The document provides estimates for repairs to various irrigation structures in Anantapuramu district that were damaged by flooding in 2012, including:
1. Repairs to the Pulesu kunta near Venkatagari palli village.
2. Repairs to the Bukkapatnam cheruvu kaluva supply channel and pickup anicut near Narepalli village.
3. Repairs to the Bukkapatnam cheruvu kaluva supply channel and pickup anicut near Kanisetty palli village.
The estimates include provisions for earthworks, concrete works, embankments, wearing surfaces, and other repairs, prepared according to the 2013-14
The document discusses the rehabilitation of the Chimney Tops Trail in Great Smoky Mountains National Park. It states that the trail rehabilitation will begin in May 2012 and occur in multiple phases. It will enhance visitor experience while protecting resources, and will use sustainable construction methods. The trail will be closed each work week to ensure crew and visitor safety during the rehabilitation work.
Jeff Varndell has over 40 years of experience in civil engineering projects related to water, wastewater, roads, coastal protection and township infrastructure. He has managed numerous projects for municipalities and other clients in South Africa and Zimbabwe, including dams, water treatment plants, sewer systems and community facilities. His experience spans all phases of projects from planning and design to construction supervision.
The document summarizes a road construction project in Uyo, Akwa Ibom State, Nigeria. Julius Berger Nigeria PLC was awarded a contract in 2011 to construct 7.2 km of dual carriageway, including a 150m flyover bridge and two 6,600m outfall drains. Due to unsuitable soil conditions, the flyover required 278 precast concrete piles 18m in length. Extensive demolition of existing structures was also required. When completed, the road will help connect Nwaniba Road to the Outer Ring Road in Uyo.
The proposed Phase II development at Hengistbury Head has the potential for some environmental impacts during construction. Minor disturbances to the local community from noise and dust are expected, as well as possible increased traffic and parking in residential areas due to car park closures. Increased noise during construction could adversely impact wildlife through hearing loss, stress, and territory abandonment. Vibration from construction vehicles and machinery may damage habitats and species in the development site. The temporary relocation of the land train route also risks exacerbating coastal erosion. With mitigation measures, most impacts are predicted to be small or medium and temporary during the construction period.
The document outlines several options (A-K) for reassigning attendance areas and boundaries for high schools in the district. Option K is recommended, which assigns all students from the Beaufort Elementary attendance area to Battery Creek High School, while Mossy Oaks and Port Royal attendance areas remain assigned to Beaufort High School. The school board votes to approve Option K.
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Crosstown TO
Construction is underway on the Crosstown LRT project, including at Kennedy Station. Crews will use a cut-and-cover construction method at Kennedy Station, which will involve utility relocations, installing support of excavation including piles and shoring, and excavating the site. In 2017, crews will relocate utilities and roads, demolish the existing north entrance, and begin support of excavation work, which may cause noise, vibration and dust. The project will build 15 underground stations along a 19-kilometre LRT route to improve transit connections in Toronto.
Chaplin Station Open House - March 2017Crosstown TO
The document provides information about the construction of the Eglinton Crosstown LRT project in Toronto. It discusses the background and players involved in the project, details about what is being built including key features and design approaches. It also covers topics like safety, accessibility, environment and sustainability measures, and descriptions of the construction process and methods being used. Updates are provided on construction progress and milestones. Information is also given about community benefits initiatives and how people can stay updated on the project.
This document summarizes a road construction project in Akwa Ibom State, Nigeria. It details that Julius Berger Nigeria PLC was awarded a contract in 2012 to dualize approximately 15 km of the Uyo-Ikot Ekpene Road over a two year period. The project involved widening the existing road from two lanes to a four lane dual carriageway with reinforced shoulders. It also included installing new drainage systems and relocating electrical infrastructure along the road. The strengthened road base and multiple asphalt layers were designed to support increased traffic and provide long-term durability.
The document discusses the rehabilitation of the Chimney Tops Trail in Great Smoky Mountains National Park. It states that the trail rehabilitation will begin in May 2012 and occur in multiple phases. It will enhance visitor experience while protecting resources, and will use sustainable construction methods. The trail will be closed each work week to ensure crew and visitor safety during the rehabilitation work.
Jeff Varndell has over 40 years of experience in civil engineering projects related to water, wastewater, roads, coastal protection and township infrastructure. He has managed numerous projects for municipalities and other clients in South Africa and Zimbabwe, including dams, water treatment plants, sewer systems and community facilities. His experience spans all phases of projects from planning and design to construction supervision.
The document summarizes a road construction project in Uyo, Akwa Ibom State, Nigeria. Julius Berger Nigeria PLC was awarded a contract in 2011 to construct 7.2 km of dual carriageway, including a 150m flyover bridge and two 6,600m outfall drains. Due to unsuitable soil conditions, the flyover required 278 precast concrete piles 18m in length. Extensive demolition of existing structures was also required. When completed, the road will help connect Nwaniba Road to the Outer Ring Road in Uyo.
The proposed Phase II development at Hengistbury Head has the potential for some environmental impacts during construction. Minor disturbances to the local community from noise and dust are expected, as well as possible increased traffic and parking in residential areas due to car park closures. Increased noise during construction could adversely impact wildlife through hearing loss, stress, and territory abandonment. Vibration from construction vehicles and machinery may damage habitats and species in the development site. The temporary relocation of the land train route also risks exacerbating coastal erosion. With mitigation measures, most impacts are predicted to be small or medium and temporary during the construction period.
