SlideShare a Scribd company logo
ISE515 Engineering Project
Management
Gayatri Vilas Nilangekar
Changda Ren
Yanli Tang
Huijian Tian
Xue Yang
Siege Engine Project - Trebuchet
CDR-Team 3
CDR Outline
Requirements	summary
SOW,	WBS,	Schedule,	Cost,	CV,	SV
Engineering	Design	Layout
Risk	Management
Performance	&	Test	Results
Lessons	Learned
Requirements Summary
1. Build a model siege engine to enter the new weapons competition for William’s expedition.
2. The Siege Engine must demonstrate the ability to meet accuracy and repeatability performance goals.
3. The Siege Engine must propel a 7 gram projectile a distance of 15 feet over a 5 foot barrier located 7
feet from the model Siege Engine.
4. The Siege Engine can hit the target in successive 5 attempts.
5. Duration: from January 27, 2015 to April 30, 2015.
(PDR review: February 3; CDR review: April 28;Test: April 30.)
6. Cost: for labor cost: $100 ISE/hour/person (overtime: $150 ISE/hour/person ),
for purchased parts, $1 = $1000 ISE
Statement of work
• Build a model Siege Engine that meet all the requirements before
April 30th . The performance is the most important element of
the triple constraint.
WBS
Task	Name Task	# Duration	(Days) Task	Starts Task	Ends Predecessors Resource	Name Resource	Rate	($ISE)
Materials	Rate	
($ISE)
Design 1 6 2015/1/28 2015/2/6
Concept	finalising 1.1 1 2015/1/28 2015/1/28 All	five	team	members 1,000
Initial	sketch	and	analysis 1.2 2 2015/1/29 2015/1/30 1.1 Gayatri,	Huijian 800
Create	a	parts	list 1.3 1 2015/1/29 2015/1/29 1.2 Yanli 200
Finalising	the	material 1.4 1 2015/1/30 2015/1/30 1.3 Yanli 200
AutoCAD	drawing	(detailed	analysis	with	tolerances) 1.5 2 2015/2/4 2015/2/5 1.4 Huijian 400
Design	validation 1.6 1 2015/2/6 2015/2/6 1.5 Huijian 200
Cost	estimate	and	data	compilation 2 2 2015/1/30 2015/2/2 1.1 Xue 400
Fabricate 3 21 2015/2/9 2015/3/26
Identifying	the	tool	requirement 3.1 1 2015/2/9 2015/2/9 1 Yanli 200
Procurement 3.2 3 2015/2/10 2015/2/12
Materials	and	tools	buying 3.2.1 2 2015/2/10 2015/2/11 3.1 Yanli,	Changda 800 70,000
Quality	check	of	materials 3.2.2 1 2015/2/12 2015/2/12 3.2.1 Changda 200
Assembly 3.3 17 2015/3/24 2015/4/15
Fabrication	of	child	parts 3.3.1 4 2015/3/24 2015/3/27 3.2 All	five	team	members 4,000
Subassembly	of	frame 3.3.2 3 2015/3/30 2015/4/1 3.3.1 Gayatri,	Changda,	Xue 1,800
Quality	Check 3.3.3 1 2015/4/2 2015/4/2 3.3.2 Xue 200
Subassembly	of	long	arm 3.3.4 1 2015/4/3 2015/4/3 3.3.3 Gayatri,	Changda,	Xue 600
Quality	check 3.3.5 1 2015/4/6 2015/4/6 3.3.4 Xue 200
Subassembly	of	short	arm 3.3.6 2 2015/4/7 2015/4/8 3.3.5 Gayatri,	Changda,	Xue 1,200
Quality	check 3.3.7 1 2015/4/9 2015/4/9 3.3.6 Changda 200
Final	Assembly 3.3.8 4 2015/4/10 2015/4/15 3.3.7 Gayatri,	Yanli,	Huijian 2,400
Inspection	and	test 4 6 2015/4/16 2015/4/23
Inspection 4.1 1 2015/4/16 2015/4/16 3.3 Yanli 200
Performance	test 4.2 3 2015/4/17 2015/4/21 4.1 All	five	team	members 3,000
Modification	(if	required) 4.3 2 2015/4/22 2015/4/23 4.2 Huijian 400
Operating	manual 4.4 2 2015/4/22 2015/4/23 4.2 Gayatri,	Changda,	Xue,	Yanli 1,600
Weekly	meetings 5 13 Time	depends	on	schedule	of	team	members All	five	team	members 13,000
Task Durations & List of Resources
• Labor	hours/person/day	 =	2
Schedule Baseline Plan – Gantt Chart
• G:	Gayatri;	H:	Huijian;	Y:	Yanli;	C:	Changda;	X:	Xue
• All:	Gayatri,	Huijian,	Yanli,	Changda,	Xue
Gantt Chart-Actual
• G:	Gayatri;	H:	Huijian;	Y:	Yanli;	C:	Changda;	X:	Xue
• All:	Gayatri,	Huijian,	Yanli,	Changda,	Xue
Task	Name Task	# Duration	(Days) Task	Starts Task	Ends Predecessors Resource	Name Resource	Rate	($ISE)
Materials	Rate	
($ISE)
Design 1 6 2015/1/28 2015/2/6
Concept	finalising 1.1 1 2015/1/28 2015/1/28 All	five	team	members 1,000
Initial	sketch	and	analysis 1.2 2 2015/1/29 2015/1/30 1.1 Gayatri,	Huijian 800
Create	a	parts	list 1.3 1 2015/1/29 2015/1/29 1.2 Yanli 200
Finalising	the	material 1.4 1 2015/1/30 2015/1/30 1.3 Yanli 200
AutoCAD	drawing	(detailed	analysis	with	tolerances) 1.5 2 2015/2/4 2015/2/5 1.4 Huijian 400
Design	validation 1.6 1 2015/2/6 2015/2/6 1.5 Huijian 200
Cost	estimate	and	data	compilation 2 2 2015/1/30 2015/2/2 1.1 Xue 400
Fabricate 3 21 2015/2/9 2015/3/26
Identifying	the	tool	requirement 3.1 1 2015/2/9 2015/2/9 1 Yanli 200
Procurement 3.2 3 2015/2/10 2015/2/12
Materials	and	tools	buying 3.2.1 2 2015/2/10 2015/2/11 3.1 Yanli,	Changda 800 70,000
Quality	check	of	materials 3.2.2 1 2015/2/12 2015/2/12 3.2.1 Changda 200
Assembly 3.3 17 2015/3/24 2015/4/15
Fabrication	of	child	parts 3.3.1 4 2015/3/24 2015/3/27 3.2 All	five	team	members 4,000
Subassembly	of	frame 3.3.2 3 2015/3/30 2015/4/1 3.3.1 Gayatri,	Changda,	Xue 1,800
Quality	Check 3.3.3 1 2015/4/2 2015/4/2 3.3.2 Xue 200
Subassembly	of	long	arm 3.3.4 1 2015/4/3 2015/4/3 3.3.3 Gayatri,	Changda,	Xue 600
