            ND           ‐             ‐        ‐               ‐          ‐    (Bq/kg)
Yachiyo                17‐Mar      78             21          ‐             ‐        ‐               ‐          ‐    (Bq/kg)
Takahagi               19‐Mar    11,000          586          ‐             ‐        ‐               ‐          ‐    (Bq/kg)
Hokota                 19‐Mar     1900            71          ‐             ‐        ‐               ‐          ‐    (Bq/kg)
Hokota                 19‐Mar     480             81          ‐             ‐        ‐               ‐          ‐    (Bq/kg)
Hitachi 
City                   18‐Mar    54100          1931          ‐              ‐       ‐               ‐          ‐    (Bq/kg)
Hitachi 
City                   18‐Mar    25200          1105          ‐              ‐       ‐               ‐          ‐    (Bq/kg)
Hitachi 
Omiya                  18‐Mar    19200          1040          ‐              ‐       ‐               ‐          ‐    (Bq/kg)
Hitachi 
Omiya                  18‐Mar    17800           908          ‐             ‐        ‐               ‐          ‐    (Bq/kg)
Naka                   18‐Mar    16100           911          ‐             ‐        ‐               ‐          ‐    (Bq/kg)
Naka                   18‐Mar    13500           966          ‐             ‐        ‐               ‐          ‐    (Bq/kg)
Hokota                 18‐Mar    7710            407         356            9        ‐               ‐          ‐    (Bq/kg)
Moriya                 18‐Mar    2100            121         590           21        ‐               ‐          ‐    (Bq/kg)
Moriya                 18‐Mar      26            ND           ‐             ‐        ‐               ‐          ‐    (Bq/kg)
Moriya                 18‐Mar     ND             ND           ‐             ‐        ‐               ‐          ‐    (Bq/kg)
Koga                   18‐Mar    4200            270          ‐             ‐        ‐               ‐          ‐    (Bq/kg)
Sakai                  18‐Mar       ‐             ‐          140           ND        ‐               ‐          ‐    (Bq/kg)
Sakai
          IAEA         18‐Mar       ‐             ‐          120           ND        ‐               ‐          ‐    (Bq/kg)

More Related Content

Similar to Technical Briefing on Radiological Situation in Japan - 21 March 2011

Summaryreactorunitstatus120411 110412123744-phpapp02
Summaryreactorunitstatus120411 110412123744-phpapp02Summaryreactorunitstatus120411 110412123744-phpapp02
Summaryreactorunitstatus120411 110412123744-phpapp02dungeon_keeper
 
Fukushima Daiichi Nuclear Power Station Accident April19 2011
Fukushima Daiichi Nuclear Power Station  Accident April19 2011Fukushima Daiichi Nuclear Power Station  Accident April19 2011
Fukushima Daiichi Nuclear Power Station Accident April19 2011Joe Miller
 
Summary of the Status of Reactor Units in Fukushima Daiichi at 19 March, 12:...
 Summary of the Status of Reactor Units in Fukushima Daiichi at 19 March, 12:... Summary of the Status of Reactor Units in Fukushima Daiichi at 19 March, 12:...
Summary of the Status of Reactor Units in Fukushima Daiichi at 19 March, 12:...International Atomic Energy Agency
 
30, 31st July 2012 - The India Blackout
30, 31st July 2012 - The India Blackout30, 31st July 2012 - The India Blackout
30, 31st July 2012 - The India Blackoutgiridaran123
 
Condition based monitoring
Condition based monitoringCondition based monitoring
Condition based monitoringNiraj Agrawal
 
Fukushima Daiichi Byu Presentation
Fukushima Daiichi Byu PresentationFukushima Daiichi Byu Presentation
Fukushima Daiichi Byu PresentationJoe Miller
 
20110327 Fukushima Earth Quake Influence(Fepc)
20110327 Fukushima Earth Quake  Influence(Fepc)20110327 Fukushima Earth Quake  Influence(Fepc)
20110327 Fukushima Earth Quake Influence(Fepc)Martin Supancic
 
Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching TransientsTransformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transientsmichaeljmack
 
INTERNSHIP REPORT-ORIGINAL (Autosaved)
INTERNSHIP REPORT-ORIGINAL (Autosaved)INTERNSHIP REPORT-ORIGINAL (Autosaved)
INTERNSHIP REPORT-ORIGINAL (Autosaved)Asafak Husain
 

Similar to Technical Briefing on Radiological Situation in Japan - 21 March 2011 (18)

Summary of reactor unit status at of 24 March-0600 UTC
Summary of reactor unit status at of 24 March-0600 UTCSummary of reactor unit status at of 24 March-0600 UTC
Summary of reactor unit status at of 24 March-0600 UTC
 
Summaryreactorunitstatus120411 110412123744-phpapp02
Summaryreactorunitstatus120411 110412123744-phpapp02Summaryreactorunitstatus120411 110412123744-phpapp02
Summaryreactorunitstatus120411 110412123744-phpapp02
 
Fukushima Daiichi Nuclear Power Station Accident April19 2011
Fukushima Daiichi Nuclear Power Station  Accident April19 2011Fukushima Daiichi Nuclear Power Station  Accident April19 2011
Fukushima Daiichi Nuclear Power Station Accident April19 2011
 
Summary of the Status of Reactor Units in Fukushima Daiichi at 19 March, 12:...
 Summary of the Status of Reactor Units in Fukushima Daiichi at 19 March, 12:... Summary of the Status of Reactor Units in Fukushima Daiichi at 19 March, 12:...
Summary of the Status of Reactor Units in Fukushima Daiichi at 19 March, 12:...
 
30, 31st July 2012 - The India Blackout
30, 31st July 2012 - The India Blackout30, 31st July 2012 - The India Blackout
30, 31st July 2012 - The India Blackout
 
Condition based monitoring
Condition based monitoringCondition based monitoring
Condition based monitoring
 
Fukushima Daiichi Byu Presentation
Fukushima Daiichi Byu PresentationFukushima Daiichi Byu Presentation
Fukushima Daiichi Byu Presentation
 
20110327 Fukushima Earth Quake Influence(Fepc)
20110327 Fukushima Earth Quake  Influence(Fepc)20110327 Fukushima Earth Quake  Influence(Fepc)
20110327 Fukushima Earth Quake Influence(Fepc)
 
F12np gaiyou e
F12np gaiyou eF12np gaiyou e
F12np gaiyou e
 
E atomizer explosion 2013.10.26
E atomizer explosion 2013.10.26E atomizer explosion 2013.10.26
E atomizer explosion 2013.10.26
 
(08) rectifiers
(08) rectifiers(08) rectifiers
(08) rectifiers
 
Power System Restoration
Power System RestorationPower System Restoration
Power System Restoration
 
Southern California Edison
Southern California EdisonSouthern California Edison
Southern California Edison
 
BHEL CCDP audit
BHEL CCDP auditBHEL CCDP audit
BHEL CCDP audit
 
WHO final
WHO  finalWHO  final
WHO final
 
Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching TransientsTransformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transients
 
INTERNSHIP REPORT-ORIGINAL (Autosaved)
INTERNSHIP REPORT-ORIGINAL (Autosaved)INTERNSHIP REPORT-ORIGINAL (Autosaved)
INTERNSHIP REPORT-ORIGINAL (Autosaved)
 
Blackout
BlackoutBlackout
Blackout
 

More from International Atomic Energy Agency

Radiological Monitoring and Consequences of Fukushima Nuclear Accident (2 Jun...
Radiological Monitoring and Consequences of Fukushima Nuclear Accident (2 Jun...Radiological Monitoring and Consequences of Fukushima Nuclear Accident (2 Jun...
Radiological Monitoring and Consequences of Fukushima Nuclear Accident (2 Jun...International Atomic Energy Agency
 