The document outlines several options (A-K) for reassigning attendance areas and boundaries for high schools in the district. Option K is recommended, which assigns all students from the Beaufort Elementary attendance area to Battery Creek High School, while Mossy Oaks and Port Royal attendance areas remain assigned to Beaufort High School. The school board votes to approve Option K.
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Crosstown TO
Construction is underway on the Crosstown LRT project, including at Kennedy Station. Crews will use a cut-and-cover construction method at Kennedy Station, which will involve utility relocations, installing support of excavation including piles and shoring, and excavating the site. In 2017, crews will relocate utilities and roads, demolish the existing north entrance, and begin support of excavation work, which may cause noise, vibration and dust. The project will build 15 underground stations along a 19-kilometre LRT route to improve transit connections in Toronto.
Chaplin Station Open House - March 2017Crosstown TO
The document provides information about the construction of the Eglinton Crosstown LRT project in Toronto. It discusses the background and players involved in the project, details about what is being built including key features and design approaches. It also covers topics like safety, accessibility, environment and sustainability measures, and descriptions of the construction process and methods being used. Updates are provided on construction progress and milestones. Information is also given about community benefits initiatives and how people can stay updated on the project.
This document summarizes a road construction project in Akwa Ibom State, Nigeria. It details that Julius Berger Nigeria PLC was awarded a contract in 2012 to dualize approximately 15 km of the Uyo-Ikot Ekpene Road over a two year period. The project involved widening the existing road from two lanes to a four lane dual carriageway with reinforced shoulders. It also included installing new drainage systems and relocating electrical infrastructure along the road. The strengthened road base and multiple asphalt layers were designed to support increased traffic and provide long-term durability.
La historia narra cómo los animales de una granja se rebelan contra su dueño, el señor Jones, cansados del maltrato. Los cerdos más inteligentes, especialmente el cerdo mayor, lideran la rebelión y expulsan al señor Jones de la granja. Con el tiempo, sin embargo, los cerdos comienzan a comportarse como los antiguos dueños, abusando de su poder y privilegios sobre los demás animales.
El documento presenta varios relatos de terror y mitos. En uno, un joven acompaña a sus amigos a una discoteca aunque es tímido. Otro relato involucra a tres personas que descubren una prenda en una tumba. Finalmente, se discuten las funciones de los mitos en diferentes culturas y cómo su narración está ligada a rituales sagrados.
The document contains multiple reports for proposed repairs and improvements to irrigation structures in Anantapuramu district that were damaged during floods in 2012. The reports provide estimates for repairing breaches to channels, restoring pickup anicuts, and reconstructing sections of dams and tanks. The estimates include provisions for excavation, concrete work, embankments, protective works, and other expenses based on the 2013-14 schedule of rates. Permanent repairs are proposed to restore water supply and irrigation to affected villages.
The document contains multiple reports for proposed repairs to various irrigation structures in Anantapuramu district that were damaged during floods in 2012. The structures include pickup anicuts, supply channels, and tanks. The reports provide estimates for repair works such as excavation, concrete work, and other provisions. The estimates are based on the 2013-14 schedule of rates. The repairs aim to restore water supply for irrigation to the ayacuts of various villages.
This document is a curriculum vitae for Akash Kore Ravi. It summarizes his work experience, education, skills, and personal details. Ravi has over 5 years of experience as a Production Engineer and over 2 years of experience in HVAC as a Site Engineer. He holds a Diploma in Mechanical Engineering from 2005. His skills include AutoCAD, MS Office, and MEP courses. He is currently working as a Body Shop Advisor at Shriram Ford in Latur, India.
Dokumen tersebut membahas berbagai topik terkait fenomena fisika dan inovasi yang berasal dari fenomena tersebut, seperti aturan Leonardo tentang pola cabang pohon, fisika ikat rambut, origami, the Cubli, dan RYNO motor. Dokumen ini mengajak pembaca untuk berimajinasi dan berinovasi dengan memanfaatkan prinsip-prinsip fisika yang dijelaskan.
How to Measure the the Quality of Service in Cloud Based Technology?Madushi Rathnayake
This study introduces a framework for service oriented cloud computing with the focus on its service quality aspects in which most demanded by cloud users. It considered two dominant sub-layers such that functional and runtime; against cloud characteristics. SEQUAL model and recent literature were used to derive the quality constructs in cloud environment whilst the opinions of the industry experts were adding more to the blend. The proposed model gives proper identification of service quality expectations and also applicable for different business or geographical contexts. The validity of it for Sri Lankan context were evaluated in this study by using questionnaire based survey while PLS-SEM (partial least squares-structural equation modeling) technique was used to evaluate the outcome. Further the research findings shows the significance of functional layer is rather expected by user than runtime layer and prioritizes quality factors of each layer; in which Service time, Information and data security, Cost benefit, Service Transparency, SLA (Service Level Agreement) are some of them.
