RIVER BASIN MANAGEMET PLANS  AND  PUBLIC PARTICIPATION  Patrick WEINGERTNER Head of the Water Planning and WFD Department  of the Rhine-Maas Water Agency (France) SEMINAR on REVITALIZATION OF RIVERS 10 – 11 – 12 MAY 2010
Short overview  on water management in France  and  Rhine Maas basin  management plans
Water management in France  combines       Regulation    Polluter pays principle      Participation of stakeholders      Planning on a river basin scale
Water management in France  ► 6  water agencies  to apply the polluter pays principle   and  ►   6  basin committees in France  to involve stakeholders in the elaboration of the management plan    Budget : € 2 billion / year   (from charges)
Water Framework Directive  The european Water Framework Directive (WFD) requires to consult the public     on the  main issues   and    on the  river basin management plan   RIVER BASIN
Public consultation in the French  Rhine-Maas River basin   2008
   All the basin committees adopted the same consultation strategy (derivative of the Rhin-Meuse pilot action in 2005)      A questionnaire sent   to each household in each basin     but with various degrees of deeph :  4,10 or 15 questions  The national consultation method
The questionnaire was also  availaible on Internet :  > www.eau2015-rhin-meuse.fr 1.8 million questionnaires sent    in the mailboxes in the French part of    the Rhine-Meuse basin at the end of May 2008    ( 28 million questionnaires at the national level) The consultation method in the French Rhine-Maas basin part …  >
Press banners or ¼ p. quadri On cover TV weekly magazines 1 page in weekly press …  with the support of a communication campaign  Two friendly mascots
Radio ads : 8 per day / 5 days TV ads  :  2 per day / 14 days …  with the support of a communication campaign
and an  dedicated internet website  also in foreign languages
   3 environmental protection NGOs    1 fishing federation    3 consumer’s NGOs Grants from the  Water Agency : 63 000 Euros 7 partner NGOs involved in the public consultation  as relays with the water agency 7689 informed  (public debates) Partnership with NGOs
An important public participation     81000 questionnaires returned  :     77 340 paper questionnaires       3 660 by internet    40 % of questionnaires included  spontaneous texts     150 local debates organized  by NGOs
The costs  ►   735 0000 Euros Questionnnaire  (Printing, dispatch, processing of the answers) 47% Supporting media planning  26 %  Exploitation of  the results  10 %  Campaign design  09, %     ► Cost / inhabitant :   0.20 € / inhabitant   ►   Costs / programme of measures  :   0.2 %
Audience success    A very large response: 400,000 returns    A very varied public: Mr & Mrs Every Day    Very many free opinions, show an interest and a wish to be heard    An overwhelming preference for “paper” consultation   Diagnosis, objectives, actions: “yes, but…”     Overall validation … often subdued      A frequent feeling that more should be done    The wish for stronger governance: regulations, controls, sanctions Relative agreement to pay    Agree to finance the water policy more … but not necessarily via the water bill    Overwhelming preference for the application of the polluter pays principle Pollutions, top priority subjects    Farming and industrial pollution in first place    Very major interest in price and water saving    Less interest in environments   A strong desire to act      The practically unanimous acceptance of changes in daily life    The wish to see all the stakeholders do likewise To sum up this experience
 The  basin committee  devoted  a complete working session  to  examine the results of the public consultation .   An additionnal document   to the management plan reflecting the internal evolutions due to the public consultation was worked out   A feedback  concerning the results of the consultation  and the consequences was organized for the public How were the opinions taken into account  ?
 To reinforce   the pace for the good status  winning back   To optimise   financial efforts  To accelerate   the re-establishment  of ecological continuity    To emphasize  the reduction  of agricultural pollution   Main evolutions concerning  the management plan after the public consultation
[object Object],[object Object],[object Object],Main subjects  requiring extra work
Conclusions   A  strong interest of public  for water quality    An appropriate consultation method  : The paper questionnaire in the mailbox gave people time to understand the  subject and the issues. A various public was reached and this way really enabled to consult  Mr and Mrs Everyday    The degree of response varied from one basin to another  :    more than 4 % in the Rhine-Meuse  basin,     less than 1 %  in Seine-Normandie and especially in major towns  (Paris – Lyon)     An open question  :  Should the method be used again  for a next consultation ?
13/05/10 A12938 – Agence de l’eau Rhin-Meuse www.eau2015-rhin-meuse.fr Muito grato pela vossa atenção Thank you for your attention

