Presentation by gursharan singh for engineeringcivil.com
This document describes a semester project on pre-engineered steel buildings completed by Gursharan Singh from June to December 2007. It provides background on pre-engineered buildings and discusses their components, applications, advantages over conventional construction, and design optimization work done as part of the project, including varying frame dimensions and loads. The project involved detailed literature review and design of pre-engineered building frames.
In this document
Powered by AI
Introduction to the project, presenter details, and time frame for the project.
Introduction of Era Building Systems Ltd. and associated companies within Era Group.
Overview of pre-engineered buildings (PEB), their customizability, and historical context in the USA.
Diverse applications of PEB including industrial buildings, warehouses, stadiums, and more.
Key benefits of PEB like aesthetic appeal, speed of construction, seismic resistance, and cost efficiency.
Description of main frame components including primary members, secondary members, and additional parts.
Discussion of design challenges such as structural planning, load types, and frame configurations.
Standard nomenclature for PEB designs and guidelines for adherence to American and IS codes.
Details on frame optimization, including dimensions, calculations of varying widths, heights, and design steps.
Documentation of site visits, processes involved in erection, and preparation for construction.
Detailed steps involved in the erection process, including checks, material receiving, and sheeting.
ERA BUILDING SYSTEMSLTD., NOIDA
PRE ENGINEERED
STEEL BUILDINGS
Concept , Design
&
Construction
3.
ERA GroupERA Group
EraInfra Engineering Ltd.Era Infra Engineering Ltd.
Era Building System Ltd.Era Building System Ltd.
Era E-Zone (India) Ltd.Era E-Zone (India) Ltd.
Era Landmarks (India) Ltd.Era Landmarks (India) Ltd.
4.
PRE ENGINEERED BUILDINGSPREENGINEERED BUILDINGS
Tailor made building based on
client’s requirement & actual
design calculations using tapered
sections.
A combination of built up section,
hot rolled section, cold formed
elements and profiled sheets
Designing and casting is done in
factory
Building components are brought
to site
Then fixed/jointed at the site
All connections are bolted.
5.
Steel wasvery expensive item in USASteel was very expensive item in USA
The concept of PEB originate from here.The concept of PEB originate from here.
The idea was that section should be provided as perThe idea was that section should be provided as per
B.M.D.B.M.D.
This lead to the saving in steel and development of PEBThis lead to the saving in steel and development of PEB
concept.concept.
BRIEF HISTORYBRIEF HISTORY
6.
APPLICATIONSAPPLICATIONS
Industrial BuildingsIndustrialBuildings
WarehousesWarehouses
Commercial ComplexesCommercial Complexes
ShowroomsShowrooms
OfficesOffices
SchoolsSchools
Indoor StadiumsIndoor Stadiums
Outdoor Stadiums with canopiesOutdoor Stadiums with canopies
Gas StationsGas Stations
Metro Stations, Bus Terminals, Parking LotsMetro Stations, Bus Terminals, Parking Lots
Primary Health Centers, Angan wadi’sPrimary Health Centers, Angan wadi’s
And many more…And many more…
P E BP E B
ADVANTAGESADVANTAGES
Aesthetic AppealAestheticAppeal
Faster CompletionFaster Completion
EconomicalEconomical
Seismic ResistanceSeismic Resistance
Ease of ExpansionEase of Expansion
Maintenance FreeMaintenance Free
Large Clear SpansLarge Clear Spans
Controlled QualityControlled Quality
Hassle FreeHassle Free
P E BP E B
10.
Self weightSelfweight
30% lighter30% lighter
Primary Member isPrimary Member is
tapered sectiontapered section
Secondary membersSecondary members
are light weight rolledare light weight rolled
framed “Z” and “C”framed “Z” and “C”
sectionsection
Self weightSelf weight
More heavyMore heavy
Primary members arePrimary members are
Hot rolled “I” sectionHot rolled “I” section
Secondary membersSecondary members
are “I” or “C” sectionare “I” or “C” section
which are heavy inwhich are heavy in
weight.weight.
11.
Delivery –average 6 to 8Delivery – average 6 to 8
weeksweeks
Foundation-simpleFoundation-simple
design, easy to constructdesign, easy to construct
& light wt.& light wt.
