Science Frenzy Project Plan
Proposed by Megan McDaniel, Allyson Bone, and George Kairis
Snapdoodle Toys
(425)408-0021
7330 NE Bothell Way
Kenmore, WA 98028
2
Table of Contents
Section 1: Project Overview ......................................................................................................................... 3
1.1 Problem Statement....................................................................................................................... 3
1.2 Project Overview.......................................................................................................................... 3
1.3 Goals and Objectives.................................................................................................................... 4
1.4 Project Scope................................................................................................................................. 4
1.5 Critical Success Factors............................................................................................................... 4
1.6 Project Assumptions..................................................................................................................... 5
1.7 Project Constraints and Risks .................................................................................................... 5
Section 2: Major Project Milestones ............................................................................................................ 5
2.1 Project Milestones ........................................................................................................................ 5
2.2 Work Breakdown Structure (WBS) ............................................................................................ 6
Section 3: Project Structure.......................................................................................................................... 6
3.1 Project Structure.......................................................................................................................... 6
3.2 Roles and Responsibilities........................................................................................................... 7
3.3 Responsibility Matrix.................................................................................................................... 7
Section 4: Project Schedule.......................................................................................................................... 8
Section 5: Budget.......................................................................................................................................... 9
Section 6: Risk Management...................................................................................................................... 10
Section 7: Approvals................................................................................................................................... 11
Section 8: Revision History......................................................................................................................... 11
Section 9: Appendices ................................................................................................................................ 11
3
Section 1: Project Overview
1.1 Problem Statement
Snapdoodle Toys is a locally owned business that relies on its close knit relationship with the
community for its survival. In order to keep customers interested and engaged at the store,
Snapdoodle hosts a variety of events. These events range from adult game nights to preschool
playdates. In order to boost sales in our science department and add a little variety to our regular
events, we have chosen to host a science themed activity day in our Kenmore store.
Snapdoodle Toys has been slowly increasing its business since the first year it opened. Last year,
growth slowed down to a 2% increase in revenue over the course of the year. This year is the first
year that Snapdoodle has not shown an increase in sales. Snapdoodle’s current priority is to
jumpstart its growth to be able to continue to expand.
One of the major concerns for Snapdoodle currently is the closure of another local toy store,
Reigning Imaginations. In the long run, this closure should increase business at Snapdoodle, but in
the short term it has heavily damaged Snapdoodle’s sales. The closeout clearance at Reigning
Imaginations is pulling customers that would normally shop at Snapdoodle into Reigning
Imaginations. In order to draw in their customers, Snapdoodle has increased their number of
events.
1.2 Project Overview
In an effort to boost sales for Snapdoodle Toys, we will be hosting a science themed event to draw
customers into the store on Saturday, May 16th. From 4:00 PM to 7:00 PM, there will be 3 play
stations for the kids to rotate through, as well as a presentation featuring experiments involving fun
chemistry reactions and dry ice. By hosting this event, we will hopefully increase the amount of
customers who visit the store and attend the events on a regular basis.
In order to measure how successful our event is, we will compare sales from the day of the event
to the sales from the previous year on the same day. We will consider the event a success if sales
increase at least 10% from the previous year. We will also evaluate the number of purchases and
attendance from new customers to determine if our marketing and outreach strategy is effective in
not just maintaining current customers, but also for making connections with new ones.
We aim to keep the costs of the event below $150 including inventory used in our event and
employee wages. George and Megan will be volunteering their time to the project and Allyson will
be accepting her regular employee wage. We will be assuming 2 employees will be present during
the time of the event to manage regular store sales and customer attendance. The greatest
constraint to our plan is the cost of materials for the 3 play stations and for the grand finale dry ice
show.
4
1.3 Goals and Objectives
The science event we are hosting will be directly supporting several of Snapdoodle’s goals and
objectives. The following table lists the business goals and objectives that the event supports and how
it supports them:
Business
Goal/Objective
Description
Increase Awareness in
Science Related Toys
Allowing children and families to play with the toys in the store with
educated staff available to help demonstrate use and explain the science.
Increase Company’s
Word of Mouth
Introducing a grand finale event will encourage parents and children to tell
their friends about the show.
Increase Customer
Loyalty
Reminding customers of Snapdoodle’s unique small business environment
will hopefully encourage parents to support a company that values every
child’s education rather than carrying the cheapest toys.
Increase Overall Sales Attracting new and returning customers for the event and promoting certain
products in particular will hopefully boost sales in those toys.
Excite and Educate
Children and Parents
Hosting a science related toy party is both educational and fun.
One-Of-A-Kind
Customer Service
This event is being run by volunteers, not the store staff. This allows the staff
to simply focus on shopping customers and answering merchandise related
questions instead of trying to juggle event planning and execution with their
day to day tasks.
1.4 Project Scope
Product Scope Description: The products/toys used during the event will be used from
Snapdoodle Toys available stock and be calculated into our total cost. The materials that were
used during the event included...
 3 different varieties of bubble mixtures (smelly, touchable, and regular).
 A bubble mystery questionnaire.
 SnapCircuit Toys provided by a company representative.
 A variety of building tools to build a marble roller coaster.
Each of these products were demonstrated as science experiments and were chosen to result as a
boost in overall sales and in that slower moving department. In addition to material requirements
staff and volunteers required additional training on site before the event to prepare the stations and
attract people to the event.
Acceptance Criteria: Before project deliverables can be accepted, signatures of the owner and
managing staff of Snapdoodle Toys needed to be collected, the available dates needed to be
available in “The Doodle Zone” and the project charter needed to be accepted.
1.5 Critical Success Factors
Please refer to Appendix 3: Performance Measurements
5
1.6 Project Assumptions
The following assumptions apply to the Snapdoodle science party. As project planning begins and more
assumptions are identified, they will be added accordingly.
 All staff and volunteers will be trained accordingly in their respective stations and given specific
responsibilities by project team members.
 Funding is available for purchasing the necessary toys and demonstrative materials.
 All department heads will provide necessary support for successful project completion.
 Project has executive-level support and backing.
 The Elenco Rep will be available for our event.
1.7 Project Constraints and Risks
The following constraints apply to the Snapdoodle Event Project.
 $1000 dollar budget
 4-7 weeks time constraint
 DoodleZone can only hold 60 people at a time.
 Megan will not be available until 3:30pm on Saturday. (Work)