Marine Environment Monitoring of Fukushima Nuclear Accident (2 June 2011)
Marine Environment Monitoring of Fukushima Nuclear Accident (2 June 2011)Marine Environment Monitoring of Fukushima Nuclear Accident (2 June 2011)
Marine Environment Monitoring of Fukushima Nuclear Accident (2 June 2011)International Atomic Energy Agency
 
Table 4: Unit 4 Reactor: Fukushima Daiichi Nuclear Power Plant - 18 May 2011
Table 4: Unit 4 Reactor: Fukushima Daiichi Nuclear Power Plant - 18 May 2011Table 4: Unit 4 Reactor: Fukushima Daiichi Nuclear Power Plant - 18 May 2011
Table 4: Unit 4 Reactor: Fukushima Daiichi Nuclear Power Plant - 18 May 2011International Atomic Energy Agency
 
Table 2: Unit 2 Reactor: Fukushima Daiichi Nuclear Power Plant - 18 May 2011
Table 2: Unit 2 Reactor: Fukushima Daiichi Nuclear Power Plant - 18 May 2011Table 2: Unit 2 Reactor: Fukushima Daiichi Nuclear Power Plant - 18 May 2011
Table 2: Unit 2 Reactor: Fukushima Daiichi Nuclear Power Plant - 18 May 2011International Atomic Energy Agency
 
Table 1: Unit 1 Reactor: Fukushima Daiichi Nuclear Power Plant - 18 May 2011
Table 1: Unit 1 Reactor: Fukushima Daiichi Nuclear Power Plant - 18 May 2011Table 1: Unit 1 Reactor: Fukushima Daiichi Nuclear Power Plant - 18 May 2011
Table 1: Unit 1 Reactor: Fukushima Daiichi Nuclear Power Plant - 18 May 2011International Atomic Energy Agency
 
Table 3: Unit 3 Reactor: Fukushima Daiichi Nuclear Power Plant - 11 May 2011
Table 3: Unit 3 Reactor: Fukushima Daiichi Nuclear Power Plant - 11 May 2011Table 3: Unit 3 Reactor: Fukushima Daiichi Nuclear Power Plant - 11 May 2011
Table 3: Unit 3 Reactor: Fukushima Daiichi Nuclear Power Plant - 11 May 2011International Atomic Energy Agency
 
Table 2: Unit 2 Reactor: Fukushima Daiichi Nuclear Power Plant - 11 May 2011
Table 2: Unit 2 Reactor: Fukushima Daiichi Nuclear Power Plant - 11 May 2011 Table 2: Unit 2 Reactor: Fukushima Daiichi Nuclear Power Plant - 11 May 2011
Table 2: Unit 2 Reactor: Fukushima Daiichi Nuclear Power Plant - 11 May 2011 International Atomic Energy Agency
 
Table 1: Unit 1 Reactor: Fukushima Daiichi Nuclear Power Plant - 11 May 2011
Table 1: Unit 1 Reactor: Fukushima Daiichi Nuclear Power Plant - 11 May 2011 Table 1: Unit 1 Reactor: Fukushima Daiichi Nuclear Power Plant - 11 May 2011
Table 1: Unit 1 Reactor: Fukushima Daiichi Nuclear Power Plant - 11 May 2011 International Atomic Energy Agency
 
Tc Programme - Delivering Results for Peace and Development (Russian)
Tc Programme - Delivering Results for Peace and Development (Russian)Tc Programme - Delivering Results for Peace and Development (Russian)
Tc Programme - Delivering Results for Peace and Development (Russian)International Atomic Energy Agency
 

More from International Atomic Energy Agency (20)

IAEA Bulletin September 2011
IAEA Bulletin September 2011IAEA Bulletin September 2011
IAEA Bulletin September 2011
 
The IAEA Legal Framework for Nuclear Safety
The IAEA Legal Framework for Nuclear SafetyThe IAEA Legal Framework for Nuclear Safety
The IAEA Legal Framework for Nuclear Safety
 
Radiological Monitoring and Consequences of Fukushima Nuclear Accident (2 Jun...
Radiological Monitoring and Consequences of Fukushima Nuclear Accident (2 Jun...Radiological Monitoring and Consequences of Fukushima Nuclear Accident (2 Jun...
Radiological Monitoring and Consequences of Fukushima Nuclear Accident (2 Jun...
 
