Question :
I am trying to use validation in the Project. Can any one tell when are the call up
points 110 and 120 trigerred ?
I want to validate one of the user defined fields in WBS.
Everything is working fine when I simulate the validation. But when I enter a value in
the user defined field and save the project then I do not get the error message as
expected.
Does anybody have an idea what could be wrong ??
Answer :
Please see if you have checked the check box for Automatic validation in the relevant
project profile.
Question :
I want to validate the customer number in one of the user fields in WBS. The
formula builder in the validation screen, it seems, does not support table fields other
than fields from PRPS. Can this be done thru some user exits ?? If yes how ?? Can u
guide me in this ??
Answer :
To use a user exit in validations, you have to perform following steps;
- copy SAP standard program GGBS002 to ZGGBS002
- create a user exit in this program (such as U902, U903 etc)
- the user exit you defined in the above mentioned program will be visible in
validations on screen tab 'Exits'
- configure your validation with 'User exit' as option
Planned Cost Differs from Actual Cost
Question :
I have a problem. I have a standard activity which the price is $1 / hr. I have created
a project in which a activity has a planned hr of qty 1. But my planned cost comes in
as '$0.83'. But when I comfirm my activity, the actual cost comes in as '$1'.
Why is my planned cost differing? What is the cause of the $0.83 instead of $1.
Where can i check and change this.
Answer :
I guess that you use different costing (and valuation) variants. so the system might
valuate plan and actuals differently.
Question :
Where and how do i control it?
Answer :
In the network header are two fields: one for the plan costing variant and one for the
actual costing variant.
You maintain the costing variants in the customizing: PS -> Costs -> Planned Costs ->
Automatic
Costing in Networks -> Costing -> Define Costing Variants. Display the costing
variant and jump to the valuation variant. There you find how the determines the
costs.
Validations in PS
Question :
I am trying to use validation in the Project. Can any one tell when are the call up
points 110 and 120 trigerred ?
I want to validate one of the user defined fields in WBS.
Everything is working fine when I simulate the validation. But when I enter a value in
the user defined field and save the project then I do not get the error message as
expected.
Does anybody have an idea what could be wrong ??
Answer :
Please see if you have checked the check box for Automatic validation in the relevant
project profile.
Question :
I want to validate the customer number in one of the user fields in WBS. The
formula builder in the validation screen, it seems, does not support table fields other
than fields from PRPS. Can this be done thru some user exits ?? If yes how ?? Can u
guide me in this ??
Answer :
To use a user exit in validations, you have to perform following steps;
- copy SAP standard program GGBS002 to ZGGBS002
- create a user exit in this program (such as U902, U903 etc)
- the user exit you defined in the above mentioned program will be visible in
validations on screen tab 'Exits'
- configure your validation with 'User exit' as option
WBS description doesn´t appear completely in hierarchical
Question :
In the hierarchical reports in PS de WBS description is not showed completely. Do
you know a way to make this appear completely?
Answer :-
We are on 4.6B and this is what you can do. :-
1) Execute report
2) Expand your results, if necessary
3) Click on any WBS line description
4) Follow the menu path Settings/Characteristic display
5) Choose lead column
6) Move object short description to the value set side of the panel
7) Move object long description to the lead column side of the panel
Save (if you have authorization). Note you can use this procedure for any other object
that may show up on the report display. i.e. navigation characteristics change the
objects displayed.
Anyway to put checks before setting to TECO?
Question :
Can anyone pl let me know about the followings:
Is there any way to put checks (in the form of tick mark etc) before setting the system
status to "TECO"- e.g. some documents are received or not etc.
Answer :
You can set the system status to Technically completed TECO which can be later on
withdrawn. The necessary changes are reflected in the system status on saving the
Network
With the setup of user statusses (tr. OIBS), you have the ability to disable the 'TECO'
as long as a certain user status 'e.g. waiting for documents' is active
WBS description doesn´t appear completely in hierarchical
Question :
In the hierarchical reports in PS de WBS description is not showed completely. Do
you know a way to make this appear completely?
Answer :-
We are on 4.6B and this is what you can do. :-
1) Execute report
2) Expand your results, if necessary
3) Click on any WBS line description
4) Follow the menu path Settings/Characteristic display
5) Choose lead column
6) Move object short description to the value set side of the panel
7) Move object long description to the lead column side of the panel
Save (if you have authorization). Note you can use this procedure for any other object
that may show up on the report display. i.e. navigation characteristics change the
objects displayed.
Anyway to put checks before setting to TECO?
Question :
Can anyone pl let me know about the followings:
Is there any way to put checks (in the form of tick mark etc) before setting the system
status to "TECO"- e.g. some documents are received or not etc.
Answer :
You can set the system status to Technically completed TECO which can be later on
withdrawn. The necessary changes are reflected in the system status on saving the
Network
With the setup of user statusses (tr. OIBS), you have the ability to disable the 'TECO'
as long as a certain user status 'e.g. waiting for documents' is active
Links to documents stored on the Web
Question :
Is there a way to create a document (under a project) which refers to a URL and not to
a document stored on a content server?
Answer :
Yes you can, but you need define in DMS customizing some points.
1.- Inner "Define Data Carriers" in Define data carrier type external "DMS" a record
with this information: TYP = IE, Description = That you want, Check ONLINE and
EX, the inside this in Define External DMS create a record with DATACAR =
INTERNET, TYP = IE, Description = That you want, Check EX.
2.- Inner "Define Workstation Applications" define an application for web pages
without file format, inside this in "Define Workstation applications in network" create
records for options 1, 2, 3, the path of location of your navigator in your PC or you