 The event will last for three hours.
The risks of our event are the weather keeping people from attending, the Elenco representative not
showing up, and the demonstration not working.
Please refer to Appendix 2: Short & Long Term Risk
Section 2: Major Project Milestones
2.1 Project Milestones
The following are the major project milestones.
Milestones/Deliverables Target Date
Project Charter 04/14/2015
Activities Planned 04/21/2015
Project Approval 04/23/2015
Schedule Set 05/09/2015
Supplies Obtained 05/10/2015
Event 05/16/2015
High-level Review 05/18/2015
6
2.2 Work Breakdown Structure (WBS)
Plan
Contact
Elenco Rep
Schedule
Choose
Activities
Boss
Approval
Purchase
Supplies
Finale
Training
Advertising
Reports
Team
Charter
Problem
Statement
Work
Breakdown
Structure
MS Project
Schedule
Budget
Set Up
Station 1
Station 2
Station 3
Finale
Execution
Interactive
Stations
Finale
Clean Up Review
Sales Data
Department
Data
Review with
Boss
Approve
Final Business
Plan
Facebook Email/Newsletters Update Website
Elementary
Schools
Event RSVPs
Section 3: Project Structure
3.1 Project Structure
Project Communications Norms:
 Every team member is expected to attend and be on time for scheduled meetings unless that
individual has notified other members before hand and has a professional or medical excuse
for their absence.
 It is the responsibility of each member to communicate with everyone else in the group their
inability to complete their responsibilities within the scheduled timing.
 In the event of a member’s inability to fulfill his/her responsibilities, the other members will
delegate equally the incomplete work among each other to ensure deadline requirements and
project completion.
 All team members are required to participate and be present for the duration of the planned
event (including set-up and teardown time as needed). If there is conflicting issues with time
or location, other members must be notified immediately.
Potential Barriers and Coping Strategies: Different schedules in terms of workload and classes.
Solutions include texting, google docs, email, or online meeting applications such as FaceTime or
Skype. Team members will be expected to respond to online content within 24 hours of posting.
 If a team member’s work is not up to the team’s standards then the team will be responsible
for providing that member with input to help them improve their work’s quality.
7
 Considering this team consists of 3 members, if there is a disagreement on how to proceed
we will negotiate to 2 ideas and take a vote by hand.
Repercussions for Breaking Communication Expectations: If this team charter is not
respected by any member for any reason then that team member will be asked to explain their
actions and collaborate with the group on how to move forward. They will also be required by
charter law to wear a full clown suit to class and perform tricks at the other members
leisure/enjoyment.
3.2 Roles and Responsibilities
The following individuals comprise the stakeholders for the project.
Role Description Name/Title
Organizer Coordinates team objectives using limited
resources
Megan McDaniel, Team
Member
Spokesperson Connects the team to Snapdoodle Toys Allyson Bone, Team
Member
Handyman Helps/operates the event stations George Kairis, Team
Member
Client Authority to accept/reject project
deliverables
Rob Pickering, Store Owner
Client Authority to accept/reject project
deliverables
Candy Caylor, Resource
Manager
Staff
Management
Provides staff members for event Polly Shinner, Store
Manager
3.3 Responsibility Matrix
Please refer to Appendix 1: Responsibility Assignment Matrix
8
Section 4: Project Schedule
9
Section 5: Budget
The following table captures the relevant costs and descriptions of these actions associated with the
total planned event period.
Action Action
Type
Description First year costs (-
indicates anticipated
savings)
Purchase Demonstration
Materials and Toys
Cost Bubble Station, SnapCircuit
Equipment, Building Materials, Dry
Ice Show
$150.00
Team members
compensation
Cost Planning, scheduling, organizing,
and running the event ($15 hourly
rate)
$437.50
Pay Employee Wages Cost 2 employees on staff from 2:00pm -
6:00pm at their standard rate
$80.00
Total Cost $667.5
By running this event we anticipate an increase of $1500 the day of the event, and an increase of
future sales due to the demonstration of the toys and the increased store brand awareness. The
gross margin of our anticipated sales on the day of the event is 55.5%.
10
Section 6: Risk Management
Below is a list of our risks and the actions taken to minimize them.
Risk
ID
WBS Rank Description Strategy
1 1.2 Yellow The DoodleZone may
not be large enough to
accommodate over 60
guests.
Create additional event space within the store to
accommodate approximately 60 customers. In addition, look
for outdoor options depending on the weather conditions.
2 1.0 Yellow Weather conditions
the day of the event.
Although weather forecast doesn’t predict any bad weather
conditions, we can’t actually control unexpected weather
changes that may occur which can affect our customer count
and revenue.
3 1.3 Green The Elenco rep (snap
circuit station) may not
show up for the event.
We will assign to a store employee the snap circuit station in
case the sales rep is unable to attend the event. In addition,
one of our team members will be familiar with the games and
take over if there are too many customers showing up.
4 1.0 Red Not everyone who
plans to attend our
event will RSVP.
When planning the event, we will aim for maximum flexibility
in order to accommodate for any level of attendance.
5 1.1 Yellow Team member lack of
product knowledge.
Team members should have full knowledge of the products
and their functions. We will hold short training sessions to get
familiar with the toys we are planning to promote.
6 1.1 Green Consistent image
during the event
promotion.
Optimize our communication with the promoters so we can all
be on the same page.
7 1.3 Red Dry Ice presentation
safety concerns.
Our dry ice presentation will take place half hour before the
event. During this half hour we will not demonstrate other
toys/products. All team members will control the space
around the dry ice presentation as we want to prevent young
children touching or playing with the dry ice material (may
cause skin burns due to extreme low temperature)
11
Section 7: Approvals
The signatures of the people below indicate an understanding in the purpose and content of this
Project charter by those signing it. By signing this document you indicate that you approve of the
proposed project outlined in this project charter and that the next steps may be taken to create a
formal project in accordance with the details outlined herein.
Section 8: Revision History
Version Date Name Description
1.0 05/07/2015 Project Plan
Outline
Began formatting and creating headings to shape the
document
1.1 5/28/2015 Google Doc Draft All group members submitted their segments
1.1 6/1/2015 Final Project
Plan
Final Document. Final formatting and wording fixes.
Section 9: Appendices
Appendix 1: Responsibility Assignment Matrix
Activity N,I,C,I Issues Delivery
Date
Owner
Project Sign Off Complete Boss on Vacation. 04/19/2015 Allyson
Event/Project
WBS
Complete No Issues. 04/21/2015 George
Contacting
Schools
Complete Verified local school’s newsletter
and event notification process.
Completion will be a few days
before the week of the event.
05/07/2015 Megan
Plan Stations Complete No issues 04/30/2015 Team
12
Contact Elenco
Rep
Complete Unable to attend, but provided
materials for event.
05/02/2015 Allyson
Microsoft Project
Schedule
Complete It is difficult to work on a single
project file on a single computer.
05/05/2015 Team
Budget and
Time-Phased
Budget
Complete Megan not available 05/05/2015 Team
Advertising Complete Facebook event page completed
and tracked by Allyson. Website
manager at Snapdoodle Toys
posted an invite on official
website.
5/12/2015 Allyson &
Snapdoodle
Manager
Final Written
Project
Complete No issues 05/21/2015 Team
Appendix 2: Short & Long Term Risk
Short Term Risks
1. Hopefully, all of the people who promote our event promote it with a consistent image.
2. Not everyone who plans to attend our event will RSVP, making it challenging to plan for the
future.
Long Term Risks
1. The DoodleZone/store may not be large enough to accommodate over 60 guests. In order
to prepare for this risk, we are creating a method that will allow guests to RSVP for the
event so that we can get a feel for how many guests will actually be appearing at the store.
We are also looking into the possibility of setting up some of our play stations outside.
2. The weather may not be very good. If the weather is poor, we will have fewer guests attend
our event. This is not a risk that we can control.
Appendix 3: Performance Measurements
The following table lists the key resources, processes, or services and their anticipated business
outcomes in measuring the performance of the project. These performance measures will be
quantified and further defined in the detailed project plan.
Key Process/Service Performance Measure
Overall Store Sales Store Sales Data (Quickbooks’ Point of Sale)
Department Sales Department Sales Data (Quickbooks’ Point of Sale)
New Attendees Customer Database (Quickbooks’ Point of Sale)
Customer Satisfaction Comment Box