This certificate certifies that Tushar Kanti Tudu, born May 4, 1977, has successfully completed the Drilling Well Control Programme for Combined Surface and Subsea BOP Stack at Level 3, issued by the International Well Control Forum on February 13, 2015 and expiring February 12, 2017 with certificate number D13SS00040488-01-H13.
IRJET- Groundwater Replenishment in Ambernath RegionIRJET Journal
The document summarizes a research paper on groundwater replenishment techniques for the Ambernath region of India. It describes how the region is experiencing water scarcity due to a rising population and overextraction of groundwater. The paper proposes several artificial groundwater recharge methods to help boost water levels, including injection wells, ditches and furrows, percolation tanks, and stream channel modifications. These techniques are suggested for specific villages based on factors like available land area, proximity to water sources, and permeability of the soil. Implementing these low-cost recharge methods is expected to provide a steady water source and curb further declines in groundwater levels during dry periods.
The document summarizes an environmental impact assessment of the Jamuna Bridge project in Bangladesh. Key points:
- The project involved constructing a 5.63km long road-rail-power bridge over the Jamuna River, along with approach roads and infrastructure.
- Potential environmental impacts identified included loss of fisheries habitat, disruption of wildlife, erosion, drainage issues, and flooding impacts.
- The assessment evaluated these impacts and proposed mitigation measures like constructing fish hatcheries, managing erosion, ensuring adequate drainage, and avoiding construction perpendicular to flood plains.
- Public consultation and environmental monitoring were recommended to minimize impacts and ensure a sustainable project.
IRJET - A Geographical Study of Nilwande Canal in Ahmednagar District, Pravar...IRJET Journal
The document discusses the Nilwande Canal irrigation project in Ahmednagar District of Maharashtra, India. It examines the current state of the Nilwande Canal and its left and right branches. The canal irrigates over 64,260 hectares of land across 182 villages in Ahmednagar and Nashik districts. The left canal branches include the Talegaon and Kopargaon branches. Work is ongoing on various sections of the left and right canals. A proposed high level canal could irrigate an additional 1,572 hectares of land through pipes. The project aims to boost irrigation and agriculture in the drought-prone region.
This document discusses plans for developing the Faculty of Engineering at the University of Jaffna, including establishing a campus in Kilinochchi. It outlines the approved budget and cadre for faculty and staff. It also summarizes various research projects planned for areas like lagoon development, water management, and renewable energy. Finally, it reviews past proposals and studies on developing the Jaffna Lagoon scheme to improve agriculture, fishing, and water resources in the region.
IRJET- Planning and Design of Small Hydro Power Station on D/S of Low Head We...IRJET Journal
This document provides details on planning and designing a small hydro power station downstream of a low head weir (Kolhapur type weir) on the Krishna River in Maharashtra, India. Key aspects summarized:
- A 1 MW power station is proposed utilizing a 7m net head and 19 cumec design discharge available 200m downstream of an existing Kolhapur type weir.
- The power station would utilize four identical 281 kW bulb turbine units within 1800mm diameter penstocks to generate up to 1124 kW of power for 8 months per year when river flows allow.
- Intake, penstock, desilting chamber, trash racks, and other infrastructure elements are designed to efficiently
This curriculum vitae summarizes the qualifications and experience of Vijayakanth M:
- He has over 9 years of experience in engineering consultancy, project management, and design of water supply schemes.
- His qualifications include a Bachelor's degree in Civil Engineering and experience working on projects in India and Qatar.
- Some of his project experience includes designing water supply schemes for municipalities in Tamil Nadu, preparing DPRs for schemes in Coimbatore and Vellore, and project management of a World Bank funded 24x7 water supply scheme in Jharkhand.
William Tarume is a Senior Civil Design Engineer from Zimbabwe with over 20 years of experience in civil engineering projects in South Africa and Zimbabwe. He holds a Bachelor's degree in Civil and Water Engineering and is a registered Professional Engineer with ECSA. He has extensive experience managing and completing various water supply, wastewater, and infrastructure projects on time and under budget for municipalities and other clients. His skills include civil design, project management, construction management, and municipal services.
This document discusses the proposed concrete lining project for the Nahar Wala Minor canal in Sahiban Disty, Punjab. The key details provided include a location map, layout plan, itemized cost estimate of Rs. 78.127 million, and anticipated benefits such as reduced water losses, improved irrigation, and strengthened local economy. An annotated table addresses observations on the project design and costing, justifying differences from the umbrella PC-1 and clarifying aspects of the earthworks, length, diversion works, and need for lining due to past flooding issues.
La historia narra cómo los animales de una granja se rebelan contra su dueño, el señor Jones, cansados del maltrato. Los cerdos más inteligentes, especialmente el cerdo mayor, lideran la rebelión y expulsan al señor Jones de la granja. Con el tiempo, sin embargo, los cerdos comienzan a comportarse como los antiguos dueños, abusando de su poder y privilegios sobre los demás animales.
El documento presenta varios relatos de terror y mitos. En uno, un joven acompaña a sus amigos a una discoteca aunque es tímido. Otro relato involucra a tres personas que descubren una prenda en una tumba. Finalmente, se discuten las funciones de los mitos en diferentes culturas y cómo su narración está ligada a rituales sagrados.