can put "%AUTO% iexplore.exe %f". Then when you create a document in the
Original field you can put the URL and in the Data Carrier field put the name that you
define in the customizing.
How to settlement auc to asset in PS?
Question :
The cost of project have settled to auc(investment asset), but when the project is
finished, in AM or in PS i can't settle auc to asset?
Pls give me some suggestion! Any idea is appreciation!
Answer :
You must set technically complete for your WBS & NW before settle AUC to Assets.
Links to documents stored on the Web
Question :
Is there a way to create a document (under a project) which refers to a URL and not to
a document stored on a content server?
Answer :
Yes you can, but you need define in DMS customizing some points.
1.- Inner "Define Data Carriers" in Define data carrier type external "DMS" a record
with this information: TYP = IE, Description = That you want, Check ONLINE and
EX, the inside this in Define External DMS create a record with DATACAR =
INTERNET, TYP = IE, Description = That you want, Check EX.
2.- Inner "Define Workstation Applications" define an application for web pages
without file format, inside this in "Define Workstation applications in network" create
records for options 1, 2, 3, the path of location of your navigator in your PC or you
can put "%AUTO% iexplore.exe %f". Then when you create a document in the
Original field you can put the URL and in the Data Carrier field put the name that you
define in the customizing.
How to settlement auc to asset in PS?
Question :
The cost of project have settled to auc(investment asset), but when the project is
finished, in AM or in PS i can't settle auc to asset?
Pls give me some suggestion! Any idea is appreciation!
Answer :
You must set technically complete for your WBS & NW before settle AUC to Assets.
Updating the current Order cost plan
Question :
We are in 46C. Starting a project, we establish an Order cost plan. We plan the
amount of work (in hours) and specify the work center for each of the activities. For
material components, we enter the forecast material costs in the field "Material
planning". We see the total and detailed by activity cost plan in CNS41 (Structure
overview) in the column "Order cost plan 000". At some point in time, the project
advancement shows that we have to reconsider the original cost plan, for instance
because the actual costs collected so far are much higher than foreseen at start-up.
Management decides to change the cost plan 000 to reflect the new forecasted
budget. Management already told that they would like to be able to specify a new
total value for the Order cost plan 000 of the activity rather then to play with the
amount of work (hours) in the activity. They say it should be something like this (for
labor): (actual cost) + (number of hours to do * cost of work center) = order cost plan
000.
What options do we have to modify the "Order cost plan 000"??
Answer :
There is a functionality called cost forecast (transaction CJ9L/CJ9M). I think this is
exactly what you require. The forecasted costs are saved in a separate CO version.
You could try to display this version in CNS41.
Create network from Sales Order
Question :
We are currently running 4.6C and have implemented SD and PS. The situation is we
want to be able to create a network automatically from the sales order during creation.
I've assigned the strategy group 85 to the material master and I've defined the network
parameters from sales order (via transaction CN08).
The result...
During creation of the sales order (transaction VA01), the network is created
successfully but the components are not transferred to the network. Is it supposed to
or not? If so, what additional configuration should I look at?
I'm not very familiar with the standard functionality so I'm hoping someone out there
has experience with this topic.
Your time and insight is greatly appreciated,
Answer :
The components in assembly processing remain on the sales order only.
In case you are working with reasonably complex scenario on BOM and procurement,
where material items have their own dependencies schedulewise e.g to design, you
should put the materials on the network. The best way to accomplish this is to do the
BOM allocation (transfer) to activities and have only the invoicing item at sales order.
Updating the current Order cost plan
Question :
We are in 46C. Starting a project, we establish an Order cost plan. We plan the
amount of work (in hours) and specify the work center for each of the activities. For
material components, we enter the forecast material costs in the field "Material
planning". We see the total and detailed by activity cost plan in CNS41 (Structure
overview) in the column "Order cost plan 000". At some point in time, the project
advancement shows that we have to reconsider the original cost plan, for instance
because the actual costs collected so far are much higher than foreseen at start-up.
Management decides to change the cost plan 000 to reflect the new forecasted
budget. Management already told that they would like to be able to specify a new
total value for the Order cost plan 000 of the activity rather then to play with the
amount of work (hours) in the activity. They say it should be something like this (for
labor): (actual cost) + (number of hours to do * cost of work center) = order cost plan
000.
What options do we have to modify the "Order cost plan 000"??
Answer :
There is a functionality called cost forecast (transaction CJ9L/CJ9M). I think this is
exactly what you require. The forecasted costs are saved in a separate CO version.
You could try to display this version in CNS41.
Create network from Sales Order
Question :
We are currently running 4.6C and have implemented SD and PS. The situation is we
want to be able to create a network automatically from the sales order during creation.
I've assigned the strategy group 85 to the material master and I've defined the network
parameters from sales order (via transaction CN08).
The result...
During creation of the sales order (transaction VA01), the network is created
successfully but the components are not transferred to the network. Is it supposed to
or not? If so, what additional configuration should I look at?
I'm not very familiar with the standard functionality so I'm hoping someone out there
has experience with this topic.
Your time and insight is greatly appreciated,
Answer :
The components in assembly processing remain on the sales order only.
In case you are working with reasonably complex scenario on BOM and procurement,
where material items have their own dependencies schedulewise e.g to design, you
should put the materials on the network. The best way to accomplish this is to do the