More Related Content

Viewers also liked

Mule smtp connector
Mule smtp connectorMule smtp connector
Mule smtp connector
Krishnakanth Goud
 
Genetic engineer performance appraisal
Genetic engineer performance appraisalGenetic engineer performance appraisal
Genetic engineer performance appraisalBigBang789
 
Assembléia geral – votação apm 2016 2018
Assembléia geral – votação apm 2016 2018Assembléia geral – votação apm 2016 2018
Assembléia geral – votação apm 2016 2018
E.M Luis Cláudio Josué
 
Sunrise enterprises
Sunrise enterprisesSunrise enterprises
Sunrise enterprises
Sunrise Enterprises
 
Gradient [PRESSKIT Version 2]
Gradient [PRESSKIT Version 2]Gradient [PRESSKIT Version 2]
Gradient [PRESSKIT Version 2]Chris O
 
Cosmic Adventure 3.9-10 World of Finite Light Speed
Cosmic Adventure 3.9-10 World of Finite Light SpeedCosmic Adventure 3.9-10 World of Finite Light Speed
Cosmic Adventure 3.9-10 World of Finite Light Speed
Stephen Kwong
 

Viewers also liked (7)

Mule smtp connector
Mule smtp connectorMule smtp connector
Mule smtp connector
 
Genetic engineer performance appraisal
Genetic engineer performance appraisalGenetic engineer performance appraisal
Genetic engineer performance appraisal
 
Assembléia geral – votação apm 2016 2018
Assembléia geral – votação apm 2016 2018Assembléia geral – votação apm 2016 2018
Assembléia geral – votação apm 2016 2018
 
Presentation1
Presentation1Presentation1
Presentation1
 
Sunrise enterprises
Sunrise enterprisesSunrise enterprises
Sunrise enterprises
 
Gradient [PRESSKIT Version 2]
Gradient [PRESSKIT Version 2]Gradient [PRESSKIT Version 2]
Gradient [PRESSKIT Version 2]
 
Cosmic Adventure 3.9-10 World of Finite Light Speed
Cosmic Adventure 3.9-10 World of Finite Light SpeedCosmic Adventure 3.9-10 World of Finite Light Speed
Cosmic Adventure 3.9-10 World of Finite Light Speed
 

Similar to Project Management Plan - Microsoft Project

Innovation Report Mobius Toy, Inc.
Innovation Report Mobius Toy, Inc.Innovation Report Mobius Toy, Inc.
Innovation Report Mobius Toy, Inc.
Jean-Luc Winkler
 
1 Private and Confidential. For X-Culture use only. .docx
  1  Private and Confidential. For X-Culture use only.  .docx  1  Private and Confidential. For X-Culture use only.  .docx
1 Private and Confidential. For X-Culture use only. .docx
joyjonna282
 
Consulting Skills Workshop
Consulting Skills WorkshopConsulting Skills Workshop
Consulting Skills Workshop
Ian Turner
 
toy manufacturers project report.
toy manufacturers project report.toy manufacturers project report.
toy manufacturers project report.
Hagi Sahib
 
Georg Jensen Pro gradu Anna Catani
Georg Jensen Pro gradu Anna CataniGeorg Jensen Pro gradu Anna Catani
Georg Jensen Pro gradu Anna CataniAnna Catani
 
Georg Jensen Pro gradu Anna Catani
Georg Jensen Pro gradu Anna CataniGeorg Jensen Pro gradu Anna Catani
Georg Jensen Pro gradu Anna CataniAnna Catani
 
