PORTFOLIO AS QUANTITY SURVEYOR AND ESTIMATOR
*HERE IS COLLECTED A BRIEF DESCRIPTION OF ALL THE PROJECTS THAT I STUDIED AS
QUANTITY SURVEYOR AND ESTIMATOR DURING MY STAY IN SERINCO. JUST INCLUDED
THE PROJECT WHERE I WAS THE MAIN QUANTITY SURVEYOR.
* ALL THE BUDGETS ARE A DIRECT CURRENCY EXCHANGE. CONSIDER THAT THE
CHILEAN CONSTRUCTION MARKET IS NOT THE BRITISH.
50 APARTMENTS
TOTAL SURFACE: 8,200 m2
TOTAL BUDGET: £ 5,555,504
14 FLOORS
GROUND FLOOR
2 UNDERGROUND FLOORS
CONCRETE STRUCTURE
GYM
SWIMMING POOL
EVENT ROOM
59 PARKING SPACES
59 STORE ROOMS
LOCATION: VIÑA DEL MAR, VALPARAISO, CHILE
BUDGET SUMMARY
7 APARTMENT MODELS
108 APARTMENTS
TOTAL SURFACE: 6,900 m2
TOTAL BUDGET: £ 5,055,709
10 FLOORS
2 UNDERGROUND FLOORS
CONCRETE STRUCTURE
GYM
SWIMMING POOL
2 EVENT ROOMS
BARBECUE AND GREEN AREA
LOCATION: LAS CONDES, SANTIAGO DE CHILE, CHILE
BUDGET SUMMARY
REFURBISHMENT "NAVY COMMAND
TALCAHUANO"
After the earthquake that took place in Concepción in February 2010. The
main facade of this building was seriously damaged. The project proposed the
removal of all the elements to be conserved, propping up of the structure,
demolition of all the structural elements damaged, rebuilding, restoration and
reinstatement of all the elements conserved.
BUDGET SUMMARY
SECOND PHASE (W2)
66m2apa a 304m2
APARTMENTS FROM 166 m2 to 304 m2
8 BUILDINGS
23 APARTMENTS
TOTAL BUDGET: £ 6,482,756
CONCRETE STRUCTURE
URBANIZATION AND GARDENS
SWIMMING POOL
BARBECUE AREA
LOCATION: CACHAGUA, VALPARAISO, CHILE
BUDGET SUMMARY
THIRD PHASE (W3)
APARTMENTS FROM 166 m2 to 304 m2
8 BUILDINGS
23 APARTMENTS
TOTAL BUDGET: £ 6,480,762
CONCRETE STRUCTURE
URBANIZATION AND GARDENS
LOCATION: CACHAGUA, VALPARAISO, CHILE
BUDGET SUMMARY

More Related Content

What's hot

PPT AHLI MUDA TEKNIK BANGUNAN GEDUNG a.pptx
PPT AHLI MUDA TEKNIK BANGUNAN GEDUNG a.pptxPPT AHLI MUDA TEKNIK BANGUNAN GEDUNG a.pptx
PPT AHLI MUDA TEKNIK BANGUNAN GEDUNG a.pptxfirmanmuhnur
 
Bahan Presentasi Yosi Andre.pptx
Bahan Presentasi Yosi Andre.pptxBahan Presentasi Yosi Andre.pptx
Bahan Presentasi Yosi Andre.pptxYosiAndre1
 
File_Soal_17_158_29_1659598070 (2).pptx
File_Soal_17_158_29_1659598070 (2).pptxFile_Soal_17_158_29_1659598070 (2).pptx
File_Soal_17_158_29_1659598070 (2).pptxRizalYogaPrasetya
 
Perbaikan Beton dan pelaksanaannyaa
Perbaikan Beton dan pelaksanaannyaaPerbaikan Beton dan pelaksanaannyaa
Perbaikan Beton dan pelaksanaannyaaAdita Utami
 
POWER POINT gedung.pptx
POWER POINT gedung.pptxPOWER POINT gedung.pptx
POWER POINT gedung.pptxDyahPriyanti1
 
UJI KOMPETENSI FR.IA.04..pptx
UJI KOMPETENSI  FR.IA.04..pptxUJI KOMPETENSI  FR.IA.04..pptx
UJI KOMPETENSI FR.IA.04..pptxAuliaNovarina
 
File_Soal_17_158_29_1659598023(1).pptx
File_Soal_17_158_29_1659598023(1).pptxFile_Soal_17_158_29_1659598023(1).pptx
File_Soal_17_158_29_1659598023(1).pptxfransisto2
 