BOM allocation (transfer) to activities and have only the invoicing item at sales order.
IM and FM
Question :
Is that possible to use IM to control investment projects and FM to control general
costs?
What is needed to be done in order to avoid conflicts between IM and PS ?
Answer :
Investment Management() IM Module is highly integrated with controlling(CO) ,
project system(PS), and Asset Management(FI-AA) components.
IF you would like to implement IM & PS you might ask yourself what additional
advantages are offered by using IM .
These Include:
1- in PS you can represent the planned and the budgeted values of all projects . using
IM you can represent the budgeting process from the organization pointview. IM
helps you track of budget amounts that you carry forward for projects that were
approved in prior fisical year.
2- Using AR in IM CAN help you decide what budget will be assigned to your
organization Unit.
IM Handles Cost Planning & Budget Approval and PS Manages Project Execution
with AVAC for the Budget for each project.
Multiple Root WBS
Question :
Can any one tell me in detail of advantages and Dis-advantages of Multiples Root
WBS in the project.And one more why do you using the same coding Mask for PD
and Root WBS.
I would appreciate in advance.
Answer :
Multiple Root WBSEs helps in budgeting scenarios where these WBSEs are funded
from different
sources say a customer project has part scope of R&D (funded by R&D).
You may also want to fund these root WBSEs from IM programs (linking to position
IDs.)
IM and FM
Question :
Is that possible to use IM to control investment projects and FM to control general
costs?
What is needed to be done in order to avoid conflicts between IM and PS ?
Answer :
Investment Management() IM Module is highly integrated with controlling(CO) ,
project system(PS), and Asset Management(FI-AA) components.
IF you would like to implement IM & PS you might ask yourself what additional
advantages are offered by using IM .
These Include:
1- in PS you can represent the planned and the budgeted values of all projects . using
IM you can represent the budgeting process from the organization pointview. IM
helps you track of budget amounts that you carry forward for projects that were
approved in prior fisical year.
2- Using AR in IM CAN help you decide what budget will be assigned to your
organization Unit.
IM Handles Cost Planning & Budget Approval and PS Manages Project Execution
with AVAC for the Budget for each project.
Multiple Root WBS
Question :
Can any one tell me in detail of advantages and Dis-advantages of Multiples Root
WBS in the project.And one more why do you using the same coding Mask for PD
and Root WBS.
I would appreciate in advance.
Answer :
Multiple Root WBSEs helps in budgeting scenarios where these WBSEs are funded
from different
sources say a customer project has part scope of R&D (funded by R&D).
You may also want to fund these root WBSEs from IM programs (linking to position
IDs.)
Question : Subject : PS Assets under Construction
Hello All,
I know that I can maintain the Plant for the WBS Element, what I would like to know
is if it is also possible to maintain the Location as well? I've heard that it is not
possible but I would like to hear other opinions. Any suggestions? We are on version
4.0B.
I would like to know since the Asset Management people here are asking if it's
possible to maintain it in PS or if this can only be done in AM.
MM is not included in this implementation, but we did set up the Plants and
Locations.
Happy Holidays!
Regards,
Reply : Subject : PS Assets under Construction
Yes, you can maintain a location for a WBS element as well. Select WBS element,
follow path Details > Orgainsation. This screen has a field called Functional Location,
apart from other orgainsation details such as Controlling Area, Company Code,
Business Area, Plant, Calender etc.
Hope this helps.
Reagrds
Question : Subject : PS Network Status's & Confirmations
Sappers:
Is there a status that can be set for a network activity that will stop time confirmations
from being processed? TECO stops changes to the basic data, but allows further time
confirmations.
TIA
Reply : Subject : PS Network Status's & Confirmations
hi...
you can lock account assignment for the network/activity in consideration depending
on whether the network is header/activity
assigned. This disallows the confirmation of the activities.
...else you can use the user status
regards...
Any Variant Capabilities in CM07 Report
I am executing the CM07 report whuich is the Variable Capacity Planning
Report.
Out of which, I like the results because I obtain the fields I need by going thru
the individual ''choose fields'' button.
However in 4,6c) it does seem to have any variant capabilities ???
I have to reenter the fields selection every item I back out of the report ... Which
is a bit anoying !!!
Anyone has any recipes for this so that columns/criterias selected can be save
guarded for the next time ???
There are Variant list capabilities for CM07 Capacity report.
Mainly via PS-> Information Systems->Resources->Tools->Resources->Selection-
>General Profile (OPA6) and also
via PS-> Information Systems->Resources->Tools->Resources->Selection->
Variant List Poifile Details (OPDT).
You create a new ''Z'' Variant Profile list with all the fields that you want to select and
show in yopur CM0? report .
Be carefull to click correctly on the greenish/yellowish arrow to bring up the field
selections pop up window...
Than associate this new Z Variant Profile to a newly defined ''Z'' General Profile...
Then after you can override with othe Variant Lists in the profile selection of the
CM07 report txn. itself if needed...
Change Documents in SAP Project
In the Customising for Create Project Profile (OPSA) there are 2 fields for
"Change Documents".
Where and how is this useful during implemenation.
There are 2 outcomes for change documents and they should both be implemented if
it's important that you keep track of changes made to a project:
General changes (the one at the top)
- any field content changes made to a project WBS after it was first saved will be
recorded in a file. eg. if you changes the WBS description, the old value and the new
value will be recorded, or if you changed a person responsible, it would also be
recorded etc. This information can be reviewed in Info Systems report CN60 to
old/new values and who/when.
Status Managment (the one checked in Status Management)
- any changes to System and User Status will be recorded, including the status history
and who/when. Changes can be seen in any project maintenance transaction (eg.
CJ02, CJ20N) by clicking on the "i" icon for a PD or WBS, then following the
internal pull-down menu path: Extras>Change Documents> For Status/All.You can
then drill-down on the satus to see its history.