More Related Content

Viewers also liked

Presentation1
Presentation1Presentation1
Presentation1Cesar37
 
City of Toronto - Long Term Waste Management Strategy - Phase 3 - Overview Pr...
City of Toronto - Long Term Waste Management Strategy - Phase 3 - Overview Pr...City of Toronto - Long Term Waste Management Strategy - Phase 3 - Overview Pr...
City of Toronto - Long Term Waste Management Strategy - Phase 3 - Overview Pr...Toronto Public Consultation Unit
 
An analytical study on impact of industrial effluent on the karun river, raip...
An analytical study on impact of industrial effluent on the karun river, raip...An analytical study on impact of industrial effluent on the karun river, raip...
An analytical study on impact of industrial effluent on the karun river, raip...Manoj Kumar Tiwari
 
City of Toronto Long Term Waste Strategy - Public Consultation Presentation, ...
City of Toronto Long Term Waste Strategy - Public Consultation Presentation, ...City of Toronto Long Term Waste Strategy - Public Consultation Presentation, ...
City of Toronto Long Term Waste Strategy - Public Consultation Presentation, ...Toronto Public Consultation Unit
 
Water conservation need of the hour
Water conservation   need of the hourWater conservation   need of the hour
Water conservation need of the hourAdane Nega
 
Water management questionnaire for industrial and institutions
Water management questionnaire for industrial and institutionsWater management questionnaire for industrial and institutions
Water management questionnaire for industrial and institutionsbiomeshubha
 

Viewers also liked (9)

Presentation1
Presentation1Presentation1
Presentation1
 
Etvs paper
Etvs paper Etvs paper
Etvs paper
 
City of Toronto - Long Term Waste Management Strategy - Phase 3 - Overview Pr...
City of Toronto - Long Term Waste Management Strategy - Phase 3 - Overview Pr...City of Toronto - Long Term Waste Management Strategy - Phase 3 - Overview Pr...
City of Toronto - Long Term Waste Management Strategy - Phase 3 - Overview Pr...
 
An analytical study on impact of industrial effluent on the karun river, raip...
An analytical study on impact of industrial effluent on the karun river, raip...An analytical study on impact of industrial effluent on the karun river, raip...
An analytical study on impact of industrial effluent on the karun river, raip...
 
City of Toronto Long Term Waste Strategy - Public Consultation Presentation, ...
City of Toronto Long Term Waste Strategy - Public Consultation Presentation, ...City of Toronto Long Term Waste Strategy - Public Consultation Presentation, ...
City of Toronto Long Term Waste Strategy - Public Consultation Presentation, ...
 
Environmental catalyst - Khor_Gold group-2014
Environmental catalyst - Khor_Gold group-2014Environmental catalyst - Khor_Gold group-2014
Environmental catalyst - Khor_Gold group-2014
 
Water conservation need of the hour
Water conservation   need of the hourWater conservation   need of the hour
Water conservation need of the hour
 
Questionnaire spain 2
Questionnaire  spain 2Questionnaire  spain 2
Questionnaire spain 2
 
Water management questionnaire for industrial and institutions
Water management questionnaire for industrial and institutionsWater management questionnaire for industrial and institutions
Water management questionnaire for industrial and institutions
 

Similar to Rio reno patrickweiingertner-2

Decentralised Development Cooperation in the Water Sector: The case of France...
Decentralised Development Cooperation in the Water Sector: The case of France...Decentralised Development Cooperation in the Water Sector: The case of France...
Decentralised Development Cooperation in the Water Sector: The case of France...OECDregions
 
Moldovan Experience with Nutrient Pollution Control in Agro-Processing
Moldovan Experience with Nutrient Pollution Control in Agro-Processing Moldovan Experience with Nutrient Pollution Control in Agro-Processing
Moldovan Experience with Nutrient Pollution Control in Agro-Processing Iwl Pcu
 
The Danube - Black Sea Strategic Partnership Program: Progress, Issues and Wa...
The Danube - Black Sea Strategic Partnership Program: Progress, Issues and Wa...The Danube - Black Sea Strategic Partnership Program: Progress, Issues and Wa...
The Danube - Black Sea Strategic Partnership Program: Progress, Issues and Wa...Iwl Pcu
 
Transboundary Water Management in Southeastern Europe
Transboundary Water Management in Southeastern EuropeTransboundary Water Management in Southeastern Europe
Transboundary Water Management in Southeastern EuropeGlobal Water Partnership
 