The document contains multiple reports for proposed repairs and improvements to irrigation structures in Anantapuramu district that were damaged during floods in 2012. The reports provide estimates for repairing breaches to channels, restoring pickup anicuts, and reconstructing sections of dams and tanks. The estimates include provisions for excavation, concrete work, embankments, protective works, and other expenses based on the 2013-14 schedule of rates. Permanent repairs are proposed to restore water supply and irrigation to affected villages.
The document contains multiple reports for proposed repairs to various irrigation structures in Anantapuramu district that were damaged during floods in 2012. The structures include pickup anicuts, supply channels, and tanks. The reports provide estimates for repair works such as excavation, concrete work, and other provisions. The estimates are based on the 2013-14 schedule of rates. The repairs aim to restore water supply for irrigation to the ayacuts of various villages.
This document is a curriculum vitae for Akash Kore Ravi. It summarizes his work experience, education, skills, and personal details. Ravi has over 5 years of experience as a Production Engineer and over 2 years of experience in HVAC as a Site Engineer. He holds a Diploma in Mechanical Engineering from 2005. His skills include AutoCAD, MS Office, and MEP courses. He is currently working as a Body Shop Advisor at Shriram Ford in Latur, India.
Dokumen tersebut membahas berbagai topik terkait fenomena fisika dan inovasi yang berasal dari fenomena tersebut, seperti aturan Leonardo tentang pola cabang pohon, fisika ikat rambut, origami, the Cubli, dan RYNO motor. Dokumen ini mengajak pembaca untuk berimajinasi dan berinovasi dengan memanfaatkan prinsip-prinsip fisika yang dijelaskan.
How to Measure the the Quality of Service in Cloud Based Technology?Madushi Rathnayake
This study introduces a framework for service oriented cloud computing with the focus on its service quality aspects in which most demanded by cloud users. It considered two dominant sub-layers such that functional and runtime; against cloud characteristics. SEQUAL model and recent literature were used to derive the quality constructs in cloud environment whilst the opinions of the industry experts were adding more to the blend. The proposed model gives proper identification of service quality expectations and also applicable for different business or geographical contexts. The validity of it for Sri Lankan context were evaluated in this study by using questionnaire based survey while PLS-SEM (partial least squares-structural equation modeling) technique was used to evaluate the outcome. Further the research findings shows the significance of functional layer is rather expected by user than runtime layer and prioritizes quality factors of each layer; in which Service time, Information and data security, Cost benefit, Service Transparency, SLA (Service Level Agreement) are some of them.
This certificate certifies that Tushar Kanti Tudu, born May 4, 1977, has successfully completed the Drilling Well Control Programme for Combined Surface and Subsea BOP Stack at Level 3, issued by the International Well Control Forum on February 13, 2015 and expiring February 12, 2017 with certificate number D13SS00040488-01-H13.
IRJET- Groundwater Replenishment in Ambernath RegionIRJET Journal
The document summarizes a research paper on groundwater replenishment techniques for the Ambernath region of India. It describes how the region is experiencing water scarcity due to a rising population and overextraction of groundwater. The paper proposes several artificial groundwater recharge methods to help boost water levels, including injection wells, ditches and furrows, percolation tanks, and stream channel modifications. These techniques are suggested for specific villages based on factors like available land area, proximity to water sources, and permeability of the soil. Implementing these low-cost recharge methods is expected to provide a steady water source and curb further declines in groundwater levels during dry periods.
The document summarizes an environmental impact assessment of the Jamuna Bridge project in Bangladesh. Key points:
- The project involved constructing a 5.63km long road-rail-power bridge over the Jamuna River, along with approach roads and infrastructure.
- Potential environmental impacts identified included loss of fisheries habitat, disruption of wildlife, erosion, drainage issues, and flooding impacts.
- The assessment evaluated these impacts and proposed mitigation measures like constructing fish hatcheries, managing erosion, ensuring adequate drainage, and avoiding construction perpendicular to flood plains.
- Public consultation and environmental monitoring were recommended to minimize impacts and ensure a sustainable project.
IRJET - A Geographical Study of Nilwande Canal in Ahmednagar District, Pravar...IRJET Journal
The document discusses the Nilwande Canal irrigation project in Ahmednagar District of Maharashtra, India. It examines the current state of the Nilwande Canal and its left and right branches. The canal irrigates over 64,260 hectares of land across 182 villages in Ahmednagar and Nashik districts. The left canal branches include the Talegaon and Kopargaon branches. Work is ongoing on various sections of the left and right canals. A proposed high level canal could irrigate an additional 1,572 hectares of land through pipes. The project aims to boost irrigation and agriculture in the drought-prone region.
This document discusses plans for developing the Faculty of Engineering at the University of Jaffna, including establishing a campus in Kilinochchi. It outlines the approved budget and cadre for faculty and staff. It also summarizes various research projects planned for areas like lagoon development, water management, and renewable energy. Finally, it reviews past proposals and studies on developing the Jaffna Lagoon scheme to improve agriculture, fishing, and water resources in the region.
IRJET- Planning and Design of Small Hydro Power Station on D/S of Low Head We...IRJET Journal
This document provides details on planning and designing a small hydro power station downstream of a low head weir (Kolhapur type weir) on the Krishna River in Maharashtra, India. Key aspects summarized:
- A 1 MW power station is proposed utilizing a 7m net head and 19 cumec design discharge available 200m downstream of an existing Kolhapur type weir.