Finance Essay Topics. Finance topics for research paper in 2021 Research pap...
Finance Essay Topics. Finance topics for research paper in 2021  Research pap...Finance Essay Topics. Finance topics for research paper in 2021  Research pap...
Finance Essay Topics. Finance topics for research paper in 2021 Research pap...
Ashley Matulevich
 
Digital brand strategy - Ugo Orlando
Digital brand strategy - Ugo OrlandoDigital brand strategy - Ugo Orlando
Digital brand strategy - Ugo Orlando
Ugo Orlando
 
Game Product Discovery: Validation & Iteration
Game Product Discovery: Validation & IterationGame Product Discovery: Validation & Iteration
Game Product Discovery: Validation & Iteration
Martyn Jones
 
Kids Brand Insight Company Presentation
Kids Brand Insight Company PresentationKids Brand Insight Company Presentation
Kids Brand Insight Company Presentation
Kids Brand Insight
 
New product development
New  product developmentNew  product development
New product developmentAwais Abid
 
BU682 KnowledgeHook.com North American Market Research
BU682  KnowledgeHook.com North American Market ResearchBU682  KnowledgeHook.com North American Market Research
BU682 KnowledgeHook.com North American Market Research
Riki Yao
 
Gc issue 20 editor lorraine stylianou
Gc issue 20 editor lorraine stylianouGc issue 20 editor lorraine stylianou
Gc issue 20 editor lorraine stylianou
Lorraine Stylianou
 
Validation and Iteration in Games - Martyn Jones
Validation and Iteration in Games - Martyn JonesValidation and Iteration in Games - Martyn Jones
Validation and Iteration in Games - Martyn Jones
Mind the Product
 
Pre production techniques pro-forma
Pre production techniques pro-formaPre production techniques pro-forma
Pre production techniques pro-formaRobyn Collinson
 
Uop qnt-561-week-3-case-study-super-fun-toys-2-papers-new
Uop qnt-561-week-3-case-study-super-fun-toys-2-papers-newUop qnt-561-week-3-case-study-super-fun-toys-2-papers-new
Uop qnt-561-week-3-case-study-super-fun-toys-2-papers-new
assignmentindi
 
Business Report Project ReFlowr
Business Report Project ReFlowrBusiness Report Project ReFlowr
Business Report Project ReFlowr
Eddy S.R.A/Eddy Saputra
 
Magma v1.4
Magma v1.4Magma v1.4

Similar to Project Management Plan - Microsoft Project (20)

Innovation Report Mobius Toy, Inc.
Innovation Report Mobius Toy, Inc.Innovation Report Mobius Toy, Inc.
Innovation Report Mobius Toy, Inc.
 
1 Private and Confidential. For X-Culture use only. .docx
  1  Private and Confidential. For X-Culture use only.  .docx  1  Private and Confidential. For X-Culture use only.  .docx
1 Private and Confidential. For X-Culture use only. .docx
 
Consulting Skills Workshop
Consulting Skills WorkshopConsulting Skills Workshop
Consulting Skills Workshop
 
toy manufacturers project report.
toy manufacturers project report.toy manufacturers project report.
toy manufacturers project report.
 
Georg Jensen Pro gradu Anna Catani
Georg Jensen Pro gradu Anna CataniGeorg Jensen Pro gradu Anna Catani
Georg Jensen Pro gradu Anna Catani
 
Georg Jensen Pro gradu Anna Catani
Georg Jensen Pro gradu Anna CataniGeorg Jensen Pro gradu Anna Catani
Georg Jensen Pro gradu Anna Catani
 
Easy Memory - Prospectus
Easy Memory - ProspectusEasy Memory - Prospectus
Easy Memory - Prospectus
 
Finance Essay Topics. Finance topics for research paper in 2021 Research pap...
Finance Essay Topics. Finance topics for research paper in 2021  Research pap...Finance Essay Topics. Finance topics for research paper in 2021  Research pap...
Finance Essay Topics. Finance topics for research paper in 2021 Research pap...
 
Digital brand strategy - Ugo Orlando
Digital brand strategy - Ugo OrlandoDigital brand strategy - Ugo Orlando
Digital brand strategy - Ugo Orlando
 
Game Product Discovery: Validation & Iteration
Game Product Discovery: Validation & IterationGame Product Discovery: Validation & Iteration
Game Product Discovery: Validation & Iteration
 
Kids Brand Insight Company Presentation
Kids Brand Insight Company PresentationKids Brand Insight Company Presentation
Kids Brand Insight Company Presentation
 
New product development
New  product developmentNew  product development
New product development
 
BU682 KnowledgeHook.com North American Market Research
BU682  KnowledgeHook.com North American Market ResearchBU682  KnowledgeHook.com North American Market Research
BU682 KnowledgeHook.com North American Market Research
 
Gc issue 20 editor lorraine stylianou
Gc issue 20 editor lorraine stylianouGc issue 20 editor lorraine stylianou
Gc issue 20 editor lorraine stylianou
 
Validation and Iteration in Games - Martyn Jones
Validation and Iteration in Games - Martyn JonesValidation and Iteration in Games - Martyn Jones
Validation and Iteration in Games - Martyn Jones
 
Pre production techniques pro-forma
Pre production techniques pro-formaPre production techniques pro-forma
Pre production techniques pro-forma
 
Uop qnt-561-week-3-case-study-super-fun-toys-2-papers-new
Uop qnt-561-week-3-case-study-super-fun-toys-2-papers-newUop qnt-561-week-3-case-study-super-fun-toys-2-papers-new
Uop qnt-561-week-3-case-study-super-fun-toys-2-papers-new
 
CB Design Process
CB Design ProcessCB Design Process
CB Design Process
 
Business Report Project ReFlowr
Business Report Project ReFlowrBusiness Report Project ReFlowr
Business Report Project ReFlowr
 
Magma v1.4
Magma v1.4Magma v1.4
Magma v1.4
 

Recently uploaded

What Are the Latest Trends in Endpoint Security for 2024?
What Are the Latest Trends in Endpoint Security for 2024?What Are the Latest Trends in Endpoint Security for 2024?
What Are the Latest Trends in Endpoint Security for 2024?
VRS Technologies
 
