6. Design Phase
Riyadh Palma -2
Number for villas = 124 units
Number for duplex = 58 units
New building for Recreation
TOTAL AREA = 78,750 Sq Mtrs
7. Introduction For Riyadh Palma 1:
Overview and purpose
Riyadh Palma compound is located in the residential area Al-Ared a
more popular residential areas of Riyadh . The compound and will
soon offer Riyadh Palma residential condominiums with unique
designs and quality unrivaled in the pool safe and quiet
environment .
Riyadh Palma residential compound had been planned
professionally to provide a contemporary lifestyle and creative
commensurate with the requirements of the population of
expatriates seeking elegance and comfort. The project will be
completed at an area of 120,000 m 2 on the proximity of King
Abdullah Financial District among many other distinctive features
real estate and will consist of 122 buildings and luxury apartment
furnished and equipped with full facilities. And will provide
residential compound Riyadh Palma options and spacious villas ,
which consists of one bedroom to four bedrooms in addition to the
residential units Duplex Apartment (DA)-Duplex(D)- Townhouse
(TH)units also .as compound has apartments and housing units
Studio System
14. Recreation Center (RC) Type
Consist of three floors
(a). Ground Floor (Gym+ Laundry+ Toilet+ kitchen+
Swimming Pool+ Restaurant + Reception +Sauna+
Jacuzzi+ Steam Bath +Supermarket+ Elevator
GF Area = 1142 M2
(b). First Floor Hotel (21Studio Type + Corridor
FF Area = 965.84 M2
( c ). Roof Floor (6 Offices + Data center + Stair )
RF Area = 315.67 M2
15.
16.
17. Studio (ST) Type : Consist of
three types of rooms
(a). Type one (Bed Room + Living Area+ Open Kitchen+
Toilet)
Area = 63.91 M2
(b). Type Two (Bed Room + Open Kitchen+ Toilet)
Area = 34.64 M2
(C). Type Three (Bed Room + Kitchen+ Toilet)
Area = 30.69 M2
40. Construction Phase
Skeleton work Started on May 2012
included (Excavation, plain
concrete, Reinforcement Concrete
for Foundation , Grade Beam,
Columns, Slabs , Masonry work &
Water Tanks.
Civil/Structural work Completed on
December 2013
41. Construction Phase
Finishing & MEP work are done on
parallel with the structural work
from March 2013
Site work started on April 2014
(Infrastructure, Water Supply,
Sanitary Work, Electrical Work,
Fiber Optic, Landscapes &
Hardscapes with same Time
From April 2014 up to now
111. Work Progress
Skeleton Work
(100% Phase 1& 2)
Finishing Work
(95% Phase 01) (65% Phase 02)
MEP Work
(90% Phase 01) ( 65% Phase 02 )
112. Site Work (Phase 01 ) 75%
Electrical Work = 90%
Infrastructure Work = 90%
Sanitary Work = 90%
Fiber Optic = 80%
Landscape & Hardscape = 35%
Asphalt = 75%
113. Completion Date For Each Phase
Completion Date For Phase 01 at the end of
February -2015 .
Completion Date For Phase 02 at the end of
April -2015