- The power station would utilize four identical 281 kW bulb turbine units within 1800mm diameter penstocks to generate up to 1124 kW of power for 8 months per year when river flows allow.
- Intake, penstock, desilting chamber, trash racks, and other infrastructure elements are designed to efficiently
This curriculum vitae summarizes the qualifications and experience of Vijayakanth M:
- He has over 9 years of experience in engineering consultancy, project management, and design of water supply schemes.
- His qualifications include a Bachelor's degree in Civil Engineering and experience working on projects in India and Qatar.
- Some of his project experience includes designing water supply schemes for municipalities in Tamil Nadu, preparing DPRs for schemes in Coimbatore and Vellore, and project management of a World Bank funded 24x7 water supply scheme in Jharkhand.
William Tarume is a Senior Civil Design Engineer from Zimbabwe with over 20 years of experience in civil engineering projects in South Africa and Zimbabwe. He holds a Bachelor's degree in Civil and Water Engineering and is a registered Professional Engineer with ECSA. He has extensive experience managing and completing various water supply, wastewater, and infrastructure projects on time and under budget for municipalities and other clients. His skills include civil design, project management, construction management, and municipal services.
This document discusses the proposed concrete lining project for the Nahar Wala Minor canal in Sahiban Disty, Punjab. The key details provided include a location map, layout plan, itemized cost estimate of Rs. 78.127 million, and anticipated benefits such as reduced water losses, improved irrigation, and strengthened local economy. An annotated table addresses observations on the project design and costing, justifying differences from the umbrella PC-1 and clarifying aspects of the earthworks, length, diversion works, and need for lining due to past flooding issues.
This document summarizes a student project on developing a highway networking system in India. It discusses connecting various cities and villages to boost economic development. The project focuses on a 55km stretch of National Highway 222 from Murbad to Malshej Ghat in Maharashtra. It describes the existing conditions including road geometry, drainage, rock conditions and the need for quality improvements. It also discusses various modern soil stabilization techniques needed for subgrade stability. The conclusion is that developing the highway networking system would increase safety and capacity while decreasing travel times and potentially reducing maintenance costs after implementing soil and rock stabilization methods.
The Irrigation & Flood Control Department of Manipur was established in 1976 to manage irrigation and flood control projects in the state. It implements various schemes funded by different sources to control flooding along rivers. These schemes involve constructing retaining walls, embankments, and channelization works along rivers prone to flooding in different districts. The department monitors the physical and financial progress of these schemes with assistance from district authorities.
Water issues of Mumbai city from the perspective of the local municipal authority in charges of supply and distribution to the city. Challenges and solutions to meeting the increasing demand for water and dealing with distribution losses among other problems.
This document analyzes a multi-village rural piped water supply scheme in Thane district of Maharashtra as a case study. The scheme provides water to 24 habitations across 16 villages. It faces issues like insufficient staffing leading to improper valve operation and low water pressure. Some villages have opted out of the scheme due to leaks and incomplete distribution lines. The study evaluates current infrastructure capacities and forecasts future demand. It recommends replacing aging pipes, increasing storage capacities, and improving operations and maintenance to make the scheme sustainable.
1) The Brantas River Basin provides water for irrigation of 907,000 hectares of land, industries using 159 cubic meters per year, and domestic use of 288 cubic meters per year in East Java, Indonesia.
2) The river faces issues of floods and droughts annually due to lack of infrastructure, as well as land use changes, sedimentation, and poor maintenance of existing structures.
3) Beginning in the 1940s, several master plans were developed with Japanese and World Bank assistance to implement flood controls, irrigation, and hydropower projects. The current plan emphasizes integrated watershed management.
This document discusses the history and current state of drinking water management in Jaipur City, India. It notes that Jaipur's water supply originated over 100 years ago from local wells but has since expanded to include surface sources like the Bisalpur Dam. Presently, Jaipur faces a water deficit of 90 MLD despite supplying 374 MLD. Issues include depleting groundwater, illegal connections, and equitable distribution. Solutions proposed include artificial groundwater recharge, reducing non-revenue water, strengthening distribution networks, and managing demand.
Erwin E. Bluemke has over 30 years of experience in environmental and municipal design engineering. Some of his projects include designing underground infrastructure, roadways, and site drainage for Cranberry Village Condominium development valued at $2.0 million and project managing its ongoing construction projects valued at $6.0 million. He also designed the Town of Elmvale Main Sewage Pumping Station, Sewage Lift Station, and Sewage Forcemain valued at $1.8 million. Additionally, he prepared technical reports, design briefs, and drawing reviews for several municipalities and applied for funding and approvals from various provincial ministries and conservation authorities.
