SlideShare a Scribd company logo
1 of 10
Extension to Ringsend Wastewater Treatment Works. Presentation to Environment and Engineering Strategic Policy Committee23/9/2010
Dublin Drainage Network
Ringsend Wastewater Treatment Works Extension Operational phase of current plant since 2005. Plant operating above design capacity. 2005 Greater Dublin Strategic Design Study. “The Ringsend Wastewater Treatment Works should be extended to its ultimate capacity” 2008 appointment of CDM as Client’s Consultant for the  Extension to the Plant.
Project Status Design Review Reports issued to DEHLG and EPA EIS Scoping Document 23/7/2010 Scheduled for issue to An Bord Pleanála March 2011 EPA Operating Licence issued on 27/7/ 2010 Marine Site Investigations Programme underway.
Design Review Report Current Plant overloaded Urban Wastewater Directive laid down stringent standards for nitrogen and phosphorous for continued discharge to the estuary. Treatment alternatives examined. Pending  the EIS the preferred option would be continued secondary treatment and the construction of an alternative discharge point between 7.5 and 10 kilometresoffshore Upon completion of the Extension, all available open space used and Works will have reached its maximum achievable capacity.
Recommended Plan Extend the capacity of the plant Provide secondary level treatment to comply with EU standards Discharge through an outfall extension Increase sludge capacity consistent with ultimate pollutant loadings Complete the Odour Control Programme.
Recommended Plan
Environmental Impact Assessment Scoping Report issued to statutory and additional consultees. Report outlines the information to be included in the EIS Water Quality	 Flora and Fauna Human Beings Traffic Soil and Geology Air and Climatic factors Noise and Vibration Landscape and Visual Archaeology and Cultural Heritage Material assets Scheduled for issue to an Bord Pleanála March 2011
EPA Licence Ringsend WWTW to be upgraded Combined sewer overflows Discharge standards Monitoring Annual Environmental Returns 2015 timeline
Marine Site Investigations Extensive geophysical surveys Geology of the Bay Drilling of Bay Route selection Extensive information will be gathered including:  marine sediment,  sub bed overburden geology,  bedrock geology and any anomalies that may be present in the bay.

More Related Content

What's hot

Integration of the MODFLOW Lak7 package in the FREEWAT GIS modelling environment
Integration of the MODFLOW Lak7 package in the FREEWAT GIS modelling environmentIntegration of the MODFLOW Lak7 package in the FREEWAT GIS modelling environment
Integration of the MODFLOW Lak7 package in the FREEWAT GIS modelling environmentMassimiliano Cannata
 
20191113 jbfs presentation final
20191113 jbfs presentation final20191113 jbfs presentation final
20191113 jbfs presentation finalecowatchers
 
DSD-INT 2017 Introduction to computational frameworks Example Ganga Basin - ...
DSD-INT 2017 Introduction to computational frameworks  Example Ganga Basin - ...DSD-INT 2017 Introduction to computational frameworks  Example Ganga Basin - ...
DSD-INT 2017 Introduction to computational frameworks Example Ganga Basin - ...Deltares
 
Integrating Flood Risk Into Catchment Management - Michael Butts (DHI)
Integrating Flood Risk Into Catchment Management - Michael Butts (DHI)Integrating Flood Risk Into Catchment Management - Michael Butts (DHI)
Integrating Flood Risk Into Catchment Management - Michael Butts (DHI)Stephen Flood
 
DSD-INT 2017 Application of the SPHY model for the Ganga basin and integratio...
DSD-INT 2017 Application of the SPHY model for the Ganga basin and integratio...DSD-INT 2017 Application of the SPHY model for the Ganga basin and integratio...
DSD-INT 2017 Application of the SPHY model for the Ganga basin and integratio...Deltares
 
Lacey Hirschvogel, MDNR, Multiple Discharger Variance, Missouri Water Seminar...
Lacey Hirschvogel, MDNR, Multiple Discharger Variance, Missouri Water Seminar...Lacey Hirschvogel, MDNR, Multiple Discharger Variance, Missouri Water Seminar...
Lacey Hirschvogel, MDNR, Multiple Discharger Variance, Missouri Water Seminar...Kevin Perry
 