Quality	check 3.3.5 1 2015/4/6 2015/4/6 3.3.4 Xue 200
Subassembly	of	short	arm 3.3.6 2 2015/4/7 2015/4/8 3.3.5 Gayatri,	Changda,	Xue 1,200
Quality	check 3.3.7 1 2015/4/9 2015/4/9 3.3.6 Changda 200
Final	Assembly 3.3.8 4 2015/4/10 2015/4/15 3.3.7 Gayatri,	Yanli,	Huijian 2,400
Inspection	and	test 4 6 2015/4/16 2015/4/23
Inspection 4.1 1 2015/4/16 2015/4/16 3.3 Yanli 200
Performance	test 4.2 3 2015/4/17 2015/4/21 4.1 All	five	team	members 3,000
Modification	(if	required) 4.3 2 2015/4/22 2015/4/23 4.2 Huijian 400
Operating	manual 4.4 2 2015/4/22 2015/4/23 4.2 Gayatri,	Changda,	Xue,	Yanli 1,600
Weekly	meetings 5 13 Time	depends	on	schedule	of	team	members All	five	team	members 13,000
Cost Baseline
• Labor	hours/person/day	 =	2
Cost Baseline
0
100
200
300
400
500
600
700
800
900
1000
Cost Baseline Graph
Daily	total	cost	
($ISE/100)
Cum	total	cost	
($ISE/100)
Week	ending Weekly	time	spent Total	hrs.
Labor Expenses	
($ISE)
Weekly	cost	
($ISE)
Cum.	cost	($ISE)
($ISE)
Gayatri Changda Yanli Huijian Xue
30-Jan 8	 4	 8	 8	 6	 34	 3,400	 0 3,400	 3,400	
6-Feb 2	 2	 2	 8	 4	 18	 1,800	 70,000	 71,800	 75,200	
13-Feb 2	 8	 8	 2	 2	 22	 2,200	 0	 2,200	 77,400	
20-Feb 2	 2	 2	 2	 2	 10	 1,000	 0	 1,000	 78,400	
27-Feb 2	 2	 2	 2	 2	 10	 1,000	 0	 1,000	 79,400	
6-Mar 2	 2	 2	 2	 2	 10	 1,000	 0	 1,000	 80,400	
13-Mar 2	 2	 2	 2	 2	 10	 1,000	 0	 1,000	 81,400	
20-Mar 2	 2	 2	 2	 2	 10	 1,000	 0	 1,000	 82,400	
27-Mar 10	 10	 10	 10	 10	 50	 5,000	 0	 5,000	 87,400	
3-Apr 10	 10	 2	 2	 12	 36	 3,600	 0	 3,600	 91,000	
10-Apr 8	 8	 4	 4	 8	 32	 3,200	 0	 3,200	 94,200	
17-Apr 10	 4	 12	 10	 4	 40	 4,000	 0	 4,000	 98,200	
24-Apr 10	 10	 10	 10	 10	 50	 5,000	 0	 5,000	 103,200	
Weekly Cost Baseline
Week
ending
Weekly time spent Total hrs.
Labor ($
ISE)
Expen
ses ($)
Expense
s ($ISE)
Weekly
cost
($ISE)
Cum.
cost
($ISE)
Cum.
budget
($ISE)
Variance
Gayatri Changda Yanli Huijian Xue
Jan 30 6 2 6 6 4 24 2400 0 0 2400 2400 3400 1000
Feb 6 2 2 2 8 4 18 1800 0 0 1800 4200 75200 71000
Feb 13 2 2 2 4 2 12 1200 0 0 1200 5400 77400 72000
Feb 20 4 4 5 2 4 19 1900 25.78 25780 27680 33080 78400 45320
Feb 27 2 2 2 2 2 10 1000 0 0 1000 34080 79400 45320
Mar 6 2 2 2 2 2 10 1000 0 0 1000 35080 80400 45320
Mar 13 0 0 0 0 0 0 0 0 0 0 35080 81400 46320
Mar 20 0 0 0 0 0 0 0 0 0 0 35080 82400 47320
Mar 27 4 4 4 4 4 20 2000 0 0 2000 37080 87400 50320
April 3 7 7 7 7 7 35 4250 6.28 6280 10530 47610 91000 43390
April 10 5 5 5 5 5 25 3250 0 0 3250 50860 94200 43340
April 17 5 5 5 5 5 5 3250 0 0 3250 54110 98200 44090
April 24 9 8 8 8 9 42 5200 0 0 5200 59310 103200 43890
Cost – Actual Cost
Cost – Actual Cost
0
20000
40000
60000
80000
100000
120000
Cum.	cost	
Cum.	budget
Variance
Week	1 Week	2	 Week	3	 Week	4	 Week	5	 Week	6	 Week	7	 Week	8	 Week	9	 Week	10	 Week	11	 Week	12 Week	13
Day 5 10 15 20 25 30 35 40 45 50 55 60 64
Plan	Value	($ISE) 2400 3200 74400 74400 74400 74400 74400 74400 78400 81000 83200 86200 90200
Actual	Cost	($ISE) 2400 3200 3400 30880 30880 30880 30880 30880 32880 36050 38300 40050 45250
Earned	Value	($ISE) 2200 3200 3400 30880 30880 30880 30880 30880 32880 36050 37550 37550 45250
CV	=	EV	- AC	($ISE) -200 0 0 0 0 0 0 0 0 0 -750 -2500 0
SV	=	EV	- PV	($ISE) -200 0 -71000 -43520 -43520 -43520 -43520 -43520 -45520 -44950 -45650 -48650 -44950
-3000
-2500
-2000
-1500
-1000
-500
0
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63
Cost	Variance	
SV and CV - Performance (0-100 Rule)
-80000
-70000
-60000
-50000
-40000
-30000
-20000
-10000
0
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63
Schedule	Variance
SV and CV – Analysis
• Week 1: CV and SV are negative because we didn’t count the weekly meeting cost($ISE200)
• Week 2 – Week 10:
CV are zero, because we finished the tasks of second week. But during week 3- Week 8, due to our midterm and spring break,
we didn’t work at that period. At Week 9, we requested for change of schedule baseline and cost baseline, afterwards, we followed
on the schedule of week 9 and week 10.
SV: There is a big variance in week 3, it is because we didn’t buy material as the schedule required. During week 4 – week 8,
there are a constant variance ($ISE43520) because we bought the material at a much lower price than we estimated, the difference
is $ISE43520 . At week 9, the variance becomes bigger, it just because we finished task 3.3.1 with $ISE2000 instead of $ISE4000.
Week 10, because we used less time to finish the tasks than we planned.
• Week 11 – Week 12:
CV - There are two negative variance because we started the tasks of 4.3 and 4.4 ahead of schedule, and finished them on
time. Therefore the time span is longer than our schedule baseline which results the big variance.
SV – During these two weeks, the variances become larger. This is also we started the tasks of 4.3 and 4.4 ahead of