More Related Content

What's hot

xCP2 0 Performance Best Practices and Guidelines
xCP2 0 Performance Best Practices and GuidelinesxCP2 0 Performance Best Practices and Guidelines
xCP2 0 Performance Best Practices and GuidelinesHaytham Ghandour
 
Rc085 010d-vaadin7
Rc085 010d-vaadin7Rc085 010d-vaadin7
Rc085 010d-vaadin7Cosmina Ivan
 
Oracle EBS 12.1.3 : Integrate OA Framework BC4J components within java concur...
Oracle EBS 12.1.3 : Integrate OA Framework BC4J components within java concur...Oracle EBS 12.1.3 : Integrate OA Framework BC4J components within java concur...
Oracle EBS 12.1.3 : Integrate OA Framework BC4J components within java concur...Amit Singh
 

What's hot (8)

UI Testing Pattern
UI Testing PatternUI Testing Pattern
UI Testing Pattern
 
Test data article
Test data articleTest data article
Test data article
 
exa_cer_g23
exa_cer_g23exa_cer_g23
exa_cer_g23
 
xCP2 0 Performance Best Practices and Guidelines
xCP2 0 Performance Best Practices and GuidelinesxCP2 0 Performance Best Practices and Guidelines
xCP2 0 Performance Best Practices and Guidelines
 
Lab4 RTC Builds
Lab4 RTC BuildsLab4 RTC Builds
Lab4 RTC Builds
 
Hats tutorial custom widget
Hats tutorial   custom widgetHats tutorial   custom widget
Hats tutorial custom widget
 
Rc085 010d-vaadin7
Rc085 010d-vaadin7Rc085 010d-vaadin7
Rc085 010d-vaadin7
 
Oracle EBS 12.1.3 : Integrate OA Framework BC4J components within java concur...
Oracle EBS 12.1.3 : Integrate OA Framework BC4J components within java concur...Oracle EBS 12.1.3 : Integrate OA Framework BC4J components within java concur...
Oracle EBS 12.1.3 : Integrate OA Framework BC4J components within java concur...
 

Viewers also liked

Capture that lead
Capture that leadCapture that lead
Capture that leadDanny Steed
 
Ejercicios de PP
Ejercicios de PPEjercicios de PP
Ejercicios de PPncalleja
 
Skill Resume
Skill ResumeSkill Resume
Skill Resumerhilding
 
NCL 2008 First Reunion Cruise Presentation
NCL 2008 First Reunion Cruise PresentationNCL 2008 First Reunion Cruise Presentation
NCL 2008 First Reunion Cruise PresentationBuckeyeTraveler
 
Nov 2012 reunion presentation
Nov 2012 reunion presentationNov 2012 reunion presentation
Nov 2012 reunion presentationBuckeyeTraveler
 
Visual Resume: Dominick White
Visual Resume: Dominick WhiteVisual Resume: Dominick White
Visual Resume: Dominick WhiteJayMirar12
 
A alma abatida - Harpa Cristã
A alma abatida - Harpa CristãA alma abatida - Harpa Cristã
A alma abatida - Harpa CristãJean Max
 
Reliability Training Lesson 1 Basics
Reliability Training Lesson 1   BasicsReliability Training Lesson 1   Basics
Reliability Training Lesson 1 Basicsrhilding
 
AudioとガジェットをWebで遊ぶ - Web Audio/MIDI Web Bluetooth -
AudioとガジェットをWebで遊ぶ - Web Audio/MIDI Web Bluetooth -AudioとガジェットをWebで遊ぶ - Web Audio/MIDI Web Bluetooth -
AudioとガジェットをWebで遊ぶ - Web Audio/MIDI Web Bluetooth -Ryoya Kawai
 
Front Architecting for the Enterprise
Front Architecting for the EnterpriseFront Architecting for the Enterprise
Front Architecting for the EnterpriseThomas Cowell
 
Web audio control-webaudio.tokyo
Web audio control-webaudio.tokyoWeb audio control-webaudio.tokyo
Web audio control-webaudio.tokyoRyoya Kawai
 
Historia clínica obstétrica, ginecológica, prenatal y perinatal.
Historia clínica obstétrica, ginecológica, prenatal y perinatal.Historia clínica obstétrica, ginecológica, prenatal y perinatal.
Historia clínica obstétrica, ginecológica, prenatal y perinatal.andreita39
 

Viewers also liked (17)

Capture that lead
Capture that leadCapture that lead
Capture that lead
 
Course content
Course contentCourse content
Course content
 
Ejercicios de PP
Ejercicios de PPEjercicios de PP
Ejercicios de PP
 
Aviso 5 separaciones
Aviso 5 separacionesAviso 5 separaciones
Aviso 5 separaciones
 
Skill Resume
Skill ResumeSkill Resume
Skill Resume
 
NCL 2008 First Reunion Cruise Presentation
NCL 2008 First Reunion Cruise PresentationNCL 2008 First Reunion Cruise Presentation
NCL 2008 First Reunion Cruise Presentation
 
Twitpic is shutting down!
Twitpic is shutting down!Twitpic is shutting down!
Twitpic is shutting down!
 
Sunu1
Sunu1Sunu1
Sunu1
 
Nov 2012 reunion presentation
Nov 2012 reunion presentationNov 2012 reunion presentation
Nov 2012 reunion presentation
 
Visual Resume: Dominick White
Visual Resume: Dominick WhiteVisual Resume: Dominick White
Visual Resume: Dominick White
 
A alma abatida - Harpa Cristã
A alma abatida - Harpa CristãA alma abatida - Harpa Cristã
A alma abatida - Harpa Cristã
 
Reliability Training Lesson 1 Basics
Reliability Training Lesson 1   BasicsReliability Training Lesson 1   Basics
Reliability Training Lesson 1 Basics
 
AudioとガジェットをWebで遊ぶ - Web Audio/MIDI Web Bluetooth -
AudioとガジェットをWebで遊ぶ - Web Audio/MIDI Web Bluetooth -AudioとガジェットをWebで遊ぶ - Web Audio/MIDI Web Bluetooth -
AudioとガジェットをWebで遊ぶ - Web Audio/MIDI Web Bluetooth -
 
Front Architecting for the Enterprise
Front Architecting for the EnterpriseFront Architecting for the Enterprise
Front Architecting for the Enterprise
 
Web audio control-webaudio.tokyo
Web audio control-webaudio.tokyoWeb audio control-webaudio.tokyo
Web audio control-webaudio.tokyo
 
Maturity?
Maturity?Maturity?
Maturity?
 