03 perencanaan teknis jembatan
03   perencanaan teknis jembatan03   perencanaan teknis jembatan
03 perencanaan teknis jembatanbudiMekka
 
I MADE SUDARMA JAYA_MANAGER LAPANGAN PEKERJAAN GEDUNG.pptx
I MADE SUDARMA JAYA_MANAGER LAPANGAN PEKERJAAN GEDUNG.pptxI MADE SUDARMA JAYA_MANAGER LAPANGAN PEKERJAAN GEDUNG.pptx
I MADE SUDARMA JAYA_MANAGER LAPANGAN PEKERJAAN GEDUNG.pptxIketutsupartha
 
PPT LV 6 IAN HENDRO.pptx
PPT LV 6 IAN HENDRO.pptxPPT LV 6 IAN HENDRO.pptx
PPT LV 6 IAN HENDRO.pptxHerdi51
 
Perencanaan teknis bangunan gedung ppt
Perencanaan teknis bangunan gedung pptPerencanaan teknis bangunan gedung ppt
Perencanaan teknis bangunan gedung pptHarun Ariesto Wijaya
 
Tata cara pengawasan.pptx
Tata cara pengawasan.pptxTata cara pengawasan.pptx
Tata cara pengawasan.pptxsahramaulidar1
 
Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)Hamza Waheed
 
PPT Ahli Muda Bidang Keahlian Teknik Sumber Daya Air.pptx
PPT Ahli Muda Bidang Keahlian Teknik Sumber Daya Air.pptxPPT Ahli Muda Bidang Keahlian Teknik Sumber Daya Air.pptx
PPT Ahli Muda Bidang Keahlian Teknik Sumber Daya Air.pptxssuser539b9a
 
Manager Pelaksanaan Gedung.pptx
Manager Pelaksanaan Gedung.pptxManager Pelaksanaan Gedung.pptx
Manager Pelaksanaan Gedung.pptxDatil1906
 
Manajemen konstruksi
Manajemen konstruksiManajemen konstruksi
Manajemen konstruksiRifky Alvian
 
Ahli Muda Bidang Keahlian Teknik Sumber Daya Air.pptx
Ahli Muda Bidang Keahlian Teknik Sumber Daya Air.pptxAhli Muda Bidang Keahlian Teknik Sumber Daya Air.pptx
Ahli Muda Bidang Keahlian Teknik Sumber Daya Air.pptxDickyAanastaSaputra
 

What's hot (20)

Action Plan.pptx
Action Plan.pptxAction Plan.pptx
Action Plan.pptx
 
PPT AHLI MUDA TEKNIK BANGUNAN GEDUNG a.pptx
PPT AHLI MUDA TEKNIK BANGUNAN GEDUNG a.pptxPPT AHLI MUDA TEKNIK BANGUNAN GEDUNG a.pptx
PPT AHLI MUDA TEKNIK BANGUNAN GEDUNG a.pptx
 
Bahan Presentasi Yosi Andre.pptx
Bahan Presentasi Yosi Andre.pptxBahan Presentasi Yosi Andre.pptx
Bahan Presentasi Yosi Andre.pptx
 
File_Soal_17_158_29_1659598070 (2).pptx
File_Soal_17_158_29_1659598070 (2).pptxFile_Soal_17_158_29_1659598070 (2).pptx
File_Soal_17_158_29_1659598070 (2).pptx
 
Perbaikan Beton dan pelaksanaannyaa
Perbaikan Beton dan pelaksanaannyaaPerbaikan Beton dan pelaksanaannyaa
Perbaikan Beton dan pelaksanaannyaa
 
POWER POINT gedung.pptx
POWER POINT gedung.pptxPOWER POINT gedung.pptx
POWER POINT gedung.pptx
 
UJI KOMPETENSI FR.IA.04..pptx
UJI KOMPETENSI  FR.IA.04..pptxUJI KOMPETENSI  FR.IA.04..pptx
UJI KOMPETENSI FR.IA.04..pptx
 
KAK PERENCANAAN
KAK PERENCANAANKAK PERENCANAAN
KAK PERENCANAAN
 
File_Soal_17_158_29_1659598023(1).pptx
File_Soal_17_158_29_1659598023(1).pptxFile_Soal_17_158_29_1659598023(1).pptx
File_Soal_17_158_29_1659598023(1).pptx
 
03 perencanaan teknis jembatan
03   perencanaan teknis jembatan03   perencanaan teknis jembatan
03 perencanaan teknis jembatan
 
I MADE SUDARMA JAYA_MANAGER LAPANGAN PEKERJAAN GEDUNG.pptx
I MADE SUDARMA JAYA_MANAGER LAPANGAN PEKERJAAN GEDUNG.pptxI MADE SUDARMA JAYA_MANAGER LAPANGAN PEKERJAAN GEDUNG.pptx
I MADE SUDARMA JAYA_MANAGER LAPANGAN PEKERJAAN GEDUNG.pptx
 