Erection cost and time-Erection cost and time-
accurately knownaccurately known
Erection process is easy,Erection process is easy,
fast, step by stepfast, step by step
Delivery- average 20 to 26Delivery- average 20 to 26
weeksweeks
Foundation- expensive,Foundation- expensive,
heavy foundationheavy foundation
required.required.
Erection cost and time-Erection cost and time-
20% more than PEB20% more than PEB
Erection process is slowErection process is slow
and extensive field laborand extensive field labor
is required.is required.
12.
Seismic Resistance-lowSeismic Resistance- low
weight flexible framesweight flexible frames
offer higher resistance tooffer higher resistance to
seismic forcesseismic forces
Overall price -30%lowerOverall price -30%lower
architecture-achieved atarchitecture-achieved at
low castlow cast
Seismic Resistance- rigidSeismic Resistance- rigid
heavy weight structuresheavy weight structures
do not perform well indo not perform well in
seismic zonesseismic zones
Overall price - HigherOverall price - Higher
Price per square meter.Price per square meter.
Architecture- achieved atArchitecture- achieved at
higher costhigher cost
13.
COMPONENTSCOMPONENTS
Main FrameMainFrame
Primary MembersPrimary Members
ColumnsColumns
RaftersRafters
SecondarySecondary
MembersMembers
PurlinsPurlins
GirtsGirts
P E BP E B
SheetingSheeting
RoofRoof
WallWall
Fascias etcFascias etc
AccessoriesAccessories
VentilatorsVentilators
Sky LightsSky Lights
Misc.Misc.
15.
OTHER MAJOR COMPONENTSOF PEB
CRANE BRACKETS &
BEAMS
MEZZANINE
FLOORS
STRUCTURAL
PARTIONS
FASCIAS CANOPIES
16.
Work doneWork done
DetailDetail Literatrue studyLiteratrue study
Optimaztion of frameOptimaztion of frame
J-286, Thermax Limited at VadodaraJ-286, Thermax Limited at Vadodara
J-327, Sub Station L & T SuratJ-327, Sub Station L & T Surat
J-275-302 Hazira, SuratJ-275-302 Hazira, Surat
J-273 L & T Talegaon, Pune.J-273 L & T Talegaon, Pune.
Plant VisitPlant Visit
Site VisitSite Visit
Load 1
X
Y
Z
PRE-ENGINEERED BUILDINGSNOMENCLATURE –PRE-ENGINEERED BUILDINGS NOMENCLATURE –
STANDARD FRAMING SYSTEMSSTANDARD FRAMING SYSTEMS
TCCS = TAPERED COLUMN CLEAR SPAN
Load 1
X
Y
Z
TCMS-1 TAPERED COLUMN MULTI-SPAN WITH 1
INTERMEDIATE COLUMN.
21.
Load 1
SSCS =SINGLE SLOPE CLEAR SPAN.
Load 1
X
Y
Z
SSMS-1= SINGLE SLOPE MULTI-SPAN WITH 1
INTERMEDIATE COLUMN
22.
GUIDELINES FOR PEBDESIGN AT PROPOSAL
STAGE
ALL DESIGNS SHALL BE AS PER MBMA AMERICAN
STANDARDS UNLESS CLIENT SPECIFIES AS PER IS
CODE
LIVE LOAD AS PER AMERICAN CODE = 0.57
KN/M^2 AND AS PER IS CODE = 0.75 KN/M^2.
(REDUCTION IN LIVE LOAD TO BE INCORPORATED
FOR BUILDINGS HAVING HIGHER SLOPES)
AS PER AMERICAN CODE :HORIZONTAL
DEFLECTION = L/180 & VERTICAL
DEFLECTION=Eh/100 FOR MAIN FRAMES.
WIND TERRAIN CATEGORY 3 IS TO BE SELECTED
UNLESS MORE DATA IS AVAILABLE.
23.
CONTD……
IN AMERICANDESIGN , WIND COEFFICIENTS TO BE
FOLLOWED AS GIVEN IN MBMA.
IN IS DESIGN, INTERNAL & EXTERNAL BUILDING
WIND COEFFICIENTS AS PER IS -875 (PART-3).