Historia clínica obstétrica, ginecológica, prenatal y perinatal.
Historia clínica obstétrica, ginecológica, prenatal y perinatal.Historia clínica obstétrica, ginecológica, prenatal y perinatal.
Historia clínica obstétrica, ginecológica, prenatal y perinatal.
 

Similar to VALIDATING PS DOCUMENTS

Sap ps module tutorial
Sap ps module tutorialSap ps module tutorial
Sap ps module tutorialachyuth10
 
PURPOSE of the project is Williams Specialty Company (WSC) reque.docx
PURPOSE of the project is Williams Specialty Company (WSC) reque.docxPURPOSE of the project is Williams Specialty Company (WSC) reque.docx
PURPOSE of the project is Williams Specialty Company (WSC) reque.docxamrit47
 
IBM Cognos Report Studio Version 10 Tips and Tricks – Webinar Q & A
IBM Cognos Report Studio Version 10 Tips and Tricks – Webinar Q & AIBM Cognos Report Studio Version 10 Tips and Tricks – Webinar Q & A
IBM Cognos Report Studio Version 10 Tips and Tricks – Webinar Q & ASenturus
 
How to broadcast a b ex report through e
How to broadcast a b ex report through eHow to broadcast a b ex report through e
How to broadcast a b ex report through eZaynab Fadlallah
 
]project-open[ Workflow Developer Tutorial Part 3
]project-open[ Workflow Developer Tutorial Part 3]project-open[ Workflow Developer Tutorial Part 3
]project-open[ Workflow Developer Tutorial Part 3Klaus Hofeditz
 
Dynamics ax 2012 workflow development
Dynamics ax 2012 workflow development Dynamics ax 2012 workflow development
Dynamics ax 2012 workflow development Ahmed Farag
 
Introduction to the .NET Access Control Service
Introduction to the .NET Access Control ServiceIntroduction to the .NET Access Control Service
Introduction to the .NET Access Control Servicebutest
 
Introduction to the .NET Access Control Service
Introduction to the .NET Access Control ServiceIntroduction to the .NET Access Control Service
Introduction to the .NET Access Control Servicebutest
 
Murach : How to develop a single-page MVC web
Murach : How to develop a single-page MVC web Murach : How to develop a single-page MVC web
Murach : How to develop a single-page MVC web MahmoudOHassouna
 
IBM Cognos 10.1.1 Active Reports New Features: Questions & Answers
IBM Cognos 10.1.1 Active Reports New Features: Questions & AnswersIBM Cognos 10.1.1 Active Reports New Features: Questions & Answers
IBM Cognos 10.1.1 Active Reports New Features: Questions & AnswersSenturus
 
sap-ps-project-systems
 sap-ps-project-systems sap-ps-project-systems
sap-ps-project-systemshollabackgirl1
 
Code instrumentation
Code instrumentationCode instrumentation
Code instrumentationMennan Tekbir
 
SAP FICO Interview Questions
SAP FICO Interview QuestionsSAP FICO Interview Questions
SAP FICO Interview QuestionsAjeesh Sudevan
 
IBM Cognos 10.1.1 Active Reports New Features: Questions & Answers
IBM Cognos 10.1.1 Active Reports New Features:  Questions & Answers IBM Cognos 10.1.1 Active Reports New Features:  Questions & Answers
IBM Cognos 10.1.1 Active Reports New Features: Questions & Answers Senturus
 
Evolutionary db development
Evolutionary db development Evolutionary db development
Evolutionary db development Open Party
 
Ps training mannual ( configuration )
Ps training mannual ( configuration )Ps training mannual ( configuration )
Ps training mannual ( configuration )Soumya De
 
Informatica interview questions by H2kInfosys
Informatica interview questions by H2kInfosysInformatica interview questions by H2kInfosys
Informatica interview questions by H2kInfosysH2kInfosys
 
Qtp interview questions_1
Qtp interview questions_1Qtp interview questions_1
Qtp interview questions_1Ramu Palanki
 

Similar to VALIDATING PS DOCUMENTS (20)

Sap ps module tutorial
Sap ps module tutorialSap ps module tutorial
Sap ps module tutorial
 
PURPOSE of the project is Williams Specialty Company (WSC) reque.docx
PURPOSE of the project is Williams Specialty Company (WSC) reque.docxPURPOSE of the project is Williams Specialty Company (WSC) reque.docx
PURPOSE of the project is Williams Specialty Company (WSC) reque.docx
 
IBM Cognos Report Studio Version 10 Tips and Tricks – Webinar Q & A
IBM Cognos Report Studio Version 10 Tips and Tricks – Webinar Q & AIBM Cognos Report Studio Version 10 Tips and Tricks – Webinar Q & A
IBM Cognos Report Studio Version 10 Tips and Tricks – Webinar Q & A
 
How to broadcast a b ex report through e
How to broadcast a b ex report through eHow to broadcast a b ex report through e
How to broadcast a b ex report through e
 
]project-open[ Workflow Developer Tutorial Part 3
]project-open[ Workflow Developer Tutorial Part 3]project-open[ Workflow Developer Tutorial Part 3
]project-open[ Workflow Developer Tutorial Part 3
 
1z0 591
1z0 5911z0 591
1z0 591
 
Dynamics ax 2012 workflow development
Dynamics ax 2012 workflow development Dynamics ax 2012 workflow development
Dynamics ax 2012 workflow development
 
Introduction to the .NET Access Control Service
Introduction to the .NET Access Control ServiceIntroduction to the .NET Access Control Service
Introduction to the .NET Access Control Service
 
Introduction to the .NET Access Control Service
Introduction to the .NET Access Control ServiceIntroduction to the .NET Access Control Service
Introduction to the .NET Access Control Service
 
Murach : How to develop a single-page MVC web
Murach : How to develop a single-page MVC web Murach : How to develop a single-page MVC web
Murach : How to develop a single-page MVC web
 