schedule, and finished them on time. Therefore the time span is longer than our schedule baseline which results the big variance.
• Week 13:
CV is zero.
SV is negative because we save a lot of cost than we estimated on the materials buying.
In a word, from SV and CV graphs, our CV and SV are always non-positive. This is because we fall behind the schedule. For the
SV, there is another reason that results in the negative SV, which is our overestimation of our material costs.
Risk Management – the Plan
Task Risk	Event	#	and	
Description
Prob. %	
(A)
Impact	
$ISE	(B)
Risk	Event	
Status	(A	
x B)
Action Owner
Preventive	(Main	
Plan)
Trigger	Point Contingent	(Plan	B)
Concept
Finalizing	&	
Initial	Sketch
1 Design	does	not meet	
requirement	of	client
40% 1,800 720 Use	Matlab to	
simulate	the
throwing	process	
and		calculate	the	
optimal	parameters
Lack	of	experience	in	
mechanical analysis	
and	engineering	design
Re-design Gayatri,	
Huijian
Cost	Estimate	 2 Cost	is	
underestimated
60% 200 120 Sum up	costs	task	by	
task	based	on	WBS
Lack	of practical	
experience
Change the	cost	
baseline	and	
request	approval	
from	client
Xue
Tool	
Requirement	
Identification
3 Incomplete
identification	of	tools
20% 400 80 Identify	the	tools	as	
the	designers’	
specification
Lack	of	communication	
between design	and	
manufacturing	team
Identify	the	
missing	tools	and	
buy	them
Yanli
Materials	and	
Tools Buying
4 Material	is	weak	or	of	
low	quality
20% 5,000 1,000 Research	and	
comparison	of	
different	material
resources
Lack	of	knowledge to	
identify	the	quality	
Buy	new	materials	
with	good	quality
Yanli,	
Changd
a
Assembly 5 Child	parts	or	
subassemblies	 not	
match	design	
specifications
40% 5,300 2,120 Measure	and	cut	as	
the	design’s	
specification
Errors	in	measuring or	
cutting
Fabricate	new
parts	or	change	
design
All	five	
membe
rs
Risk Management – the Steps Taken
• Design: we use Matlab to validate design and decide the tolerance on critical part
• Tools: we looked for additional resources for tools instead of depending on only one resource
• Materials: search for suppliers (bookstore, Home Depot) and finalizing the suppliers based on
quality and cost; bought extra materials in case of manufacturing damage
• Assembly: Extra time allocated to assembly; thorough discussion for any change in design, and
changes in design are for ease of assembly, no change in critical parts
• Schedule: we work extra time; we crash the project; we develop agenda before meeting and follow
up the decided activities
• Monitor and control: we apply project management tools such as inch-stone, EVA to control the
triple constraints of the project
Design Layout (Preliminary Design )
Final Design
Design – Prototype
Trial Distance	to	target	(inch)
1 1.4
2 0
3 0
4 2.1
5 1.9
6 0.7
7 0
8 1.2
9 2.7
10 0
Mean 1.0	
Variance 1.022	
0
1
2
3
4
5
6
7
8
0 1 2 3 4 5 6 7 8 9 10
Distance	/inch
Trial
Evidence That the Trebuchet Meets Requirements
• We recorded a video which will show the performance.
Video Evidence
Performance - Design Evolution
Parameters
Length 1.5m
Height 1m
Weight 2Kg
Projectile 7g
Angle -30°; 45°
Lessons Learned
Project Management aspect
• Team is the core of entire project. We take fully advantage of every team member’s strongpoint and distribute work
package accordingly.(eg, one person is dedicated to monitor project activities is very effective)
• We abide by the control requirements of triple constraint and it is useful.(eg, time - on time, ahead of schedule 10
days; cost – within budget, save 46%; performance – acceptable)
• Project schedule is the critical tool for project success. We should spend more time to build and track schedule so that
better control the progress.
• Developing risk response plan early is important.
• Since the duration of this project is quite long, it is very necessary to develop and maintain the team morale and
harmony.
• It is quite important to distribute the work equally.
• Make sure all team members are bought in and keep everyone updated.
Lessons Learned
Technical Aspect
• We should explore more and make better use of MS project software to control and monitor the entire project.
• Consider the DFMEA (Design for Manufacturing and Assembly) points in initial design.
• Preparation of prototype to identify tools and manufacturing issues.
• Use cost estimation methods(eg, WBS elements, up-down) in order to predict the cost of the project more
realistically.
Project Management aspect _ Continue
• In order to make the weekly meeting more efficient, we should spend more time for the preparation of the
agenda and while meeting we should clear with the agenda and follow up of the responsibilities decided.
• Involvement and agreement of each team member in each critical decision of the project.
T
E
A
M
03
Siege engine project

