STATEMENT OF WORK ACCOMPLISHED
Contract ID
Contract
Amount
Status
Major
Categoriesof
Work Code
Total AsBuilt
Cost Per Major
Work Category
11-DL-0043Cluster II 2,541,123.17 completed BRC/RCP 100.00%
11-DL-0049Cluster VIII 1,123,278.59 completed MBG 100.00%
11-DL-0050Cluster IX 2,051,126.63 completed MBG 100.00%
11-DL-0088Road Upgrading (gravelto concrete) based ongravelroad strategies,
Traffic Benchmark for upgrading to paved roadstandard (HDM-4 Project Analysis)
Intermittent Sections, NationalSecondary Road, MSR, Jct.Lopez-Buenavista Road,
Lopez, Buenavista
24,261,655.30 completed RCP 100.00%
11-DL-0099Rehab./Reconstruction/Strengthening ofBridges along national roads,
Sumulong Bridge along Daang Maharlika (LZ), Calauag, Quezon
9,026,794.33 completed BRS 100.00%
12-DL-0002Improvement ofFarm toMarketRoad, Brgy. Tiniguiban,Brgy. Buli,
Calauag, Quezon 1,939,831.80 completed RCG/RCP 100.00%
12-DL-0003Improvement ofFarm toMarketRoad, Brgy. Tiniguiban-Brgy.
Lainglaingan, Calauag, Quezon 1,454,851.27 completed RCG/RCP 100.00%
12-DL-0004Improvement ofFarm toMarketRoad, Brgy. Tiniguiban -Brgy. Tamis -
Brgy. Sinag, Calauag,Quezon 2,424,833.12 completed RCG/RCP 100.00%
12-DL-0005Improvement ofFarm toMarketRoad, Brgy. Kigtan -Brgy. Mambaling,
Calauag, Quezon 1,939,844.03 completed RCG/RCP 100.00%
12-DL-0006Improvement ofFarm toMarketRoad, Brgy. Pandanan -Brgy. Sta. Rosa -
Brgy. Maglipad, Calauag, Quezon
1,939,835.26 completed RCP 100.00%
12-DK-0003Concreting ofLucban-Tayabas ProvincialRoad, Brgy. Nagsinamo Portion,
Sitio Centro, Lucban, Quezon 996,907.75 completed RCP 100.00%
11-DJ-0149Rehab/concreting ofCritical Section Brgy.Bukal Surto Buenavista West, 1,928,600.00 completed RCP 100.00%
Candelaria, Quezon
11-DL-0076Road Upgrading (gravelto paved) MSR, Jct.Lopez-Buenavista Road,
KO220+510- KO220+539, Lopez, Quezon 465,122.44 completed RCP 100.00%
Southern Luzon State University: Supply and Installation ofMain CircuitBreaker
(MCB) and Panel(MDP2) at Main Campus Incoming Powerto Power Houseand
ModificationofExisting Panel MDP1,FEEDERS to MTS -1,2,3
1,185,750.00 completed MBG 100.00%
11-DK-0107Repair/MaintenanceofTrafficSafety Devices (pavement markings) along
Famy-RealInfanta Road 354,279.60 completed TEA 100.00%
11-DL-0073PreventiveMaintenance,QuirinoHighway, KO278+000-KO281+182(int.