Marine Environment Monitoring of Fukushima Nuclear Accident (2 June 2011)
Marine Environment Monitoring of Fukushima Nuclear Accident (2 June 2011)Marine Environment Monitoring of Fukushima Nuclear Accident (2 June 2011)
Marine Environment Monitoring of Fukushima Nuclear Accident (2 June 2011)
 
Summary of Reactor Status (2 June 2011)
Summary of Reactor Status (2 June 2011)Summary of Reactor Status (2 June 2011)
Summary of Reactor Status (2 June 2011)
 
Table 4: Unit 4 Reactor: Fukushima Daiichi Nuclear Power Plant - 18 May 2011
Table 4: Unit 4 Reactor: Fukushima Daiichi Nuclear Power Plant - 18 May 2011Table 4: Unit 4 Reactor: Fukushima Daiichi Nuclear Power Plant - 18 May 2011
Table 4: Unit 4 Reactor: Fukushima Daiichi Nuclear Power Plant - 18 May 2011
 
Table 2: Unit 2 Reactor: Fukushima Daiichi Nuclear Power Plant - 18 May 2011
Table 2: Unit 2 Reactor: Fukushima Daiichi Nuclear Power Plant - 18 May 2011Table 2: Unit 2 Reactor: Fukushima Daiichi Nuclear Power Plant - 18 May 2011
Table 2: Unit 2 Reactor: Fukushima Daiichi Nuclear Power Plant - 18 May 2011
 
Table 1: Unit 1 Reactor: Fukushima Daiichi Nuclear Power Plant - 18 May 2011
Table 1: Unit 1 Reactor: Fukushima Daiichi Nuclear Power Plant - 18 May 2011Table 1: Unit 1 Reactor: Fukushima Daiichi Nuclear Power Plant - 18 May 2011
Table 1: Unit 1 Reactor: Fukushima Daiichi Nuclear Power Plant - 18 May 2011
 
Table 3: Unit 3 Reactor: Fukushima Daiichi Nuclear Power Plant - 11 May 2011
Table 3: Unit 3 Reactor: Fukushima Daiichi Nuclear Power Plant - 11 May 2011Table 3: Unit 3 Reactor: Fukushima Daiichi Nuclear Power Plant - 11 May 2011
Table 3: Unit 3 Reactor: Fukushima Daiichi Nuclear Power Plant - 11 May 2011
 
Table 2: Unit 2 Reactor: Fukushima Daiichi Nuclear Power Plant - 11 May 2011
Table 2: Unit 2 Reactor: Fukushima Daiichi Nuclear Power Plant - 11 May 2011 Table 2: Unit 2 Reactor: Fukushima Daiichi Nuclear Power Plant - 11 May 2011
Table 2: Unit 2 Reactor: Fukushima Daiichi Nuclear Power Plant - 11 May 2011
 
Table 1: Unit 1 Reactor: Fukushima Daiichi Nuclear Power Plant - 11 May 2011
Table 1: Unit 1 Reactor: Fukushima Daiichi Nuclear Power Plant - 11 May 2011 Table 1: Unit 1 Reactor: Fukushima Daiichi Nuclear Power Plant - 11 May 2011
Table 1: Unit 1 Reactor: Fukushima Daiichi Nuclear Power Plant - 11 May 2011
 
Fukushima Marine Environment Monitoring - 5 May 2011
Fukushima Marine Environment Monitoring - 5 May 2011Fukushima Marine Environment Monitoring - 5 May 2011
Fukushima Marine Environment Monitoring - 5 May 2011
 
Radiological Monitoring and Consequences - 5 May 2011
Radiological Monitoring and Consequences - 5 May 2011Radiological Monitoring and Consequences - 5 May 2011
Radiological Monitoring and Consequences - 5 May 2011
 