DSD-INT 2019 ShorelineS and future coastline modelling - Roelvink
DSD-INT 2019 ShorelineS and future coastline modelling - RoelvinkDSD-INT 2019 ShorelineS and future coastline modelling - Roelvink
DSD-INT 2019 ShorelineS and future coastline modelling - RoelvinkDeltares
 
Demonstration project design, Ed Steadman, EERC
Demonstration project design, Ed Steadman, EERCDemonstration project design, Ed Steadman, EERC
Demonstration project design, Ed Steadman, EERCGlobal CCS Institute
 
Hazen & Sawyer NYC Green Infrastructure Co-Benefits Study and Calculator
Hazen & Sawyer NYC Green Infrastructure Co-Benefits Study and CalculatorHazen & Sawyer NYC Green Infrastructure Co-Benefits Study and Calculator
Hazen & Sawyer NYC Green Infrastructure Co-Benefits Study and CalculatorMichael Galvin
 
DSD-INT 2020 Using Delft3D to model mechanical and tidal flushing rates in Co...
DSD-INT 2020 Using Delft3D to model mechanical and tidal flushing rates in Co...DSD-INT 2020 Using Delft3D to model mechanical and tidal flushing rates in Co...
DSD-INT 2020 Using Delft3D to model mechanical and tidal flushing rates in Co...Deltares
 
LCRA Lane City Reservoir Project, Karen Bondy
LCRA Lane City Reservoir Project, Karen BondyLCRA Lane City Reservoir Project, Karen Bondy
LCRA Lane City Reservoir Project, Karen BondyTWCA
 
Navy presentation to the Moffett Field Restoration Advisory Board on May 15, ...
Navy presentation to the Moffett Field Restoration Advisory Board on May 15, ...Navy presentation to the Moffett Field Restoration Advisory Board on May 15, ...
Navy presentation to the Moffett Field Restoration Advisory Board on May 15, ...Steve Williams
 
Sustainable Public Works: Benefits of Taking Envision Beyond the Boundary of ...
Sustainable Public Works: Benefits of Taking Envision Beyond the Boundary of ...Sustainable Public Works: Benefits of Taking Envision Beyond the Boundary of ...
Sustainable Public Works: Benefits of Taking Envision Beyond the Boundary of ...Youn Sim, Ph.D., P.E.
 

What's hot (20)

Integration of the MODFLOW Lak7 package in the FREEWAT GIS modelling environment
Integration of the MODFLOW Lak7 package in the FREEWAT GIS modelling environmentIntegration of the MODFLOW Lak7 package in the FREEWAT GIS modelling environment
Integration of the MODFLOW Lak7 package in the FREEWAT GIS modelling environment
 
TMDLs in Wastewater
TMDLs in WastewaterTMDLs in Wastewater
TMDLs in Wastewater
 
February 2022 Texas Water Development Board Updates
February 2022 Texas Water Development Board UpdatesFebruary 2022 Texas Water Development Board Updates
February 2022 Texas Water Development Board Updates
 
20191113 jbfs presentation final
20191113 jbfs presentation final20191113 jbfs presentation final
20191113 jbfs presentation final
 
DSD-INT 2017 Introduction to computational frameworks Example Ganga Basin - ...
DSD-INT 2017 Introduction to computational frameworks  Example Ganga Basin - ...DSD-INT 2017 Introduction to computational frameworks  Example Ganga Basin - ...
DSD-INT 2017 Introduction to computational frameworks Example Ganga Basin - ...
 
Integrating Flood Risk Into Catchment Management - Michael Butts (DHI)
Integrating Flood Risk Into Catchment Management - Michael Butts (DHI)Integrating Flood Risk Into Catchment Management - Michael Butts (DHI)
Integrating Flood Risk Into Catchment Management - Michael Butts (DHI)
 
DSD-INT 2017 Application of the SPHY model for the Ganga basin and integratio...
DSD-INT 2017 Application of the SPHY model for the Ganga basin and integratio...DSD-INT 2017 Application of the SPHY model for the Ganga basin and integratio...
DSD-INT 2017 Application of the SPHY model for the Ganga basin and integratio...
 
