DATE OF
LESSON
PROD OR POST
PRODUCTION
TASK (WHAT YOU
WILL BE DOING)
WHERE WILL THE
TASK TAKE PLACE
WHAT CREW AND
CAST ARE NEEDED
WHAT PROPS AND COSTUMES
ARE NEEDED
WHAT EQUIPMENT IS
NEEDED
28TH
JANUARY- 4TH
FEBRUARY
PRODUCTION-
FILMING
FILMING SCENES 2, ½
OF 4, 7 & 8
TO BE FILMED IN THE
MORNINGS(7AM-
12PM FOR BEST
POSSIBLELIGHTING)
AT HOME (SCENES
INSIDEGEORGE’S
HOUSE)
CAST NEEDED: GEORGE
ANDGEORGE’S WIFE
CREW NEEDED: LUCY
(DIRECTOR)
GEORGE WILL BE CHANGED
FROMPYJAMAS/CASUALWEAR
TO ASSIGNEDFISHERMAN
CLOTHING ASSCENES
PROGRESS
GEORGE’S WIFE WILL BE
DRESSED IN HER ASSIGNED
CLOTHING FORTHE SCENES SHE
IS FEATURED IN
PROPS:BREAKFAST/CLOTHING
ANDFISHINGEQUIPMENT
CANON CAMERA TO FILM,
LIGHTS, TRIPOD AND
MICROPHONE
4TH
FEBRUARY-
8TH
FEBRUARY
PRODUCTION-
FILMING
FILMING OUTDOOR
PARTSOF SCENE 4
DRIVEWAYAT HOME
(ASGEORGE GETS
INTOVEHICLE) AND
THEN LOCATIONS
TOWARDSTHE LAKE
ANDARRIVALAT THE
LAKE
CAST NEEDED: GEORGE
CREW NEEDED: LUCY
(DIRECTOR)
GEORGE WILL BE IN ASSIGNED
FISHERMAN CLOTHING
PROPS:FISHINGEQUIPMENT
CANON CAMERA TO FILM,
LIGHTS, TRIPOD AND
MICROPHONEANDWIND
BREAK FOROUTDOOR
NOISE
9TH
FEBRUARY PRODUCTION-
FILMING
FULL DAY FILMING
SCENE 3 (WHICH IS
ALSOTO BE
DISPLAYEDON THE
TELEVISION IN SCENE
7)
LAKE- MAIN
LOCATION
CAST NEEDED:
GEORGE, THE
POLICEMAN AND
FORENSICEXTRASIN
BACKGROUND
CREW NEEDED: LUCY
(DIRECTOR)
GEORGE WILL BE IN ASSIGNED
FISHERMAN CLOTHING
THE POLICEMAN WILL BE
DRESSED IN POLICEUNIFORM
PROPS:FISHINGEQUIPMENT,
ANYPOLICE PROPSSUCH AS
POLICETAPE ETC
CANON CAMERA TO FILM,
LIGHTS, TRIPOD AND
MICROPHONEANDWIND
BREAK FOROUTDOOR
NOISE
10TH
FEBRUARY
PRODUCTION-
FILMING
FULL DAY FILMING
SCENE 6 (MAIN
SCENE)
LAKE- MAIN
LOCATION
CAST NEEDED: GEORGE
CREW NEEDED: LUCY
(DIRECTOR)
GEORGE WILL BE IN ASSIGNED
FISHERMAN CLOTHING
PROPS:MAKEUP FOR BRUISES,
FISHINGEQUIPMENT
CANON CAMERA TO FILM,
LIGHTS, TRIPOD AND
MICROPHONEANDWIND
BREAK FOROUTDOOR
NOISE
11TH
-17TH
FEBRUARY
PRODUCTION-
FILMING
SCENE 1 (ALSOTO BE
DISPLAYEDAT THE
END OF SCENE6) AND
REST OF SCENE 6 IF
NOT COMPLETED
LAKE- MAIN
LOCATION
CAST NEEDED: GEORGE
CREW NEEDED: LUCY
(DIRECTOR)
GEORGE WILL BE IN ASSIGNED
FISHERMAN CLOTHING
PROPS:MAKEUP FOR BRUISES,