More Related Content

Similar to Siege engine project

SAT Practice Tests
SAT Practice TestsSAT Practice Tests
SAT Practice Tests
Muhammad Arslan
 
Spot welding lobe curve simulation
Spot welding lobe curve simulationSpot welding lobe curve simulation
Spot welding lobe curve simulation
Rashidi Asari
 
Unite steel drill pipe and tool joints
Unite steel drill pipe and tool jointsUnite steel drill pipe and tool joints
Unite steel drill pipe and tool joints
Shanghai Unite Steel
 
REDUCTION OF RE SLEEVING TIME IN LD2
REDUCTION OF RE SLEEVING TIME IN LD2 REDUCTION OF RE SLEEVING TIME IN LD2
REDUCTION OF RE SLEEVING TIME IN LD2
Chandra sekhar sahoo
 
Ijariie1175
Ijariie1175Ijariie1175
Ijariie1175
IJARIIE JOURNAL
 
Unite steel tool joints mechanical property
Unite steel tool joints mechanical propertyUnite steel tool joints mechanical property
Unite steel tool joints mechanical property
Shanghai Unite Steel
 
Rice Co-Op Presentation
Rice Co-Op PresentationRice Co-Op Presentation
Rice Co-Op Presentation
Scott Rice
 
Chapter7
Chapter7Chapter7
Chapter7
Jack Weller
 
ES&FX.singlepweb email
ES&FX.singlepweb emailES&FX.singlepweb email
ES&FX.singlepweb email
Christopher Rotondo
 
Tubna s16
Tubna s16Tubna s16
Tubna s16
Amr Al-Dayarneh
 
GS Template 120213
GS Template 120213GS Template 120213
GS Template 120213
Don McCrum
 
Vaghaldhara Vocational Training Center
Vaghaldhara Vocational Training CenterVaghaldhara Vocational Training Center
Vaghaldhara Vocational Training Center
Shishir Desai
 
Final report
Final reportFinal report
Final report
Sumeet Divatagi
 
Nist project class report
Nist project class reportNist project class report
Nist project class report
alikhosravani
 
Shem a. noah cv
Shem a. noah cvShem a. noah cv
Shem a. noah cv
Shem Noah
 
Solar Tech
Solar TechSolar Tech
Solar Tech
Sajid Ali
 
Centre console back
Centre console backCentre console back
Centre console back
Mekhalaramesh
 