Presentation - Workshop 2: The implementation of the Polluter Pays Principle,...
Presentation - Workshop 2: The implementation of the Polluter Pays Principle,...Presentation - Workshop 2: The implementation of the Polluter Pays Principle,...
Presentation - Workshop 2: The implementation of the Polluter Pays Principle,...OECD Environment
 
Integrated Drought Management Programme, as presented at the World Irrigation...
Integrated Drought Management Programme, as presented at the World Irrigation...Integrated Drought Management Programme, as presented at the World Irrigation...
Integrated Drought Management Programme, as presented at the World Irrigation...Global Water Partnership
 
Cop21 & paris pact, eric tardieu, oieau
Cop21 & paris pact, eric tardieu, oieauCop21 & paris pact, eric tardieu, oieau
Cop21 & paris pact, eric tardieu, oieauOECD Governance
 
Ses 3 wg2_molinos_econ_distrissueslowerebro
Ses 3 wg2_molinos_econ_distrissueslowerebroSes 3 wg2_molinos_econ_distrissueslowerebro
Ses 3 wg2_molinos_econ_distrissueslowerebroVolkmar Hartje
 
WMO UPDATE Secretary general Prof. Petteri Taalas
WMO UPDATE Secretary general Prof. Petteri TaalasWMO UPDATE Secretary general Prof. Petteri Taalas
WMO UPDATE Secretary general Prof. Petteri TaalasGabriel Labrador
 
UNECE Session: Raimund Mair, ICPDR, 15th January UN Water Zaragoza Conference
UNECE Session: Raimund Mair, ICPDR, 15th January UN Water Zaragoza ConferenceUNECE Session: Raimund Mair, ICPDR, 15th January UN Water Zaragoza Conference
UNECE Session: Raimund Mair, ICPDR, 15th January UN Water Zaragoza Conferencewater-decade
 
water-jpi-presentation.pdf
water-jpi-presentation.pdfwater-jpi-presentation.pdf
water-jpi-presentation.pdfNagalakshmiS15
 

Similar to Rio reno patrickweiingertner-2 (20)

“The role of RBMPs for integrating the implementation of national strategies ...
“The role of RBMPs for integrating the implementation of national strategies ...“The role of RBMPs for integrating the implementation of national strategies ...
“The role of RBMPs for integrating the implementation of national strategies ...
 
Decentralised Development Cooperation in the Water Sector: The case of France...
Decentralised Development Cooperation in the Water Sector: The case of France...Decentralised Development Cooperation in the Water Sector: The case of France...
Decentralised Development Cooperation in the Water Sector: The case of France...
 
Launching activities on RBMPs in Georgia and Azerbaijan
Launching activities on RBMPs in Georgia and AzerbaijanLaunching activities on RBMPs in Georgia and Azerbaijan
Launching activities on RBMPs in Georgia and Azerbaijan
 
World Water Forum 2012
World Water Forum 2012World Water Forum 2012
World Water Forum 2012
 
Case study: The Stake-Pay-Say principle in the Netherlands
Case study: The Stake-Pay-Say principle in the NetherlandsCase study: The Stake-Pay-Say principle in the Netherlands
Case study: The Stake-Pay-Say principle in the Netherlands
 
About GWP Presentation
About GWP PresentationAbout GWP Presentation
About GWP Presentation
 
Introduction to economic instruments & the study
Introduction to economic instruments & the studyIntroduction to economic instruments & the study
Introduction to economic instruments & the study
 
Moldovan Experience with Nutrient Pollution Control in Agro-Processing
Moldovan Experience with Nutrient Pollution Control in Agro-Processing Moldovan Experience with Nutrient Pollution Control in Agro-Processing
Moldovan Experience with Nutrient Pollution Control in Agro-Processing
 
WORKSHOP RIVER BASIN MANAGEMENT PLAN 29 MAY 2018, MINSK
WORKSHOP RIVER BASIN MANAGEMENT PLAN 29 MAY 2018, MINSKWORKSHOP RIVER BASIN MANAGEMENT PLAN 29 MAY 2018, MINSK
WORKSHOP RIVER BASIN MANAGEMENT PLAN 29 MAY 2018, MINSK
 
The Danube - Black Sea Strategic Partnership Program: Progress, Issues and Wa...
The Danube - Black Sea Strategic Partnership Program: Progress, Issues and Wa...The Danube - Black Sea Strategic Partnership Program: Progress, Issues and Wa...
The Danube - Black Sea Strategic Partnership Program: Progress, Issues and Wa...
 