PPT LV 6 IAN HENDRO.pptx
PPT LV 6 IAN HENDRO.pptxPPT LV 6 IAN HENDRO.pptx
PPT LV 6 IAN HENDRO.pptx
 
Perencanaan teknis bangunan gedung ppt
Perencanaan teknis bangunan gedung pptPerencanaan teknis bangunan gedung ppt
Perencanaan teknis bangunan gedung ppt
 
Presentasi 8.pptx
Presentasi  8.pptxPresentasi  8.pptx
Presentasi 8.pptx
 
Tata cara pengawasan.pptx
Tata cara pengawasan.pptxTata cara pengawasan.pptx
Tata cara pengawasan.pptx
 
Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)
 
PPT Ahli Muda Bidang Keahlian Teknik Sumber Daya Air.pptx
PPT Ahli Muda Bidang Keahlian Teknik Sumber Daya Air.pptxPPT Ahli Muda Bidang Keahlian Teknik Sumber Daya Air.pptx
PPT Ahli Muda Bidang Keahlian Teknik Sumber Daya Air.pptx
 
Manager Pelaksanaan Gedung.pptx
Manager Pelaksanaan Gedung.pptxManager Pelaksanaan Gedung.pptx
Manager Pelaksanaan Gedung.pptx
 
Manajemen konstruksi
Manajemen konstruksiManajemen konstruksi
Manajemen konstruksi
 
Ahli Muda Bidang Keahlian Teknik Sumber Daya Air.pptx
Ahli Muda Bidang Keahlian Teknik Sumber Daya Air.pptxAhli Muda Bidang Keahlian Teknik Sumber Daya Air.pptx
Ahli Muda Bidang Keahlian Teknik Sumber Daya Air.pptx
 

PORTFOLIO AS QUANTITY SURVEYOR AND ESTIMATOR

  • 1. PORTFOLIO AS QUANTITY SURVEYOR AND ESTIMATOR *HERE IS COLLECTED A BRIEF DESCRIPTION OF ALL THE PROJECTS THAT I STUDIED AS QUANTITY SURVEYOR AND ESTIMATOR DURING MY STAY IN SERINCO. JUST INCLUDED THE PROJECT WHERE I WAS THE MAIN QUANTITY SURVEYOR. * ALL THE BUDGETS ARE A DIRECT CURRENCY EXCHANGE. CONSIDER THAT THE CHILEAN CONSTRUCTION MARKET IS NOT THE BRITISH.
  • 2. 50 APARTMENTS TOTAL SURFACE: 8,200 m2 TOTAL BUDGET: £ 5,555,504 14 FLOORS GROUND FLOOR 2 UNDERGROUND FLOORS CONCRETE STRUCTURE GYM SWIMMING POOL EVENT ROOM 59 PARKING SPACES 59 STORE ROOMS LOCATION: VIÑA DEL MAR, VALPARAISO, CHILE
  • 4. 7 APARTMENT MODELS 108 APARTMENTS TOTAL SURFACE: 6,900 m2 TOTAL BUDGET: £ 5,055,709 10 FLOORS 2 UNDERGROUND FLOORS CONCRETE STRUCTURE GYM SWIMMING POOL 2 EVENT ROOMS BARBECUE AND GREEN AREA LOCATION: LAS CONDES, SANTIAGO DE CHILE, CHILE
  • 6. REFURBISHMENT "NAVY COMMAND TALCAHUANO" After the earthquake that took place in Concepción in February 2010. The main facade of this building was seriously damaged. The project proposed the removal of all the elements to be conserved, propping up of the structure, demolition of all the structural elements damaged, rebuilding, restoration and reinstatement of all the elements conserved.
  • 8. SECOND PHASE (W2) 66m2apa a 304m2 APARTMENTS FROM 166 m2 to 304 m2 8 BUILDINGS 23 APARTMENTS TOTAL BUDGET: £ 6,482,756 CONCRETE STRUCTURE URBANIZATION AND GARDENS SWIMMING POOL BARBECUE AREA LOCATION: CACHAGUA, VALPARAISO, CHILE
  • 9. BUDGET SUMMARY THIRD PHASE (W3) APARTMENTS FROM 166 m2 to 304 m2 8 BUILDINGS 23 APARTMENTS TOTAL BUDGET: £ 6,480,762 CONCRETE STRUCTURE URBANIZATION AND GARDENS LOCATION: CACHAGUA, VALPARAISO, CHILE