Earthmovers: Top Earth Moving Equipments
Earthmovers: Top Earth Moving EquipmentsEarthmovers: Top Earth Moving Equipments
Earthmovers: Top Earth Moving Equipments
earthmoverinternatio
 
Importance of BWTS in the Maritime Industry
Importance of BWTS in the Maritime IndustryImportance of BWTS in the Maritime Industry
Importance of BWTS in the Maritime Industry
Blessed Marine Automation
 
SECUREX UK FOR SECURITY SERVICES AND MOBILE PATROL
SECUREX UK FOR SECURITY SERVICES AND MOBILE PATROLSECUREX UK FOR SECURITY SERVICES AND MOBILE PATROL
SECUREX UK FOR SECURITY SERVICES AND MOBILE PATROL
securexukweb
 
Best Catering Event Planner Miso-Hungry.pptx
Best Catering Event Planner  Miso-Hungry.pptxBest Catering Event Planner  Miso-Hungry.pptx
Best Catering Event Planner Miso-Hungry.pptx
Miso Hungry
 
Best steel industrial company LLC in UAE
Best steel industrial company LLC in UAEBest steel industrial company LLC in UAE
Best steel industrial company LLC in UAE
alafnanmetals
 
Nature’s Paradise Glamorous And Sustainable Designs For Your Outdoor Living S...
Nature’s Paradise Glamorous And Sustainable Designs For Your Outdoor Living S...Nature’s Paradise Glamorous And Sustainable Designs For Your Outdoor Living S...
Nature’s Paradise Glamorous And Sustainable Designs For Your Outdoor Living S...
Landscape Express
 
Elevate Your Brand with Digital Marketing for Fashion Industry
Elevate Your Brand with Digital Marketing for Fashion IndustryElevate Your Brand with Digital Marketing for Fashion Industry
Elevate Your Brand with Digital Marketing for Fashion Industry
Matebiz Pvt. Ltd
 
Are Gutters Necessary? Explore the details now!
Are Gutters Necessary? Explore the details now!Are Gutters Necessary? Explore the details now!
Are Gutters Necessary? Explore the details now!
AmeliaLauren3
 
Chandigarh call garal serives 9512450098
Chandigarh call garal serives 9512450098Chandigarh call garal serives 9512450098
Chandigarh call garal serives 9512450098
Chandigarh export services garal
 
Delightful Finds: Unveiling the Power of Gifts Under 100
Delightful Finds: Unveiling the Power of Gifts Under 100Delightful Finds: Unveiling the Power of Gifts Under 100
Delightful Finds: Unveiling the Power of Gifts Under 100
JoyTree Global
 
Comprehensive Water Damage Restoration Services
Comprehensive Water Damage Restoration ServicesComprehensive Water Damage Restoration Services
Comprehensive Water Damage Restoration Services
kleenupdisaster
 
Hospitality Training for Hotel Industries
Hospitality Training for Hotel IndustriesHospitality Training for Hotel Industries
Hospitality Training for Hotel Industries
VanieTAnggita
 
BEst VASHIKARAN SPECIALIST 9463629203 in UK Baba ji Love Marriage problem sol...
BEst VASHIKARAN SPECIALIST 9463629203 in UK Baba ji Love Marriage problem sol...BEst VASHIKARAN SPECIALIST 9463629203 in UK Baba ji Love Marriage problem sol...
BEst VASHIKARAN SPECIALIST 9463629203 in UK Baba ji Love Marriage problem sol...
gitapress3
 
Maximizing Efficiency with Integrated Water Management Systems
Maximizing Efficiency with Integrated Water Management SystemsMaximizing Efficiency with Integrated Water Management Systems
Maximizing Efficiency with Integrated Water Management Systems
Irri Design Studio
 
The Jamstack Revolution: Building Dynamic Websites with Static Site Generator...
The Jamstack Revolution: Building Dynamic Websites with Static Site Generator...The Jamstack Revolution: Building Dynamic Websites with Static Site Generator...
The Jamstack Revolution: Building Dynamic Websites with Static Site Generator...
Softradix Technologies
 
Inspect Edge & NSPIRE Inspection Application - Streamline Housing Inspections
Inspect Edge & NSPIRE Inspection Application - Streamline Housing InspectionsInspect Edge & NSPIRE Inspection Application - Streamline Housing Inspections
Inspect Edge & NSPIRE Inspection Application - Streamline Housing Inspections
inspectedge1
 
BesT panDit Ji LoVe problem solution 9463629203 UK uSA California New Zealand...
BesT panDit Ji LoVe problem solution 9463629203 UK uSA California New Zealand...BesT panDit Ji LoVe problem solution 9463629203 UK uSA California New Zealand...
BesT panDit Ji LoVe problem solution 9463629203 UK uSA California New Zealand...
gitapress3
 
SIMBA SQUAD : Best seo company in perth
SIMBA SQUAD :  Best seo company in perthSIMBA SQUAD :  Best seo company in perth
SIMBA SQUAD : Best seo company in perth
ridebiler
 
How Does Littering Affect the Environment.
How Does Littering Affect the Environment.How Does Littering Affect the Environment.
How Does Littering Affect the Environment.
ClenliDirect
 

Recently uploaded (20)

What Are the Latest Trends in Endpoint Security for 2024?
What Are the Latest Trends in Endpoint Security for 2024?What Are the Latest Trends in Endpoint Security for 2024?
What Are the Latest Trends in Endpoint Security for 2024?
 