Rio reno patrickweiingertner-1
Rio reno patrickweiingertner-1 Rio reno patrickweiingertner-1
Rio reno patrickweiingertner-1
 
Transboundary Water Management in Southeastern Europe
Transboundary Water Management in Southeastern EuropeTransboundary Water Management in Southeastern Europe
Transboundary Water Management in Southeastern Europe
 
Presentation - Workshop 2: The implementation of the Polluter Pays Principle,...
Presentation - Workshop 2: The implementation of the Polluter Pays Principle,...Presentation - Workshop 2: The implementation of the Polluter Pays Principle,...
Presentation - Workshop 2: The implementation of the Polluter Pays Principle,...
 
Integrated Drought Management Programme, as presented at the World Irrigation...
Integrated Drought Management Programme, as presented at the World Irrigation...Integrated Drought Management Programme, as presented at the World Irrigation...
Integrated Drought Management Programme, as presented at the World Irrigation...
 
SustSan workshop: GWP CEE Sustainable Sanitation Programme by Darja Istenic
SustSan workshop: GWP CEE Sustainable Sanitation Programme by Darja IstenicSustSan workshop: GWP CEE Sustainable Sanitation Programme by Darja Istenic
SustSan workshop: GWP CEE Sustainable Sanitation Programme by Darja Istenic
 
Cop21 & paris pact, eric tardieu, oieau
Cop21 & paris pact, eric tardieu, oieauCop21 & paris pact, eric tardieu, oieau
Cop21 & paris pact, eric tardieu, oieau
 
Ses 3 wg2_molinos_econ_distrissueslowerebro
Ses 3 wg2_molinos_econ_distrissueslowerebroSes 3 wg2_molinos_econ_distrissueslowerebro
Ses 3 wg2_molinos_econ_distrissueslowerebro
 
WMO UPDATE Secretary general Prof. Petteri Taalas
WMO UPDATE Secretary general Prof. Petteri TaalasWMO UPDATE Secretary general Prof. Petteri Taalas
WMO UPDATE Secretary general Prof. Petteri Taalas
 
UNECE Session: Raimund Mair, ICPDR, 15th January UN Water Zaragoza Conference
UNECE Session: Raimund Mair, ICPDR, 15th January UN Water Zaragoza ConferenceUNECE Session: Raimund Mair, ICPDR, 15th January UN Water Zaragoza Conference
UNECE Session: Raimund Mair, ICPDR, 15th January UN Water Zaragoza Conference
 
water-jpi-presentation.pdf
water-jpi-presentation.pdfwater-jpi-presentation.pdf
water-jpi-presentation.pdf
 

More from Expresso das Idéias Produções

More from Expresso das Idéias Produções (7)

Programa drenurbs prefeiturabh-ricardoaroeira
Programa drenurbs prefeiturabh-ricardoaroeiraPrograma drenurbs prefeiturabh-ricardoaroeira
Programa drenurbs prefeiturabh-ricardoaroeira
 
Tim randle dam removal in the united states
Tim randle   dam removal in the united statesTim randle   dam removal in the united states
Tim randle dam removal in the united states
 
Tim randle dam removal in the united states
Tim randle   dam removal in the united statesTim randle   dam removal in the united states
Tim randle dam removal in the united states
 
Revitalização riosãofrancisco joseluizsouza-minsiteriointegracaonacional
Revitalização riosãofrancisco joseluizsouza-minsiteriointegracaonacionalRevitalização riosãofrancisco joseluizsouza-minsiteriointegracaonacional
Revitalização riosãofrancisco joseluizsouza-minsiteriointegracaonacional
 
Rio danubio europa-wolfgangstaltzer
Rio danubio europa-wolfgangstaltzerRio danubio europa-wolfgangstaltzer
Rio danubio europa-wolfgangstaltzer
 
Rio cheoggyeecheon coreiadosul-soohongnoh
Rio cheoggyeecheon coreiadosul-soohongnohRio cheoggyeecheon coreiadosul-soohongnoh
Rio cheoggyeecheon coreiadosul-soohongnoh
 
Projeto manuelzao riodasvelhas-polignano
Projeto manuelzao riodasvelhas-polignanoProjeto manuelzao riodasvelhas-polignano
Projeto manuelzao riodasvelhas-polignano
 