Lacey Hirschvogel, MDNR, Multiple Discharger Variance, Missouri Water Seminar...
Lacey Hirschvogel, MDNR, Multiple Discharger Variance, Missouri Water Seminar...Lacey Hirschvogel, MDNR, Multiple Discharger Variance, Missouri Water Seminar...
Lacey Hirschvogel, MDNR, Multiple Discharger Variance, Missouri Water Seminar...
 
DSD-INT 2019 ShorelineS and future coastline modelling - Roelvink
DSD-INT 2019 ShorelineS and future coastline modelling - RoelvinkDSD-INT 2019 ShorelineS and future coastline modelling - Roelvink
DSD-INT 2019 ShorelineS and future coastline modelling - Roelvink
 
Demonstration project design, Ed Steadman, EERC
Demonstration project design, Ed Steadman, EERCDemonstration project design, Ed Steadman, EERC
Demonstration project design, Ed Steadman, EERC
 
March 22, 2012
March 22, 2012March 22, 2012
March 22, 2012
 
Wp special master-plan[071113]
Wp special master-plan[071113]Wp special master-plan[071113]
Wp special master-plan[071113]
 
Hazen & Sawyer NYC Green Infrastructure Co-Benefits Study and Calculator
Hazen & Sawyer NYC Green Infrastructure Co-Benefits Study and CalculatorHazen & Sawyer NYC Green Infrastructure Co-Benefits Study and Calculator
Hazen & Sawyer NYC Green Infrastructure Co-Benefits Study and Calculator
 
Land cover change analysis
Land cover change analysisLand cover change analysis
Land cover change analysis
 
DSD-INT 2020 Using Delft3D to model mechanical and tidal flushing rates in Co...
DSD-INT 2020 Using Delft3D to model mechanical and tidal flushing rates in Co...DSD-INT 2020 Using Delft3D to model mechanical and tidal flushing rates in Co...
DSD-INT 2020 Using Delft3D to model mechanical and tidal flushing rates in Co...
 
Drainage Master Plan
Drainage Master PlanDrainage Master Plan
Drainage Master Plan
 
LCRA Lane City Reservoir Project, Karen Bondy
LCRA Lane City Reservoir Project, Karen BondyLCRA Lane City Reservoir Project, Karen Bondy
LCRA Lane City Reservoir Project, Karen Bondy
 
Navy presentation to the Moffett Field Restoration Advisory Board on May 15, ...
Navy presentation to the Moffett Field Restoration Advisory Board on May 15, ...Navy presentation to the Moffett Field Restoration Advisory Board on May 15, ...
Navy presentation to the Moffett Field Restoration Advisory Board on May 15, ...
 
2013 01 24
2013 01 242013 01 24
2013 01 24
 
Sustainable Public Works: Benefits of Taking Envision Beyond the Boundary of ...
Sustainable Public Works: Benefits of Taking Envision Beyond the Boundary of ...Sustainable Public Works: Benefits of Taking Envision Beyond the Boundary of ...
Sustainable Public Works: Benefits of Taking Envision Beyond the Boundary of ...
 

Similar to Ringsend plant extension

David Bridge presentation, Communicating Environmental Geoscience workshop, ...
David Bridge presentation,  Communicating Environmental Geoscience workshop, ...David Bridge presentation,  Communicating Environmental Geoscience workshop, ...
David Bridge presentation, Communicating Environmental Geoscience workshop, ...dliverman
 
EPA Steering Committee Meeting slides, Dec, 8, 2020
EPA Steering Committee Meeting slides, Dec, 8, 2020EPA Steering Committee Meeting slides, Dec, 8, 2020
EPA Steering Committee Meeting slides, Dec, 8, 2020Mark Healy
 
CaBA conference 2015 III
CaBA conference 2015  IIICaBA conference 2015  III
CaBA conference 2015 IIICaBASupport
 
11. CatchmentCARE: improving water quality in cross-border catchments - Con M...
11. CatchmentCARE: improving water quality in cross-border catchments - Con M...11. CatchmentCARE: improving water quality in cross-border catchments - Con M...
11. CatchmentCARE: improving water quality in cross-border catchments - Con M...Environmental Protection Agency, Ireland
 