Summary of reactor unit status - 5 May 2011
Summary of reactor unit status - 5 May 2011Summary of reactor unit status - 5 May 2011
Summary of reactor unit status - 5 May 2011
 
Table summary of reactor unit status at 27-april-0700 utc
Table summary of reactor unit status at 27-april-0700 utcTable summary of reactor unit status at 27-april-0700 utc
Table summary of reactor unit status at 27-april-0700 utc
 
Table summary of reactor unit status at 26-april-0700 utc
Table summary of reactor unit status at 26-april-0700 utcTable summary of reactor unit status at 26-april-0700 utc
Table summary of reactor unit status at 26-april-0700 utc
 
Summary of reactor unit status - 19 April 2011
Summary of reactor unit status - 19 April 2011Summary of reactor unit status - 19 April 2011
Summary of reactor unit status - 19 April 2011
 
Radiological Monitoring and Consequences - 19 April 2011
Radiological Monitoring and Consequences - 19 April 2011Radiological Monitoring and Consequences - 19 April 2011
Radiological Monitoring and Consequences - 19 April 2011
 
Tc Programme - Delivering Results for Peace and Development (Russian)
Tc Programme - Delivering Results for Peace and Development (Russian)Tc Programme - Delivering Results for Peace and Development (Russian)
Tc Programme - Delivering Results for Peace and Development (Russian)
 
Tc programme presentation UN audience
Tc programme presentation UN audienceTc programme presentation UN audience
Tc programme presentation UN audience
 