Casing specification api
Casing specification apiCasing specification api
Casing specification api
2ndgenre
 
Sbc ball screw-catalog
Sbc ball screw-catalogSbc ball screw-catalog
Sbc ball screw-catalog
Universidad Complutense de Madrid
 
2015 Intern Presentation Jakeway
2015 Intern Presentation Jakeway2015 Intern Presentation Jakeway
2015 Intern Presentation Jakeway
Maryrose Jakeway
 

Similar to Siege engine project (20)

SAT Practice Tests
SAT Practice TestsSAT Practice Tests
SAT Practice Tests
 
Spot welding lobe curve simulation
Spot welding lobe curve simulationSpot welding lobe curve simulation
Spot welding lobe curve simulation
 
Unite steel drill pipe and tool joints
Unite steel drill pipe and tool jointsUnite steel drill pipe and tool joints
Unite steel drill pipe and tool joints
 
REDUCTION OF RE SLEEVING TIME IN LD2
REDUCTION OF RE SLEEVING TIME IN LD2 REDUCTION OF RE SLEEVING TIME IN LD2
REDUCTION OF RE SLEEVING TIME IN LD2
 
Ijariie1175
Ijariie1175Ijariie1175
Ijariie1175
 
Unite steel tool joints mechanical property
Unite steel tool joints mechanical propertyUnite steel tool joints mechanical property
Unite steel tool joints mechanical property
 
Rice Co-Op Presentation
Rice Co-Op PresentationRice Co-Op Presentation
Rice Co-Op Presentation
 
Chapter7
Chapter7Chapter7
Chapter7
 
ES&FX.singlepweb email
ES&FX.singlepweb emailES&FX.singlepweb email
ES&FX.singlepweb email
 
Tubna s16
Tubna s16Tubna s16
Tubna s16
 
GS Template 120213
GS Template 120213GS Template 120213
GS Template 120213
 
Vaghaldhara Vocational Training Center
Vaghaldhara Vocational Training CenterVaghaldhara Vocational Training Center
Vaghaldhara Vocational Training Center
 
Final report
Final reportFinal report
Final report
 
Nist project class report
Nist project class reportNist project class report
Nist project class report
 
Shem a. noah cv
Shem a. noah cvShem a. noah cv
Shem a. noah cv
 
Solar Tech
Solar TechSolar Tech
Solar Tech
 
Centre console back
Centre console backCentre console back
Centre console back
 
Casing specification api
Casing specification apiCasing specification api
Casing specification api
 
Sbc ball screw-catalog
Sbc ball screw-catalogSbc ball screw-catalog
Sbc ball screw-catalog
 
2015 Intern Presentation Jakeway
2015 Intern Presentation Jakeway2015 Intern Presentation Jakeway
2015 Intern Presentation Jakeway
 

More from Huijian Tian

AME 588 project-Huijian Tian
AME 588 project-Huijian TianAME 588 project-Huijian Tian
AME 588 project-Huijian Tian
Huijian Tian
 
LA maps
LA mapsLA maps
LA maps
Huijian Tian
 
Z motor guard
Z motor guardZ motor guard
Z motor guard
Huijian Tian
 
3D printer Cooling test
3D printer Cooling test3D printer Cooling test
3D printer Cooling test
Huijian Tian
 
Shroud design
Shroud designShroud design
Shroud design
Huijian Tian
 
MASC534term paper-Huijian Tian
MASC534term paper-Huijian TianMASC534term paper-Huijian Tian
MASC534term paper-Huijian Tian
Huijian Tian
 
CBA_report
CBA_reportCBA_report
CBA_report
Huijian Tian
 
Letter recommendation
Letter recommendationLetter recommendation
Letter recommendationHuijian Tian
 

More from Huijian Tian (8)

AME 588 project-Huijian Tian
AME 588 project-Huijian TianAME 588 project-Huijian Tian
AME 588 project-Huijian Tian
 
LA maps
LA mapsLA maps
LA maps
 
Z motor guard
Z motor guardZ motor guard
Z motor guard
 
3D printer Cooling test
3D printer Cooling test3D printer Cooling test
3D printer Cooling test
 
Shroud design
Shroud designShroud design
Shroud design
 
MASC534term paper-Huijian Tian
MASC534term paper-Huijian TianMASC534term paper-Huijian Tian
MASC534term paper-Huijian Tian
 
CBA_report
CBA_reportCBA_report
CBA_report
 
Letter recommendation
Letter recommendationLetter recommendation
Letter recommendation
 