FISHINGEQUIPMENT
CANON CAMERA TO FILM,
LIGHTS, TRIPOD AND
MICROPHONEANDWIND
BREAK FOROUTDOOR
NOISE
17TH
-24TH
FEBRUARY
PRODUCTION-
FILMING
ALL WEEK FILMING
SCENESTHAT HAVE
NOT BEEN FINISHED
(ANYEXTRA SHOTSI
FEEL I MAY NEED)
GEORGE’S HOUSE,
LAKE
CAST NEEDED:
GEORGE, THE
POLICEMAN,GEORGE’S
WIFE
CREW NEEDED: LUCY
(DIRECTOR)
GEORGE WILL BE IN ASSIGNED
FISHERMAN CLOTHING
THE POLICEMAN WILL BE
DRESSED IN POLICEUNIFORM
GEORGE’S WIFE DRESSED IN
HER ASSIGNEDOUTFIT
CANON CAMERA TO FILM,
LIGHTS, TRIPOD AND
MICROPHONEANDWIND
BREAK FOROUTDOOR
NOISE
24TH
FEBRUARY-
15TH
MARCH
POST PRODUCTION-
EDITING
DELETING SCENES
THAT AREN’TGOING
TO BE INCLUDED,
RENAMINGSCENES
ANDEDIT FILM
MEDIA ROOMS AT
SCHOOL AND
EDITING AT HOME
EDITOR: LUCY N/A ADOBE PREMIERE PRO,
COMPUTER, SD CARD,
CARD READER
15TH
MARCH-
22ND
MARCH
POST PRODUCTION-
EDITING
EDIT FILM ANDFINAL
FINISHINGTOUCHES
BEFORE HAND IN
DATE
MEDIA ROOMS AT
SCHOOL AND
EDITING AT HOME
EDITOR: LUCY N/A ADOBE PREMIERE PRO,
COMPUTER, SD CARD,
CARD READER
Production Plan

Production Plan

  • 1.
    DATE OF LESSON PROD ORPOST PRODUCTION TASK (WHAT YOU WILL BE DOING) WHERE WILL THE TASK TAKE PLACE WHAT CREW AND CAST ARE NEEDED WHAT PROPS AND COSTUMES ARE NEEDED WHAT EQUIPMENT IS NEEDED 28TH JANUARY- 4TH FEBRUARY PRODUCTION- FILMING FILMING SCENES 2, ½ OF 4, 7 & 8 TO BE FILMED IN THE MORNINGS(7AM- 12PM FOR BEST POSSIBLELIGHTING) AT HOME (SCENES INSIDEGEORGE’S HOUSE) CAST NEEDED: GEORGE ANDGEORGE’S WIFE CREW NEEDED: LUCY (DIRECTOR) GEORGE WILL BE CHANGED FROMPYJAMAS/CASUALWEAR TO ASSIGNEDFISHERMAN CLOTHING ASSCENES PROGRESS GEORGE’S WIFE WILL BE DRESSED IN HER ASSIGNED CLOTHING FORTHE SCENES SHE IS FEATURED IN PROPS:BREAKFAST/CLOTHING ANDFISHINGEQUIPMENT CANON CAMERA TO FILM, LIGHTS, TRIPOD AND MICROPHONE 4TH FEBRUARY- 8TH FEBRUARY PRODUCTION- FILMING FILMING OUTDOOR PARTSOF SCENE 4 DRIVEWAYAT HOME (ASGEORGE GETS INTOVEHICLE) AND THEN LOCATIONS TOWARDSTHE LAKE ANDARRIVALAT THE LAKE CAST NEEDED: GEORGE CREW NEEDED: LUCY (DIRECTOR) GEORGE WILL BE IN ASSIGNED FISHERMAN CLOTHING PROPS:FISHINGEQUIPMENT CANON CAMERA TO FILM, LIGHTS, TRIPOD AND MICROPHONEANDWIND BREAK FOROUTDOOR NOISE
  • 2.