IBM Cognos 10.1.1 Active Reports New Features: Questions & Answers
IBM Cognos 10.1.1 Active Reports New Features: Questions & AnswersIBM Cognos 10.1.1 Active Reports New Features: Questions & Answers
IBM Cognos 10.1.1 Active Reports New Features: Questions & Answers
 
sap-ps-project-systems
 sap-ps-project-systems sap-ps-project-systems
sap-ps-project-systems
 
Sapps
SappsSapps
Sapps
 
Code instrumentation
Code instrumentationCode instrumentation
Code instrumentation
 
SAP FICO Interview Questions
SAP FICO Interview QuestionsSAP FICO Interview Questions
SAP FICO Interview Questions
 
IBM Cognos 10.1.1 Active Reports New Features: Questions & Answers
IBM Cognos 10.1.1 Active Reports New Features:  Questions & Answers IBM Cognos 10.1.1 Active Reports New Features:  Questions & Answers
IBM Cognos 10.1.1 Active Reports New Features: Questions & Answers
 
Evolutionary db development
Evolutionary db development Evolutionary db development
Evolutionary db development
 
Ps training mannual ( configuration )
Ps training mannual ( configuration )Ps training mannual ( configuration )
Ps training mannual ( configuration )
 
Informatica interview questions by H2kInfosys
Informatica interview questions by H2kInfosysInformatica interview questions by H2kInfosys
Informatica interview questions by H2kInfosys
 
Qtp interview questions_1
Qtp interview questions_1Qtp interview questions_1
Qtp interview questions_1
 