Technical Briefing on Radiological Situation in Japan - 21 March 2011

  • 1. Opening Remarks – Technical Briefing (21/3/2011) 1. Current Situation We are seeing some steady improvements, but the overall situation at the Fukushima Daiichi nuclear power plant remains very serious. High levels of contamination have been measured in the locality of the plant. The restoration of electrical power to Unit 2, which we reported yesterday, is good news. AC power is available and an electrical load check to pumps etc. is currently on-going. Work on the restoration of off-site power to Units 3 and 4 is also underway. Seawater is still being injected into the reactor pressure vessels of Units 1, 2 and 3. Pressure in the reactor pressure vessel and the containment vessel drywell at Unit 3, which had been rising yesterday, has again fallen. Water is being sprayed periodically into the spent fuel pools at Units 2, 3 and 4. The Agency still lacks data on water levels and temperatures in the spent fuel pools at Units 1, 2, 3 and 4. Following the restoration of cooling at Units 5 and 6, temperatures in the spent fuel pools continue to decline. 2. Radiation Monitoring As I reported yesterday, the IAEA radiation monitoring team took measurements at distances from 56 to 200 km from the Fukushima nuclear power plant. At two locations in Fukushima Prefecture gamma dose rate and beta-gamma contamination measurements have been repeated. These measurements showed high beta-gamma contamination levels. Measurements by the IAEA and the Japanese authorities were taken at the same time and locations. The Japanese and independent IAEA measurements gave comparable results. Measurement of gamma dose rate and beta-gamma contamination were taken on 20 March at more locations. The dose-rate results ranged from 2-160 microsieverts per hour, which compares to a typical natural background level of around 0.1 microsieverts per hour. High- levels of beta-gamma contamination have been measured between 16-58 km from the plant. Available results show contamination ranging from 0.2-0.9 MBq per square metre. Further measurements are needed to assess possible contamination beyond the area currently monitored – both closer to the facility and further way. We have no contamination measurements showing that that contamination levels are high at greater distances than 58 km from the plant, but this cannot be excluded. I have no further information available regarding the measurement of alpha radiation. As I reported yesterday, from the measurements taken within the evacuation zone (20 km), no significant alpha radiation had been detected at that time. In the coming days, the IAEA monitoring team will continue to take measurements in the Fukushima prefecture. We are seeking data from Japan on radioactivity contamination measurements for the rest of Japan.
  • 2. Some results on the monitoring of foodstuffs have been made available by Japan to the IAEA and FAO. Results provided recently by the Japanese authorities range up to 55,000 Bq per kg of I-131 in samples of Spinach taken in in the Ibaraki Prefecture. These high values are significantly above Japanese limits for restricting food consumption (i.e. 2,000 Bq/kg). I understand that the Japanese Government is actively considering relevant precautionary measures and has instructed four Prefectures (Ibaraki, Totigi, Gunma, Fukushima) to refrain, for the time being, from distributing two types of vegetables (spinach and kakina) from these Prefectures and milk from Fukshima. 3. Agency Activities The Director General briefed the Board of Governors today on the outcome of his visit to Tokyo.
  • 3. Unit 1 2 3 4 Power (MWe /MWth) 460/1380 784/2381 784/2381 784/2381 Type of Reactor BWR-3 BWR-4 BWR-4 BWR-4 In service – auto In service – auto In service – auto Status at time of EQ Outage shutdown shutdown shutdown Core and fuel integrity Damaged Damaged Damaged No fuel in the Reactor RPV & RCS integrity Unknown Unknown Unknown Not applicable due to Containment integrity Not Damaged Damage suspected No information outage plant status AC Power available – AC Power Substation connected Not available Not available Load check is ongoing Building Severe damage Slight damage Severe damage Severe damage Around half of Fuel is Around half of Fuel is Around half of Fuel is Water level of RPV uncovered (Stable) uncovered (Stable) uncovered (Stable) Pressure of RPV Stabilized Unreliable Readings Decreased Not applicable due to CV Pressure Drywell Stable Stable Decreased outage plant status Water injection to RPV Seawater Seawater Seawater Water injection to CV No information No information No information Periodic spraying from Periodic spraying from Periodic spraying Spent Fuel Pool Status No information outside outside from outside 3/21/2011 07:00 AM