Siege engine project

  • 1. ISE515 Engineering Project Management Gayatri Vilas Nilangekar Changda Ren Yanli Tang Huijian Tian Xue Yang Siege Engine Project - Trebuchet CDR-Team 3
  • 3. Requirements Summary 1. Build a model siege engine to enter the new weapons competition for William’s expedition. 2. The Siege Engine must demonstrate the ability to meet accuracy and repeatability performance goals. 3. The Siege Engine must propel a 7 gram projectile a distance of 15 feet over a 5 foot barrier located 7 feet from the model Siege Engine. 4. The Siege Engine can hit the target in successive 5 attempts. 5. Duration: from January 27, 2015 to April 30, 2015. (PDR review: February 3; CDR review: April 28;Test: April 30.) 6. Cost: for labor cost: $100 ISE/hour/person (overtime: $150 ISE/hour/person ), for purchased parts, $1 = $1000 ISE
  • 4. Statement of work • Build a model Siege Engine that meet all the requirements before April 30th . The performance is the most important element of the triple constraint.
  • 5. WBS
  • 6. Task Name Task # Duration (Days) Task Starts Task Ends Predecessors Resource Name Resource Rate ($ISE) Materials Rate ($ISE) Design 1 6 2015/1/28 2015/2/6 Concept finalising 1.1 1 2015/1/28 2015/1/28 All five team members 1,000 Initial sketch and analysis 1.2 2 2015/1/29 2015/1/30 1.1 Gayatri, Huijian 800 Create a parts list 1.3 1 2015/1/29 2015/1/29 1.2 Yanli 200 Finalising the material 1.4 1 2015/1/30 2015/1/30 1.3 Yanli 200 AutoCAD drawing (detailed analysis with tolerances) 1.5 2 2015/2/4 2015/2/5 1.4 Huijian 400 Design validation 1.6 1 2015/2/6 2015/2/6 1.5 Huijian 200 Cost estimate and data compilation 2 2 2015/1/30 2015/2/2 1.1 Xue 400 Fabricate 3 21 2015/2/9 2015/3/26 Identifying the tool requirement 3.1 1 2015/2/9 2015/2/9 1 Yanli 200 Procurement 3.2 3 2015/2/10 2015/2/12 Materials and tools buying 3.2.1 2 2015/2/10 2015/2/11 3.1 Yanli, Changda 800 70,000 Quality check of materials 3.2.2 1 2015/2/12 2015/2/12 3.2.1 Changda 200 Assembly 3.3 17 2015/3/24 2015/4/15 Fabrication of child parts 3.3.1 4 2015/3/24 2015/3/27 3.2 All five team members 4,000 Subassembly of frame 3.3.2 3 2015/3/30 2015/4/1 3.3.1 Gayatri, Changda, Xue 1,800 Quality Check 3.3.3 1 2015/4/2 2015/4/2 3.3.2 Xue 200 Subassembly of long arm 3.3.4 1 2015/4/3 2015/4/3 3.3.3 Gayatri, Changda, Xue 600 Quality check 3.3.5 1 2015/4/6 2015/4/6 3.3.4 Xue 200 Subassembly of short arm 3.3.6 2 2015/4/7 2015/4/8 3.3.5 Gayatri, Changda, Xue 1,200 Quality check 3.3.7 1 2015/4/9 2015/4/9 3.3.6 Changda 200 Final Assembly 3.3.8 4 2015/4/10 2015/4/15 3.3.7 Gayatri, Yanli, Huijian 2,400 Inspection and test 4 6 2015/4/16 2015/4/23 Inspection 4.1 1 2015/4/16 2015/4/16 3.3 Yanli 200 Performance test 4.2 3 2015/4/17 2015/4/21 4.1 All five team members 3,000 Modification (if required) 4.3 2 2015/4/22 2015/4/23 4.2 Huijian 400 Operating manual 4.4 2 2015/4/22 2015/4/23 4.2 Gayatri, Changda, Xue, Yanli 1,600 Weekly meetings 5 13 Time depends on schedule of team members All five team members 13,000 Task Durations & List of Resources • Labor hours/person/day = 2
  • 7. Schedule Baseline Plan – Gantt Chart • G: Gayatri; H: Huijian; Y: Yanli; C: Changda; X: Xue • All: Gayatri, Huijian, Yanli, Changda, Xue
  • 9. Task Name Task # Duration (Days) Task Starts Task Ends Predecessors Resource Name Resource Rate ($ISE) Materials Rate ($ISE) Design 1 6 2015/1/28 2015/2/6 Concept finalising 1.1 1 2015/1/28 2015/1/28 All five team members 1,000 Initial sketch and analysis 1.2 2 2015/1/29 2015/1/30 1.1 Gayatri, Huijian 800 Create a parts list 1.3 1 2015/1/29 2015/1/29 1.2 Yanli 200 Finalising the material 1.4 1 2015/1/30 2015/1/30 1.3 Yanli 200 AutoCAD drawing (detailed analysis with tolerances) 1.5 2 2015/2/4 2015/2/5 1.4 Huijian 400 Design validation 1.6 1 2015/2/6 2015/2/6 1.5 Huijian 200 Cost estimate and data compilation 2 2 2015/1/30 2015/2/2 1.1 Xue 400 Fabricate 3 21 2015/2/9 2015/3/26 Identifying the tool requirement 3.1 1 2015/2/9 2015/2/9 1 Yanli 200 Procurement 3.2 3 2015/2/10 2015/2/12 Materials and tools buying 3.2.1 2 2015/2/10 2015/2/11 3.1 Yanli, Changda 800 70,000 Quality check of materials 3.2.2 1 2015/2/12 2015/2/12 3.2.1 Changda 200 Assembly 3.3 17 2015/3/24 2015/4/15 Fabrication of child parts 3.3.1 4 2015/3/24 2015/3/27 3.2 All five team members 4,000 Subassembly of frame 3.3.2 3 2015/3/30 2015/4/1 3.3.1 Gayatri, Changda, Xue 1,800 Quality Check 3.3.3 1 2015/4/2 2015/4/2 3.3.2 Xue 200 Subassembly of long arm 3.3.4 1 2015/4/3 2015/4/3 3.3.3 Gayatri, Changda, Xue 600 Quality check 3.3.5 1 2015/4/6 2015/4/6 3.3.4 Xue 200 Subassembly of short arm 3.3.6 2 2015/4/7 2015/4/8 3.3.5 Gayatri, Changda, Xue 1,200 Quality check 3.3.7 1 2015/4/9 2015/4/9 3.3.6 Changda 200 Final Assembly 3.3.8 4 2015/4/10 2015/4/15 3.3.7 Gayatri, Yanli, Huijian 2,400 Inspection and test 4 6 2015/4/16 2015/4/23 Inspection 4.1 1 2015/4/16 2015/4/16 3.3 Yanli 200 Performance test 4.2 3 2015/4/17 2015/4/21 4.1 All five team members 3,000 Modification (if required) 4.3 2 2015/4/22 2015/4/23 4.2 Huijian 400 Operating manual 4.4 2 2015/4/22 2015/4/23 4.2 Gayatri, Changda, Xue, Yanli 1,600 Weekly meetings 5 13 Time depends on schedule of team members All five team members 13,000 Cost Baseline • Labor hours/person/day = 2