VALIDATING PS DOCUMENTS

  • 1. Validations in PS Question : I am trying to use validation in the Project. Can any one tell when are the call up points 110 and 120 trigerred ? I want to validate one of the user defined fields in WBS. Everything is working fine when I simulate the validation. But when I enter a value in the user defined field and save the project then I do not get the error message as expected. Does anybody have an idea what could be wrong ?? Answer : Please see if you have checked the check box for Automatic validation in the relevant project profile. Question : I want to validate the customer number in one of the user fields in WBS. The formula builder in the validation screen, it seems, does not support table fields other than fields from PRPS. Can this be done thru some user exits ?? If yes how ?? Can u guide me in this ?? Answer : To use a user exit in validations, you have to perform following steps; - copy SAP standard program GGBS002 to ZGGBS002 - create a user exit in this program (such as U902, U903 etc) - the user exit you defined in the above mentioned program will be visible in validations on screen tab 'Exits' - configure your validation with 'User exit' as option Planned Cost Differs from Actual Cost Question :
  • 2. I have a problem. I have a standard activity which the price is $1 / hr. I have created a project in which a activity has a planned hr of qty 1. But my planned cost comes in as '$0.83'. But when I comfirm my activity, the actual cost comes in as '$1'. Why is my planned cost differing? What is the cause of the $0.83 instead of $1. Where can i check and change this. Answer : I guess that you use different costing (and valuation) variants. so the system might valuate plan and actuals differently. Question : Where and how do i control it? Answer : In the network header are two fields: one for the plan costing variant and one for the actual costing variant. You maintain the costing variants in the customizing: PS -> Costs -> Planned Costs -> Automatic Costing in Networks -> Costing -> Define Costing Variants. Display the costing variant and jump to the valuation variant. There you find how the determines the costs. Validations in PS Question : I am trying to use validation in the Project. Can any one tell when are the call up points 110 and 120 trigerred ? I want to validate one of the user defined fields in WBS. Everything is working fine when I simulate the validation. But when I enter a value in the user defined field and save the project then I do not get the error message as expected.
  • 3. Does anybody have an idea what could be wrong ?? Answer : Please see if you have checked the check box for Automatic validation in the relevant project profile. Question : I want to validate the customer number in one of the user fields in WBS. The formula builder in the validation screen, it seems, does not support table fields other than fields from PRPS. Can this be done thru some user exits ?? If yes how ?? Can u guide me in this ?? Answer : To use a user exit in validations, you have to perform following steps; - copy SAP standard program GGBS002 to ZGGBS002 - create a user exit in this program (such as U902, U903 etc) - the user exit you defined in the above mentioned program will be visible in validations on screen tab 'Exits' - configure your validation with 'User exit' as option WBS description doesn´t appear completely in hierarchical Question : In the hierarchical reports in PS de WBS description is not showed completely. Do you know a way to make this appear completely? Answer :- We are on 4.6B and this is what you can do. :- 1) Execute report 2) Expand your results, if necessary 3) Click on any WBS line description 4) Follow the menu path Settings/Characteristic display 5) Choose lead column 6) Move object short description to the value set side of the panel 7) Move object long description to the lead column side of the panel
  • 4. Save (if you have authorization). Note you can use this procedure for any other object that may show up on the report display. i.e. navigation characteristics change the objects displayed. Anyway to put checks before setting to TECO? Question : Can anyone pl let me know about the followings: Is there any way to put checks (in the form of tick mark etc) before setting the system status to "TECO"- e.g. some documents are received or not etc. Answer : You can set the system status to Technically completed TECO which can be later on withdrawn. The necessary changes are reflected in the system status on saving the Network With the setup of user statusses (tr. OIBS), you have the ability to disable the 'TECO' as long as a certain user status 'e.g. waiting for documents' is active WBS description doesn´t appear completely in hierarchical Question : In the hierarchical reports in PS de WBS description is not showed completely. Do you know a way to make this appear completely? Answer :- We are on 4.6B and this is what you can do. :- 1) Execute report 2) Expand your results, if necessary 3) Click on any WBS line description 4) Follow the menu path Settings/Characteristic display 5) Choose lead column 6) Move object short description to the value set side of the panel 7) Move object long description to the lead column side of the panel
  • 5. Save (if you have authorization). Note you can use this procedure for any other object that may show up on the report display. i.e. navigation characteristics change the objects displayed. Anyway to put checks before setting to TECO? Question : Can anyone pl let me know about the followings: Is there any way to put checks (in the form of tick mark etc) before setting the system status to "TECO"- e.g. some documents are received or not etc. Answer : You can set the system status to Technically completed TECO which can be later on withdrawn. The necessary changes are reflected in the system status on saving the Network With the setup of user statusses (tr. OIBS), you have the ability to disable the 'TECO' as long as a certain user status 'e.g. waiting for documents' is active Links to documents stored on the Web Question : Is there a way to create a document (under a project) which refers to a URL and not to a document stored on a content server? Answer : Yes you can, but you need define in DMS customizing some points. 1.- Inner "Define Data Carriers" in Define data carrier type external "DMS" a record with this information: TYP = IE, Description = That you want, Check ONLINE and EX, the inside this in Define External DMS create a record with DATACAR = INTERNET, TYP = IE, Description = That you want, Check EX. 2.- Inner "Define Workstation Applications" define an application for web pages without file format, inside this in "Define Workstation applications in network" create records for options 1, 2, 3, the path of location of your navigator in your PC or you can put "%AUTO% iexplore.exe %f". Then when you create a document in the
  • 6. Original field you can put the URL and in the Data Carrier field put the name that you define in the customizing. How to settlement auc to asset in PS? Question : The cost of project have settled to auc(investment asset), but when the project is finished, in AM or in PS i can't settle auc to asset? Pls give me some suggestion! Any idea is appreciation! Answer : You must set technically complete for your WBS & NW before settle AUC to Assets. Links to documents stored on the Web Question : Is there a way to create a document (under a project) which refers to a URL and not to a document stored on a content server? Answer : Yes you can, but you need define in DMS customizing some points. 1.- Inner "Define Data Carriers" in Define data carrier type external "DMS" a record with this information: TYP = IE, Description = That you want, Check ONLINE and EX, the inside this in Define External DMS create a record with DATACAR = INTERNET, TYP = IE, Description = That you want, Check EX. 2.- Inner "Define Workstation Applications" define an application for web pages without file format, inside this in "Define Workstation applications in network" create records for options 1, 2, 3, the path of location of your navigator in your PC or you can put "%AUTO% iexplore.exe %f". Then when you create a document in the Original field you can put the URL and in the Data Carrier field put the name that you define in the customizing.
  • 7. How to settlement auc to asset in PS? Question : The cost of project have settled to auc(investment asset), but when the project is finished, in AM or in PS i can't settle auc to asset? Pls give me some suggestion! Any idea is appreciation! Answer : You must set technically complete for your WBS & NW before settle AUC to Assets. Updating the current Order cost plan Question : We are in 46C. Starting a project, we establish an Order cost plan. We plan the amount of work (in hours) and specify the work center for each of the activities. For material components, we enter the forecast material costs in the field "Material planning". We see the total and detailed by activity cost plan in CNS41 (Structure overview) in the column "Order cost plan 000". At some point in time, the project advancement shows that we have to reconsider the original cost plan, for instance because the actual costs collected so far are much higher than foreseen at start-up. Management decides to change the cost plan 000 to reflect the new forecasted budget. Management already told that they would like to be able to specify a new total value for the Order cost plan 000 of the activity rather then to play with the amount of work (hours) in the activity. They say it should be something like this (for labor): (actual cost) + (number of hours to do * cost of work center) = order cost plan 000. What options do we have to modify the "Order cost plan 000"?? Answer : There is a functionality called cost forecast (transaction CJ9L/CJ9M). I think this is exactly what you require. The forecasted costs are saved in a separate CO version. You could try to display this version in CNS41. Create network from Sales Order