The document discusses plans to double the railway line between Utraitia and Zafrabad stations in Lucknow Division of Northern Railway. It will cost approximately 72 crores and involve doubling 12.5 km of track including 2 stations. Work will include expanding formations, bridges, adding ballast, installing new rails, sleepers, points and crossings, upgrading level crossings, and improving station buildings and platforms. Progress on related doubling projects is also provided, such as launching a girder at Anoopganj station in April 2015 and constructing an LHS at Faizabad using cut and cover method from July 15-20, 2015. Details of the current status of the project were obtained from the Northern Railway office in August
The document summarizes a hydrologic report on flooding and sedimentation in the Magasawang Tubig and Bucayao River Basins in Oriental Mindoro, Philippines. It describes the area, stream types and geometry, flow regimes, sedimentation and flooding problems, and identifies mitigation measures. Key findings include extensive sediment deposition from upstream rivers loosening after a 1994 earthquake, flood flows bifurcating from one river to another, and recommendations for comprehensive basin studies and erosion control.
IRJET- Hydraulic and Structural Design of Water Treatment PlantIRJET Journal
This document summarizes the hydraulic and structural design of a water treatment plant in Thodupuzha, India. It includes population forecasting to estimate water demand, surveying of the area to determine pipe routing and elevations, and hydraulic design of intake wells, pumps, treatment components (aerator, flash mixer, clariflocculator, rapid sand filters), chemical storage, and clear water storage. It also describes the structural design of the clariflocculator walls, base, columns, and central shaft. The design was completed using standard manuals and software to generate drawings of the hydraulic systems and structural components.
The first phase of the Northern Collector Water Tunnel project is located along the eastern fringes of the Aberdare Conservation area approximately 60 kilometer north of Nairobi county.
The works are located in Kangema and Kigumo sub counties of Murang'a county
The Northern Collector Water Tunnel Project Report
zigbee technology
1. Report to accompany the Improvements to Pulesu kunta near Venkatagari palli village in
Puttaparthy mandal of Anantapuram (Dist)
Est .Rs
The kunta namely Pulesu kunta is situated about 3km west of Venkatagari palli village
in Puttaparthy mandal of Anantapuram dist., The kunta has free catchment from local hills
namely Nerudu konda which is in forest limits. The kunta is constructed across Pedda vanka
which is running from Kotla palli catchment. The kunta is constructed long back. The kunta is
breached long back and the water getting wasted without storing in the kunta.
So it is proposed for permanent repairs to the breached kunta with the following
provisions.
The estimate is prepared with the following provisions
1) Earth work in execation for foundations.
2) Providing and laying M10-40MSA for foundation concrete
3) Providing and laying M15-20MSA for super structure concrete
4) Providing and laying homogenious embankment
5) Providing and laying 30mm pitching works
6) Provision towards VAT@ 5%
7) Provision towards Cess@ 1%
8) Provision towards stationary, Xerox and Photography charges.
The estimate is prepared based on the current schedule of rates for the year 2014-15
2. Report to accompany the Improvements to the Bukkapatnam cheruvu kaluva of Narepalli near
Narepalli (V) in kothacheuruvu (M) of Anantapuramu (Dist)
Est .Rs. 9.31 Lac
The supply channel namely Bukkapatnam cheruvu kaluva of Nare palli is takes off
from a pickup anicut constructed across Chitravati river about 3.0 Km South of Nare palli village
in Kothacheruvu mandal in Anantapuramu dist., The channel has an direct ayacut of about 185
acres and an indirect ayacut of about 45 acres due to the improvement of ground water. The
kaluva is constructed long back and due seasonal variations the kaluva got damaged at several
places. Due to this ayacut of Narepalli village could not able to get proper water for irrigation.
Hence, it is proposed for repairs to the channel.
So it is proposed for permanent repairs to the supply channel and permanent
restoration of pickup anicut.
The estimate is prepared with the following provisions
1) Earth work in execation for foundations.
2) Providing and laying M10-40MSA for foundation concrete
3) Providing and laying M15-20MSA for super structure concrete
4) Providing and layinc M20_20MSA for wearing coat
3) Provision towards VAT@ 5%
4) Provision towards Cess@ 1%
5) Provision towards stationary, Xerox and Photography charges.
The estimate is prepared based on the current schedule of rates for the year 2013-14.
3. Assitatnat Executive Engineer Deputy Executive Engineer Execuive Engineer
IB section, Kothacheruvu IB sudvision, Gorantla IB Division, Penukonda
Report to accompany the Improvements to the Bukkapatnam cheruvu kaluva of Kanisetty
palli near Kanisetty palli (V) in kothacheuruvu (M) of Anantapuramu (Dist)
Est .Rs. 9.35 Lac
The supply channel namely Bukkapatnam cheruvu kaluva of Kanisetty palli is takes
off from a pickup anicut constructed across Chitravati river about 3.5 Km South of Kanisetty
palli village in Kothacheruvu mandal in Anantapuramu dist., The channel has an direct ayacut
of about 185 acres and an indirect ayacut of about 100 acres due to the improvement of
ground water. The kaluva is constructed long back and due seasonal variations the kaluva got
damaged at several places. Due to this ayacut of Kanisetty palli village could not able to get
proper water for irrigation. Hence, it is proposed for repairs to the channel.
So it is proposed for permanent repairs to the supply channel and permanent
restoration of pickup anicut.
The estimate is prepared with the following provisions
1) Earth work in execation for foundations.
2) Providing and laying M10-40MSA for foundation concrete
3) Providing and laying M15-20MSA for super structure concrete
4) Providing and layinc M20_20MSA for wearing coat
3) Provision towards VAT@ 5%
4) Provision towards Cess@ 1%
5) Provision towards stationary, Xerox and Photography charges.