Earthmovers: Top Earth Moving Equipments
Earthmovers: Top Earth Moving EquipmentsEarthmovers: Top Earth Moving Equipments
Earthmovers: Top Earth Moving Equipments
 
Importance of BWTS in the Maritime Industry
Importance of BWTS in the Maritime IndustryImportance of BWTS in the Maritime Industry
Importance of BWTS in the Maritime Industry
 
SECUREX UK FOR SECURITY SERVICES AND MOBILE PATROL
SECUREX UK FOR SECURITY SERVICES AND MOBILE PATROLSECUREX UK FOR SECURITY SERVICES AND MOBILE PATROL
SECUREX UK FOR SECURITY SERVICES AND MOBILE PATROL
 
Best Catering Event Planner Miso-Hungry.pptx
Best Catering Event Planner  Miso-Hungry.pptxBest Catering Event Planner  Miso-Hungry.pptx
Best Catering Event Planner Miso-Hungry.pptx
 
Best steel industrial company LLC in UAE
Best steel industrial company LLC in UAEBest steel industrial company LLC in UAE
Best steel industrial company LLC in UAE
 
Nature’s Paradise Glamorous And Sustainable Designs For Your Outdoor Living S...
Nature’s Paradise Glamorous And Sustainable Designs For Your Outdoor Living S...Nature’s Paradise Glamorous And Sustainable Designs For Your Outdoor Living S...
Nature’s Paradise Glamorous And Sustainable Designs For Your Outdoor Living S...
 
Elevate Your Brand with Digital Marketing for Fashion Industry
Elevate Your Brand with Digital Marketing for Fashion IndustryElevate Your Brand with Digital Marketing for Fashion Industry
Elevate Your Brand with Digital Marketing for Fashion Industry
 
Are Gutters Necessary? Explore the details now!
Are Gutters Necessary? Explore the details now!Are Gutters Necessary? Explore the details now!
Are Gutters Necessary? Explore the details now!
 
Chandigarh call garal serives 9512450098
Chandigarh call garal serives 9512450098Chandigarh call garal serives 9512450098
Chandigarh call garal serives 9512450098
 
Delightful Finds: Unveiling the Power of Gifts Under 100
Delightful Finds: Unveiling the Power of Gifts Under 100Delightful Finds: Unveiling the Power of Gifts Under 100
Delightful Finds: Unveiling the Power of Gifts Under 100
 
Comprehensive Water Damage Restoration Services
Comprehensive Water Damage Restoration ServicesComprehensive Water Damage Restoration Services
Comprehensive Water Damage Restoration Services
 
Hospitality Training for Hotel Industries
Hospitality Training for Hotel IndustriesHospitality Training for Hotel Industries
Hospitality Training for Hotel Industries
 
BEst VASHIKARAN SPECIALIST 9463629203 in UK Baba ji Love Marriage problem sol...
BEst VASHIKARAN SPECIALIST 9463629203 in UK Baba ji Love Marriage problem sol...BEst VASHIKARAN SPECIALIST 9463629203 in UK Baba ji Love Marriage problem sol...
BEst VASHIKARAN SPECIALIST 9463629203 in UK Baba ji Love Marriage problem sol...
 
Maximizing Efficiency with Integrated Water Management Systems
Maximizing Efficiency with Integrated Water Management SystemsMaximizing Efficiency with Integrated Water Management Systems
Maximizing Efficiency with Integrated Water Management Systems
 
The Jamstack Revolution: Building Dynamic Websites with Static Site Generator...
The Jamstack Revolution: Building Dynamic Websites with Static Site Generator...The Jamstack Revolution: Building Dynamic Websites with Static Site Generator...
The Jamstack Revolution: Building Dynamic Websites with Static Site Generator...
 
Inspect Edge & NSPIRE Inspection Application - Streamline Housing Inspections
Inspect Edge & NSPIRE Inspection Application - Streamline Housing InspectionsInspect Edge & NSPIRE Inspection Application - Streamline Housing Inspections
Inspect Edge & NSPIRE Inspection Application - Streamline Housing Inspections
 
BesT panDit Ji LoVe problem solution 9463629203 UK uSA California New Zealand...
BesT panDit Ji LoVe problem solution 9463629203 UK uSA California New Zealand...BesT panDit Ji LoVe problem solution 9463629203 UK uSA California New Zealand...
BesT panDit Ji LoVe problem solution 9463629203 UK uSA California New Zealand...
 
SIMBA SQUAD : Best seo company in perth
SIMBA SQUAD :  Best seo company in perthSIMBA SQUAD :  Best seo company in perth
SIMBA SQUAD : Best seo company in perth
 
How Does Littering Affect the Environment.
How Does Littering Affect the Environment.How Does Littering Affect the Environment.
How Does Littering Affect the Environment.
 