  • 10. Cost Baseline 0 100 200 300 400 500 600 700 800 900 1000 Cost Baseline Graph Daily total cost ($ISE/100) Cum total cost ($ISE/100)
  • 11. Week ending Weekly time spent Total hrs. Labor Expenses ($ISE) Weekly cost ($ISE) Cum. cost ($ISE) ($ISE) Gayatri Changda Yanli Huijian Xue 30-Jan 8 4 8 8 6 34 3,400 0 3,400 3,400 6-Feb 2 2 2 8 4 18 1,800 70,000 71,800 75,200 13-Feb 2 8 8 2 2 22 2,200 0 2,200 77,400 20-Feb 2 2 2 2 2 10 1,000 0 1,000 78,400 27-Feb 2 2 2 2 2 10 1,000 0 1,000 79,400 6-Mar 2 2 2 2 2 10 1,000 0 1,000 80,400 13-Mar 2 2 2 2 2 10 1,000 0 1,000 81,400 20-Mar 2 2 2 2 2 10 1,000 0 1,000 82,400 27-Mar 10 10 10 10 10 50 5,000 0 5,000 87,400 3-Apr 10 10 2 2 12 36 3,600 0 3,600 91,000 10-Apr 8 8 4 4 8 32 3,200 0 3,200 94,200 17-Apr 10 4 12 10 4 40 4,000 0 4,000 98,200 24-Apr 10 10 10 10 10 50 5,000 0 5,000 103,200 Weekly Cost Baseline
  • 12. Week ending Weekly time spent Total hrs. Labor ($ ISE) Expen ses ($) Expense s ($ISE) Weekly cost ($ISE) Cum. cost ($ISE) Cum. budget ($ISE) Variance Gayatri Changda Yanli Huijian Xue Jan 30 6 2 6 6 4 24 2400 0 0 2400 2400 3400 1000 Feb 6 2 2 2 8 4 18 1800 0 0 1800 4200 75200 71000 Feb 13 2 2 2 4 2 12 1200 0 0 1200 5400 77400 72000 Feb 20 4 4 5 2 4 19 1900 25.78 25780 27680 33080 78400 45320 Feb 27 2 2 2 2 2 10 1000 0 0 1000 34080 79400 45320 Mar 6 2 2 2 2 2 10 1000 0 0 1000 35080 80400 45320 Mar 13 0 0 0 0 0 0 0 0 0 0 35080 81400 46320 Mar 20 0 0 0 0 0 0 0 0 0 0 35080 82400 47320 Mar 27 4 4 4 4 4 20 2000 0 0 2000 37080 87400 50320 April 3 7 7 7 7 7 35 4250 6.28 6280 10530 47610 91000 43390 April 10 5 5 5 5 5 25 3250 0 0 3250 50860 94200 43340 April 17 5 5 5 5 5 5 3250 0 0 3250 54110 98200 44090 April 24 9 8 8 8 9 42 5200 0 0 5200 59310 103200 43890 Cost – Actual Cost
  • 13. Cost – Actual Cost 0 20000 40000 60000 80000 100000 120000 Cum. cost Cum. budget Variance
  • 14. Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Day 5 10 15 20 25 30 35 40 45 50 55 60 64 Plan Value ($ISE) 2400 3200 74400 74400 74400 74400 74400 74400 78400 81000 83200 86200 90200 Actual Cost ($ISE) 2400 3200 3400 30880 30880 30880 30880 30880 32880 36050 38300 40050 45250 Earned Value ($ISE) 2200 3200 3400 30880 30880 30880 30880 30880 32880 36050 37550 37550 45250 CV = EV - AC ($ISE) -200 0 0 0 0 0 0 0 0 0 -750 -2500 0 SV = EV - PV ($ISE) -200 0 -71000 -43520 -43520 -43520 -43520 -43520 -45520 -44950 -45650 -48650 -44950 -3000 -2500 -2000 -1500 -1000 -500 0 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63 Cost Variance SV and CV - Performance (0-100 Rule) -80000 -70000 -60000 -50000 -40000 -30000 -20000 -10000 0 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63 Schedule Variance
  • 15. SV and CV – Analysis • Week 1: CV and SV are negative because we didn’t count the weekly meeting cost($ISE200) • Week 2 – Week 10: CV are zero, because we finished the tasks of second week. But during week 3- Week 8, due to our midterm and spring break, we didn’t work at that period. At Week 9, we requested for change of schedule baseline and cost baseline, afterwards, we followed on the schedule of week 9 and week 10. SV: There is a big variance in week 3, it is because we didn’t buy material as the schedule required. During week 4 – week 8, there are a constant variance ($ISE43520) because we bought the material at a much lower price than we estimated, the difference is $ISE43520 . At week 9, the variance becomes bigger, it just because we finished task 3.3.1 with $ISE2000 instead of $ISE4000. Week 10, because we used less time to finish the tasks than we planned. • Week 11 – Week 12: CV - There are two negative variance because we started the tasks of 4.3 and 4.4 ahead of schedule, and finished them on time. Therefore the time span is longer than our schedule baseline which results the big variance. SV – During these two weeks, the variances become larger. This is also we started the tasks of 4.3 and 4.4 ahead of schedule, and finished them on time. Therefore the time span is longer than our schedule baseline which results the big variance. • Week 13: CV is zero. SV is negative because we save a lot of cost than we estimated on the materials buying. In a word, from SV and CV graphs, our CV and SV are always non-positive. This is because we fall behind the schedule. For the SV, there is another reason that results in the negative SV, which is our overestimation of our material costs.