The estimate is prepared based on the current schedule of rates for the year 2013-14.
4. Assitatnat Executive Engineer Deputy Executive Engineer Execuive Engineer
IB section, Kothacheruvu IB sudvision, Gorantla IB Division, Penukonda
Report to accompany the Permanent Flood damage repairs to the Pickupa anicut to
feed Devara kaluva near Pothula kunta (V) in kothacheuruvu (M) of Anantapuramu (Dist)
Est .Rs. 9.86 Lac
The supply channel namely Devara kaluva is takes off from a pickup anicut
constructed across Vangaperu river about 0.75 Km South East of Pothula kunta village in
Kothacheruvu mandal in Anantapuramu dist., The channel has an direct ayacut of about 45.26
acres and an indirect ayacut of about 60 acres due to the improvement of ground water. Due to
heavy floods on 11.09.2012. about mm rain fall, The supply channel got breached about
150mts and also pick up anicut is damaged severly and thus Devara kaluva does not received
proper water .
So it is proposed for permanent repairs to the supply channel and permanent
restoration of pickup anicut.
The estimate is prepared with the following provisions
1) Earth work in execation for foundations.
2) Providing and laying M10-40MSA for foundation concrete
3) Providing and laying M15-20MSA for super structure concrete
4) Providing and layinc M20_20MSA for wearing coat
5) Providing and laying M20-20MSA for skin wall concrete
6) Provision towards VAT@ 5%
7) Provision towards Cess@ 1%
8) Provision towards stationary, Xerox and Photography charges.
The estimate is prepared based on the current schedule of rates for the year 2013-14.
5. Assitatnat Executive Engineer Deputy Executive Engineer Execuive Engineer
IB section, Kothacheruvu IB sudvision, Gorantla IB Division, P enukonda
Report to accompany the Permanent Flood damage repairs to the Pickupa anicut to feed
Byrapuram tank near Byrapuram (V) in kothacheuruvu (M) of Anantapuramu (Dist)
Est .Rs. 9.98 Lac
The supply channel namely Byrapuram kaluva is takes off from a pickup anicut
constructed across Vangaperu river about 8.0 Km South of Byrapuram, village in Kothacheruvu
mandal in Anantapuramu dist., The channel has an direct ayacut of about 55.74 acres and an
ayacut of about 98 acres from Byrapuram Mi tank. Due to heavy floods on 11.09.2012. about
mm rain fall, The supply channel got breached about 25 mts length. Also the pickup anicut got
damaged severly.
So it is proposed for permanent repairs to the supply channel and permanent
restoration of pickup anicut.
The estimate is prepared with the following provisions
1) Earth work in execation for foundations.
2) Providing and laying M10-40MSA for foundation concrete
3) Providing and laying M15-20MSA for super structure concrete
4) Providing and layinc M20_20MSA for wearing coat
5) Providing and Laying of M20-20MSA for skin wall concrete
3) Provision towards VAT@ 5%
4) Provision towards Cess@ 1%
5) Provision towards stationary, Xerox and Photography charges.
The estimate is prepared based on the current schedule of rates for the year 2013-14.
6. Assitatnat Executive Engineer Deputy Executive Engineer Execuive Engineer
IB section, Kothacheruvu IB sudvision, Gorantla IB Division, Penukonda
Report to accompany the Permanent Flood damage repairs to the anicut across
Yerravanka near (Venkataramana land) in Pothula kunta (V) in kothacheuruvu (M) of
Anantapuramu (Dist)
Est .Rs. 7.05 Lac
The anicut constructed across Yerra river about 0.50Km North-west of Pothula kunta
village in Kothacheruvu mandal in Anantapuramu dist., The channel has an an indirect ayacut
of about 65 acres due to the improvement of ground water. And about 25 BORE WEELS MAY
GET RECHARED. Due to heavy floods on 11.09.2012. about mm rain fall, The ANICUT got
breached about 20mts on L/S and also pick up anicut is damaged severly and thus the water
getting wasted.
So it is proposed for permanent repairs and permanent restoration of pickup anicut.
The estimate is prepared with the following provisions
1) Earth work in execation for foundations.
2) Providing and laying M10-40MSA for foundation concrete
3) Providing and laying M15-20MSA for super structure concrete
4) Providing and layinc M20_20MSA for wearing coat
5) Provision towards VAT@ 5%
6) Provision towards Cess@ 1%
7) Provision towards stationary, Xerox and Photography charges.
The estimate is prepared based on the current schedule of rates for the year 2013-14.
7. Assitatnat Executive Engineer Deputy Executive Engineer Execuive Engineer
IB section, Kothacheruvu IB sudvision, Gorantla IB Division, Penukonda
Report to accompany the Permanent Flood damage repairs to the Pickupa anicut to feed
Bandala kaluva near Bandla palli (V) in kothacheuruvu (M) of Anantapuramu (Dist)
Est .Rs. 9.82 Lac
The supply channel namely Bandala palli kaluva is takes off from a pickup anicut
constructed across Vangaperu river about 1.50Km South of Bandla palli village in Kothacheruvu
mandal in Anantapuramu dist., The channel has an direct ayacut of about 13.39 acres and an
indirect ayacut of about 45 acres due to the improvement of ground water. Due to heavy
floods on 11.09.2012. about mm rain fall, The supply channel got breached and also pickup
anicut damaged severly.