Supertram - Tram Train Pilot - Sheffield - Rotherham
Supertram - Tram Train Pilot - Sheffield - RotherhamSupertram - Tram Train Pilot - Sheffield - Rotherham
Supertram - Tram Train Pilot - Sheffield - RotherhamSepehr Aghamehdi
 
Nick Willenbrock - Future DoW CoP
Nick Willenbrock - Future DoW CoPNick Willenbrock - Future DoW CoP
Nick Willenbrock - Future DoW CoPIES / IAQM
 
Academia: Richard Lawford, Morgan State University, 16th January UN Water Zar...
Academia: Richard Lawford, Morgan State University, 16th January UN Water Zar...Academia: Richard Lawford, Morgan State University, 16th January UN Water Zar...
Academia: Richard Lawford, Morgan State University, 16th January UN Water Zar...water-decade
 
Glen Cooper Natural England
Glen Cooper Natural EnglandGlen Cooper Natural England
Glen Cooper Natural EnglandRebeccaSlack
 
Eia of township and area development projects
Eia of township and area development projectsEia of township and area development projects
Eia of township and area development projectsSandeep Kumar
 
C4.02: Development of an Integrated Global Water Quality Monitoring and Forec...
C4.02: Development of an Integrated Global Water Quality Monitoring and Forec...C4.02: Development of an Integrated Global Water Quality Monitoring and Forec...
C4.02: Development of an Integrated Global Water Quality Monitoring and Forec...Blue Planet Symposium
 
Project SABRE (Source Area BioRemediation) – an Overview
Project SABRE (Source Area BioRemediation) – an OverviewProject SABRE (Source Area BioRemediation) – an Overview
Project SABRE (Source Area BioRemediation) – an Overviewian_farrar
 
Dr Donata Dubber and Dr Laurence Gill 2013: Water saving technologies to redu...
Dr Donata Dubber and Dr Laurence Gill 2013: Water saving technologies to redu...Dr Donata Dubber and Dr Laurence Gill 2013: Water saving technologies to redu...
Dr Donata Dubber and Dr Laurence Gill 2013: Water saving technologies to redu...Arne Backlund
 
Water saving technologies to reduce water consumption and wastewater producti...
Water saving technologies to reduce water consumption and wastewater producti...Water saving technologies to reduce water consumption and wastewater producti...
Water saving technologies to reduce water consumption and wastewater producti...Arne Backlund
 
AAEE E3Competition-Winners-2002
AAEE E3Competition-Winners-2002AAEE E3Competition-Winners-2002
AAEE E3Competition-Winners-2002Dennis Palalay
 

Similar to Ringsend plant extension (20)

David Bridge presentation, Communicating Environmental Geoscience workshop, ...
David Bridge presentation,  Communicating Environmental Geoscience workshop, ...David Bridge presentation,  Communicating Environmental Geoscience workshop, ...
David Bridge presentation, Communicating Environmental Geoscience workshop, ...
 
EPA Steering Committee Meeting slides, Dec, 8, 2020
EPA Steering Committee Meeting slides, Dec, 8, 2020EPA Steering Committee Meeting slides, Dec, 8, 2020
EPA Steering Committee Meeting slides, Dec, 8, 2020
 
15. Licensing of Large Point Source Discharges
15. Licensing of Large Point Source Discharges15. Licensing of Large Point Source Discharges
15. Licensing of Large Point Source Discharges
 
CaBA conference 2015 III
CaBA conference 2015  IIICaBA conference 2015  III
CaBA conference 2015 III
 
File287
File287File287
File287
 
11. CatchmentCARE: improving water quality in cross-border catchments - Con M...
11. CatchmentCARE: improving water quality in cross-border catchments - Con M...11. CatchmentCARE: improving water quality in cross-border catchments - Con M...
11. CatchmentCARE: improving water quality in cross-border catchments - Con M...
 