  • 16. Risk Management – the Plan Task Risk Event # and Description Prob. % (A) Impact $ISE (B) Risk Event Status (A x B) Action Owner Preventive (Main Plan) Trigger Point Contingent (Plan B) Concept Finalizing & Initial Sketch 1 Design does not meet requirement of client 40% 1,800 720 Use Matlab to simulate the throwing process and calculate the optimal parameters Lack of experience in mechanical analysis and engineering design Re-design Gayatri, Huijian Cost Estimate 2 Cost is underestimated 60% 200 120 Sum up costs task by task based on WBS Lack of practical experience Change the cost baseline and request approval from client Xue Tool Requirement Identification 3 Incomplete identification of tools 20% 400 80 Identify the tools as the designers’ specification Lack of communication between design and manufacturing team Identify the missing tools and buy them Yanli Materials and Tools Buying 4 Material is weak or of low quality 20% 5,000 1,000 Research and comparison of different material resources Lack of knowledge to identify the quality Buy new materials with good quality Yanli, Changd a Assembly 5 Child parts or subassemblies not match design specifications 40% 5,300 2,120 Measure and cut as the design’s specification Errors in measuring or cutting Fabricate new parts or change design All five membe rs
  • 17. Risk Management – the Steps Taken • Design: we use Matlab to validate design and decide the tolerance on critical part • Tools: we looked for additional resources for tools instead of depending on only one resource • Materials: search for suppliers (bookstore, Home Depot) and finalizing the suppliers based on quality and cost; bought extra materials in case of manufacturing damage • Assembly: Extra time allocated to assembly; thorough discussion for any change in design, and changes in design are for ease of assembly, no change in critical parts • Schedule: we work extra time; we crash the project; we develop agenda before meeting and follow up the decided activities • Monitor and control: we apply project management tools such as inch-stone, EVA to control the triple constraints of the project
  • 21. Trial Distance to target (inch) 1 1.4 2 0 3 0 4 2.1 5 1.9 6 0.7 7 0 8 1.2 9 2.7 10 0 Mean 1.0 Variance 1.022 0 1 2 3 4 5 6 7 8 0 1 2 3 4 5 6 7 8 9 10 Distance /inch Trial Evidence That the Trebuchet Meets Requirements • We recorded a video which will show the performance.
  • 23. Performance - Design Evolution Parameters Length 1.5m Height 1m Weight 2Kg Projectile 7g Angle -30°; 45°
  • 24. Lessons Learned Project Management aspect • Team is the core of entire project. We take fully advantage of every team member’s strongpoint and distribute work package accordingly.(eg, one person is dedicated to monitor project activities is very effective) • We abide by the control requirements of triple constraint and it is useful.(eg, time - on time, ahead of schedule 10 days; cost – within budget, save 46%; performance – acceptable) • Project schedule is the critical tool for project success. We should spend more time to build and track schedule so that better control the progress. • Developing risk response plan early is important. • Since the duration of this project is quite long, it is very necessary to develop and maintain the team morale and harmony. • It is quite important to distribute the work equally. • Make sure all team members are bought in and keep everyone updated.
  • 25. Lessons Learned Technical Aspect • We should explore more and make better use of MS project software to control and monitor the entire project. • Consider the DFMEA (Design for Manufacturing and Assembly) points in initial design. • Preparation of prototype to identify tools and manufacturing issues. • Use cost estimation methods(eg, WBS elements, up-down) in order to predict the cost of the project more realistically. Project Management aspect _ Continue • In order to make the weekly meeting more efficient, we should spend more time for the preparation of the agenda and while meeting we should clear with the agenda and follow up of the responsibilities decided. • Involvement and agreement of each team member in each critical decision of the project.
  • 26.