Rio reno patrickweiingertner-2

  • 1. RIVER BASIN MANAGEMET PLANS AND PUBLIC PARTICIPATION Patrick WEINGERTNER Head of the Water Planning and WFD Department of the Rhine-Maas Water Agency (France) SEMINAR on REVITALIZATION OF RIVERS 10 – 11 – 12 MAY 2010
  • 2. Short overview on water management in France and Rhine Maas basin management plans
  • 3. Water management in France combines  Regulation  Polluter pays principle  Participation of stakeholders  Planning on a river basin scale
  • 4. Water management in France ► 6 water agencies to apply the polluter pays principle and ► 6 basin committees in France to involve stakeholders in the elaboration of the management plan  Budget : € 2 billion / year (from charges)
  • 5. Water Framework Directive The european Water Framework Directive (WFD) requires to consult the public  on the main issues and  on the river basin management plan RIVER BASIN
  • 6. Public consultation in the French Rhine-Maas River basin 2008
  • 7. All the basin committees adopted the same consultation strategy (derivative of the Rhin-Meuse pilot action in 2005)  A questionnaire sent to each household in each basin  but with various degrees of deeph : 4,10 or 15 questions The national consultation method
  • 8. The questionnaire was also availaible on Internet : > www.eau2015-rhin-meuse.fr 1.8 million questionnaires sent in the mailboxes in the French part of the Rhine-Meuse basin at the end of May 2008 ( 28 million questionnaires at the national level) The consultation method in the French Rhine-Maas basin part … >
  • 9. Press banners or ¼ p. quadri On cover TV weekly magazines 1 page in weekly press … with the support of a communication campaign Two friendly mascots
  • 10. Radio ads : 8 per day / 5 days TV ads : 2 per day / 14 days … with the support of a communication campaign
  • 11. and an dedicated internet website also in foreign languages
  • 12. 3 environmental protection NGOs  1 fishing federation  3 consumer’s NGOs Grants from the Water Agency : 63 000 Euros 7 partner NGOs involved in the public consultation as relays with the water agency 7689 informed (public debates) Partnership with NGOs
  • 13. An important public participation  81000 questionnaires returned :  77 340 paper questionnaires  3 660 by internet  40 % of questionnaires included spontaneous texts  150 local debates organized by NGOs
  • 14. The costs ► 735 0000 Euros Questionnnaire (Printing, dispatch, processing of the answers) 47% Supporting media planning 26 % Exploitation of the results 10 % Campaign design 09, % ► Cost / inhabitant : 0.20 € / inhabitant ► Costs / programme of measures : 0.2 %
  • 15. Audience success  A very large response: 400,000 returns  A very varied public: Mr & Mrs Every Day  Very many free opinions, show an interest and a wish to be heard  An overwhelming preference for “paper” consultation Diagnosis, objectives, actions: “yes, but…”   Overall validation … often subdued  A frequent feeling that more should be done  The wish for stronger governance: regulations, controls, sanctions Relative agreement to pay  Agree to finance the water policy more … but not necessarily via the water bill  Overwhelming preference for the application of the polluter pays principle Pollutions, top priority subjects  Farming and industrial pollution in first place  Very major interest in price and water saving  Less interest in environments A strong desire to act  The practically unanimous acceptance of changes in daily life  The wish to see all the stakeholders do likewise To sum up this experience
  • 16.  The basin committee devoted a complete working session to examine the results of the public consultation .  An additionnal document to the management plan reflecting the internal evolutions due to the public consultation was worked out  A feedback concerning the results of the consultation and the consequences was organized for the public How were the opinions taken into account ?
  • 17.  To reinforce the pace for the good status winning back  To optimise financial efforts  To accelerate the re-establishment of ecological continuity  To emphasize the reduction of agricultural pollution Main evolutions concerning the management plan after the public consultation
  • 18.
  • 19. Conclusions  A strong interest of public for water quality  An appropriate consultation method : The paper questionnaire in the mailbox gave people time to understand the subject and the issues. A various public was reached and this way really enabled to consult Mr and Mrs Everyday  The degree of response varied from one basin to another :  more than 4 % in the Rhine-Meuse basin,  less than 1 % in Seine-Normandie and especially in major towns (Paris – Lyon)  An open question : Should the method be used again for a next consultation ?
  • 20. 13/05/10 A12938 – Agence de l’eau Rhin-Meuse www.eau2015-rhin-meuse.fr Muito grato pela vossa atenção Thank you for your attention

Editor's Notes

  1.   ’ 
  2.  ’
  3.       ’      
  4.       ’      