  • 8. Question : We are currently running 4.6C and have implemented SD and PS. The situation is we want to be able to create a network automatically from the sales order during creation. I've assigned the strategy group 85 to the material master and I've defined the network parameters from sales order (via transaction CN08). The result... During creation of the sales order (transaction VA01), the network is created successfully but the components are not transferred to the network. Is it supposed to or not? If so, what additional configuration should I look at? I'm not very familiar with the standard functionality so I'm hoping someone out there has experience with this topic. Your time and insight is greatly appreciated, Answer : The components in assembly processing remain on the sales order only. In case you are working with reasonably complex scenario on BOM and procurement, where material items have their own dependencies schedulewise e.g to design, you should put the materials on the network. The best way to accomplish this is to do the BOM allocation (transfer) to activities and have only the invoicing item at sales order. Updating the current Order cost plan Question : We are in 46C. Starting a project, we establish an Order cost plan. We plan the amount of work (in hours) and specify the work center for each of the activities. For material components, we enter the forecast material costs in the field "Material planning". We see the total and detailed by activity cost plan in CNS41 (Structure overview) in the column "Order cost plan 000". At some point in time, the project advancement shows that we have to reconsider the original cost plan, for instance because the actual costs collected so far are much higher than foreseen at start-up. Management decides to change the cost plan 000 to reflect the new forecasted budget. Management already told that they would like to be able to specify a new total value for the Order cost plan 000 of the activity rather then to play with the
  • 9. amount of work (hours) in the activity. They say it should be something like this (for labor): (actual cost) + (number of hours to do * cost of work center) = order cost plan 000. What options do we have to modify the "Order cost plan 000"?? Answer : There is a functionality called cost forecast (transaction CJ9L/CJ9M). I think this is exactly what you require. The forecasted costs are saved in a separate CO version. You could try to display this version in CNS41. Create network from Sales Order Question : We are currently running 4.6C and have implemented SD and PS. The situation is we want to be able to create a network automatically from the sales order during creation. I've assigned the strategy group 85 to the material master and I've defined the network parameters from sales order (via transaction CN08). The result... During creation of the sales order (transaction VA01), the network is created successfully but the components are not transferred to the network. Is it supposed to or not? If so, what additional configuration should I look at? I'm not very familiar with the standard functionality so I'm hoping someone out there has experience with this topic. Your time and insight is greatly appreciated, Answer : The components in assembly processing remain on the sales order only. In case you are working with reasonably complex scenario on BOM and procurement, where material items have their own dependencies schedulewise e.g to design, you should put the materials on the network. The best way to accomplish this is to do the BOM allocation (transfer) to activities and have only the invoicing item at sales order.
  • 10. IM and FM Question : Is that possible to use IM to control investment projects and FM to control general costs? What is needed to be done in order to avoid conflicts between IM and PS ? Answer : Investment Management() IM Module is highly integrated with controlling(CO) , project system(PS), and Asset Management(FI-AA) components. IF you would like to implement IM & PS you might ask yourself what additional advantages are offered by using IM . These Include: 1- in PS you can represent the planned and the budgeted values of all projects . using IM you can represent the budgeting process from the organization pointview. IM helps you track of budget amounts that you carry forward for projects that were approved in prior fisical year. 2- Using AR in IM CAN help you decide what budget will be assigned to your organization Unit. IM Handles Cost Planning & Budget Approval and PS Manages Project Execution with AVAC for the Budget for each project. Multiple Root WBS Question : Can any one tell me in detail of advantages and Dis-advantages of Multiples Root WBS in the project.And one more why do you using the same coding Mask for PD and Root WBS. I would appreciate in advance. Answer :
  • 11. Multiple Root WBSEs helps in budgeting scenarios where these WBSEs are funded from different sources say a customer project has part scope of R&D (funded by R&D). You may also want to fund these root WBSEs from IM programs (linking to position IDs.) IM and FM Question : Is that possible to use IM to control investment projects and FM to control general costs? What is needed to be done in order to avoid conflicts between IM and PS ? Answer : Investment Management() IM Module is highly integrated with controlling(CO) , project system(PS), and Asset Management(FI-AA) components. IF you would like to implement IM & PS you might ask yourself what additional advantages are offered by using IM . These Include: 1- in PS you can represent the planned and the budgeted values of all projects . using IM you can represent the budgeting process from the organization pointview. IM helps you track of budget amounts that you carry forward for projects that were approved in prior fisical year. 2- Using AR in IM CAN help you decide what budget will be assigned to your organization Unit. IM Handles Cost Planning & Budget Approval and PS Manages Project Execution with AVAC for the Budget for each project. Multiple Root WBS Question :
  • 12. Can any one tell me in detail of advantages and Dis-advantages of Multiples Root WBS in the project.And one more why do you using the same coding Mask for PD and Root WBS. I would appreciate in advance. Answer : Multiple Root WBSEs helps in budgeting scenarios where these WBSEs are funded from different sources say a customer project has part scope of R&D (funded by R&D). You may also want to fund these root WBSEs from IM programs (linking to position IDs.) Question : Subject : PS Assets under Construction Hello All, I know that I can maintain the Plant for the WBS Element, what I would like to know is if it is also possible to maintain the Location as well? I've heard that it is not possible but I would like to hear other opinions. Any suggestions? We are on version 4.0B. I would like to know since the Asset Management people here are asking if it's possible to maintain it in PS or if this can only be done in AM. MM is not included in this implementation, but we did set up the Plants and Locations. Happy Holidays! Regards, Reply : Subject : PS Assets under Construction Yes, you can maintain a location for a WBS element as well. Select WBS element, follow path Details > Orgainsation. This screen has a field called Functional Location, apart from other orgainsation details such as Controlling Area, Company Code, Business Area, Plant, Calender etc.
  • 13. Hope this helps. Reagrds Question : Subject : PS Network Status's & Confirmations Sappers: Is there a status that can be set for a network activity that will stop time confirmations from being processed? TECO stops changes to the basic data, but allows further time confirmations. TIA Reply : Subject : PS Network Status's & Confirmations hi... you can lock account assignment for the network/activity in consideration depending on whether the network is header/activity assigned. This disallows the confirmation of the activities. ...else you can use the user status regards... Any Variant Capabilities in CM07 Report I am executing the CM07 report whuich is the Variable Capacity Planning Report. Out of which, I like the results because I obtain the fields I need by going thru the individual ''choose fields'' button. However in 4,6c) it does seem to have any variant capabilities ??? I have to reenter the fields selection every item I back out of the report ... Which is a bit anoying !!! Anyone has any recipes for this so that columns/criterias selected can be save guarded for the next time ???
  • 14. There are Variant list capabilities for CM07 Capacity report. Mainly via PS-> Information Systems->Resources->Tools->Resources->Selection- >General Profile (OPA6) and also via PS-> Information Systems->Resources->Tools->Resources->Selection-> Variant List Poifile Details (OPDT). You create a new ''Z'' Variant Profile list with all the fields that you want to select and show in yopur CM0? report . Be carefull to click correctly on the greenish/yellowish arrow to bring up the field selections pop up window... Than associate this new Z Variant Profile to a newly defined ''Z'' General Profile... Then after you can override with othe Variant Lists in the profile selection of the CM07 report txn. itself if needed... Change Documents in SAP Project In the Customising for Create Project Profile (OPSA) there are 2 fields for "Change Documents". Where and how is this useful during implemenation. There are 2 outcomes for change documents and they should both be implemented if it's important that you keep track of changes made to a project: General changes (the one at the top) - any field content changes made to a project WBS after it was first saved will be recorded in a file. eg. if you changes the WBS description, the old value and the new value will be recorded, or if you changed a person responsible, it would also be recorded etc. This information can be reviewed in Info Systems report CN60 to old/new values and who/when. Status Managment (the one checked in Status Management) - any changes to System and User Status will be recorded, including the status history and who/when. Changes can be seen in any project maintenance transaction (eg.
  • 15. CJ02, CJ20N) by clicking on the "i" icon for a PD or WBS, then following the internal pull-down menu path: Extras>Change Documents> For Status/All.You can then drill-down on the satus to see its history.