    9TH FEBRUARY PRODUCTION- FILMING FULL DAYFILMING SCENE 3 (WHICH IS ALSOTO BE DISPLAYEDON THE TELEVISION IN SCENE 7) LAKE- MAIN LOCATION CAST NEEDED: GEORGE, THE POLICEMAN AND FORENSICEXTRASIN BACKGROUND CREW NEEDED: LUCY (DIRECTOR) GEORGE WILL BE IN ASSIGNED FISHERMAN CLOTHING THE POLICEMAN WILL BE DRESSED IN POLICEUNIFORM PROPS:FISHINGEQUIPMENT, ANYPOLICE PROPSSUCH AS POLICETAPE ETC CANON CAMERA TO FILM, LIGHTS, TRIPOD AND MICROPHONEANDWIND BREAK FOROUTDOOR NOISE 10TH FEBRUARY PRODUCTION- FILMING FULL DAY FILMING SCENE 6 (MAIN SCENE) LAKE- MAIN LOCATION CAST NEEDED: GEORGE CREW NEEDED: LUCY (DIRECTOR) GEORGE WILL BE IN ASSIGNED FISHERMAN CLOTHING PROPS:MAKEUP FOR BRUISES, FISHINGEQUIPMENT CANON CAMERA TO FILM, LIGHTS, TRIPOD AND MICROPHONEANDWIND BREAK FOROUTDOOR NOISE 11TH -17TH FEBRUARY PRODUCTION- FILMING SCENE 1 (ALSOTO BE DISPLAYEDAT THE END OF SCENE6) AND REST OF SCENE 6 IF NOT COMPLETED LAKE- MAIN LOCATION CAST NEEDED: GEORGE CREW NEEDED: LUCY (DIRECTOR) GEORGE WILL BE IN ASSIGNED FISHERMAN CLOTHING PROPS:MAKEUP FOR BRUISES, FISHINGEQUIPMENT CANON CAMERA TO FILM, LIGHTS, TRIPOD AND MICROPHONEANDWIND BREAK FOROUTDOOR NOISE
  • 3.
    17TH -24TH FEBRUARY PRODUCTION- FILMING ALL WEEK FILMING SCENESTHATHAVE NOT BEEN FINISHED (ANYEXTRA SHOTSI FEEL I MAY NEED) GEORGE’S HOUSE, LAKE CAST NEEDED: GEORGE, THE POLICEMAN,GEORGE’S WIFE CREW NEEDED: LUCY (DIRECTOR) GEORGE WILL BE IN ASSIGNED FISHERMAN CLOTHING THE POLICEMAN WILL BE DRESSED IN POLICEUNIFORM GEORGE’S WIFE DRESSED IN HER ASSIGNEDOUTFIT CANON CAMERA TO FILM, LIGHTS, TRIPOD AND MICROPHONEANDWIND BREAK FOROUTDOOR NOISE 24TH FEBRUARY- 15TH MARCH POST PRODUCTION- EDITING DELETING SCENES THAT AREN’TGOING TO BE INCLUDED, RENAMINGSCENES ANDEDIT FILM MEDIA ROOMS AT SCHOOL AND EDITING AT HOME EDITOR: LUCY N/A ADOBE PREMIERE PRO, COMPUTER, SD CARD, CARD READER 15TH MARCH- 22ND MARCH POST PRODUCTION- EDITING EDIT FILM ANDFINAL FINISHINGTOUCHES BEFORE HAND IN DATE MEDIA ROOMS AT SCHOOL AND EDITING AT HOME EDITOR: LUCY N/A ADOBE PREMIERE PRO, COMPUTER, SD CARD, CARD READER