GENERALLY BUILDINGS ARE TO BE DESIGNED AS
PINNED EXCEPT FOR BUILDING SPAN >30M OR
CRANE CAPACITY OF MORE THAN 5 TONS OR
HEIGHT GREATER THAN 9 M
STANDARD PURLIN LAPS SHOULD BE 385 mm
24.
Optimisation of frameOptimisationof frame
Basic FrameBasic Frame
• Width of the frame = 20 mWidth of the frame = 20 m
• Height of the frame = 6 mHeight of the frame = 6 m
• Length of the frame = 70 mLength of the frame = 70 m
• Bay spacing l = 7 mBay spacing l = 7 m
• Slop of roof i= 1:10Slop of roof i= 1:10
• Wind speed v = 43 m/sWind speed v = 43 m/s
• Seismic zone = 4Seismic zone = 4
25.
Varying of Widthof FrameVarying of Width of Frame
Only Primary Frame
Design Purline 250 X 2.5 mm2
Spacing-1.5
7.67 kg/m
Design Girt 200X1.75
mm2
Spacing-1.5
6.09 kg/m
26.
Varying Height andwidthVarying Height and width
Design Purline 250 X 2.5 mm2
Spacing-1.5
7.67 kg/m
Spacing-1.5
Design Girt 250X2.0 mm2
Spacing-1.5
6.09 kg/m
Spacing-1.5
Only Primary Frame
27.
Varying Bay lengthwith HeightVarying Bay length with Height
Heigth-6 Heigth-8 Heigth-9
Purline Girt Purline Girt Purline Girt
6 Z 200X1.75
Spacing-1.5
Z 200X1.75
Spacing-1.5
Z 200X1.75
Spacing-1.5
Z 200X1.75
Spacing-1.5
Z 200X1.75
Spacing-1.5
Z 200X1.75
Spacing-1.5
7 Z 250X 2.0
Spacing-1.5
Z 250X1.75
Spacing-1.35
Z 250X 2.0
Spacing-1.5
Z 250X1.75
Spacing-1.35
Z 250X 2.0
Spacing-1.5
Z 250X1.75
Spacing-1.35
8 Z 250 X 2.5
Spacing-1.5
Z 250 X 2.5
Spacing-1.5
Z 250 X 2.5
Spacing-1.5
Z 250 X 2.5
Spacing-1.5
Z 250 X 2.5
Spacing-1.5
Z 250 X 2.5
Spacing-1.5
9 C250 X 2.5
Spacing-1.4
C 250 X 2.5
Spacing-1.35
C250 X 2.5
Spacing-1.4
C 250 X 2.5
Spacing-1.35
C250 X 2.5
Spacing-1.4
C 250 X 2.5
Spacing-1.35
10 C 250 X 2.5
Spacing-1.0
C 250 X 2.5
Spacing-1.0
C 250 X 2.5
Spacing-1.0
C 250 X 2.5
Spacing-1.0
C 250 X 2.5
Spacing-1.0
C 250 X 2.5
Spacing-1.0
Total weight of Frame, Purline and Girt
28.
Varying bay lengthwith widthVarying bay length with width
Heigth-6 Heigth-8 Heigth-9
Purline Girt Purline Girt Purline Girt
6 Z 200X1.75
Spacing-1.5
Z 200X1.75
Spacing-1.5
Z 200X1.75
Spacing-1.5
Z 200X1.75
Spacing-1.5
Z 200X1.75
Spacing-1.5
Z 200X1.75
Spacing-1.5
7 Z 250X 2.0
Spacing-1.5
Z 250X1.75
Spacing-1.35
Z 250X 2.0
Spacing-1.5
Z 250X1.75
Spacing-1.35
Z 250X 2.0
Spacing-1.5
Z 250X1.75
Spacing-1.35
8 Z 250 X 2.5
Spacing-1.5
Z 250 X 2.5
Spacing-1.5
Z 250 X 2.5
Spacing-1.5
Z 250 X 2.5
Spacing-1.5
Z 250 X 2.5
Spacing-1.5
Z 250 X 2.5
Spacing-1.5
9 C250 X 2.5
Spacing-1.4
C 250 X 2.5
Spacing-1.35
C250 X 2.5
Spacing-1.4
C 250 X 2.5
Spacing-1.35
C250 X 2.5
Spacing-1.4
C 250 X 2.5
Spacing-1.35
10 C 250 X 2.5
Spacing-1.0
C 250 X 2.5
Spacing-1.0
C 250 X 2.5
Spacing-1.0
C 250 X 2.5
Spacing-1.0
C 250 X 2.5
Spacing-1.0
C 250 X 2.5
Spacing-1.0
Total weight of Frame, Purline and Girt
29.