  • 4. Unit 5 6 Power 784/2381 1100/3293 Type of Reactor BWR-4 BWR-5 Status at the EQ occurred Outage Outage Core and Fuel Cold Shutdown Cold Shutdown Severe condition RPV & RCS integrity Intact Intact Containment int. No damage expected No damage expected Concern AC Power 2nd Emergency diesel from Emergency diesel Unit 6 Off-site power being restored No immediate concern Building No damage reported No damage reported Water level of RPV Above fuel Above fuel Pressure of RPV Cooling restored Cooling restored Containment Pressure No information No information Water injection to RPV Injection in Progress Injection in Progress Water injection to CV Not needed now Not needed now Spent Fuel Pool Status Cooling restored Cooling restored 3/21/2011 07:00 AM
  • 5. Technical Briefing on the Radiological Situation in Japan 21 March 2011 IAEA International Atomic Energy Agency
  • 6. Daiichi NPP On-Site gamma dose rate (updated) IAEA
  • 7. Evolution of gamma dose rates after radioactive releases surrounding Daiichi NPP since 15 March 2011 (Selected monitoring posts) IAEA Information provided by MEXT-Japan
  • 8. Gamma dose rates North of Daiichi NPP Japan (microSv/h), 15-20 March IAEA
  • 9. Gamma dose rates between Tokyo and Daiichi NPP (microSv/h), 15-20 March IAEA
  • 10. Gamma dose rates close to Tokyo, (microSv/h), 15-20 March IAEA
  • 11. Measurements by the IAEA monitoring team on 20 March 2011 Location Distanc Time, JST Dose rate Alpha beta +  Contamination e to (24h) micro  (counts  gamma Becquerel per  Mega‐ NPP Sv/h per  (counts per  cm 2 Becquerel  (km) second) second) per m2 Mini Stop near  Kawamata Hospital 58 10:32 5.7 0 3440 58.5 0.585 Nihonmatsu‐Towa‐ cho 52 10:55 4.2 0 2368 40.3 0.403 Towa‐cho Michino‐ eki 49 11:05 3.1 0 1270 21.6 0.216 At crossing of Road  349 and Road 50 46 11:30 1.9 0 1973 33.5 0.335 Suichuji bus stop 43 11:42 2 0 2260 38.4 0.384 JA Tamura 39 11:57 2.6 0 2265 38.5 0.385 Border between  Kuzuo‐mura and  34 12:09 11.7 0 3152 53.6 0.536 Tamura‐shi Kuzuo village office 29 13:47 11.2 0 4874 82.9 0.829 Road 50 28 15:25 7.2 0 5030 85.5 0.855 Border between  Namie town and  20 14:55 161 0 overload na na Kuzuo village Gate of Ogaki‐dam  management office 16 14:31 83 0 overload na na IAEA 7
  • 12. Measurements by the IAEA monitoring team on 19 March 2011 Location Time,  Distance  Dose  Alpha beta +  Contamination JST from  rate  (counts  gamma (24h) Fukushim (micro  per  (counts per  a Sv/h) second) second) Becquerel  Mega‐ Daiichi  per cm2 Becquerel  NPP (km) per m2 Saitama  Prefecture Hasuda 17:00 200 0.04 0 27 ‐ - Tochigi   Prefecture  Sano 17:27 180 0.16 0 150 2.5 0.03 Kamikochi 18:17 140 0.18 0.2 *) 240 4.1 0.04 Nasukogem 20:17 220 2.9 0 2300 39.3 0.39 Fukushimi  Prefecture Abukuma 21:05 60 3.5 0.08*) 3750 64 0.64 Gohyakugawa 21:58 56 3 0 3900 66.3 0.66 IAEA 8
  • 13. Maps with prefectures where foodstuffs were measured IAEA 9
  • 14. Ibaraki: Results from measurements of radionuclides in foodstuffs Name Sampling Date Spniach & other leafy vegs Spring Onion Milk (unprocessed) UNITS JST I‐131 Cs‐137 I‐131 Cs‐137 I‐131 Cs‐137 Cs‐134 Kitaibaraki 18‐Mar 24000 690 350 ND ‐ ‐ ‐ (Bq/kg) Kamisu 17‐Mar 56 ND ‐ ‐ ‐ ‐ ‐ (Bq/kg) Yachiyo 17‐Mar 78 21 ‐ ‐ ‐ ‐ ‐ (Bq/kg) Takahagi 19‐Mar 11,000 586 ‐ ‐ ‐ ‐ ‐ (Bq/kg) Hokota 19‐Mar 1900 71 ‐ ‐ ‐ ‐ ‐ (Bq/kg) Hokota 19‐Mar 480 81 ‐ ‐ ‐ ‐ ‐ (Bq/kg) Hitachi  City 18‐Mar 54100 1931 ‐ ‐ ‐ ‐ ‐ (Bq/kg) Hitachi  City 18‐Mar 25200 1105 ‐ ‐ ‐ ‐ ‐ (Bq/kg) Hitachi  Omiya 18‐Mar 19200 1040 ‐ ‐ ‐ ‐ ‐ (Bq/kg) Hitachi  Omiya 18‐Mar 17800 908 ‐ ‐ ‐ ‐ ‐ (Bq/kg) Naka 18‐Mar 16100 911 ‐ ‐ ‐ ‐ ‐ (Bq/kg) Naka 18‐Mar 13500 966 ‐ ‐ ‐ ‐ ‐ (Bq/kg) Hokota 18‐Mar 7710 407 356 9 ‐ ‐ ‐ (Bq/kg) Moriya 18‐Mar 2100 121 590 21 ‐ ‐ ‐ (Bq/kg) Moriya 18‐Mar 26 ND ‐ ‐ ‐ ‐ ‐ (Bq/kg) Moriya 18‐Mar ND ND ‐ ‐ ‐ ‐ ‐ (Bq/kg) Koga 18‐Mar 4200 270 ‐ ‐ ‐ ‐ ‐ (Bq/kg) Sakai 18‐Mar ‐ ‐ 140 ND ‐ ‐ ‐ (Bq/kg) Sakai IAEA 18‐Mar ‐ ‐ 120 ND ‐ ‐ ‐ (Bq/kg)