October 20, 2022
FULL LAND DEVELOPMENT WORKS
GREEN MEADOWS RESIDENCES PHASE 3E
SCOPE OF WORKS
OVERALL
ACCOMPLISHMENT
FOUR MAJOR LAND DEVELOPMENT WORKS 6.72%
SPECIAL LAND DEVELOPMENT WORKS 9.33%
OVERALL TO-DATE 7.04%
OVERALL STATUS
TARGET VS. ACTUAL ACCOMPLISHMENTS
BLOCK GRADING/SUBGRADE
PREPARATION
DONE TO DATE
BACKLOG
TARGET FOR THIS MONTH
BLOCK 8
BLOCK 9
ROAD 10
DRAINAGE WORKS
ROAD 12
ROAD 11
ROAD 13
ROAD 14
DONE TO DATE (RCP & MANHOLE CONSTRUCTION)
BACKLOG
TARGET FOR THIS MONTH
PERIMETER FENCE
BLOCK 12
DONE TO DATE (26 SPANS OF CHB PERIMETER FENCE)
(4 SPANS OF RETAINING WALL)
TARGET FOR THIS MONTH
BLOCK 14

Reports for accomplishment in construction project