Supertram - Tram Train Pilot - Sheffield - Rotherham
Supertram - Tram Train Pilot - Sheffield - RotherhamSupertram - Tram Train Pilot - Sheffield - Rotherham
Supertram - Tram Train Pilot - Sheffield - Rotherham
 
Nick Willenbrock - Future DoW CoP
Nick Willenbrock - Future DoW CoPNick Willenbrock - Future DoW CoP
Nick Willenbrock - Future DoW CoP
 
Esi Year In Review
Esi Year In ReviewEsi Year In Review
Esi Year In Review
 
Aczmp athens, greece
Aczmp   athens, greeceAczmp   athens, greece
Aczmp athens, greece
 
007 NCWRM 2011 Nikitas_H2020
007 NCWRM 2011 Nikitas_H2020007 NCWRM 2011 Nikitas_H2020
007 NCWRM 2011 Nikitas_H2020
 
Academia: Richard Lawford, Morgan State University, 16th January UN Water Zar...
Academia: Richard Lawford, Morgan State University, 16th January UN Water Zar...Academia: Richard Lawford, Morgan State University, 16th January UN Water Zar...
Academia: Richard Lawford, Morgan State University, 16th January UN Water Zar...
 
Glen Cooper Natural England
Glen Cooper Natural EnglandGlen Cooper Natural England
Glen Cooper Natural England
 
Eia of township and area development projects
Eia of township and area development projectsEia of township and area development projects
Eia of township and area development projects
 
C4.02: Development of an Integrated Global Water Quality Monitoring and Forec...
C4.02: Development of an Integrated Global Water Quality Monitoring and Forec...C4.02: Development of an Integrated Global Water Quality Monitoring and Forec...
C4.02: Development of an Integrated Global Water Quality Monitoring and Forec...
 
Project SABRE (Source Area BioRemediation) – an Overview
Project SABRE (Source Area BioRemediation) – an OverviewProject SABRE (Source Area BioRemediation) – an Overview
Project SABRE (Source Area BioRemediation) – an Overview
 
Project SABRE overview
Project SABRE overviewProject SABRE overview
Project SABRE overview
 
Dr Donata Dubber and Dr Laurence Gill 2013: Water saving technologies to redu...
Dr Donata Dubber and Dr Laurence Gill 2013: Water saving technologies to redu...Dr Donata Dubber and Dr Laurence Gill 2013: Water saving technologies to redu...
Dr Donata Dubber and Dr Laurence Gill 2013: Water saving technologies to redu...
 
Water saving technologies to reduce water consumption and wastewater producti...
Water saving technologies to reduce water consumption and wastewater producti...Water saving technologies to reduce water consumption and wastewater producti...
Water saving technologies to reduce water consumption and wastewater producti...
 
AAEE E3Competition-Winners-2002
AAEE E3Competition-Winners-2002AAEE E3Competition-Winners-2002
AAEE E3Competition-Winners-2002
 

More from Naoise

Sk 069 - ga working drawings
Sk 069 - ga working drawingsSk 069 - ga working drawings
Sk 069 - ga working drawingsNaoise
 
Clontarf to city centre cycle scheme
Clontarf to city centre cycle schemeClontarf to city centre cycle scheme
Clontarf to city centre cycle schemeNaoise
 
17203 consultative forum no 3 30112018 issue compressed
17203 consultative forum no 3 30112018 issue compressed17203 consultative forum no 3 30112018 issue compressed
17203 consultative forum no 3 30112018 issue compressedNaoise
 
Griffith Avenue SHD ncac presentation 21 01-2019
Griffith Avenue SHD ncac presentation 21 01-2019Griffith Avenue SHD ncac presentation 21 01-2019
Griffith Avenue SHD ncac presentation 21 01-2019Naoise
 
Report no. 082019 of the environment strategic policy committee changes to ...
Report no. 082019 of the environment strategic policy committee   changes to ...Report no. 082019 of the environment strategic policy committee   changes to ...
Report no. 082019 of the environment strategic policy committee changes to ...Naoise
 
Letter to An Taoiseach
Letter to An TaoiseachLetter to An Taoiseach
Letter to An TaoiseachNaoise
 