section) Tagkawayan, Quezon 1,059,605.88 completed RCA 100.00%
11-DK-0124Concreting ofCriticalSection (calumpang-tayabas) Tayabas City
1,927,969.35 completed RCP 100.00%
12-DK-0020Completion ofMulti-Purpose Building atBrgy. Nagsinamo,Lucban,
Quezon 489,779.33 completed MBG 100.00%
12-DL-0030Repair/Improvement ofMulti-Purpose Building, TiniguibanElem. School,
Calauag, Quezon 474,986.08 completed MBG 100.00%
12-DL-0020Concreting ofCritical Section / PortionofFarmto Market Roadin
Quezon: Calauag, Vinas to Tiniguiban,Calauag,Quezon
9,503,258.28 completed RCP 100.00%
12-DL-0021Concreting ofCriticalSection / PortionofFarmto Market Roadin
Quezon: Calauag: Vinas toKapaluhan, Calauag,Quezon
4,843,009.98 completed RCP 100.00%
12-DO-0031 Construction ofLucbanDiversio Road including RROW AcquisitionPhase
II, Quezon Province
4,130,419.10 completed RCP 100.00%
12-DL-0092Road Upgrading (gravelto paved) MSR Jct.,Lopez-Buenavista Road,
Lopez, Quezon
45,375,407.05 completed RCP 100.00%
12-DL-0093Road Upgrading (gravelto paved) MSR Jct.,Lopez-Catanauan Road, 30,154,821.97 completed RCP 100.00%
Lopez, Quezon
13-DK-0155Completion of(4) Storey Eight(8) ClassroomSchoolBuilding at Paaralang
Sekundaryang Lucban (PSL), Lucban, Quezon 4,454,263.47 completed MBG 66.00%
13-DK-0159ConstructionofLucban Diversion Road,Lucban,Quezon, K0123_919.10-
K0123+986.56, K0123+919.10-K0128+691.30 36,752,011.64 completed RCP 95.00%
14-DL-0026Asset PreservationofNational Roads -Rehabilitation / Reconstruction/
Upgrading of Damaged Paved Roads Including DrainaigeBased onPavement
ManagementNational Secondary Roads, 1. MSR Jct. Lopez -Hondagua Port Road
K0221+(-)678 -K0226+000,Lopez, Quezon
8,728,096.59 on-going
14-DL-0047Road Upgrading (Gravel toPaved) Based onGravelRoad Strategies,
Traffic Benchmark for Upgrading to Paved RoadStandard (HDM-4 Project Analysis)
(Intermittent Section), NationalSecondary Roads,6. MSR Jct. -Lopez -Catanauan
Road -K0227+578-K0228+113. 7.MSR Jct.- Lopez catanauanRoad Road-
K0228+245 -K0228+660, 8.MSR Jct-Lopez -Catanauan Road - K0229+087-
K0229+595 amd9. MSR Jct. Lopez -Catanauan Road - K0229+655-K0230+000
45,027,341.17 on-going
14-DP-0003Constructionofbarangay roads,Brgy. Ildefonso,Brgy. St.Rosa,Brgy. San
Benito, Alaminos,Laguna;Brgy. Talaga, Rizal, Laguna, Brgy. Atisan, San Pablo City
9,468,373.35 completed
Widening of NationalRoad Along Lucban-Luisiana Road, Lucban, Quezon K0128+692
- K0130+692
37,508,769.52 on-going

STATEMENT OF WORK ACCOMPLISHED

  • 1.
    STATEMENT OF WORKACCOMPLISHED Contract ID Contract Amount Status Major Categoriesof Work Code Total AsBuilt Cost Per Major Work Category 11-DL-0043Cluster II 2,541,123.17 completed BRC/RCP 100.00% 11-DL-0049Cluster VIII 1,123,278.59 completed MBG 100.00% 11-DL-0050Cluster IX 2,051,126.63 completed MBG 100.00% 11-DL-0088Road Upgrading (gravelto concrete) based ongravelroad strategies, Traffic Benchmark for upgrading to paved roadstandard (HDM-4 Project Analysis) Intermittent Sections, NationalSecondary Road, MSR, Jct.Lopez-Buenavista Road, Lopez, Buenavista 24,261,655.30 completed RCP 100.00% 11-DL-0099Rehab./Reconstruction/Strengthening ofBridges along national roads, Sumulong Bridge along Daang Maharlika (LZ), Calauag, Quezon 9,026,794.33 completed BRS 100.00% 12-DL-0002Improvement ofFarm toMarketRoad, Brgy. Tiniguiban,Brgy. Buli, Calauag, Quezon 1,939,831.80 completed RCG/RCP 100.00% 12-DL-0003Improvement ofFarm toMarketRoad, Brgy. Tiniguiban-Brgy. Lainglaingan, Calauag, Quezon 1,454,851.27 completed RCG/RCP 100.00% 12-DL-0004Improvement ofFarm toMarketRoad, Brgy. Tiniguiban -Brgy. Tamis - Brgy. Sinag, Calauag,Quezon 2,424,833.12 completed RCG/RCP 100.00% 12-DL-0005Improvement ofFarm toMarketRoad, Brgy. Kigtan -Brgy. Mambaling, Calauag, Quezon 1,939,844.03 completed RCG/RCP 100.00% 12-DL-0006Improvement ofFarm toMarketRoad, Brgy. Pandanan -Brgy. Sta. Rosa - Brgy. Maglipad, Calauag, Quezon 1,939,835.26 completed RCP 100.00% 12-DK-0003Concreting ofLucban-Tayabas ProvincialRoad, Brgy. Nagsinamo Portion, Sitio Centro, Lucban, Quezon 996,907.75 completed RCP 100.00% 11-DJ-0149Rehab/concreting ofCritical Section Brgy.Bukal Surto Buenavista West, 1,928,600.00 completed RCP 100.00%
  • 2.