Project Management Plan - Microsoft Project

  • 1. 1 Science Frenzy Project Plan Proposed by Megan McDaniel, Allyson Bone, and George Kairis Snapdoodle Toys (425)408-0021 7330 NE Bothell Way Kenmore, WA 98028
  • 2. 2 Table of Contents Section 1: Project Overview ......................................................................................................................... 3 1.1 Problem Statement....................................................................................................................... 3 1.2 Project Overview.......................................................................................................................... 3 1.3 Goals and Objectives.................................................................................................................... 4 1.4 Project Scope................................................................................................................................. 4 1.5 Critical Success Factors............................................................................................................... 4 1.6 Project Assumptions..................................................................................................................... 5 1.7 Project Constraints and Risks .................................................................................................... 5 Section 2: Major Project Milestones ............................................................................................................ 5 2.1 Project Milestones ........................................................................................................................ 5 2.2 Work Breakdown Structure (WBS) ............................................................................................ 6 Section 3: Project Structure.......................................................................................................................... 6 3.1 Project Structure.......................................................................................................................... 6 3.2 Roles and Responsibilities........................................................................................................... 7 3.3 Responsibility Matrix.................................................................................................................... 7 Section 4: Project Schedule.......................................................................................................................... 8 Section 5: Budget.......................................................................................................................................... 9 Section 6: Risk Management...................................................................................................................... 10 Section 7: Approvals................................................................................................................................... 11 Section 8: Revision History......................................................................................................................... 11 Section 9: Appendices ................................................................................................................................ 11
  • 3. 3 Section 1: Project Overview 1.1 Problem Statement Snapdoodle Toys is a locally owned business that relies on its close knit relationship with the community for its survival. In order to keep customers interested and engaged at the store, Snapdoodle hosts a variety of events. These events range from adult game nights to preschool playdates. In order to boost sales in our science department and add a little variety to our regular events, we have chosen to host a science themed activity day in our Kenmore store. Snapdoodle Toys has been slowly increasing its business since the first year it opened. Last year, growth slowed down to a 2% increase in revenue over the course of the year. This year is the first year that Snapdoodle has not shown an increase in sales. Snapdoodle’s current priority is to jumpstart its growth to be able to continue to expand. One of the major concerns for Snapdoodle currently is the closure of another local toy store, Reigning Imaginations. In the long run, this closure should increase business at Snapdoodle, but in the short term it has heavily damaged Snapdoodle’s sales. The closeout clearance at Reigning Imaginations is pulling customers that would normally shop at Snapdoodle into Reigning Imaginations. In order to draw in their customers, Snapdoodle has increased their number of events. 1.2 Project Overview In an effort to boost sales for Snapdoodle Toys, we will be hosting a science themed event to draw customers into the store on Saturday, May 16th. From 4:00 PM to 7:00 PM, there will be 3 play stations for the kids to rotate through, as well as a presentation featuring experiments involving fun chemistry reactions and dry ice. By hosting this event, we will hopefully increase the amount of customers who visit the store and attend the events on a regular basis. In order to measure how successful our event is, we will compare sales from the day of the event to the sales from the previous year on the same day. We will consider the event a success if sales increase at least 10% from the previous year. We will also evaluate the number of purchases and attendance from new customers to determine if our marketing and outreach strategy is effective in not just maintaining current customers, but also for making connections with new ones. We aim to keep the costs of the event below $150 including inventory used in our event and employee wages. George and Megan will be volunteering their time to the project and Allyson will be accepting her regular employee wage. We will be assuming 2 employees will be present during the time of the event to manage regular store sales and customer attendance. The greatest constraint to our plan is the cost of materials for the 3 play stations and for the grand finale dry ice show.
  • 4. 4 1.3 Goals and Objectives The science event we are hosting will be directly supporting several of Snapdoodle’s goals and objectives. The following table lists the business goals and objectives that the event supports and how it supports them: Business Goal/Objective Description Increase Awareness in Science Related Toys Allowing children and families to play with the toys in the store with educated staff available to help demonstrate use and explain the science. Increase Company’s Word of Mouth Introducing a grand finale event will encourage parents and children to tell their friends about the show. Increase Customer Loyalty Reminding customers of Snapdoodle’s unique small business environment will hopefully encourage parents to support a company that values every child’s education rather than carrying the cheapest toys. Increase Overall Sales Attracting new and returning customers for the event and promoting certain products in particular will hopefully boost sales in those toys. Excite and Educate Children and Parents Hosting a science related toy party is both educational and fun. One-Of-A-Kind Customer Service This event is being run by volunteers, not the store staff. This allows the staff to simply focus on shopping customers and answering merchandise related questions instead of trying to juggle event planning and execution with their day to day tasks. 1.4 Project Scope Product Scope Description: The products/toys used during the event will be used from Snapdoodle Toys available stock and be calculated into our total cost. The materials that were used during the event included...  3 different varieties of bubble mixtures (smelly, touchable, and regular).  A bubble mystery questionnaire.  SnapCircuit Toys provided by a company representative.  A variety of building tools to build a marble roller coaster. Each of these products were demonstrated as science experiments and were chosen to result as a boost in overall sales and in that slower moving department. In addition to material requirements staff and volunteers required additional training on site before the event to prepare the stations and attract people to the event. Acceptance Criteria: Before project deliverables can be accepted, signatures of the owner and managing staff of Snapdoodle Toys needed to be collected, the available dates needed to be available in “The Doodle Zone” and the project charter needed to be accepted. 1.5 Critical Success Factors Please refer to Appendix 3: Performance Measurements
  • 5. 5 1.6 Project Assumptions The following assumptions apply to the Snapdoodle science party. As project planning begins and more assumptions are identified, they will be added accordingly.  All staff and volunteers will be trained accordingly in their respective stations and given specific responsibilities by project team members.  Funding is available for purchasing the necessary toys and demonstrative materials.  All department heads will provide necessary support for successful project completion.  Project has executive-level support and backing.  The Elenco Rep will be available for our event. 1.7 Project Constraints and Risks The following constraints apply to the Snapdoodle Event Project.  $1000 dollar budget  4-7 weeks time constraint  DoodleZone can only hold 60 people at a time.  Megan will not be available until 3:30pm on Saturday. (Work)  The event will last for three hours. The risks of our event are the weather keeping people from attending, the Elenco representative not showing up, and the demonstration not working. Please refer to Appendix 2: Short & Long Term Risk Section 2: Major Project Milestones 2.1 Project Milestones The following are the major project milestones. Milestones/Deliverables Target Date Project Charter 04/14/2015 Activities Planned 04/21/2015 Project Approval 04/23/2015 Schedule Set 05/09/2015 Supplies Obtained 05/10/2015 Event 05/16/2015 High-level Review 05/18/2015