DCC CEO Report to ABP
DCC CEO Report to ABPDCC CEO Report to ABP
DCC CEO Report to ABPNaoise
 
Doc09102017 00001
Doc09102017 00001Doc09102017 00001
Doc09102017 00001Naoise
 
2017.09.07 dcc120033 cyclist safety slides
2017.09.07 dcc120033 cyclist safety slides2017.09.07 dcc120033 cyclist safety slides
2017.09.07 dcc120033 cyclist safety slidesNaoise
 
2017.08.28 db ncac&cac clontarf to city centre cycle route part 8 expla...
2017.08.28 db   ncac&cac clontarf to city centre cycle route part 8 expla...2017.08.28 db   ncac&cac clontarf to city centre cycle route part 8 expla...
2017.08.28 db ncac&cac clontarf to city centre cycle route part 8 expla...Naoise
 
Abp150416
Abp150416Abp150416
Abp150416Naoise
 
DCC Dollymount Flood Defence Report
DCC Dollymount Flood Defence ReportDCC Dollymount Flood Defence Report
DCC Dollymount Flood Defence ReportNaoise
 
Dollymount Flood Defence schematic
Dollymount Flood Defence schematicDollymount Flood Defence schematic
Dollymount Flood Defence schematicNaoise
 
Dollymount flood wall review feb 2016 rev2
Dollymount flood wall review feb 2016 rev2Dollymount flood wall review feb 2016 rev2
Dollymount flood wall review feb 2016 rev2Naoise
 
Draft Litter Management Plan
Draft Litter Management PlanDraft Litter Management Plan
Draft Litter Management PlanNaoise
 
Dollymount externalexpert ommgoc
Dollymount externalexpert ommgocDollymount externalexpert ommgoc
Dollymount externalexpert ommgocNaoise
 
Dollymount External Expert
Dollymount External ExpertDollymount External Expert
Dollymount External ExpertNaoise
 
Proposed additional car parking facility - south of Timber Bridge
Proposed additional car parking facility  - south of Timber BridgeProposed additional car parking facility  - south of Timber Bridge
Proposed additional car parking facility - south of Timber BridgeNaoise
 
Fairview Christmas Lights Switchon
Fairview Christmas Lights SwitchonFairview Christmas Lights Switchon
Fairview Christmas Lights SwitchonNaoise
 
S2S Presentation to DCC - 11th November 2015
S2S Presentation to DCC - 11th November 2015S2S Presentation to DCC - 11th November 2015
S2S Presentation to DCC - 11th November 2015Naoise
 

More from Naoise (20)

Sk 069 - ga working drawings
Sk 069 - ga working drawingsSk 069 - ga working drawings
Sk 069 - ga working drawings
 
Clontarf to city centre cycle scheme
Clontarf to city centre cycle schemeClontarf to city centre cycle scheme
Clontarf to city centre cycle scheme
 
17203 consultative forum no 3 30112018 issue compressed
17203 consultative forum no 3 30112018 issue compressed17203 consultative forum no 3 30112018 issue compressed
17203 consultative forum no 3 30112018 issue compressed
 
Griffith Avenue SHD ncac presentation 21 01-2019
Griffith Avenue SHD ncac presentation 21 01-2019Griffith Avenue SHD ncac presentation 21 01-2019
Griffith Avenue SHD ncac presentation 21 01-2019
 
Report no. 082019 of the environment strategic policy committee changes to ...
Report no. 082019 of the environment strategic policy committee   changes to ...Report no. 082019 of the environment strategic policy committee   changes to ...
Report no. 082019 of the environment strategic policy committee changes to ...
 
Letter to An Taoiseach
Letter to An TaoiseachLetter to An Taoiseach
Letter to An Taoiseach
 
DCC CEO Report to ABP
DCC CEO Report to ABPDCC CEO Report to ABP
DCC CEO Report to ABP
 
Doc09102017 00001
Doc09102017 00001Doc09102017 00001
Doc09102017 00001
 
2017.09.07 dcc120033 cyclist safety slides
2017.09.07 dcc120033 cyclist safety slides2017.09.07 dcc120033 cyclist safety slides
2017.09.07 dcc120033 cyclist safety slides
 
2017.08.28 db ncac&cac clontarf to city centre cycle route part 8 expla...
2017.08.28 db   ncac&cac clontarf to city centre cycle route part 8 expla...2017.08.28 db   ncac&cac clontarf to city centre cycle route part 8 expla...
2017.08.28 db ncac&cac clontarf to city centre cycle route part 8 expla...
 