So it is proposed for permanent repairs to the supply channel and permanent
restoration of pickup anicut.
The estimate is prepared with the following provisions
1) Earth work in execation for foundations.
2) Providing and laying M10-40MSA for foundation concrete
3) Providing and laying M15-20MSA for super structure concrete
4) Providing and layinc M20_20MSA for wearing coat
5) Providing and Laying of M20-20MSA for skin wall concrete
3) Provision towards VAT@ 5%
4) Provision towards Cess@ 1%
5) Provision towards stationary, Xerox and Photography charges.
The estimate is prepared based on the current schedule of rates for the year 2013-14.
8. Assitatnat Executive Engineer Deputy Executive Engineer Execuive Engineer
IB section, Kothacheruvu IB sudvision, Gorantla IB Division, P enukonda
Report to accompany the Permanent Flood damage repairs to the Pickupa anicut to feed
Kankanala kaluva near Bandla palli (V) in kothacheuruvu (M) of Anantapuramu (Dist)
Est .Rs. 9.99 Lac
The supply channel namely Kankanala kaluva is takes off from a pickup anicut
constructed across Vangaperu river about 1.80Km South of Bandla palli village in Kothacheruvu
mandal in Anantapuramu dist., The channel has an direct ayacut of about 54.59 acres and an
indirect ayacut of about 45 acres due to the improvement of ground water. Due to heavy
floods on 11.09.2012. about mm rain fall, The supply channel got breached and also pickup
anicut damaged severly.
So it is proposed for permanent repairs to the supply channel and permanent
restoration of pickup anicut.
The estimate is prepared with the following provisions
1) Earth work in execation for foundations.
2) Providing and laying M10-40MSA for foundation concrete
3) Providing and laying M15-20MSA for super structure concrete
4) Providing and layinc M20_20MSA for wearing coat
5) Providing and Laying of M20-20MSA for skin wall concrete
3) Provision towards VAT@ 5%
4) Provision towards Cess@ 1%
5) Provision towards stationary, Xerox and Photography charges.
The estimate is prepared based on the current schedule of rates for the year 2013-14.
9. Assitatnat Executive Engineer Deputy Executive Engineer Execuive Engineer
IB section, Kothacheruvu IB sudvision, Gorantla IB Division, P enukonda
Report to accompany the Permanent Flood damage repairs to the Pickupa anicut to feed
Pennaraju kaluva near Bandla palli (V) in kothacheuruvu (M) of Anantapuramu (Dist)
Est .Rs. 24.20 Lac
The supply channel namely Pennaraju kaluva is takes off from a pickup anicut
constructed across Vangaperu river about 1.20Km South of Bandla palli village in Kothacheruvu
mandal in Anantapuramu dist., The channel has an direct ayacut of about 35.98 acres and an
indirect ayacut of about 60 acres due to the improvement of ground water. Due to heavy
floods on 11.09.2012. about mm rain fall, The supply channel got breached and also pickup
anicut damaged severly.
So it is proposed for permanent repairs to the supply channel and permanent
restoration of pickup anicut.
The estimate is prepared with the following provisions
1) Earth work in execation for foundations.
2) Providing and laying M10-40MSA for foundation concrete
3) Providing and laying M15-20MSA for super structure concrete
4) Providing and layinc M20_20MSA for wearing coat
5) Providing and Laying of M20-20MSA for skin wall concrete
3) Provision towards VAT@ 5%
4) Provision towards Cess@ 1%
5) Provision towards stationary, Xerox and Photography charges.
The estimate is prepared based on the current schedule of rates for the year 2013-14.
10. Assistant Executive Engineer Deputy Executive Engineer Execuive Engineer
IB section, Kothacheruvu IB sudvision, Gorantla IB Division, Penukonda
Report to accompany the Permanent Flood damage repairs to the Pickupa anicut to feed K.Locherla MI tank
kothacheuruvu (M) of Anantapuramu (Dist)
Est .Rs. 24.20 Lac
The supply channel namely Pennaraju kaluva is takes off from a pickup anicut constructed across V
South of Bandla palli village in Kothacheruvu mandal in Anantapuramu dist., The channel has an direct ayacut
indirect ayacut of about 60 acres due to the improvement of ground water. Due to heavy floods on 11.09.2012
supply channel got breached and also pickup anicut damaged severly.
So it is proposed for permanent repairs to the supply channel and permanent restoration of pickup an
The estimate is prepared with the following provisions
1) Earth work in execation for foundations.
2) Providing and laying M10-40MSA for foundation concrete
3) Providing and laying M15-20MSA for super structure concrete
4) Providing and layinc M20_20MSA for wearing coat
5) Providing and Laying of M20-20MSA for skin wall concrete
3) Provision towards VAT@ 5%
4) Provision towards Cess@ 1%
5) Provision towards stationary, Xerox and Photography charges.
The estimate is prepared based on the current schedule of rates for the year 2013-14.
Assistant Executive Engineer Deputy Executive Engineer Execuive Engineer