  • 6. 6 2.2 Work Breakdown Structure (WBS) Plan Contact Elenco Rep Schedule Choose Activities Boss Approval Purchase Supplies Finale Training Advertising Reports Team Charter Problem Statement Work Breakdown Structure MS Project Schedule Budget Set Up Station 1 Station 2 Station 3 Finale Execution Interactive Stations Finale Clean Up Review Sales Data Department Data Review with Boss Approve Final Business Plan Facebook Email/Newsletters Update Website Elementary Schools Event RSVPs Section 3: Project Structure 3.1 Project Structure Project Communications Norms:  Every team member is expected to attend and be on time for scheduled meetings unless that individual has notified other members before hand and has a professional or medical excuse for their absence.  It is the responsibility of each member to communicate with everyone else in the group their inability to complete their responsibilities within the scheduled timing.  In the event of a member’s inability to fulfill his/her responsibilities, the other members will delegate equally the incomplete work among each other to ensure deadline requirements and project completion.  All team members are required to participate and be present for the duration of the planned event (including set-up and teardown time as needed). If there is conflicting issues with time or location, other members must be notified immediately. Potential Barriers and Coping Strategies: Different schedules in terms of workload and classes. Solutions include texting, google docs, email, or online meeting applications such as FaceTime or Skype. Team members will be expected to respond to online content within 24 hours of posting.  If a team member’s work is not up to the team’s standards then the team will be responsible for providing that member with input to help them improve their work’s quality.
  • 7. 7  Considering this team consists of 3 members, if there is a disagreement on how to proceed we will negotiate to 2 ideas and take a vote by hand. Repercussions for Breaking Communication Expectations: If this team charter is not respected by any member for any reason then that team member will be asked to explain their actions and collaborate with the group on how to move forward. They will also be required by charter law to wear a full clown suit to class and perform tricks at the other members leisure/enjoyment. 3.2 Roles and Responsibilities The following individuals comprise the stakeholders for the project. Role Description Name/Title Organizer Coordinates team objectives using limited resources Megan McDaniel, Team Member Spokesperson Connects the team to Snapdoodle Toys Allyson Bone, Team Member Handyman Helps/operates the event stations George Kairis, Team Member Client Authority to accept/reject project deliverables Rob Pickering, Store Owner Client Authority to accept/reject project deliverables Candy Caylor, Resource Manager Staff Management Provides staff members for event Polly Shinner, Store Manager 3.3 Responsibility Matrix Please refer to Appendix 1: Responsibility Assignment Matrix
  • 9. 9 Section 5: Budget The following table captures the relevant costs and descriptions of these actions associated with the total planned event period. Action Action Type Description First year costs (- indicates anticipated savings) Purchase Demonstration Materials and Toys Cost Bubble Station, SnapCircuit Equipment, Building Materials, Dry Ice Show $150.00 Team members compensation Cost Planning, scheduling, organizing, and running the event ($15 hourly rate) $437.50 Pay Employee Wages Cost 2 employees on staff from 2:00pm - 6:00pm at their standard rate $80.00 Total Cost $667.5 By running this event we anticipate an increase of $1500 the day of the event, and an increase of future sales due to the demonstration of the toys and the increased store brand awareness. The gross margin of our anticipated sales on the day of the event is 55.5%.
  • 10. 10 Section 6: Risk Management Below is a list of our risks and the actions taken to minimize them. Risk ID WBS Rank Description Strategy 1 1.2 Yellow The DoodleZone may not be large enough to accommodate over 60 guests. Create additional event space within the store to accommodate approximately 60 customers. In addition, look for outdoor options depending on the weather conditions. 2 1.0 Yellow Weather conditions the day of the event. Although weather forecast doesn’t predict any bad weather conditions, we can’t actually control unexpected weather changes that may occur which can affect our customer count and revenue. 3 1.3 Green The Elenco rep (snap circuit station) may not show up for the event. We will assign to a store employee the snap circuit station in case the sales rep is unable to attend the event. In addition, one of our team members will be familiar with the games and take over if there are too many customers showing up. 4 1.0 Red Not everyone who plans to attend our event will RSVP. When planning the event, we will aim for maximum flexibility in order to accommodate for any level of attendance. 5 1.1 Yellow Team member lack of product knowledge. Team members should have full knowledge of the products and their functions. We will hold short training sessions to get familiar with the toys we are planning to promote. 6 1.1 Green Consistent image during the event promotion. Optimize our communication with the promoters so we can all be on the same page. 7 1.3 Red Dry Ice presentation safety concerns. Our dry ice presentation will take place half hour before the event. During this half hour we will not demonstrate other toys/products. All team members will control the space around the dry ice presentation as we want to prevent young children touching or playing with the dry ice material (may cause skin burns due to extreme low temperature)
  • 11. 11 Section 7: Approvals The signatures of the people below indicate an understanding in the purpose and content of this Project charter by those signing it. By signing this document you indicate that you approve of the proposed project outlined in this project charter and that the next steps may be taken to create a formal project in accordance with the details outlined herein. Section 8: Revision History Version Date Name Description 1.0 05/07/2015 Project Plan Outline Began formatting and creating headings to shape the document 1.1 5/28/2015 Google Doc Draft All group members submitted their segments 1.1 6/1/2015 Final Project Plan Final Document. Final formatting and wording fixes. Section 9: Appendices Appendix 1: Responsibility Assignment Matrix Activity N,I,C,I Issues Delivery Date Owner Project Sign Off Complete Boss on Vacation. 04/19/2015 Allyson Event/Project WBS Complete No Issues. 04/21/2015 George Contacting Schools Complete Verified local school’s newsletter and event notification process. Completion will be a few days before the week of the event. 05/07/2015 Megan Plan Stations Complete No issues 04/30/2015 Team
  • 12. 12 Contact Elenco Rep Complete Unable to attend, but provided materials for event. 05/02/2015 Allyson Microsoft Project Schedule Complete It is difficult to work on a single project file on a single computer. 05/05/2015 Team Budget and Time-Phased Budget Complete Megan not available 05/05/2015 Team Advertising Complete Facebook event page completed and tracked by Allyson. Website manager at Snapdoodle Toys posted an invite on official website. 5/12/2015 Allyson & Snapdoodle Manager Final Written Project Complete No issues 05/21/2015 Team Appendix 2: Short & Long Term Risk Short Term Risks 1. Hopefully, all of the people who promote our event promote it with a consistent image. 2. Not everyone who plans to attend our event will RSVP, making it challenging to plan for the future. Long Term Risks 1. The DoodleZone/store may not be large enough to accommodate over 60 guests. In order to prepare for this risk, we are creating a method that will allow guests to RSVP for the event so that we can get a feel for how many guests will actually be appearing at the store. We are also looking into the possibility of setting up some of our play stations outside. 2. The weather may not be very good. If the weather is poor, we will have fewer guests attend our event. This is not a risk that we can control. Appendix 3: Performance Measurements The following table lists the key resources, processes, or services and their anticipated business outcomes in measuring the performance of the project. These performance measures will be quantified and further defined in the detailed project plan. Key Process/Service Performance Measure Overall Store Sales Store Sales Data (Quickbooks’ Point of Sale) Department Sales Department Sales Data (Quickbooks’ Point of Sale) New Attendees Customer Database (Quickbooks’ Point of Sale) Customer Satisfaction Comment Box