    Candelaria, Quezon 11-DL-0076Road Upgrading(gravelto paved) MSR, Jct.Lopez-Buenavista Road, KO220+510- KO220+539, Lopez, Quezon 465,122.44 completed RCP 100.00% Southern Luzon State University: Supply and Installation ofMain CircuitBreaker (MCB) and Panel(MDP2) at Main Campus Incoming Powerto Power Houseand ModificationofExisting Panel MDP1,FEEDERS to MTS -1,2,3 1,185,750.00 completed MBG 100.00% 11-DK-0107Repair/MaintenanceofTrafficSafety Devices (pavement markings) along Famy-RealInfanta Road 354,279.60 completed TEA 100.00% 11-DL-0073PreventiveMaintenance,QuirinoHighway, KO278+000-KO281+182(int. section) Tagkawayan, Quezon 1,059,605.88 completed RCA 100.00% 11-DK-0124Concreting ofCriticalSection (calumpang-tayabas) Tayabas City 1,927,969.35 completed RCP 100.00% 12-DK-0020Completion ofMulti-Purpose Building atBrgy. Nagsinamo,Lucban, Quezon 489,779.33 completed MBG 100.00% 12-DL-0030Repair/Improvement ofMulti-Purpose Building, TiniguibanElem. School, Calauag, Quezon 474,986.08 completed MBG 100.00% 12-DL-0020Concreting ofCritical Section / PortionofFarmto Market Roadin Quezon: Calauag, Vinas to Tiniguiban,Calauag,Quezon 9,503,258.28 completed RCP 100.00% 12-DL-0021Concreting ofCriticalSection / PortionofFarmto Market Roadin Quezon: Calauag: Vinas toKapaluhan, Calauag,Quezon 4,843,009.98 completed RCP 100.00% 12-DO-0031 Construction ofLucbanDiversio Road including RROW AcquisitionPhase II, Quezon Province 4,130,419.10 completed RCP 100.00% 12-DL-0092Road Upgrading (gravelto paved) MSR Jct.,Lopez-Buenavista Road, Lopez, Quezon 45,375,407.05 completed RCP 100.00% 12-DL-0093Road Upgrading (gravelto paved) MSR Jct.,Lopez-Catanauan Road, 30,154,821.97 completed RCP 100.00%
  • 3.
    Lopez, Quezon 13-DK-0155Completion of(4)Storey Eight(8) ClassroomSchoolBuilding at Paaralang Sekundaryang Lucban (PSL), Lucban, Quezon 4,454,263.47 completed MBG 66.00% 13-DK-0159ConstructionofLucban Diversion Road,Lucban,Quezon, K0123_919.10- K0123+986.56, K0123+919.10-K0128+691.30 36,752,011.64 completed RCP 95.00% 14-DL-0026Asset PreservationofNational Roads -Rehabilitation / Reconstruction/ Upgrading of Damaged Paved Roads Including DrainaigeBased onPavement ManagementNational Secondary Roads, 1. MSR Jct. Lopez -Hondagua Port Road K0221+(-)678 -K0226+000,Lopez, Quezon 8,728,096.59 on-going 14-DL-0047Road Upgrading (Gravel toPaved) Based onGravelRoad Strategies, Traffic Benchmark for Upgrading to Paved RoadStandard (HDM-4 Project Analysis) (Intermittent Section), NationalSecondary Roads,6. MSR Jct. -Lopez -Catanauan Road -K0227+578-K0228+113. 7.MSR Jct.- Lopez catanauanRoad Road- K0228+245 -K0228+660, 8.MSR Jct-Lopez -Catanauan Road - K0229+087- K0229+595 amd9. MSR Jct. Lopez -Catanauan Road - K0229+655-K0230+000 45,027,341.17 on-going 14-DP-0003Constructionofbarangay roads,Brgy. Ildefonso,Brgy. St.Rosa,Brgy. San Benito, Alaminos,Laguna;Brgy. Talaga, Rizal, Laguna, Brgy. Atisan, San Pablo City 9,468,373.35 completed Widening of NationalRoad Along Lucban-Luisiana Road, Lucban, Quezon K0128+692 - K0130+692 37,508,769.52 on-going