Varying wind speedwith widthVarying wind speed with widthwind Width-20m Width-35
speed Purline Girt Purline Girt
33 Z 200 X 1.75
Spacing-1.5
Z 200X1.75
Spacing-1.5
Z 200 X 1.75
Spacing-1.5
Z 200X1.75
Spacing-1.5
39 Z 200 X 2.0
Spacing-1.5
Z 200X2.0
Spacing-1.5
Z 200 X 2.0
Spacing-1.5
Z 200X2.0
Spacing-1.5
43 Z 250 X 2
Spacing-1.5
Z 250X2.0
Spacing-1.4
Z 250 X 2
Spacing-1.5
Z 250X2.0
Spacing-1.4
47 Z 250 X 2.5
Spacing-1.5
Z 250X2.0
Spacing-1.45
Z 250 X 2.5
Spacing-1.5
Z 250X2.0
Spacing-1.45
50 Z 250 X 2.5
Spacing-1.5
Z 250 X 2.5
Spacing-1.5
Z 250 X 2.5
Spacing-1.5
Z 250 X 2.5
Spacing-1.5
55 C 250 X 2.5
Spacing-1.35
C 250 X 2.5
Spacing-1.5
C 250 X 2.5
Spacing-1.35
C 250 X 2.5
Spacing-1.5
Total weight of Frame, Purline and Girt
30.
Steps of DesignStepsof Design
Wind load calculationWind load calculation
Purline DesignPurline Design
Girt DesignGirt Design
Design of Main FrameDesign of Main Frame
Base PlateBase Plate
Anchor Bolt design for Moment ConditionAnchor Bolt design for Moment Condition
Anchor Bolt design for Shear ConditionAnchor Bolt design for Shear Condition
Gable column designGable column design
Design of connection plateDesign of connection plate
Cranes DesignCranes Design
PROCESSESPROCESSES
PEB
BUILT UP LINECOLD FORM LINE SHEETING
PRIMARY
MEMBERS
CKD
C & Z PURLINS
LINE
HR SECTIONS
&
MISCELLANEOUS
PARTS
ROOF & WALL
SHEETING
GUTTER,
FLASHINGS,
TRIMS, ETC
CKD CKD CKD ACCESSORIES
SHIPMENT
P E BP E B
ERECTION SYSTEMERECTION SYSTEM
UNDERSTANDING THE ENGINEERINGUNDERSTANDING THE ENGINEERING
DOCUMENTS.DOCUMENTS.
1.1. Anchor Bolt Setting PlanAnchor Bolt Setting Plan
2.2. Cross sectionCross section
3.3. Roof framing planRoof framing plan
4.4. Roof sheeting & framingRoof sheeting & framing
5.5. Sidewall sheeting & framingSidewall sheeting & framing
6.6. Other drawingsOther drawings
7.7. Bill of materialsBill of materials
43.
CONTD…CONTD…
Preparation forErectionPreparation for Erection
1.1. Pre Erection checksPre Erection checks
2.2. Receiving Materials at siteReceiving Materials at site
3.3. Unloading ContainersUnloading Containers
Erection of the FramingErection of the Framing
1.1. Preparation of the First BayPreparation of the First Bay
2.2. Main framesMain frames
3.3. Mezzanine floorsMezzanine floors
4.4. Crane BeamsCrane Beams
44.
CONTD….CONTD….
Sheeting & TrimmingSheeting& Trimming
Sheeting preparationSheeting preparation
Sheeting the wallsSheeting the walls
Sheeting the roofsSheeting the roofs
Miscellaneous trimmingsMiscellaneous trimmings
FasciaFascia