Abp150416
Abp150416Abp150416
Abp150416
 
DCC Dollymount Flood Defence Report
DCC Dollymount Flood Defence ReportDCC Dollymount Flood Defence Report
DCC Dollymount Flood Defence Report
 
Dollymount Flood Defence schematic
Dollymount Flood Defence schematicDollymount Flood Defence schematic
Dollymount Flood Defence schematic
 
Dollymount flood wall review feb 2016 rev2
Dollymount flood wall review feb 2016 rev2Dollymount flood wall review feb 2016 rev2
Dollymount flood wall review feb 2016 rev2
 
Draft Litter Management Plan
Draft Litter Management PlanDraft Litter Management Plan
Draft Litter Management Plan
 
Dollymount externalexpert ommgoc
Dollymount externalexpert ommgocDollymount externalexpert ommgoc
Dollymount externalexpert ommgoc
 
Dollymount External Expert
Dollymount External ExpertDollymount External Expert
Dollymount External Expert
 
Proposed additional car parking facility - south of Timber Bridge
Proposed additional car parking facility  - south of Timber BridgeProposed additional car parking facility  - south of Timber Bridge
Proposed additional car parking facility - south of Timber Bridge
 
Fairview Christmas Lights Switchon
Fairview Christmas Lights SwitchonFairview Christmas Lights Switchon
Fairview Christmas Lights Switchon
 
S2S Presentation to DCC - 11th November 2015
S2S Presentation to DCC - 11th November 2015S2S Presentation to DCC - 11th November 2015
S2S Presentation to DCC - 11th November 2015
 

Ringsend plant extension

  • 1. Extension to Ringsend Wastewater Treatment Works. Presentation to Environment and Engineering Strategic Policy Committee23/9/2010
  • 3. Ringsend Wastewater Treatment Works Extension Operational phase of current plant since 2005. Plant operating above design capacity. 2005 Greater Dublin Strategic Design Study. “The Ringsend Wastewater Treatment Works should be extended to its ultimate capacity” 2008 appointment of CDM as Client’s Consultant for the Extension to the Plant.
  • 4. Project Status Design Review Reports issued to DEHLG and EPA EIS Scoping Document 23/7/2010 Scheduled for issue to An Bord Pleanála March 2011 EPA Operating Licence issued on 27/7/ 2010 Marine Site Investigations Programme underway.
  • 5. Design Review Report Current Plant overloaded Urban Wastewater Directive laid down stringent standards for nitrogen and phosphorous for continued discharge to the estuary. Treatment alternatives examined. Pending the EIS the preferred option would be continued secondary treatment and the construction of an alternative discharge point between 7.5 and 10 kilometresoffshore Upon completion of the Extension, all available open space used and Works will have reached its maximum achievable capacity.
  • 6. Recommended Plan Extend the capacity of the plant Provide secondary level treatment to comply with EU standards Discharge through an outfall extension Increase sludge capacity consistent with ultimate pollutant loadings Complete the Odour Control Programme.
  • 8. Environmental Impact Assessment Scoping Report issued to statutory and additional consultees. Report outlines the information to be included in the EIS Water Quality Flora and Fauna Human Beings Traffic Soil and Geology Air and Climatic factors Noise and Vibration Landscape and Visual Archaeology and Cultural Heritage Material assets Scheduled for issue to an Bord Pleanála March 2011
  • 9. EPA Licence Ringsend WWTW to be upgraded Combined sewer overflows Discharge standards Monitoring Annual Environmental Returns 2015 timeline
  • 10. Marine Site Investigations Extensive geophysical surveys Geology of the Bay Drilling of Bay Route selection Extensive information will be gathered including: marine sediment, sub bed overburden geology, bedrock geology and any anomalies that may be present in the bay.